MPG West ( 2022 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of -                                 )
    )
    MPG West                                     ) ASBCA Nos. 61100, 61560, 61570
    )
    Under Contract No. HDEC09-15-D-0002          )
    APPEARANCES FOR THE APPELLANT:                  Yuki Haraguchi, Esq.
    J. Travis Pittman, Esq.
    Holmes Pittman & Haraguchi, LLP
    Greensboro, MD
    APPEARANCES FOR THE GOVERNMENT: Brian Lucero, Esq.
    Deputy General Counsel
    Betsy Dulin, Esq.
    Daniel O. O’Connor, Esq.
    Trial Attorneys
    Defense Commissary Agency
    Fort Lee, VA
    OPINION BY ADMINISTRATIVE JUDGE WOODROW
    ON APPELLANT’S MOTION FOR RECONSIDERATION
    I. Background
    These appeals concern a requirements contract with the Defense Commissary
    Agency (DeCA) to supply fresh fruits and vegetables (FF&V) to U.S. Military
    commissaries (i.e., grocery stores) in Japan and South Korea.
    Following a three-day hearing, the Board issued an opinion on November 9,
    2020, concluding that appellant, MPG West, LLC (MPG), did not meet its burden of
    proving that the government breached the contract or that the government
    constructively changed the terms of the contract. MPG West, LLC, 
    ASBCA No. 61100
     et al., 
    20-1 BCA ¶ 37,739
     at 183,156.
    MPG moves for reconsideration of the Board’s November 9, 2020 decision.
    Familiarity with that opinion is assumed. Because MPG West has not demonstrated
    errors in our findings of fact or conclusions of law, and because MPG West has not
    introduced newly discovered evidence, we deny the motion for reconsideration.
    II. Standard of Review
    In deciding a motion for reconsideration, we examine whether the motion is
    based upon newly discovered evidence, mistakes in our findings of fact, or errors of
    law. Precision Standard, Inc., 
    ASBCA No. 58135
    , 
    16-1 BCA ¶ 36,504
     at 177,860. A
    motion for reconsideration does not provide the moving party the opportunity to
    reargue its position or to advance arguments that properly should have been presented
    in an earlier proceeding. See Dixon v. Shinseki, 
    741 F.3d 1367
    , 1378 (Fed. Cir. 2014).
    The moving party must show a compelling reason why the Board should modify its
    decision. ADT Construction Group, Inc., 
    ASBCA No. 55358
    , 
    14-1 BCA ¶ 35,508
    at 174,041.
    III. Appellant Has Not Identified New Evidence or Material Mistakes in our Findings of
    Fact
    MPG alleges several mistakes in the Board’s findings of fact. As we discuss
    below, MPG’s disagreements with the Board’s findings go to the weight accorded to
    particular testimony or to the Board’s conclusions based upon uncontroverted
    evidence. MPG offers no new factual information to rebut the Board’s findings.
    Moreover, none of MPG’s alleged mistaken facts, even if true, would change the
    Board’s conclusion that MPG failed to demonstrate that the government breached the
    contract.
    A. MPG’s Efforts to Locally Source Produce
    First, MPG alleges error in the Board’s factual findings concerning
    MPG’s failure to implement a local sourcing program for fresh produce. MPG
    specifically contests the following factual findings:
    76. MPG West never implemented the local sourcing plan
    (tr. 2/260, 264, 3/44-45). Instead, MPG West continued to
    source most of its produce from the United States and
    Mexico (tr. 3/44).
    77. MPG West sourced produce in the United States and
    Mexico through its “broker” and sister company, Parma
    Fruit, also owned by Mr. Penny (tr. 1/ 219-20). MPG West
    paid brokerage fees to Parma Fruit for items sourced in the
    United States and Mexico (tr. 1/219-20).
    2
    78. By sourcing produce from the United States and
    Mexico, MPG West incurred the additional cost of
    transporting the produce to Korea and Japan (tr. 3/44).
    MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,141.
    Specifically, MPG contends that it “established its subcontractor Interharvest as
    a vehicle to supply local produce in Japan” (app. mot. at 2). MPG points to one of the
    weekly pricing spreadsheets prepared by the government’s pricing specialists as an
    example of a point in time in which MPG had obtained over 50% of the required
    produce items from local sources (app. mot. at 3).
    MPG also points to the testimony of its owner, Mr. Penny, that MPG had
    purchased local produce in Korea from various local wholesale distributors during the
    period from December 2015 through August 2016 (app. mot. at 3). MPG further
    points to statements by various public officials regarding MPG’s efforts to source as
    much local produce as possible (app. mot. at 3-4).
    In its reply supporting its motion for reconsideration, MPG sets forth a
    “Schedule 1” table purporting to show that its import costs decreased while its
    in-country costs increased on a month-to-month basis from October 2015 to
    February 2016. According to MPG, the “Schedule 1” table draws on data from MPG’s
    Proof of Costs Statement and from Rule 4 tabs 13b, 43i, and 41. (App. reply at 2-3)
    These examples are unpersuasive and do not overcome the weight of evidence
    demonstrating that MPG was unprepared to locally source produce and never
    implemented a plan to do so. For example, MPG’s own post-hearing factual findings
    acknowledge its difficulties in sourcing local produce, particularly at the beginning of
    the contract, including acknowledging that it would take 3-4 months to establish
    sources for local produce and that produce that is not grown on contract is often
    expensive and difficult to obtain on the open market (app. post-hearing facts 110-23).
    Moreover, the Board’s factual findings are based on unrebutted transcript
    testimony. For example, roughly two months after the contract started, in a
    January 2016 meeting with DeCA representatives, MPG assured DeCA that MPG had
    a plan to locally source produce through local contractors, including approximately
    100 items through the Yongsan facility in Korea. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,141. Despite confirming its local sourcing plan in correspondence
    with DeCA, MPG never implemented the plan and continued to source most of its
    produce from the United States and Mexico. 
    Id.
    Finally, the “Schedule 1” table, set forth in MPG’s reply brief, was not a
    hearing exhibit, nor did MPG provide it in its pre- or post-hearing briefs. Although
    3
    MPG asserts that the information summarized in the table was contained in its
    Rule 4 exhibits, the Board is not obligated to locate, organize, and summarize MPG’s
    voluminous billing records on behalf of MPG. See GSC Constr., Inc., ASBCA
    Nos. 59402, 59601, 
    21-1 BCA ¶ 37,751
     at 183,251 (stating that the Board will not
    scour the record for appellant’s evidence or do appellant’s work for it).
    ∗
    Ultimately, while it may be true that MPG was able to gradually reduce its
    dependence on imported produce during the period from December 2015 until
    February 2016, it is also true that MPG did not have a local sourcing plan in place
    at the start of the contract. Indeed, as MPG’s owner testified, MPG relied upon its
    “sister” company, Parma Fruit, to import produce from the United States and Mexico
    at the onset of the contract and continued to do so even as MPG attempted to secure
    local sources. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,141.
    At bottom, MPG has not provided any new evidence to rebut the
    Board’s factual findings. To the extent that the Board’s findings neglected to describe
    adequately MPG’s increased sourcing of local produce over the last months of its
    contract performance, it does not change our conclusion that MPG initially failed to
    implement a local sourcing plan, despite being on notice that locally sourcing produce
    was crucial to successful performance of the contract. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,152.
    B. Whether the Government Directed MPG to Alter its Prices and
    Remove Items from the Stream of Commerce
    MPG next finds fault with the Board’s findings that the government asked,
    rather than mandated, that MPG lower its prices or remove produce items from the
    ordering guide (app. mot. at 4). According to MPG, the Board’s factual findings failed
    to acknowledge that the government’s requests were directives, rather than requests.
    ∗
    “We are not charged with sorting through a haystack of documents to locate relevant
    facts. If we were to engage in such efforts it would cripple our ability to
    perform our basic function of providing a just, inexpensive and expeditious
    remedy . . . . In briefing we expect the parties to make specific reference to
    each remaining document which they contend supports their position. In the
    absence of such specific reference, parties risk documents not being considered
    in reaching our decision.” Gary Aircraft Corp., 
    ASBCA No. 21731
    , 
    91-3 BCA ¶ 24,122
     at 120,718 (quoting Hawaiian Dredging & Constr. Co., 
    ASBCA No. 25594
    , 
    84-2 BCA ¶ 17,290
     at 86,125).
    4
    Specifically, at Fact 96, the Board found that:
    96. If an item was finally determined to be unreasonably
    priced, Ms. Bennet and/or a member of her team requested
    the item be removed from the ordering guide or offered at
    a lower price (tr. 3/86, 91).
    Similarly, the Board found:
    100. During these calls, DeCA would ask MPG West to
    offer certain products at lower prices (tr. 1/97-99,
    177-79).
    101. During the weekly meetings, DeCA sometimes asked
    appellant to remove products, including products on the
    HVCI list and bagged salad, from the commissary catalogs
    due to the price (tr. 1/177-79; app. supp. R4, tab 57 at 96;
    R4, tabs 851, 867-68).
    (Op. at 183,142)
    Citing testimony from its owner, MPG asserts that the government continually
    pressured MPG to lower its prices and “directed MPG to set aside its contract rights
    under penalty of default termination” (app. mot. at 4).
    MPG offers no new facts or evidence to rebut the Board’s factual findings.
    MPG also ignores the context provided by the Board’s other factual findings regarding
    the weekly price review process. In particular, DeCA’s requests concerning pricing
    were made in the context of weekly pricing meetings, at which representatives of
    DeCA and MPG would negotiate the final fixed price of items. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,142-43. Although it was true that DeCA occasionally would
    direct MPG to either reduce a price or remove an item, it would do so only in
    accordance with the contractual requirement that prices must be fair and reasonable
    considering the market conditions at the time. 
    Id.
    Although high prices were a common concern at the weekly meetings, the
    DeCA Produce Category Manager testified that DeCA typically would question only
    ten or so items out of a catalog of 400 offerings. On a weekly basis, DeCA approved
    the vast majority of the items submitted by MPG West. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,142. For those items that DeCA questioned, DeCA gave MPG an
    opportunity to explain the price. 
    Id.
     Indeed, in some situations, MPG would refuse to
    lower its prices, stating that the proposed price was the “new retail price” or due to a
    “FOB increase.” 
    Id. at 183,143
    . In all cases, MPG was free to make a business
    5
    decision to remove unavailable items (id.), or alter its profit margin on individual
    items. 
    Id. at 183,142
    .
    The weight of evidence and testimony demonstrates that the Board correctly
    concluded that the government did not breach its contractual obligations when
    conducting its weekly review of MPG’s produce catalog.
    C. Whether the Status of Forces Agreement Obligated MPG to Import
    Certain Produce Items
    MPG also challenges the Board’s factual findings that MPG was not obligated
    to import any produce under the Status of Forces Agreements (SOFA) between the
    United States and Korea and Japan. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,141.
    Specifically, MPG challenges the testimony of the contracting officer, Ms. Petra Pulze,
    that MPG could choose whether or not to import items under the SOFA. 
    Id.
     MPG
    challenges her testimony by alleging that the “United States government official in
    charge of SOFA compliance in Korea” successfully rebutted Ms. Pulze’s testimony
    (app. mot. at 5).
    We disagree. The contract expressly states that it is not subject to SOFA, and
    Ms. Pulze’s testimony demonstrates that DeCA’s conduct was consistent with the
    contract. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,141.
    Ms. Pulze testified that the contract permitted embargoed items to be imported
    under the SOFA, but that doing so would require the contractor to coordinate with
    DeCA. She further testified that MPG never asked DeCA to have any items imported
    under SOFA (tr. 2/73-74). In response to a direct question about whether the SOFA
    importation process was mandatory, Ms. Pulze explained that it was not. MPG West,
    LLC, 
    20-1 BCA ¶ 37,739
     at 183,141. Instead, the contract expressly stated that it
    required FOB destination delivery. 
    Id. at 183,138
    . Indeed, the term was the subject of
    published vendor questions and bid protests challenging its feasibility, so MPG West
    should have been fully aware of the requirement. 
    Id. at 183,137
    .
    Moreover, DeCA amended the solicitation to specifically state that “[a]ny costs
    associated with the transportation and customs clearance of imported products must be
    included into the offered F.O.B. destination price” (app. supp. R4, tab 898 at 7).
    MPG West unilaterally chose to import items under the SOFA agreement.
    MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,141. As a consequence, DeCA had no
    duty to coordinate with SOFA representatives, other than to assist when MPG West
    requested and to avoid hindering MPG West. Indeed, DeCA did so when it wrote a
    letter to South Korean customs explaining that MPG West was permitted to import
    6
    embargoed items for sale in the commissaries. This letter achieved the desired result,
    as importation difficulties ended after the letter. 
    Id.
    The weight of evidence demonstrates that MPG possessed the discretion to
    import items through either commercial channels or through the SOFA process and
    that its choice was a business decision, not a mandate from the government.
    IV. Appellant’s Challenge to the Board’s Contract Interpretation Fails to Establish an
    Error of Law
    A. The Government’s Estimation of its Requirements in the Solicitation
    Was Not a Breach of Contract
    MPG asserts that the government breached the requirements contract when it
    failed to revise its historical data to account for changes to the contract’s structure
    (app. mot. at 6). Specifically, MPG asserts that the government estimated its
    requirements based on historical data from the incumbent contract while failing to take
    into account the fact that the new contract relied upon obtaining local produce rather
    than imports under the SOFA. In support, MPG cites a series of cases establishing that
    the government is in breach of contract when it inadequately or negligently estimates
    its requirements (app. mot. at 6).
    MPG’s recitation of the law in its motion for reconsideration is not
    substantively different from the Board’s discussion of the law in its opinion. MPG
    West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,147. As we stated, a breach of contract can
    occur when a government estimate is inadequately or negligently prepared and is
    included without correction in a solicitation or contract. 
    Id.
     We further clarified that
    the critical measure for determining whether an estimate was negligently prepared is
    whether the estimate is based upon all relevant information that is reasonably available
    to the government at the time of the award. 
    Id.
    MPG’s argument, therefore, is not with the Board’s understanding of the law,
    but rather with the Board’s conclusion – based on that law – that MPG failed to
    provide specific evidence that DeCA was negligent in estimating weekly produce
    quantities. 
    Id. at 183,148
    .
    MPG makes several arguments in support of its challenge to the
    Board’s reasoning, all of which it previously made at the hearing or in its post-hearing
    briefing. MPG cites no new evidence in its challenge to the Board’s conclusions. The
    Board considered and addressed each of these arguments in its opinion. See Dixon v.
    Shinseki, 
    741 F.3d 1367
    , 1378 (Fed. Cir. 2014) (holding that motion for
    reconsideration does not provide the moving party with an opportunity to reargue its
    7
    position); Philips Lighting North America, 
    ASBCA No. 61769
     et al., 
    21-1 BCA ¶ 37,821
     at 183,647.
    First, MPG contends that the government was negligent by estimating its
    requirements based upon historical data from the incumbent contract, despite the fact
    that the new contract involved a significant change to the business model from the
    incumbent contract. In addition, MPG contends that the CO’s admission – that she
    did not perform a business case analysis to support her estimates of the
    government’s requirements – further compounds the government’s negligence. (App.
    mot. at 6-7)
    MPG made these same arguments in its post-hearing briefing (app. post-hearing
    br. at 32). We continue to find MPG’s arguments unpersuasive. Because the
    government’s estimates for its requirements were based upon historical consumption
    rates, it was reasonable for the government to assume store patrons would continue to
    need similar items and quantities of produce. MPG West, LLC, 
    20-1 BCA ¶ 37,739
    at 183,137. The fact that the new contract expressly required the new contractor to use
    local sources as much as possible has no bearing on the reasonableness of the
    government’s requirements. MPG has not provided specific evidence that DeCA was
    negligent in estimating weekly produce quantities, nor does MPG provide any new
    evidence in its motion for reconsideration. 
    Id. at 183,148
    .
    Next, MPG argues that the government was negligent because it ignored
    information indicating that the new contract model would make it difficult for the
    contractor to meet the government’s requirements. Specifically, MPG alleges that
    DeCA ignored a market research report prepared by the incumbent contractor warning
    that it would be difficult to satisfy the government’s requirements via local sources.
    MPG further argues that the U.S. SOFA representative in Korea warned the
    government in April 2014 that it would have difficulty obtaining its requirements
    under the new contract model. (App. mot. at 7)
    We previously addressed these specific arguments in our opinion. Regarding
    the February 2018 market research report, we reviewed the report’s conclusions and
    did not find them dispositive. Specifically, based upon the unrebutted testimony of the
    project manager for the research report, we found that the report did not segregate data
    generated during MPG West’s performance from data generated after other contractors
    took over in July 2016. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,144. We also
    concluded that the report did not study the impact of the contract on MPG West,
    did not evaluate DeCA’s conduct of weekly price reviews, and did not evaluate the
    startup process nor MPG West’s delivery of bagged salads. 
    Id.
     Based upon these
    findings, we concluded that the report did not demonstrate that the government was
    negligent in preparing its requirements. We see no reason to change these conclusions
    upon reconsideration.
    8
    The cases MPG West relies upon in its criticism of the Board’s conclusions
    do not alter our conclusions.
    These appeals are not like Burnham Associates, Inc., 
    ASBCA No. 60780
    , 
    18-1 BCA ¶ 36,934
    , a case cited by MPG. In Burnham, the Board found the government
    negligent in preparing a dredging estimate when it significantly underestimated the
    quantity of soil to be dredged from the Boston Harbor. 
    Id. at 179,942-43
    . Nor are
    these appeals like Rumsfeld v. Applied Companies, Inc., 
    325 F.3d 1328
     (Fed.
    Cir. 2003), another case cited by MPG. In Rumsfeld, the United States Court of
    Appeals for the Federal Circuit affirmed the Board’s finding that the government was
    negligent when it failed to inform the contractor that quantity estimates contained in its
    request for proposals was greatly overstated. 
    Id. at 1335
    .
    Here, in contrast, MPG does not raise an issue with the quantities of produce set
    forth in the government’s estimates of its requirements. MPG does not allege that the
    government over- or under-estimated its needs. Instead, MPG’s quarrel is with the
    purported difficulties of sourcing that produce in accordance with the terms of the
    contract.
    As we held in our opinion, the contract expressly placed the burden (and
    concomitant risk) of sourcing produce on the contractor. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,149, 183,154. As we found, the record demonstrates that MPG West
    failed to timely implement a local sourcing plan, instead sourcing most of its produce
    from overseas. 
    Id. at 183,141
    . Moreover, the record further demonstrates that
    MPG’s successor contractors were able to fill the contract’s requirements using
    predominantly local sources (app. post-hearing br. at 2-3).
    Finally, MPG argues that the government was negligent, because the DOD
    Inspector General (IG) performed an audit of the government’s market research and
    made a specific finding that it was inadequate (app. mot. at 7).
    We expressly addressed the IG’s market research report in our opinion,
    concluding that the IG report did not demonstrate that DeCA breached the contract.
    MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,149. We concluded that the IG’s market
    research report was not dispositive, because it did not differentiate between data
    generated during MPG West’s performance from data generated after other contractors
    took over the contract in July 2016. 
    Id. at 183,144
    . Moreover, the report did not
    address DeCA’s weekly price reviews, nor its delivery of bagged salads. 
    Id.
    MPG’s motion for reconsideration raises no new arguments and introduces no new
    facts that would cause us to change our conclusions.
    9
    B. Whether the Government Breached the Contract by Varying its
    Requirements to Avoid the Fixed Price
    MPG next asserts that the government acted in bad faith as a matter of law
    when it varied its requirements in order to avoid obligations under the contract (app.
    reply at 4). Specifically, MPG argues that the government decreased its requirements
    in order to avoid its contract obligations by asking MPG West to take items off the
    shelf because they were too highly priced, and because DeCA was concerned that the
    high prices for certain items would create negative publicity (app. mot. at 8-9).
    MPG cites Medart, Inc. v. Austin, 
    967 F.2d 579
    , 581 (Fed. Cir. 1992), for the
    proposition that a requirements contract obligates the government to fill all its
    requirements at the agreed price. This is an overstatement of the holding in that case.
    Medart holds that the government must use information that is reasonably available in
    order to estimate its requirements, and that the contractor bears the risk of variances in
    quantity. 
    967 F.2d at 582
    . In Medart, the Federal Circuit affirmed the Civilian Board
    of Contract Appeals’ holding that the government used reasonable care in computing
    its estimated needs based upon the previous year’s orders. The Court specifically held
    that the government was not required to apply any of the specific methods advanced
    by the appellant, such as contacting or polling end-users about their projected needs
    and budgets, considering the use of statistical formulas such as regression analysis, or
    checking the effectiveness of its estimating procedure based on past performance. 
    Id.
    Medart supports the Board’s reasoning that DeCA used reasonable care in
    estimating its requirements and that DeCA was not required to undertake extraordinary
    measures, such as performing a business case analysis to support its estimates of the
    government’s requirements.
    MPG additionally cites Simplix, 
    ASBCA No. 52570
    , 
    06-1 BCA ¶ 33,240
    (2006), for the proposition that variation in the government’s requirements may be a
    breach of contract when the government acts in bad faith. MPG’s recitation of the law
    governing requirements contracts ignores the Federal Circuit’s central holding in
    Technical Assistance Int’l v. United States, 
    150 F.3d 1369
     (Fed. Cir. 1998).
    Specifically, Technical Assistance held that the buyer has significant freedom in
    determining its requirements because it has bargained for such flexibility by paying a
    premium price for the goods provided. 
    Id. at 1372
    .
    We comprehensively addressed this argument in section II.C. of our previous
    opinion. Consistent with the central holding in Technical Assistance, we hold that the
    contract expressly permitted DeCA the flexibility to order produce from other
    providers, as long as the contract with MPG West was the “primary source.” MPG
    West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,149-50. We further held that: DeCA conducted
    its weekly pricing review in a manner that was reasonable and consistent with the
    10
    contract terms; that DeCA developed and applied reasonable and consistent criteria to
    evaluate weekly prices based on the past history of prices for particular items; and that
    DeCA approved the vast majority of the items submitted by MPG West on a weekly
    basis. 
    Id. at 183,150
    . Finally, for those items that it questioned, DeCA identified why
    it was questioning the price and gave MPG West an opportunity to explain the price.
    
    Id.
    MPG’s motion for reconsideration raises no new arguments and introduces no
    new facts that would cause us to change the conclusions set forth in our opinion.
    C. Whether the Government Satisfied the Implied Duty of Cooperation
    MPG challenges the Board’s statement of the law regarding the implied duty of
    cooperation, contending that the Board incorrectly states that the duty of cooperation
    requires only that the government not interfere with performance. Citing a variety of
    Board cases, MPG asserts that the law imposes a more expansive duty on the
    government, including an obligation to “do what is reasonably necessary to enable the
    contractor to perform.” (App. mot. at 12) MPG’s recitation of the law is correct, but
    is not fundamentally at odds with the Board’s statement of the law concerning the duty
    of cooperation. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,154.
    MPG contends that the contract was “doomed from the start,” because it
    involved a significant overhaul of the contract model for supplying commissaries in
    the Pacific theater and was imposed “without even performing adequate market
    research or a business case analysis” (app. mot. at 13). This is simply a restatement of
    arguments MPG previously made and gives us no reason to reconsider our decision.
    MPG further contends that the “Board’s [legal] error is compounded by the
    mistakes of fact that support its reasoning” (app. mot. at 13). As we discussed above,
    we have examined MPG’s allegations of errors in our factual findings and have
    concluded that the record supports our findings. MPG’s real issue, therefore, is not
    with the Board’s understanding of law, but rather with the Board’s application of the
    law.
    The bottom line is that the contract placed responsibility for compliance with
    host-nation laws solely on the contractor, and the contractor had a great deal of
    discretion as to how it would comply. MPG West, LLC, 
    20-1 BCA ¶ 37,739
    at 183,154. Moreover, as we discussed in our opinion, the government did more than
    just “basically stay out of the way” (app. mot. at 12). For example, in an effort to ease
    the South Korean importation process for MPG, DeCA wrote a letter to South Korean
    customs officials explaining that MPG was permitted to import items embargoed
    under the SOFA, provided that the items would be sold in the commissaries. MPG
    West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,141.
    11
    MPG makes no new arguments and introduces no evidence in support of its
    request for reconsideration. Therefore, we have no reason to change the conclusions
    set forth in our opinion.
    D. Whether the Bagged Salad Specifications Were Defective
    MPG’s final contention is that the Board erred in concluding that the bagged
    salad specifications were not defective. According to MPG, the Board’s conclusion
    was based on a misstatement of MPG’s claim and an insufficient statement of the law
    concerning defective specifications (app. mot. at 14). Citing Essex Electro Engineers
    v. Danzig, 
    224 F.3d 1283
     (Fed. Cir. 2000), MPG contends that the threshold question
    in a defective specification claim is whether the contractor can follow the
    government’s specifications and achieve the result for which the government has
    contracted (app. mot. at 15). According to MPG, it was impossible for MPG to supply
    the government’s bagged salad requirements via FOB destination freight at a fixed
    price that included all costs and profit and also achieve a patron savings discount (app.
    mot. at 15). For example, if it is economically impracticable to supply a specified
    product at a price buyers are willing to pay, then it would support the contention that
    the specification is defective (app. br. at 16 (citing Brazier Lumber Co., 
    ASBCA No. 18601
    , 
    76-2 BCA ¶ 12,207
    )).
    As we explained in our decision, to recover on a defective specification theory,
    MPG West must show that there was a defect, that it reasonably relied upon the defect,
    and that the defect was latent. MPG West, LLC, 
    20-1 BCA ¶ 37,739
     at 183,155 (citing
    E.L. Hamm & Assocs., Inc. v. England, 
    379 F.3d 1334
    , 1339 (Fed. Cir. 2004)).
    MPG offers no new facts or legal arguments to support its position that the
    Board erred in its findings or legal conclusions. Moreover, MPG West’s criticism of
    the Board’s decision does not address the Board’s conclusion that MPG West failed to
    demonstrate that it relied on the allegedly defective specification. Indeed, when MPG
    West concluded that it could not profitably perform, the government agreed to remove
    the bagged salad requirement. Id. at 183,143.
    Perhaps understanding that its defective specification theory lacks merit, MPG
    West now argues, for the first time, that meeting the bagged salad specification was
    commercially impracticable (app. mot. at 16-19). Specifically, MPG West contends
    that “the contract specified that MPG must supply the government's bagged salad
    requirements via FOB destination freight at a fixed price that included all costs and
    profit and achieved a patron savings discount.” According to MPG West, achieving a
    patron savings discount simply was not possible with FOB delivery and a fixed price
    that includes all contractor costs. (App. mot. at 15)
    12
    A motion for reconsideration is not the appropriate place to raise an argument
    for the first time. See Dixon, 741 F.3d at 1378 (refusing to entertain an argument that
    should properly should have been presented in an earlier proceeding). To establish
    commercial impracticability, the contractor must demonstrate that it has exhausted
    all of its alternatives for performance, not merely that its costs have become more
    expensive than originally contemplated. Jennie-O Foods, Inc. v. United States, 
    580 F.2d 400
    , 409 (Ct. Cl. 1978).
    Here, MPG West has not demonstrated that it exhausted all of its alternatives
    for supplying bagged salads. Other than testimony that DeCA suggested corrective
    actions, such as DeCA assuming bagged salad shipments to Korea, MPG West has
    proffered no evidence that it pursued other alternatives (tr. 2/213).
    Rather than exhaust all alternatives for supplying bagged salads, MPG West
    asked DeCA to remove the bagged salad requirement, and DeCA did so. MPG West,
    LLC, 
    20-1 BCA ¶ 37,739
     at 183,143. Moreover, MPG West admits that its successor
    contractor was able to successfully perform the contract (app. post-hearing br. at 2).
    The fact that the government agreed to remove the bagged salad requirement has no
    bearing on whether it was impossible to meet the requirement. Indeed, the change was
    bilateral and made at MPG West’s request. 
    Id. at 183,156
    .
    MPG contends that, in Korea, it was impossible to perform the contract with
    local bagged salads in lieu of imports, because the U.S. government command in
    charge of food safety never provided MPG with the necessary authorization. MPG
    offers no new facts in support of this argument, which the Board previously rejected.
    
    Id. at 183,149
    .
    Finally, MPG’s contention that it could not meet the bagged salad requirement
    while achieving a patron savings discount is without basis, because bagged salads were
    not among the items to be considered in calculating the patron savings requirement.
    
    Id. at 183,143
    . As we explained in our opinion, the contract contained a “Patron
    Savings Requirement” applicable to 35 items of produce listed at Attachment 4 called
    “High Volume Core Items” (HVCI). The contract defined the Patron Savings
    Requirement as a price savings to the commissary patron when compared to the prices
    of like items from comparable private sector retail stores within the local commuting
    area of a commissary store in the host country.
    13
    Under the Patron Savings Requirement, MPG West warranted that prices for
    the listed HVCI would provide a minimum percentage of savings when compared to
    the prices in comparable private-sector retail stores. 
    Id. at 183,139
    .
    For these reasons, we deny the motion for reconsideration.
    Dated: September 20, 2022
    KENNETH D. WOODROW
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    RICHARD SHACKLEFORD                              J. REID PROUTY
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 61100, 61560, 61570,
    Appeals of MPG West, rendered in conformance with the Board’s Charter.
    Dated: September 20, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    14