Heartland Energy Partners LLC ( 2022 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                  )
    )
    Heartland Energy Partners LLC                )    
    ASBCA No. 62979
    )
    Under Contract No. W912HQ-18-D-0010          )
    APPEARANCE FOR THE APPELLANT:                     William A. Shook, Esq.
    The Law Offices of William A. Shook PLLC
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                   Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Jesse C. Lee, Esq.
    Siobhan Fabio, Esq.
    Engineer Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS ON THE
    GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT
    In September 2019, appellant, Heartland Energy Partners, LLC (Heartland) was
    awarded a task order against a commercial items contract with the United States Army
    Corps of Engineers (USACE or government). Relevant to this appeal, the task order
    contained 11 firm-fixed-price contract line items (CLINs) for physical security
    consulting services. In March 2020, the USACE instructed Heartland to discontinue
    performance on four of the CLINs, due to the spread of the novel Coronavirus
    (COVID-19), and the resulting restrictions on travel and in-person training.
    Rather than terminate the CLINs, the government instead attempted to negotiate
    with Heartland to allow Heartland to perform alternative tasks, or for a descope of the
    CLINs; however, the parties did not reach agreement prior to the end of the task order
    performance period. Heartland now contends that it is entitled to payment of the firm-
    fixed-price CLIN amounts, despite not having performed the required work. The
    government contends that its instruction to discontinue performance was an actual or
    constructive termination for convenience such that Heartland is entitled to
    compensation only for the work performed. We agree with the government that the
    task order was constructively terminated for convenience, and grant the government’s
    motion for summary judgment, in part. However, we note that a termination for
    convenience essentially converts a firm-fixed-price CLIN to a cost-type CLIN, and,
    thus, that Heartland’s compensation will not necessarily be limited to the amounts
    invoiced prior to the government’s instruction to discontinue performance.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    I. The Contract and Task Order
    On September 18, 2018, the USACE issued solicitation number
    W912HQ18R0009 for commercial services relating to support for its physical security
    mission under Federal Acquisition Regulation (FAR) Part 12, Acquisition of
    Commercial Items (R4, tab 81 at 1). On September 24, 2018, the USACE and
    Heartland entered into contract W912HQ18D0010, an indefinite delivery indefinite
    quantity (IDIQ) commercial items contract for physical security program support
    services (R4, tab 2 at 186-92). On July 15, 2019, the Humphreys Engineer Center
    Support Activity (HECSA) contracting officer, Wesley (Dale) Dewar, issued to
    Heartland a request for proposal for task order 3 (app. supp. R4, tab H1 at 1-2).
    Heartland submitted its proposal response on August 1, 2019, to HECSA contract
    specialist, David Kaplan (app. supp. R4, tab H2A at 56-61). Task order 3 was issued
    to Heartland on September 6, 2019, utilizing Standard Form (SF) 1449
    “Solicitation/Contract/Order For Commercial Items” (R4, tab 3 at 227).
    Task order 3 consisted of 11 firm-fixed-priced CLINs involving commercial
    services for technical, analytical, planning, and administrative support to USACE’s
    physical security mission, and two cost-reimbursement CLINs for related travel and
    other direct costs (id. at 227-35). Each of the fixed-price CLINs had a quantity of one
    where the unit was the “project,” or the completion of all tasks under that CLIN (id. at
    229-34). The total price for the fixed-priced CLINs was $1,581,412.76 (id.). The two
    remaining CLINS (1012 and 1013) reflected cost reimbursement for travel costs with
    an estimated cost of $68,576.34 and “other direct costs” with an estimated cost of
    $73,869.00. (id. at 234-35). The CLINs provided for delivery during the period of
    performance of September 6, 2019 to September 5, 2020 (id. at 236-37). The
    performance work statement reflected the task sequencing and delivery schedule in
    more detail, with some delivery schedules being unspecified (id. at 242-56).
    The contract incorporated various contract terms, including CONTRACT
    TERMS AND CONDITIONS—COMMERCIAL ITEMS (JAN 2017) at FAR 52.212-
    4 (R4, tab 2 at 193). The Commercial Items clause provides in relevant part:
    (c) Changes. Changes in the terms and conditions of this
    contract may be made only by written agreement of the
    parties.
    ....
    2
    (i)    Payment.- (1) Items accepted.
    Payment shall be made for items accepted by the
    Government that have been delivered to the delivery
    destinations set forth in this contract.
    ....
    (l) Termination for the Government’s convenience. The
    Government reserves the right to terminate this contract, or
    any part hereof, for its sole convenience. In the event of
    such termination, the Contractor shall immediately stop all
    work hereunder and shall immediately cause any and all of
    its suppliers and subcontractors to cease work. Subject to
    the terms of this contract, the Contractor shall be paid a
    percentage of the contract price reflecting the percentage
    of the work performed prior to the notice of termination,
    plus reasonable charges the Contractor can demonstrate to
    the satisfaction of the Government using its standard
    record keeping system, have resulted from the termination.
    The Contractor shall not be required to comply with the
    cost accounting standards or contract cost principles for
    this purpose. This paragraph does not give the
    Government any right to audit the Contractor’s records.
    The Contractor shall not be paid for any work performed
    or costs incurred which reasonably could have been
    avoided.
    FAR 52.212-4.
    The payment instructions in task order 3 directed Heartland to “bill the
    government on a monthly basis” (R4, tab 3 at 264). The government directed
    Heartland to bill 1/12th of each of the task order’s total firm-fixed-price CLINs each
    month, rather than billing for services as performed (R4, tab 8a at 410). Additional
    invoice instructions specify that “[t]he Government shall pay the Contractor as full
    compensation for all work required, performed and accepted under this contract,
    inclusive of all costs and expenses, the firm-fixed price stated in this contract” (R4,
    tab 3 at 282). On March 17, 2020, the parties executed a bilateral modification
    (mod 2) reducing the scope of CLIN 1010, making other changes, and decreasing the
    total task order price by $35,031 to $1,688,827.10 (R4, tab 5 at 331).
    3
    II. COVID -19 Restrictions and Efforts To Modify The Scope of the Task Order
    On March 27, 2020, the government informed Heartland that, due to COVID-
    19 restrictions, it was to discontinue performance on CLINs 1004, 1008, 1010, and
    1011 (R4, tab 8a at 410). The notification was by memorandum signed by
    David Kaplan, a Contract Specialist, without authority to modify the contract (id.; R4,
    tab 3 at 264, app. resp. at attachment 1). Heartland was further instructed to
    discontinue invoicing for the affected CLINs (R4, tab 8a at 410). Additionally, per the
    guidance received from HECSA contracting, for all future invoices Heartland was
    directed to only invoice for services actually delivered for the CLIN, rather than billing
    1/12th of the CLIN amount each month. The instructions referred to the previous
    direction to invoice in equal increments for the duration of the period of performance
    as an “incorrect instruction.” (Id.)
    The CLINs subject to the March 27, 2020, direction to discontinue performance
    involved travel and in-person meetings that did not comply with then-current guidance
    by the Department of Defense (DoD) (id.). CLIN 1004 Task 3 – Program Protection
    Review involved, among other things, Heartland travelling to seven USACE locations
    to brief the local commander, conduct interviews of local physical security program
    leaders, and record observations of local physical security programs (R4, tab 3 at 245-
    46). CLIN 1008 Task 7 Physical Security Program/Project Management Program of
    Instruction involved Heartland conducting two separate training sessions in a
    classroom setting with 30-40 USACE security personnel. One session was to be in the
    Washington, DC area, and the other was to be at a location to be determined. (Id.
    at 250-51) Heartland performed a session in Alexandria, Virginia in November 2019
    (app. resp. at attachment 11 at 1 - 5). Consistent with the government’s invoicing
    instructions, Heartland did not bill the actual cost of that session but rather billed
    1/12th of the total CLIN for the month of November 2019 (app. resp. at attachment 4
    at 1). CLIN 1010 Task 9 – Conduct Vulnerability Assessments for Nuclear Reactor,
    SNM, or Chemical Agents at 3 CONUS Sites, involved Heartland conducting
    assessments of USACE sites, to be determined, with nuclear reactors, special
    nuclear material, chemical agents, and/or biological select agents or toxins (R4, tab 3
    at 254-56). CLIN 1011 Task 10 – Department of the Army Security Guard (DASG)
    and Contract Security Guards (CSG) Training, involved Heartland conducting two
    separate eight-day in-person training sessions for approximately 30 attendees each.
    Heartland was to instruct attendees in fire and range risk management for live-fire
    qualification in 9MM pistols and/or additional weapons systems. (Id. at 256)
    On March 30, 2020, the contract specialist transmitted a proposed modification
    (mod 3) reflecting the removal of the affected tasks and requesting that Heartland
    submit a price proposal to reflect the proposed reduction in scope (R4, tabs 9 at 411,
    9a at 412-58). The communication also noted the payments paragraph of the
    commercial items clause at 52.212-4(i), reiterating, “Heartland may be paid for
    4
    services actually performed and accepted” (R4, tab 9 at 411). On April 1, 2020, in
    response to the proposal, Heartland noted that the government could not unilaterally
    modify the contract, but could terminate for convenience of the government, stating:
    In other words, it is my understanding that the government
    does not have the right to make unilateral changes in the
    contract. I do understand that the government has the right
    to do a partial termination for its convenience under
    52.214-4(l). Please confirm that I am to treat the
    descoping as a partial termination for the government’s
    convenience.
    (R4, tab 11 at 461) The government did not respond to Heartland’s question. On
    April 9, 2020, Heartland transmitted its reduction in scope estimate for mod 3,
    reflecting a reduction of $216,878.18 under the assumption that it would invoice under
    mod 3 starting April 2020 (R4, tabs 12 at 463, 12a at 465). On April 24, 2020,
    representatives of the government and Heartland met via telephone to discuss the
    proposed changes to the contract, but no agreement was reached (R4, tabs 14 at 468,
    15 at 471).
    In addition to removing the affected tasks from task order 3 the parties
    discussed a resolution that would, among other things, add an additional program of
    instruction to CLIN 1008; add two training sessions to CLIN 1011; redistribute
    funding from CLINs 1004 and 1010 to CLINs 1008 and 1011 in the amount of
    $146,004.43; not process invoices attributed to CLINs 1004 and 1011 until COVID
    restrictions were lifted; and, extend the period of performance for CLINs 1008 and
    1011 by 12 months (R4, tabs 16a at 473-74, 18 at 511-12). On May 5, 2020,
    Paul Gates, representative of Heartland, professed Heartland’s consent to the changes
    to the performance work statement but had questions about invoicing (R4, tab 19
    at 513). On May 18, 2020, Heartland submitted an invoice for April 2020 that omitted
    CLINs 1004 and 1010 1 per the contract specialist’s instruction (R4, tabs 24 at 534, 24a
    at 535). This invoice was accepted (R4, tab 25 at 536).
    On May 29, 2020, the contract specialist transmitted via e-mail the draft
    modification 3 to the task order, incorporating the parties’ draft changes and providing
    “I anticipate questions so let me know if you want to schedule a call with the
    [contracting officer] and myself” (R4, tab 26 at 538). On June 3, 2020, Mr. Gates
    responded with concerns about the schedule and the possibility that in-person training
    sessions may not be possible until at least February 2021. He suggested scheduling
    1
    It is not clear from the record why Heartland was permitted to bill for CLINs 1008
    and 1011, but it may have been based on the assumption that work would be
    performed on the two CLINs pursuant to the proposed resolution.
    5
    training sessions in the then near future with a contingent plan to move to a remote
    environment should COVID restrictions remain in place by the scheduled date. (R4,
    tab 28 at 588) On June 5, 2020, Heartland sent the government its proposed adjusted
    invoicing schedule (R4, tabs 29 at 590, 29a at 592). On July 23, 2020, Heartland
    began invoicing the government for the affected tasks, based on the government’s
    prior instruction to invoice equal monthly amounts. On July 28, 2020, invoices for
    May 2020 and June 2020 were rejected by the government for “charging for services
    that were not rendered nor received . . . .” (R4, tabs 37 at 623-24, 37a at 625, 37b
    at 626)
    On July 30, 2020, the government sent Heartland a memorandum reflecting the
    changes to task order 3 resulting from COVID 19 restrictions. The changes were to
    remove any performance on CLINs 1004, 1008, 1010, and 1011, as well as the
    flexibly-priced CLIN 1012. (R4, tabs 38 at 627, 38a at 628-29) Unlike the March 27,
    2020 direction, this was signed by the contracting officer, but he did not cite the
    government’s right to terminate the CLINs for the convenience of the government as a
    basis for the action (R4, tab 38a at 629). On July 31, 2020, Heartland expressed
    concern with what it viewed as unauthorized unilateral changes to the contract in
    violation of the changes clause at FAR 52.21204(c) and offered to continue
    negotiations (R4, tab 39). The negotiations were ultimately unsuccessful. The
    government transmitted one last proposed modification that would have had Heartland
    produce training videos in place of in person training sessions (R4, tab 44 at 628, 44a
    at 639). This was rejected by Heartland because the proposed reduced price would
    “not account for the costs already incurred by Heartland in being prepared to deliver
    the services required by the existing scope of work within the period of performance”
    (R4, tab 45 at 685). The remaining invoices were first submitted with charges for the
    affected tasks and rejected (R4, tabs 77 at 727, 79 at 729). The government
    subsequently accepted modified invoices that did not include the monthly allocated
    charges for the affected line items (R4, tabs 74 at 724, 76 at 726, 78 at 728, 80 at 730).
    III. Heartland’s Claim and Appeal
    Heartland submitted a certified claim in the amount of $211,624.52 plus interest
    on January 4, 2021, for nonpayment against the affected CLINs, asserting that
    no bilateral change was made to task order 3 pursuant to FAR 52.212-4(c) (R4, tab 1
    at 1-2). The parties unsuccessfully attempted to negotiate a resolution to Heartland’s
    claim (R4, tabs 52 at 698, 59 at 708). On July 12, 2021, Heartland appealed to the
    Board, asserting jurisdiction based upon a deemed denial by the contracting officer. In
    its complaint, dated July 12, 2021, Heartland pleaded the existence of “a contract for
    commercial services” (compl. ¶ 8).
    6
    DECISION
    I.     Standard of Review
    We will grant summary judgment only if there is “no genuine issue as to any
    material fact and [] the moving party is entitled to judgment as a matter of law.”
    Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322 (1986) (citation omitted). A material fact
    is one that may affect the outcome of the decision. Anderson v. Liberty Lobby, Inc.,
    
    477 U.S. 242
    , 248 (1986). “The moving party bears the burden of establishing the
    absence of any genuine issue of material fact and all significant doubt over factual
    issues must be resolved in favor of the party opposing summary judgment.” Mingus
    Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987). Once the
    moving party has met its burden of establishing the absence of disputed material facts,
    then the non-moving party must set forth specific facts, not conclusory statements or
    bare assertions, to defeat the motion. Pure Gold, Inc. v. Syntex (U.S.A.), Inc., 
    739 F.2d 624
    , 626-27 (Fed. Cir. 1984). “A genuine issue of material fact arises when the
    nonmovant presents sufficient evidence upon which a reasonable fact finder, drawing
    the requisite inferences and applying the applicable evidentiary standard, could decide
    the issue in favor of the nonmovant.” C. Sanchez and Son, Inc. v. United States,
    
    6 F.3d 1539
    , 1541 (Fed. Cir. 1993) (citation omitted).
    II.    There Was a Constructive Partial Termination for Convenience
    The government moves for summary judgment, asserting that it has no
    obligation to pay Heartland for work that Heartland did not perform, or alternatively,
    that there was an actual or constructive partial termination for convenience of the
    relevant CLINs that excused the government from paying the firm-fixed price contract
    amounts for services not provided (gov’t mot. at 16-22). Heartland opposes the
    government’s motion, asserting that the government’s direction to stop performance of
    the CLINs was not issued by the contracting officer (app. resp. at 22-23) and that the
    termination for convenience clause in the contract does not apply to this task order
    because the task order is one for services rather than commercial items (app. resp.
    at 25-26). We hold that there was a constructive termination for convenience of the
    relevant CLINs.
    A. Constructive Partial Termination for Convenience of The Government
    On March 27, 2020, the contract specialist directed Heartland to stop
    performance on CLINs 1004, 1008, 1010, and 1011 (R4, tab 8a at 410). The contract
    7
    contains the commercial items provision, FAR 52.212-4 2 (R4, tab 2 at 193). The
    termination for convenience clause provides:
    (l) Termination for the Government’s convenience. The
    Government reserves the right to terminate this contract, or
    any part hereof, for its sole convenience. In the event of
    such termination, the Contractor shall immediately stop all
    work hereunder and shall immediately cause any and all of
    its suppliers and subcontractors to cease work. . . .
    FAR 52.212-4(l). Thus, subject to the authority issue discussed below, the
    government possessed the right to terminate Heartland’s performance of the relevant
    CLINs. The fact that the government did not cite the termination for convenience
    provision does not prevent us from treating this as a termination for convenience. See,
    e.g., R&R Sys. Sols., LLC, 
    ASBCA No. 61269
    , 
    19-1 BCA ¶ 37,269
     at 181,359.
    B. The Contract Specialist’s Lack of Authority Makes This a Constructive
    Partial Termination
    Heartland asserts, and the government does not contest, that the March 27,
    2020, direction to Heartland to suspend performance was issued by a contract
    specialist who was without authority to bind the government (app. resp. at 23; gov’t
    reply at 9). The government contends that this was a procedural defect that was cured
    by the contracting officer’s ratification, or that there was a constructive termination.
    We agree that there was a partial constructive termination for convenience.
    Heartland is correct that a termination can only be ordered by an authorized
    contracting officer. A lack of authority issue normally arises before the Board when a
    contractor follows a direction from a government official without contracting authority
    and then the government disclaims that direction. However, here, the government
    affirms the instruction, and Heartland followed the government’s direction. Had the
    direction come from an authorized representative, obviously Heartland would have
    been required to comply with the direction, and failure to follow the direction would
    constitute a breach of contract. With an invalid direction, had Heartland continued to
    perform the contract, it could have argued that the direction to discontinue
    performance was invalid, and attempted to bill for its performance. 3 Here, Heartland
    2
    FAR 52.212-4 was modified after the events of this appeal and is now titled
    “CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS
    AND COMMERCIAL SERVICES” (NOV 2021).
    3
    We make no findings as to whether Heartland would be entitled to payment for work
    performed following receipt of the March 27, 2020, direction to stop
    performance.
    8
    followed the direction and stopped performance. If we were to hold that the March 27,
    2020, direction was not a constructive termination for convenience, Heartland would
    have been in breach of its duty to perform CLINs 1004, 1008, 1010, and 1011.
    The government asserts that there was a termination for convenience (rather
    than a constructive termination) of the CLINs based upon the contracting officer’s
    ratification (gov’t mot. at 16-17). In this appeal, the distinction between actual and
    constructive termination for convenience is of no legal significance. That said, we do
    not see objective evidence of ratification by the contracting officer. In fact, when
    Heartland requested clarification as to whether the government’s direction to stop
    performance on the CLINs was a termination for convenience, the government never
    responded (R4, tab 11 at 461). On July 22, 2020, nearly four months after the initial
    direction to stop performance, the contracting officer affirmed that Heartland was to
    stop performance, but still did not indicate that the CLINs were terminated for
    convenience of the government (R4, tab 38a at 628-29). In addition, Heartland’s
    appeal is before the Board as a deemed denial because the contracting officer did not
    issue a final decision where he could have invoked a termination for convenience.
    The contracting officer had knowledge of the contract specialist’s instruction to
    stop performance but took no action to formally ratify the direction. “Ratification
    requires knowledge of material facts involving the unauthorized act and approval of
    the activity by one with authority.” Winter v. Cath-dr/Balti Joint Venture, 
    497 F.3d 1339
    , 1347 (Fed. Cir. 2007) (citing Harbert/Lummus Agrifuels Projects v. United
    States, 
    142 F.3d 1429
    , 1433-34 (Fed. Cir. 1998)). Ratification generally requires that
    the superior official have authority to ratify, knowledge of the subordinate’s
    unauthorized act, and then act to adopt the unauthorized action. Reliable Disposal
    Co., 
    ASBCA No. 40100
    , 
    91-2 BCA ¶ 23,895
     at 119,717. Here the contracting officer
    clearly had knowledge of the contract specialist’s action, and possessed authority, but
    we see no evidence that he acted to adopt the unauthorized action. Instead, he
    unsuccessfully attempted to negotiate a bilateral modification to descope the CLINs.
    To ratify the subordinate’s actions would have been to formally terminate the CLINs
    for convenience of the government, rather than allowing the task order to expire
    without clarifying the basis for the direction to suspend performance.
    Despite the contracting officer’s failure to terminate the CLINs for convenience
    of the government, the legal fiction of a constructive termination is clearly applicable.
    A “constructive termination of convenience [is] ‘a legal fiction which imposes the
    standard limitations of the termination clause upon a plaintiff even though the
    termination was never actually ordered by the contracting officer.’” Catherine
    Kurkjian, 
    ASBCA No. 61154
    , 
    20-1 BCA ¶ 37,594
     at 182,538 (aff’d sub nom. Kurkjian
    v. Sec’y of the Army, 
    2021 WL 3520624
     (Fed. Cir. Aug. 11, 2021), cert denied, 
    142 S.Ct. 1428
     (2022)) (quoting Kalvar Corp., Inc. v. United States, 
    543 F.2d 1298
    , 1306
    (Ct. Cl. 1976)).
    9
    [A] Government directive to end performance of the work
    will not be considered a breach but rather a convenience
    termination – if it could lawfully come under that clause –
    even though the contracting officer wrongly calls it a
    cancellation . . . or erroneously thinks that he can terminate
    the work on some other ground.
    United Technologies Corporation Pratt & Whitney Group, Government Engines and
    Space Propulsion, ASBCA Nos. 46880, 46881, 
    97-1 BCA ¶ 28,818
     at 143,802
    (quoting G.C. Casebolt Co. v. United States, 
    421 F.2d 710
    , 712 (Fed Cir. 1970)). In a
    constructive termination for convenience, the government’s actions can amount to a
    termination for convenience even in circumstances in which the government has
    stopped or curtailed a contractor’s performance for reasons that turn out to be
    questionable or invalid. See Maxima Corp. v. United States, 
    847 F.2d 1549
    , 1552-53
    (Fed. Cir. 1988). Here, the DoD COVID restrictions provided the contracting officer
    with a valid reason to direct Heartland to suspend performance; however, the
    contracting officer failed to actually terminate the CLIN, and instead attempted to
    negotiate a bilateral reduction in scope. We hold that CLINs 1004, 1008, 1010, and
    1011 were terminated for the convenience of the government.
    C. The Task Order Was for Commercial Services Under FAR Part 12
    Heartland’s other challenge to a constructive termination for convenience is its
    assertion that FAR 52.212-4(l) is inapplicable to the task order, because the task order
    was a contract for services (app. resp. at 25-26). Heartland premises this argument on
    the holding of the United States Court of Appeals for the Federal Circuit in JKB Sols.
    & Servs., LLC v. United States, 
    18 F.4th 704
     (Fed. Cir. 2021). In JKB the Federal
    Circuit held that the commercial items termination for convenience clause at FAR
    52.212-4 did not apply to the services contract at issue in that appeal. 
    Id. at 710-11
    .
    However, JKB does not control in this appeal for two reasons. First, the task order in
    this appeal is a commercial items contract, and therefore is subject to FAR 52.212-4.
    Second, even if the task order were a non-commercial services contract, we would
    read the applicable termination for convenience clause into the task order pursuant to
    the Christian doctrine. See, e.g., Fluor Intercontinental, Inc., ASBCA Nos. 62550,
    62672, 
    22-1 BCA ¶ 38,105
     at 185,101 n.4 (distinguishing JKB from a situation where,
    as here, the contractor has admitted that the contract was of the type covered by the
    contract’s termination for convenience clause and noting that the Christian doctrine
    would read the applicable termination for convenience clause into the contract).
    In JKB, the government did not dispute in its summary judgment motion JKB’s
    characterization of the contract as a non-commercial services contract, and not a
    commercial items contract. JKB, 18 F.4th at 710 n.2. The Federal Circuit then treated
    10
    the contract as a non-commercial services contract. Id. at 710. Here, the contract at
    issue is a commercial items contract. The solicitation for the IDIQ contract applicable
    to this appeal, and the contract, both explicitly state that it is a solicitation for
    commercial items (R4, tabs 81 at 1, 2 at 186). In addition, Heartland’s own complaint
    states that it was “a contract for commercial services” (compl. ¶ 8). Thus, Heartland’s
    own compliant establishes that FAR 52.212-4 is applicable to the task order and
    provides the government with the right to terminate the task order for convenience of
    the government. Moreover, Heartland provides no argument in support of its
    allegation that the task order was for non-commercial services and not a FAR Part 12
    commercial items acquisition (which includes commercial services) 4. Heartland
    simply asserts that “[t]here is no doubt that Task Order 3 in question is for services and
    not items” (app. resp. at 3).
    The Board is not bound by the parties’ characterization of the contract. The
    determination of a contract type is a matter of law, Maintenance Engineers v. United
    States, 
    749 F.2d 724
    , 726 n.3 (Fed. Cir. 1984), and we are not bound either by what
    the contract is called or by the label attached to it by the parties. Mason v. United
    States, 
    615 F.2d 1343
    , 1346 (Ct. Cl. 1980). However, even if we were to determine
    that Heartland’s task order was actually a non-commercial services contract, and not a
    commercial items contract, we would read the applicable termination for convenience
    clause into the contract pursuant to the Christian doctrine. That doctrine provides that
    a mandatory clause will be read into a government contract if it “expresses a
    significant or deeply ingrained strand of public procurement policy” JKB, 18 F.4th
    at 708 n.1 (citing Gen. Eng’g & Mach. Works v. O’Keefe, 
    991 F.2d 775
    , 779 (Fed. Cir.
    1993)). Binding precedent holds that the termination for convenience clause is such a
    provision. G. L. Christian & Associates v. United States, 
    312 F.2d 418
    , 426-27 (Ct.
    Cl. 1963). JKB does nothing to change the applicability of the Christian doctrine.
    Procedurally, JKB was on appeal to the Federal Circuit from a grant of summary
    judgment by the Court of Federal Claims. The Federal Circuit held that the
    commercial items termination for convenience provision did not apply, because “the
    government simply incorporated a FAR provision that, on its face, applies only to
    commercial items contracts.” JKB, 18 F.4th at 711. The court also recognized that the
    applicable termination for convenience clause could be read into the contract by the
    Christian doctrine. However, since the trial court had not considered this question in
    the first instance, the Federal Circuit remanded the question back to the trial court. Id.
    Here, it is clear that the subject contract was, indeed, a commercial items contract for
    services under FAR Part 12, and, as such, FAR 52.212-4(l) is applicable to the task
    order. Accordingly, Heartland’s arguments must fail.
    4
    FAR 12.102 Applicability reads: (a) This part shall be used for the acquisition of
    supplies or services that meet the definitions of “commercial product” or
    “commercial service” at 2.101.
    11
    III.   A Partial Termination for Convenience of A Fixed-Price Contract Line
    Item Is Treated Like a Cost-Type Line Item
    The government contends that its initial billing instructions, which directed
    Heartland to bill 1/12th of the firm-fixed CLIN amount each month, regardless of the
    work actually performed during that month, converted the task order into severable
    units accepted and received by the government such that the government bears no
    additional financial liability to Heartland (gov’t mot. at 15-16; gov’t reply at 17-18).
    Heartland contends that the modification of the billing procedure did not account for
    its costs incurred (app. resp. at 23-25, citing R4, tab 45 at 685).
    The government’s argument that the billing instructions converted the contract
    into severable units ignores its direction to Heartland to suspend performance. If, as
    we have found above, the direction was a constructive termination for convenience,
    Heartland is entitled to termination costs. If the direction was not a constructive
    termination for convenience, it would be a unilateral change and Heartland would be
    entitled to breach of contract damages. Pursuant to the termination for convenience
    clause, Heartland is entitled to
    . . . be paid a percentage of the contract price reflecting the
    percentage of the work performed prior to the notice of
    termination, plus reasonable charges the Contractor can
    demonstrate to the satisfaction of the Government using its
    standard record keeping system, have resulted from the
    termination.
    FAR 52.212-4(l). “The termination for convenience of a fixed-price contract or line
    item has the ‘general effect of’ converting the contract or line item into a cost-
    reimbursement contract.” Phoenix Data Solutions f/k/a Aetna Government Health
    Plans, 
    ASBCA No. 60207
    , 
    18-1 BCA ¶ 37,164
     at 180,917 (citing New York
    Shipbuilding Co., A Division of Merritt-Chapman & Scott Corp., 
    ASBCA No. 15443
    ,
    
    73-1 BCA ¶ 9852
     at 46,019).
    To the extent that Heartland contends that its monthly billing of 1/12th of the
    CLIN amount did “not account for the costs already incurred by Heartland in being
    prepared to deliver the services required by the existing scope of work within the
    period of performance” (R4, tab 45 at 685), it will be able seek reimbursement
    pursuant to the termination for convenience, with its costs being reviewed essentially
    as if the relevant CLINs were cost-type CLINs. However, this cost-type analysis
    conceivably could penalize Heartland if it performed less work on a CLIN than has
    already been compensated (that is, less than 7/12ths of the CLIN (September –
    March)). In that event, Heartland may have been overcompensated and may owe
    12
    money to the government. Heartland has not submitted a termination settlement
    proposal, and we make no findings of fact regarding the costs it is entitled to claim.
    CONCLUSION
    For the reasons stated above, we grant the government’s motion for summary
    judgment, in part, and hold that there was a constructive termination for convenience
    of the relevant CLINs. However, this does not resolve the appeal. Heartland’s
    entitlement to further compensation, if any, will be addressed in further proceedings.
    Dated: September 12, 2022
    DAVID D’ALESSANDRIS
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    RICHARD SHACKLEFORD                                OWEN C. WILSON
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    13
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62979
    , Appeal of Heartland
    Energy Partners LLC, rendered in conformance with the Board’s Charter.
    Dated: September 12, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    14