Ace Electronics Defense Systems ( 2022 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                   )
    )
    Ace Electronics Defense Systems               )     
    ASBCA No. 63224
    )
    Under Contract No. N63394-20-D-0002           )
    APPEARANCE FOR THE APPELLANT:                       Adam D. Bruski, Esq.
    Warner Norcross + Judd LLP
    Midland, MI
    APPEARANCES FOR THE GOVERNMENT:                     Craig D. Jensen, Esq.
    Navy Chief Trial Attorney
    Andrea S. Maglasang-Miller, Esq.
    Matthew B. Hawkins, Esq.
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE MELNICK DISMISSING THE APPEAL
    FOR FAILURE TO STATE A CLAIM
    Ace Electronics Defense Systems, LLC (Ace), seeks compensation due to
    increased costs it experienced performing a firm-fixed price contract with the Naval
    Surface Warfare Center (government). Ace’s complaint fails to allege facts that support
    any recovery under the contract and therefore we dismiss the appeal for failure to state a
    claim upon which relief can be granted.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    The government issued a delivery order to Ace under the indefinite-delivery,
    indefinite-quantity contract identified above for various assemblies and parts associated
    with cruise missiles (compl. ¶ 2; R4, tab 1 at 221, tab 3). The delivery order contained
    numerous firm-fixed price line items for a total price of $11,700,479 (R4, tab 3).
    Ace obtains some elements for the ordered components from another vendor
    (compl. ¶ 3). Since 2020, the other vendor’s prices for the materials associated with two
    line items have risen substantially. The vendor has given little insight into the cause
    other than to assert they are related to the COVID-19 pandemic. (Compl. ¶ 4) Ace is
    unable to obtain the items from another vendor. It has submitted several requests for cost
    adjustment to the government reflecting the vendor’s quoted prices, which have been
    denied. The cost increases have substantially altered the economics of the contract and
    put financial stress on Ace. (Compl. ¶¶ 5-6, 13) The increase is unlike anything Ace has
    ever experienced (compl. ¶ 11).
    On July 2, 2020, the Office of the Undersecretary of Defense for Acquisition and
    Sustainment issued a memo entitled “Guidance for Assessment of Other COVID-19
    Related Impacts and Costs.” In part the memo states the following:
    The COVID-19 pandemic has presented historic and
    unprecedented challenges for the Department, its mission, and
    its people. These challenges require us to use all of our
    experience and skill to find innovative solutions to both
    protect Government interests and ensure the continued health
    of the Defense Industrial Base to support our mission.
    Unlike contractors performing under cost-type contracts,
    contractors under fixed-price contracts generally must bear
    the risk of cost increases, including those due to COVID-19
    (e.g., costs associated with PPE, social distancing, and
    supplier delays and inefficiencies). However, Contracting
    Officers are granted discretion, subject to the availability of
    funds, to modify contracts (e.g., under FAR 52.243-1,
    Changes Fixed Price, and its applicable alternatives) to reflect
    changes to the Government’s needs as a result of COVID-19.
    (Compl. ¶ 12)
    Ace has incurred $113,993.46 in additional costs related to the two line items due
    to the vendor’s increased pricing (compl. ¶ 16). Ace alleges breach of contract by the
    government for failure to adjust the contract price (compl. at 2). “Ace believes that under
    the circumstances, it is appropriate to apply the Fixed Cost with Economic Price
    Adjustment provisions of the Federal Acquisition Regulation to this Contract. FAR
    16.203 and/or changes provisions of FAR 43.205 and 53.243-1.” (Compl. ¶ 15)
    Ace submitted a certified claim to the contracting officer dated February 9, 2022
    (R4, tab 4). 1 The claim’s allegations are substantially identical to the complaint. The
    claim was denied on February 24, 2022 (compl. ¶ 8). Ace has appealed and seeks
    $113,993.46 (compl. at 4).
    The government moves to dismiss the complaint on the ground that it fails to state
    a claim upon which relief may be granted.
    1
    Ace alleges it submitted the claim on February 2, 2022 (compl. ¶ 7). The discrepancy is
    irrelevant to this decision.
    2
    DECISION
    A complaint is subject to dismissal for failure to state a claim when it fails to
    “allege facts ‘plausibly suggesting (not merely consistent with)’ a showing of entitlement
    to relief.” Cary v. United States, 
    552 F.3d 1373
    , 1376 (Fed. Cir. 2009) (quoting Bell
    Atlantic Corp. v. Twombly, 
    550 U.S. 544
    , 557 (2007)). The allegations must “raise a
    right to relief above the speculative level” and state a claim “that is plausible on its face.”
    
    Id.
     We “must accept all well-pleaded facts as true and view them in the light most
    favorable to the non-moving party.” Rack Room Shoes v. United States, 
    718 F.3d 1370
    ,
    1376 (Fed. Cir. 2013) (quoting United States v. Ford Motor Co., 
    497 F.3d 1331
    , 1336
    (Fed. Cir. 2007)); see also Parwan Grp., 
    ASBCA No. 60657
    , 
    18-1 BCA ¶ 37,082
    at 180,498 (quoting Kellogg Brown & Root Servs., Inc. v. United States, 
    728 F.3d 1348
    ,
    1365 (Fed. Cir. 2013)). However, “[t]hreadbare recitals of the elements of a cause of
    action, supported by mere conclusory statements, do not suffice.” Rack Room Shoes, 718
    F.3d at 1376 (quoting Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009)). We are not bound to
    Ace’s legal conclusions. 
    Id.
     The motion will be granted when the facts asserted do not
    entitle the claimant to a legal remedy. Lindsay v. United States, 
    295 F.3d 1252
    , 1257
    (Fed. Cir. 2002); Arab Shah Constr. Co., 
    ASBCA No. 61565
    , 
    19-1 BCA ¶ 37,266
    at 181,348. In addition to the complaint, we may consider “matters incorporated by
    reference or integral to the claim, items subject to judicial notice, [and] matters of public
    record.” A&D Auto Sales, Inc. v. United States, 
    748 F.3d 1142
    , 1147 (Fed. Cir. 2014)
    (quoting 5B CHARLES ALAN WRIGHT & ARTHUR R. MILLER, FEDERAL PRACTICE AND
    PROCEDURE § 1357 (3d ed. 2004)). Because interpretation of the parties’ contract rights
    is integral to the claim, and that is a question of law, NOAA Md., LLC v. Adm’r of the
    Gen. Servs. Admin., 
    997 F.3d 1159
    , 1165 (Fed. Cir. 2021), we consider the contract’s
    terms in determining whether the complaint asserts a claim upon which relief may be
    granted. See Parwan Grp., 
    18-1 BCA ¶ 37,082
     at 180,498.
    The complaint concedes that the contract is fixed price (compl. ¶ 10). “Under a
    firm-fixed price arrangement, [Ace] assumed ‘maximum risk and full responsibility for
    all costs and resulting profit or loss.’” Parsons Gov’t Servs., Inc., 
    ASBCA No. 61630
    ,
    
    20-1 BCA ¶ 37,655
     at 182,815 (quoting FAR 16.202-1). Thus, “[t]he price was ‘not
    subject to any adjustment on the basis of [Ace’s] cost experience in performing the
    contract.’” Id.; see also Zafer Taahhut Insaat ve Ticaret A.S. v. United States, 
    833 F.3d 1356
    , 1361 (Fed. Cir. 2016)). The essence of Ace’s complaint is that it encountered
    higher prices from its vendor for certain components than it expected due to the COVID
    pandemic. However, it has not identified any clause of the contract that would shift the
    risk of such costs to the government. See Pernix Serka Joint Venture v. Dept. of State,
    3
    CBCA No. 5683, 
    20-1 BCA ¶ 37,589
     at 182,522-23 (rejecting a claim under a fixed price
    contract for increased performance costs caused by an unforeseen epidemic). 2
    Ace quotes the July 2, 2020, memo from the Office of the Undersecretary of
    Defense for Acquisition and Sustainment but does not allege how it dictates entitlement
    to recover. We agree with the government that the memorandum is not a part of the
    contract or delivery order and nothing in it governs the parties’ rights under those
    instruments. Moreover, after noting the challenges that the pandemic posed to the
    government’s interests and the health of the defense industry, the memo observes that
    contractors performing fixed price contracts generally must bear the risk of cost increases
    due to the pandemic. It grants discretion to contracting officers to modify contracts to
    reflect changes to the government’s needs resulting from the pandemic. (Compl. ¶ 12)
    Ace has not alleged that this contract was modified by the contracting officer to reflect
    any changes to the government’s needs. 3 Ace’s suggestion that the memo imposes a
    contractual obligation upon the government to grant a price adjustment because Ace
    experienced higher costs due to the pandemic is not correct.
    Ace’s reliance in the complaint upon Federal Acquisition Regulation (FAR)
    16.203, 43.205 and 53.243-1 is also misplaced.
    2
    Ace does not allege that the increased costs have made performance commercially
    impracticable, which might entitle it to an equitable adjustment if proven.
    Raytheon Co. v. White, 
    305 F.3d 1354
    , 1367 (Fed. Cir. 2002). That would require
    it to allege extraordinarily excessive or unreasonable costs or burdens that make
    performance commercially senseless. 
    Id.
     at 1367-68 (citing examples of
    commercial impracticability, such as contract performance that would have
    required 17 years at a cost of $400 million rather than 720 days and $16.92
    million, or a seven-month performance period that turned into an unsuccessful
    four-year period with a 148 percent cost overrun); see also Parwan, 
    18-1 BCA ¶ 37,082
     at 180,496 (explaining that simply showing economic hardship is
    insufficient). It would also require Ace to not have assumed the risk of the event
    causing the impracticability. Raytheon, 
    305 F.3d at 1367
    . Here, Ace does not
    even allege that its $113,993.46 in higher costs have caused it to suffer a loss on
    this $11,700,479 delivery order.
    3
    Additionally, a subsequent memo from the same source, dated May 25, 2022, clarifies
    that “[s]ince cost impacts due to unanticipated inflation are not a result of a
    contracting officer-directed change, [contracting officers] should not agree to
    contractor [equitable adjustments] submitted in response to changed economic
    conditions” (gov’t reply ex. 1, at 2, available at
    https://www.acq.osd.mil/dpap/policy/policyvault/USA000999-22-DPC.pdf).
    4
    FAR 16.203 describes the circumstances for awarding a fixed price contract with
    economic price adjustment, which would provide for upward or downward revision of
    the price upon the occurrence of specified contingencies. Contracting officers are
    permitted to use this type of contract when there is serious doubt concerning the stability
    of market or labor conditions that will exist during an extended period of performance
    and contingencies that would otherwise be included in the contract price can be identified
    and covered separately in the contract. FAR 16.203-2; see also FAR 16.203-4. Such a
    contract shall not be used unless the contracting officer determines that it is necessary
    either to protect the contractor and the government against significant fluctuations in
    labor or material costs or to provide for contract price adjustment in the event of changes
    in the contractor’s established prices. FAR 16.203-3.
    This contract and delivery order did not contain a price adjustment clause. Ace
    does not allege it was somehow misled at the time of award to believe that the contract
    would receive such an adjustment should the prices of its materials increase.
    Nevertheless, Ace’s opposition to the motion to dismiss demands that the Board rewrite
    the contract now to include such a clause because of the “unprecedented circumstances
    experienced during the execution phase of this project,” which we presume means the
    COVID pandemic. Ace contends that the government’s refusal to incorporate the clause
    now and its insistence upon performance at the agreed upon price is arbitrary and
    capricious. Ace cites no authority for the proposition that a fixed price contract must be
    revised after the fact to include a price adjustment clause when the contractor experiences
    unexpected price increases due to a pandemic. Such a ruling would turn on its head
    Ace’s assumption of the maximum risk and full responsibility for all costs and resulting
    profit or loss.
    FAR 43.205 provides instructions for the inclusion of a Changes Clause in
    contracts. This contract incorporated FAR 52.243-1, CHANGES-FIXED PRICE (AUG
    1987) (R4, tab 1 at 243). That clause permits the contracting officer to make certain
    written changes within the general scope of the contract and provides for an equitable
    adjustment for increases or decreases in the cost of, or time required for, performance
    caused by the change. The complaint lacks any allegation that written changes by the
    contracting officer caused Ace’s alleged cost increases. Instead, Ace alleges it incurred
    increased costs from price increases imposed upon it by its vendor (compl. ¶¶ 4, 11).
    Ace’s further contention in its opposition, that the government’s insistence that it
    perform constitutes a constructive change given its vendor’s price increases, is also
    unsupported by the complaint’s allegations. To prevail upon a constructive change a
    contractor must “show (1) that it performed work beyond the contract requirements, and
    (2) that the additional work was ordered, expressly or impliedly, by the government.”
    Bell/Heery v. United States, 
    739 F.3d 1324
    , 1335 (Fed. Cir. 2014); Kellogg Brown &
    Root Servs., ASBCA Nos. 59385, 59744, 
    20-1 BCA ¶ 37,656
     at 182,829. The complaint
    5
    fails to plausibly suggest any facts that could establish either of those elements. That the
    government continued to expect the contract’s prescribed performance from Ace at the
    agreed upon price is not an order to perform additional work. Ace’s additional
    suggestion that its allegations support a cardinal change, which requires a demonstration
    that the government effected an alteration in work requiring performance materially
    different from what was bargained for, fails for the same reasons. See U.S. Aeroteam,
    Inc. v. United States, No. 2021-2272, 
    2022 WL 2431626
    , at *3 (Fed. Cir. July 5, 2022).
    Ace’s final argument in its effort to salvage its complaint is to suggest that by
    failing to recognize the changed environment in which the contract was to be performed,
    and compensating Ace for its higher costs, the government’s action constitutes a breach
    of the contract’s duty of good faith and fair dealing. 4 The duty of good faith and fair
    dealing prohibits “interference with or failure to cooperate in the other party’s
    performance.” LaBatte v. United States, 
    899 F.3d 1373
    , 1379 (Fed. Cir. 2018) (quoting
    RESTATEMENT (SECOND) OF CONTRACTS § 205 cmt. d (1981)). Ace emphasizes the
    observation in Centex Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005), that
    parties are obligated “not to act so as to destroy the reasonable expectations of the other
    party regarding the fruits of the contract.” However, “a specific promise must be
    undermined for the implied duty to be violated.” Dobyns v. United States, 
    915 F.3d 733
    ,
    739 (Fed. Cir. 2019). It “must be ‘keyed to the obligations and opportunities established
    in the contract,’ so as to not fundamentally alter the parties’ intended allocation of
    burdens and benefits associated with the contract.” 
    Id.
     (quoting Lakeshore Eng’g. Servs.,
    Inc. v. United States, 
    748 F.3d 1341
    , 1349 (Fed. Cir. 2014)). The complaint does not
    contain any allegations that plausibly suggest that the government’s refusal to relieve Ace
    from the firm-fixed price to which Ace committed itself undermines any specific promise
    or destroys Ace’s reasonable expectations regarding the fruits of the contract. See
    Lakeshore Eng’g. Servs., 748 F.3d at 1349 (holding that given the payment terms agreed
    upon by the parties, the government’s refusal to pay more to account for cost increases
    did not destroy the contractor’s reasonable expectations under the contract).
    4
    We disagree with the government’s contention in its reply that this argument flows from
    a separate set of operative facts than those set out in Ace’s certified claim.
    Accordingly, we deny its request that the argument be dismissed for lack of
    jurisdiction. See Wilwood Eng. Inc., ASBCA Nos. 62773, 62774, 
    22-1 BCA ¶ 38,116
     at 185,144-45.
    6
    CONCLUSION
    Ace has failed to state a claim upon which relief can be granted. The appeal is
    dismissed with prejudice.
    Dated: October 5, 2022
    MARK A. MELNICK
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    RICHARD SHACKLEFORD                               J REID PROUTY
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 63224
    , Appeal of Ace
    Electronics Defense Systems, rendered in conformance with the Board’s Charter.
    Dated: October 5, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    7