Granite Construction Company ( 2020 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    Granite Construction Company                 )      ASBCA No. 62281
    )
    Under Contract No. W9126G-15-C-0037          )
    APPEARANCES FOR THE APPELLANT:                    Michael A. Branca, Esq.
    Joshua Morehouse, Esq.
    Peckar & Abramson, P.C.
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                   Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Clark Bartee, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, Galveston
    OPINION BY ADMINISTRATIVE JUDGE CLARKE
    ON CROSS-MOTIONS FOR SUMMARY JUDGMENT
    Although we have before us cross-motions for summary judgment, because there
    are disputed material facts, we ultimately grant only partial summary judgment. This
    case involves the proper interpretation of the Federal Acquisition Regulation (FAR)
    52.249-10, DEFAULT (APR 1984), and FAR 52.242-14, SUSPENSION OF WORK
    (APR 1984) and whether the monthly anticipated adverse weather delay in Specification
    SECTION 01 10 00.00 45, 1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE
    WEATHER may be subtracted from a suspension period. We have jurisdiction pursuant
    to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. We find that the
    adverse weather delay may not be subtracted from a suspension period and grant partial
    summary judgment to Granite.
    STATEMENT OF FACTS (SOF) FOR THE PURPOSES OF THE MOTION
    For purposes of resolving the pending cross-motions for summary judgment, the
    parties entered into a joint stipulation of twenty-five numbered paragraphs which is
    incorporated below.
    1. On August 31, 2015, Granite Construction Company (Granite) was awarded
    Contract No. W9126G-15-C-0037 by the United States Army Corps of Engineers (COE)
    to perform the construction of new outlet structures and cutoff walls at the Addicks and
    Barker dams as a portion of the Buffalo Bayou and Tributaries federal flood control
    project in Houston, Texas (R4, tab 1).
    2. On September 29, 2015, the COE issued and Granite acknowledged a Notice to
    Proceed to Granite that established a required completion date of the contract of May 31,
    2019.
    3. At all times relevant to this action, the COE exercised exclusive control over
    the operation of Addicks and Barker dams.
    4. Under Section 01 00 10, part 1.4 of the contract, under normal conditions the
    combined release of water from the Addicks and Barker dams was to be limited to 2,000
    cubic feet per second (CFS) as measured downstream at the Piney Point gauging station
    (R4, tab 1 at 2628-29).
    5. Section 00 31 33, paragraph 2.3 of the contract similarly provides that the
    combined releases cannot exceed 2,000 CFS under normal operating conditions and that
    the maximum discharge from one reservoir of 2,000 CFS requires the other to be closed.
    6. On August 25, 2017, Hurricane Harvey made landfall on the coast of Texas. In
    the following days, Hurricane Harvey brought rain as well as flooding to the Houston,
    Texas, Metropolitan Area, which includes the contract project site at the Addicks and
    Barker Dams.
    7. After the landfall of Hurricane Harvey, on or before August 28, 2017, the COE
    began releasing water from the Addicks and Barker dams, with the combined flow rate
    increasing to over 4,000 CFS.
    8. The COE continued to increase the combined flows of water from the Addicks
    and Barker dams through August 29, 2017.
    9. By August 29, 2017, the combined discharges from Addicks and Barker dams
    into the Buffalo Bayou, in conjunction with flows entering Buffalo Bayou downstream of
    the dams, caused the measured flow at the Piney Point gauging station to be in excess of
    10,000 CFS.
    10. By letter dated September 5, 2017, the COE issued Serial Letter No. C-0039
    to Granite, which directed Granite to “SUSPEND WORK” on Construction of the New
    Outlet Structure at the Addicks Dam site; Construction of Cutoff Walls and New Outlet
    Structure at the Barker Dam site; and Construction of Cutoff Walls at the Noble Road site
    of Barker Dam, both retroactively to August 28, 2017 and prospectively through
    October 15, 2017, pursuant to FAR 52.242-14, SUSPENSION OF WORK (APR 1984)
    (R4, tab 3).
    2
    11. The suspension of work outlined in Serial Letter No. C-0039 did not apply to
    contract requirements to assist in emergency repairs of damage to the dams; repairs to
    any part of the temporary or permanent work performed by Granite that is damaged by
    the flood from Hurricane Harvey; construction activities related to site recovery and
    restoration which could be performed safely, as conditions improved; and activities that
    were not affected by the flooding in and around the dams.
    12. The total period of suspension ordered by the contracting officer (CO) was
    49 calendar days, from August 28, 2017 through October 15, 2017.
    13. After the suspension expired, Granite and the COE executed Modification
    No. A00030, which extended the Contract time by 49 calendar days. In part,
    Modification No. A00030 states that it was issued “for delays from the suspension of
    work due to Hurricane Harvey during the period August 28, 2017 thru October 15, 2017”
    (R4, tab 4).
    14. Modification No. A00030 states that it is “not a release of claims by the
    Contractor and does not preclude the Contractor from pursuing any claim for monetary
    compensation from events occurring during the timeframe of the days covered in this
    modification” (R4, tab 4 at 003547).
    15. On June 14, 2018, Granite submitted a Request for Equitable Adjustment
    seeking $1,250,474 and five (5) calendar days as compensation for the additional costs
    that it had incurred as a result of the suspension of work to the extent directed by the
    COE’s September 5, 2017, letter.
    16. On November 30, 2018, the COE and Granite executed bilateral Modification
    No. P00008 for $961,008 and four (4) calendar days as compensation to Granite for
    additional work performed and for its time-related costs associated with 30 of the 49 days
    for which the work was suspended. The modification referenced Hurricane Harvey and
    stated in part that it included “cost associated with the direction to partially suspend work
    on September 5, 2017 due to unprecedented rain and flooding caused by Hurricane
    Harvey as well as site reclamation activities required to repair the site to pre-flood
    conditions.” (R4, tab 5)
    17. Modification No. P00008 included an express reservation of rights for Granite
    to pursue compensation for the remaining 19 days of time-related costs in the amount of
    $233,779.
    18. Modification No. P00008 excluded compensation for Granite’s time-related
    costs associated with the remaining 19 days requested by Granite in part due to contract
    Section 01 10 00.00 45, part 1.4 which provides a chart of monthly anticipated adverse
    weather delay days.
    3
    19. Contract Section 01 10 00.00 45, paragraph 1.4 is titled “TIME EXTENSIONS
    FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989) (ER 415-1-15).”
    20. Paragraph 1.4.2, “Baseline for Monthly Weather Time Evaluations” requires
    the contractor’s progress schedule to reflect these anticipated adverse weather delays in
    all weather dependent activities.
    21. The exclusion of compensation for 19 days was based in part upon the
    anticipated adverse weather days identified in paragraph 1.4.2 of Section 01 10 00.00 45.
    22. By letter dated May 23, 2019, Granite submitted a certified claim under the
    contract and requested a final decision of the CO. Granite’s claim sought $233,779, plus
    interest, which represented the time-related costs that Granite alleged it had incurred as a
    result of an express suspension of the work by the COE. (R4, tab 6)
    23. By letter dated August 30, 2019, the CO issued a final decision denying
    Granite’s claim (R4, tab 8).
    24. To date, the COE has not compensated Granite for its time-related costs
    associated with the remaining 19 days of claimed delay.
    25. On November 26, 2019, Granite filed its Notice of Appeal to the COE’s
    denial of its claim with the Armed Services Board of Contract Appeals (ASBCA).
    The following clauses and specification are incorporated into the contract and
    relevant to our decision:
    26. FAR 52.242-14, SUSPENSION OF WORK (APR 1984) states in pertinent
    part:
    (a) The CO may order the Contractor, in writing, to
    suspend, delay, or interrupt all or any part of the work of this
    contract for the period of time that the CO determines
    appropriate for the convenience of the Government.
    (b) If the performance of all or any part of the work is, for
    an unreasonable period of time, suspended, delayed, or
    interrupted (1) by an act of the CO in the administration of
    this contract, or (2) by the CO’s failure to act within the time
    specified in this contract (or within a reasonable time if not
    specified), an adjustment shall be made for any increase in the
    cost of performance of this contract (excluding profit)
    4
    necessarily caused by the unreasonable suspension, delay, or
    interruption, and the contract modified in writing accordingly.
    However, no adjustment shall be made under this clause
    for any suspension, delay, or interruption to the extent that
    performance would have been so suspended, delayed, or
    interrupted by any other cause, including the fault or
    negligence of the Contractor, or for which an equitable
    adjustment is provided for or excluded under any other term
    or condition of this contract.
    (c) A claim under this clause shall not be allowed-
    (1) For any costs incurred more than 20 days before
    the Contractor shall have notified the CO in writing of the act
    or failure to act involved (but this requirement shall not apply
    as to a claim resulting from a suspension order); and
    (2) Unless the claim, in an amount stated, is asserted
    in writing as soon as practicable after the termination of the
    suspension, delay, or interruption, but not later than the date
    of final payment under the contract.
    (R4, tab 1 at 2575)
    27. FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION)
    (APR 1984):
    (a) If the Contractor refuses or fails to prosecute the
    work or any separable part, with the diligence that will insure
    its completion within the time specified in this contract
    including any extension, or fails to complete the work within
    this time, the Government may, by written notice to the
    Contractor, terminate the right to proceed with the work (or
    the separable part of the work) that has been delayed. In this
    event, the Government may take over the work and complete
    it by contract or otherwise, and may take possession of and
    use any materials, appliances, and plant on the work site
    necessary for completing the work. The Contractor and its
    sureties shall be liable for any damage to the Government
    resulting from the Contractor’s refusal or failure to complete
    the work within the specified time, whether or not the
    Contractor’s right to proceed with the work is terminated.
    5
    This liability includes any increased costs incurred by the
    Government in completing the work.
    (b) The Contractor’s right to proceed shall not be
    terminated nor the Contractor charged with damages under
    this clause, if-
    (1) The delay in completing the work arises from
    unforeseeable causes beyond the control and without the fault
    or negligence of the Contractor. Examples of such causes
    include-
    (i) Acts of God or of the public enemy,
    (ii) Acts of the Government in either its sovereign or
    contractual capacity,
    (iii) Acts of another Contractor in the performance
    of a contract with the Government,
    (iv) Fires,
    (v) Floods,
    (vi) Epidemics,
    (vii) Quarantine restrictions,
    (viii) Strikes,
    (ix) Freight embargoes,
    (x) Unusually severe weather, or
    (xi) Delays of subcontractors or suppliers at any tier
    arising from unforeseeable causes beyond the control and
    without the fault or negligence of both the Contractor and the
    subcontractors or suppliers; and
    (2) The Contractor, within 10 days from the beginning of
    any delay (unless extended by the CO), notifies the CO in
    writing of the causes of delay. The Contracting Officer shall
    ascertain the facts and the extent of delay. If, in the judgment
    6
    of the Contracting Officer, the findings of fact warrant such
    action, the time for completing the work shall be extended.
    The findings of the CO shall be final and conclusive on the
    parties, but subject to appeal under the Disputes clause.
    (c) If, after termination of the Contractor’s right to
    proceed, it is determined that the Contractor was not in
    default, or that the delay was excusable, the rights and
    obligations of the parties will be the same as if the
    termination had been issued for the convenience of the
    Government.
    (d) The rights and remedies of the Government in this
    clause are in addition to any other rights and remedies
    provided by law or under this contract.
    (R4, tab 1 at 2575)
    28. SECTION 01 10 00.00 45 NON-REGULATED SPECIAL CONTRACT
    REQUIREMENTS:
    1.4 TIME EXTENSIONS FOR UNUSUALLY
    SEVERE WEATHER (31 OCT 1989) (ER 415-1-15)
    1.4.1 General
    This provision specifies the procedure for
    determination of time extensions for unusually severe weather
    in accordance with the CONTRACT CLAUSE entitled
    DEFAULT (FIXED-PRICE CONSTRUCTION). For the
    Contracting Officer to award a time extension under this
    CLAUSE, the following conditions shall be satisfied.
    1.4.1.1 Unusually Severe Weather
    The weather experienced at the project site during the
    Contract period must be found to be unusually severe, that is,
    more severe than the adverse weather anticipated for the
    project location during any given month.
    7
    1.4.1.2 Completion Delay
    The unusually severe weather must actually cause a
    delay to the completion of the project. The delay must be
    beyond the control and without the fault or negligence of the
    Contractor.
    1.4.2 Baseline for Monthly Weather Time Evaluations
    The following schedule of monthly anticipated adverse
    weather delays is based on National Oceanic and
    Atmospheric Administration (NOAA) or similar data for the
    project location and will constitute the base line for monthly
    weather time evaluations. The Contractor’s progress
    schedule must reflect these anticipated adverse weather
    delays in all weather dependent activities.
    MONTHLY ANTICIPATED ADVERSE WEATHER
    DELAY
    WORK DAYS BASED ON 7 DAY WORK WEEK
    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
    DEC
    (11) (8) (6) (6) (7) (9) (7) (10) (13) (10) (8)
    (10)
    1.4.3 Record
    Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout
    the contract, the contractor will record on the daily Contractor Quality Control (CQC)
    report, the occurrence of adverse weather and resultant impact to normally scheduled
    work. Actual adverse weather delay days must prevent work on critical activities for
    50 percent or more of the contractor’s scheduled work day. The number of actual
    adverse weather delay days shall include days impacted by actual adverse weather (even
    if adverse weather occurred in previous month), be calculated chronologically from the
    first to the last day of each month, and be recorded as full days. If the number of actual
    adverse weather delay days exceeds the number of days anticipated in Subparagraph:
    Baseline for Monthly Weather Time Evaluations above, the Contracting Officer will
    convert any qualifying delays to calendar days, giving full consideration for equivalent
    fair weather work days, and issue a modification in accordance with the CONTRACT
    CLAUSE entitled DEFAULT (FIXED PRICE CONSTRUCTION). (R4, tab 1
    at 5, 2633)
    8
    DECISION
    Positions of the Parties
    Granite contends that the COE admitted that its 49 day suspension was
    unreasonable, “[f]irst, by compensating Granite for 30 of the 49 days of the suspension,
    the Government has already acknowledged that the suspension was for an unreasonable
    period of time” (app. mot. at 9; see also app. mot at 3-4). The Suspension Clause
    authorizes an adjustment in the cost of performance if the suspension is for an
    unreasonable period of time. FAR 52.242-14(b). Granite contends that the 49 day
    suspension was not caused by Hurricane Harvey, “[t]he 49-day duration of the delay was
    never based on actual adverse weather. Rather, it was based on the Government’s release
    of waters from the Addicks and Barker dams and the associated flooding of the work
    site” (app. opp’n at 3; see also app. opp’n at 4, 6-7, 9). Granite contends, “[t]he Adverse
    Weather Provision has no interrelationship with the Suspension Clause, i.e., the
    anticipated adverse weather days contained in the Adverse Weather Provision are not
    actual delays and cannot be an ‘other cause’ of delay under the Suspension Clause. The
    CO was wrong to rely on the Adverse Weather Provision to deny Granite compensation
    for 19 days of the 49-day directed suspension” (app. mot. at 8-9). Granite argues
    “Contract Specification 01 10 00.00 45 (the ‘Adverse Weather Provision’), and
    particularly Paragraph 1.4 of that Specification, provided the Government with no basis
    to deny Granite compensation for the full 49-day suspension period. (R4 tab 6, 003556)
    The Adverse Weather Provision only applies to the determination of time extensions for
    adverse weather under ‘the CONTRACT CLAUSE entitled DEFAULT [FIXED PRICE]’
    (FAR 52.249-10, or the ‘Default Clause’). Because the Suspension Notice was issued
    under the Suspension Clause, the Default Clause (and thus the Adverse Weather
    Provision) was irrelevant to determining whether Granite would receive compensation for
    the Government’s directed suspension.” (App. mot. at 4) “The only disputed issue is
    whether the 19 anticipated adverse weather days identified in the Adverse Weather
    Provision for the period of the suspension are an ‘other cause’ of delay” (app. mot. at 6).
    Concerning the COE’s position, the quantum amount claimed by Granite is not in
    dispute. By letter dated September 3, 2020, the COE stipulated that the quantum amount
    of $233,779 is accurate (ASBCA Case File).
    The COE argues that its decision to compensate Granite for 30 of the 49 day
    suspension was “equitable” and not an admission that the suspension was unreasonable,
    “Granite received a time extension for the full period of the delay, and USACE further
    agreed as an equitable matter to compensate Granite for a portion of that period even
    though the delay had been otherwise reasonable in duration” (gov’t opp’n at 3; gov’t mot.
    at 10). The COE contends the suspension was caused by Hurricane Harvey, “[i]t is clear
    from the stipulated facts and administrative record that Granite’s performance under the
    contract was impacted by the ‘unprecedented rain and flooding’ of Hurricane Harvey,
    9
    and Granite subsequently acknowledged and agreed to this when it executed
    Modifications Nos. A00030 and P00008” (gov’t opp’n at 3). The COE points out,
    “Granite’s position overlooks the important fact that when it agreed to the 49 days of
    time extension under Modification No. A00030, it did so pursuant to the Adverse
    Weather Clause of the contract (gov’t opp’n at 5). The COE argues that “[o]ver the 49
    calendar day period of delay resulting from Hurricane Harvey and its associated impacts
    from August 28, 2017 to October 15, 2017, 19 of those days were specifically anticipated
    by the parties as non-compensable adverse weather work days under the Adverse
    Weather Clause” (gov’t opp’n at 5). “[T]he Default (Fixed-Price Construction) clause
    and the Adverse Weather Clause exclude equitable adjustments, and as such satisfy the
    provision of the Suspension of Work Clause as it relates to preclusion of adjustments
    where ‘an equitable adjustment is . . . excluded under any other term or condition of this
    contract’. FAR 52.242-14(b)(2). The clauses, when harmonized and interpreted
    together, clearly contemplate that the 19 days of anticipated and actual delay resulting
    from Hurricane Harvey should not be compensable.” (Gov’t opp’n at 6)
    Legal Standard for Summary Judgment
    We evaluate the cross-motions for summary judgment under the well-settled
    standard: “Summary judgment is properly granted only where there is no genuine issue
    of material fact and the movant is entitled to judgment as a matter of law. The moving
    party bears the burden of establishing the absence of any genuine issue of material fact
    and all significant doubt over factual issues must be resolved in favor of the party
    opposing summary judgment.” Mingus Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987) (citations omitted). In the course of the Board’s evaluation
    of a motion for summary judgment, “our role is not ‘to weigh the evidence and determine
    the truth of the matter,’ but rather to ascertain whether material facts are disputed and
    whether there exists any genuine issue for trial.” Holmes & Narver Constructors, Inc.,
    ASBCA Nos. 52429, 52551, 02-1 BCA ¶ 31,849 at 157,393 (quoting Anderson v. Liberty
    Lobby, Inc., 
    477 U.S. 242
    , 249 (1986)). A material fact is one which may make a
    difference in the outcome of the case. Liberty 
    Lobby, 477 U.S. at 248
    . The opposing
    party must assert facts sufficient to show a dispute of material fact. New Iraq Ahd Co.,
    ASBCA No. 59304, 15-1 BCA ¶ 35,849 at 175,291-92 (citing 
    Mingus, 812 F.2d at 1390-91
    ) (“To ward off summary judgment, the non-moving party must do more than
    make mere allegations; it must assert facts sufficient to show a dispute of material fact.”);
    see Lee’s Ford Dock, Inc., ASBCA No. 59041, 16-1 BCA ¶ 36,298 at 177,010.
    However, questions of law are susceptible to summary judgment. R.L. Persons Const.,
    Inc., ASBCA No. 60121, 18-1 BCA ¶ 37,007 at 180,236-237 (“Contract interpretation—
    particularly the issue of whether a contract is ambiguous—is a question of law that
    generally is amenable to summary judgment.”)
    10
    Rules of Contract Interpretation
    The basic rules of contract interpretation were well-stated in TEG-Paradigm Envtl,
    Inc. v. U.S., 
    465 F.3d 1329
    (Fed. Cir. 2006):
    When interpreting a contract, “‘the language of [the] contract
    must be given that meaning that would be derived from the
    contract by a reasonably intelligent person acquainted with
    the contemporaneous circumstances.’” Metric Constructors,
    Inc. v. Nat’l Aeronautics & Space Admin., 
    169 F.3d 747
    , 752
    (Fed. Cir. 1999) (quoting Hol-Gar Mfg. Corp. v. United
    States, 
    169 Ct. Cl. 384
    , 
    351 F.2d 972
    , 975 (Ct. Cl. 1965)).
    
    TEG-Paradigm, 465 F.3d at 1338
    ; see also LAI Services, Inc. v. Gates, 
    573 F.3d 1306
    ,
    1314 (Fed. Cir. 2009).
    The contract must be read as a whole:
    Contract interpretation begins with the language of the
    written agreement. Foley Co. v. United States, 
    11 F.3d 1032
    ,
    1034 (Fed. Cir. 1993). When interpreting the contract, the
    document must be considered as a whole and interpreted so as
    to harmonize and give reasonable meaning to all of its parts.
    McAbee Constr., Inc. v. United States, 
    97 F.3d 1431
    , 1434-35
    (Fed. Cir. 1996). An interpretation that gives meaning to all
    parts of the contract is to be preferred over one that leaves a
    portion of the contract useless, inexplicable, void, or
    superfluous. Gould, Inc. v. United States, 
    935 F.2d 1271
    ,
    1274 (Fed. Cir. 1991)
    NVT Technologies, Inc. v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir. 2004). A
    contractor’s interpretation need not be the best interpretation, it need only be within the
    “zone of reasonableness.” States Roofing Corp. v. Winter, 
    587 F.3d 1364
    , 1369 (Fed.
    Cir. 2009).
    Reasonableness is a Question of Fact
    The parties dispute whether the 49 day suspension period was “reasonable,” as
    that word is used in the Suspension Clause, or not. Granite contends that the fact the
    COE compensated it for 30 of the 49 days of suspension is an admission that the delay
    was unreasonable (app. mot. at 9; app. opp’n at 3-4). The COE counters that it
    compensated Granite based on “equity” and not a belief that the 49 day suspension was
    unreasonable (gov’t opp’n at 3; gov’t mot. at 10). Whether a government-caused delay is
    11
    reasonable or unreasonable depends on the particular circumstances of the case.
    P.R. Burke Corp. v. United States, 
    277 F.3d 1346
    , 1360 (Fed. Cir. 2002) (“What is a
    reasonable period of time for the government to do a particular act under the contract is
    entirely dependent upon the circumstances of the particular case.”). Given the disputes
    about the circumstances here, we have a disputed material fact that precludes resolution
    of that fact by summary judgment. 1 However, we can decide the matter of the proper
    interplay and interpretation of FAR 52.242-14, Suspension of Work, FAR 52.249-10,
    Default (Fixed-Price Construction), and SECTION 01 10 00.00 45, 1.4 TIME
    EXTENSIONS FOR UNUSUALLY SEVERE WEATHER which is a question of law.
    Interpreting the Default Clause, Suspension Clause and SECTION 01 10 00.00 45 does
    not Support Deducting Anticipated Severe Weather Delay from the Suspension Period
    The Default Clause, FAR 52.249-10, Default (Fixed-Price Construction), defines
    the facts supporting a decision to terminate a contract for default. The primary basis
    encompassed in the clause for the right to terminate is based on a contractor’s
    unsuccessful completion of the contract within the “time specified.” However, the clause
    provides a defense to termination through a contractor’s right to an extension in time for
    delay arising from, “unforeseeable causes beyond the control and without the fault or
    negligence of the Contractor.” FAR 52.249-10(b)(1). The Default Clause includes a list
    of examples of “unforeseeable causes” of delay.
    Id. One of the
    examples is “Unusually
    severe weather.” FAR 52.249-10(b)(1)(x). If delay was caused by unusually severe
    weather, the CO “shall” extend the time for completing the work. FAR 52.249-10(b)(2).
    There is no right to compensation in the Default Clause, only the right to additional time
    to avoid default. There is nothing in the Default Clause linking it in any way to the
    Suspension of Work Clause, FAR 52.242-14.
    Contract Specification SECTION 01 10 00.00 45, 1.4 TIME EXTENSIONS FOR
    UNUSUALLY SEVERE WEATHER, provides guidance to the CO in determining if
    weather is “unusually severe” for purposes of the Default Clause (SOF ¶ 28). There are
    several prerequisites to be satisfied before a time extension “shall” be granted under the
    Default Clause. Section 1.4.1.2 Completion Delay requires that the delay be on the
    critical path, i.e., the unusually severe weather must actually cause a delay to the
    completion of the project. Section 01 10 00.00 45 includes a list of monthly “anticipated
    adverse weather delay” as follows:
    1   We do not discuss Granite’s contention that the delay was not caused by Hurricane
    Harvey because that argument seemed farfetched and immaterial. Granite,
    however, is free to pursue and explain this contention if it desires.
    12
    MONTHLY ANTICIPATED ADVERSE WEATHER
    DELAY
    WORK DAYS BASED ON 7 DAY WORK WEEK
    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
    DEC
    (11) (8) (6) (6) (7) (9) (7) (10) (13) (10) (8)
    (10)
    The contractor must incorporate the monthly anticipated adverse weather delay in its
    Critical Path Method (CPM) schedule (1.4.2 Baseline for Monthly Weather Time
    Evaluations). That means the anticipated adverse weather delay, if it occurs, would not
    cause a critical path delay because it is already built into each month’s schedule.
    Therefore, such a delay would not be cause for the CO to extend the time to complete the
    contract. Relatedly, the listed monthly anticipated adverse weather delay is used to
    calculate the delay caused by “unusually severe weather” for use in accordance with the
    Default Clause. To be considered “unusually severe weather,” the actual delay for each
    month must exceed the anticipated adverse weather delay for the time period involved.
    Advance Constr. Servs., Inc., ASBCA No. 55232, 11-2 BCA ¶ 34,776 at 171,133 (“Thus,
    under Section b of this provision,[ 2] referred to hereinafter as the Unusually Severe
    Weather clause, the contractor will only be allowed a time extension due to weather in a
    given month for days in excess of those already accounted for in the contract.”). For
    example, in this appeal the parties agree that there are nineteen (19) days of anticipated
    adverse weather delay (SOF ¶¶ 17-18, 21, 24). This is based on the forty-nine (49) day
    suspension from August 28, 2017 to October 15, 2017 (SOF ¶ 12). The 19 days is
    comprised of one (1) day from August, thirteen (13) days from September and five (5)
    days from October based on the monthly anticipated adverse weather delay listed in the
    specification. Therefore, days of severe weather delay over the 19 days between
    August 28, 2017 and October 15, 2017, would qualify as “unusually severe weather”
    justifying an extension pursuant to the Default Clause. Applying the rules of contract
    interpretation quoted above, there is nothing in SECTION 01 10 00.00 45 providing for
    the 19 days of anticipated adverse weather delay to be subtracted from the 49 days of
    suspension imposed under the Suspension of Work Clause. Moreover, there is nothing in
    SECTION 01 10 00.00 45 providing for compensation for the unusually severe weather.
    The Section only defines what constitutes “unusually severe weather” for the CO’s use in
    determining if default is excused under the Default Clause. There is nothing in
    SECTION 01 10 00.00 45 linking it and the Default Clause in any way with the
    2   The “provision” is an Unusually Severe Weather Clause substantially the same as
    SECTION 01 10 00.00 45, 1.4 TIME EXTENSIONS FOR UNUSUALLY
    SEVERE WEATHER (SOF ¶ 28).
    13
    Suspension of Work Clause, FAR 52.242-14. That brings us to the Suspension of Work
    Clause itself.
    The Suspension of Work Clause, FAR 52.242-14, allows the CO to “suspend,
    delay, or interrupt” work under the contract (SOF ¶ 26). If the suspension is reasonable
    there is no cost to the government. If the suspension is caused (1) by an act of the CO in
    the administration of this contract or (2) by the CO’s failure to act within the time
    specified in this contract, and is “unreasonable,” the contractor is entitled to an
    adjustment in its cost to perform. Unusually severe weather cannot be caused by the
    CO’s action or failure to act so it cannot trigger a cost increase under the Suspension of
    Work Clause. Moreover, there is a “no adjustment” provision Clause, which provides
    that, “to the extent that performance would have been so suspended, delayed, or
    interrupted by any other cause, including the fault or negligence of the Contractor, or for
    which an equitable adjustment is provided for or excluded under any other term or
    condition of this contract” there shall be no adjustment in the cost to perform (SOF ¶ 26).
    The government argues that the Adverse Weather Clause combined with the
    Default Clause, basically provides that the contractually-anticipated days of bad weather
    for each month are excluded from compensation. Thus, according to the COE, these
    anticipated days of bad weather are precluded by the “no adjustment” clause. (Gov’t br.
    at 8-9) But the Adverse Weather Clause is applicable only to the Default Clause and is
    only used to calculate the number of days for which weather delays provide an excuse for
    late performance, as discussed above; its language does not purport to either provide for
    or exclude an equitable adjustment for weather delays. Accordingly, there is no basis to
    find that the days excluded for purposes of Default Clause time extension calculations are
    also excluded from compensation by the “no adjustment” section of the Suspension of
    Work Clause. Thus, if Granite can prove entitlement to an “adjustment” to its cost of
    performance under the Suspension of Work Clause, the Default Clause would not trigger
    the “no adjustment” provision of the Suspension of Work Clause.
    Granite seeks $233,779, undisputed by the COE, for the 19 days associated with
    the anticipated adverse weather delay in Section 01 10 00.00 45. We have found that
    there is no link between the Suspension of Work Clause and the Default Clause which
    brings Section 01 10 00.00 45 into play with the Suspension Clause. Therefore, the
    COE’s interpretation that the 19 days of anticipated adverse weather delay may be
    subtracted from the 49 days of suspension based on Section 01 10 00.00 45 is not within
    the “zone of reasonableness.” States 
    Roofing, 587 F.3d at 1369
    . To the extent the COE
    argues that the contract interpretation guidance “[w]hen interpreting the contract, the
    document must be considered as a whole and interpreted so as to harmonize and give
    reasonable meaning to all of its parts” (NVT Technologies, 
    Inc., 370 F.3d at 1159
    )
    somehow justified subtracting the 19 days of anticipated adverse weather from the
    49 days of suspension, we reject the argument. All that is left is for the COE to prove
    that the suspension was reasonable and as such Granite is not entitled to any more
    14
    compensation than what the COE gave it based on “equity.” Alternatively, Granite
    would need to prove that the suspension was unreasonable. As we discussed above,
    “reasonableness” involves questions of disputed material fact not susceptible to
    resolution by summary judgment.
    CONCLUSION
    In accordance with the above we grant partial summary judgment to Granite and
    leave the question of the reasonableness of the suspension period for further proceedings.
    Dated: December 3, 2020
    CRAIG S. CLARKE
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    RICHARD SHACKLEFORD                                J. REID PROUTY
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 62281, Appeal of Granite
    Construction Company, rendered in conformance with the Board’s Charter.
    Dated: December 8, 2020
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    15