M.L. Energia, Inc. ( 2020 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    M. L. Energia, Inc.                            )      
    ASBCA No. 58975
    )
    Under Contract No. NAS 10-98025                )
    APPEARANCE FOR THE APPELLANT:                         Bruce I. Afran, Esq.
    Princeton, N.J.
    APPEARANCES FOR THE GOVERNMENT:                       Scott W. Barber, Esq.
    NASA Chief Trial Attorney
    Bradley W. Smith, Esq.
    H. Joseph Batey, Esq.
    Trial Attorneys
    Kennedy Space Center, FL
    OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD
    ON APPELLANT'S MOTION FOR RECONSIDERATION
    The Board issued its decision on quantum in this appeal on April 4, 2019,
    wherein we found that appellant was not entitled to payment of any additional contract
    amounts. M. L. Energia, Inc. (Energia) received the decision on April 10, 2019, and
    timely filed its motion for reconsideration on May 1, 2019. We deny the motion.
    DECISION
    Our standards for deciding a motion for reconsideration are well established:
    Reconsideration does not provide a party an opportunity to
    reargue issues that were previously raised and decided.
    Precision Standard, Inc., 
    ASBCA No. 58135
    , 16-1 BCA
    ,J 36,504 at 177,860. The movant must establish a
    compelling reason to modify the earlier decision. 
    Id.
     We
    look to whether the movant presents newly discovered
    evidence, mistakes in findings of fact, or errors of law. 
    Id.
    A motion for reconsideration does not provide a litigant a
    '"second bite at the apple" or the opportunity to advance
    arguments that properly should have been presented in an
    earlier proceeding. Dixon v. Shinseki, 
    741 F.3d 1367
    , 1378
    (Fed. Cir. 2014).
    American Int'l Contractors, Inc., ASBCA Nos. 60948, 61166, 18-1 BCA ,-r 37,194
    at 181,070-71.
    In its motion appellant (pro se at this stage) continues to challenge our decisions
    on entitlement (ML. Energia, Inc., 
    ASBCA No. 55947
    , 12-2 BCA ,-r 35,110; recon.
    granted in part, 13 BCA ,-r 35,284). The government replied, correctly pointing out
    that appellant raised no new legal or factual (newly discovered or otherwise)
    arguments. Subsequently, appellant filed, by counsel, a memorandum in support of
    motion for reconsideration. Appellant rehashes causation again, arguing that the
    failure ofNASA to identify a test site caused delay and thus it was the government's
    fault, not appellant's, that the work never was completed. Even if that were true, and it
    is not, appellant also fully contributed to the failure of the work to be timely
    completed. Such failures were fully described in our first decision on entitlement.
    In any event, there is no basis for paying appellant for work that was not
    performed. Reminding appellant again, it had a firm fixed-price contract and it does
    not get all of the money unless it does all of the work. Thus, even if the government
    were responsible for the failure to complete the work (timely or not all of it), that does
    not give rise to entitlement to money appellant has not earned.
    Finally, appellant argues:
    [I]t would appear the Board had no jurisdiction to enter
    judgment in favor of the agency since the government, by
    failing to file its own claim for equitable reduction, failed
    to preserve its rights and waived such claims. The
    government had a six-year period in which to bring its
    claim of an equitable reduction against Energia but failed
    to file any claim.l*l As the government never actually filed
    a claim, it would appear to have waived any claim to the
    equitable reduction and the Board should have made no
    finding ofNASA's entitlement.
    (App. mot. at 5)
    The opposite is true. In 2001, NASA informed Energia that the government
    was taking an equitable reduction under the Inspection clause of the contract in the
    amount of $153,615. Dr. Lavid objected several times to the contracting officer (CO),
    • Appellant does not allege when the so-called six-year period began to run.
    2
    and did so as late as June 28, 2002. The contract was closed out on September 4,
    2002. Nearly four years later, Dr. Lavid requested reconsideration of the denial of the
    payment. NASA declined to reconsider and thus, Energia filed a certified claim for
    $153,615. The claim was denied in a final decision in late 2007 and it was timely
    appealed to this Board. See ML. Energia, 
    ASBCA No. 55947
    , 12-2 BCA, 35,110
    at 172,407-08 (findings 90-91, 93, 96-98, 100-03). Thus the appeal is properly before
    the Board.
    When the work was not timely completed the contract's Inspection clause gave
    the government the right to accept the work and take an equitable reduction in contract
    price. The amount of the equitable reduction was the subject of our quantum decision.
    Appellant has not provided us with a compelling reason to modify our quantum
    decision. Nor has it shown newly discovered evidence, mistakes in our findings of fact
    or errors of law.
    CONCLUSION
    Appellant's motion for reconsideration of our quantum decision is cl~nied.
    -------
    Dated: January 27, 2020
    RICHARD SHACKLEFORD
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I concur
    MICHAEL T. PAUL
    Administrative Judge
    Armed Services Board
    Armed Services Board                             of Contract Appeals
    of Contract Appeals
    3
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58975
    , Appeal ofM. L.
    Energia, Inc., rendered in conformance with the Board's Charter.
    Dated:
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    4
    

Document Info

Docket Number: ASBCA No. 58975

Judges: Shackleford

Filed Date: 1/27/2020

Precedential Status: Precedential

Modified Date: 2/12/2020