GSC Construction, Inc. ( 2020 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    GSC Construction, Inc.                       )      ASBCA No. 61380
    )
    Under Contract No. W912HN-10-D-0049          )
    Task Order 0007                             )
    APPEARANCE FOR THE APPELLANT:                       Mr. George L. McKnight
    President
    APPEARANCES FOR THE GOVERNMENT:                     Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Laura J. Arnett, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, Savannah
    OPINION BY ADMINISTRATIVE JUDGE MCNULTY
    Before us is the government’s motion for summary judgment. We partially
    grant the motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On September 25, 2012, the U.S. Army Engineer District Savannah
    (government) issued Task Order (TO) 0007 to GSC Construction, Inc. (GSC or
    appellant) under an indefinite-delivery, indefinite-quantity multiple award task order
    contract (MATOC), Contract No. W912HN-10-D-0049 for the design and renovation
    of an Army Ranger barracks building, Building 2833, located at Fort Benning, Georgia.
    The task order included options relating to design and renovation services for Building
    2834 as well. The barracks buildings are also referred to as the “Rip Rope” buildings.
    The task order established a 540 calendar day period of performance measured from the
    date of receipt of Notice to Proceed (NTP). (R4, tab 6 at 1-5)
    2. GSC acknowledged receiving the NTP on November 21, 2012, thereby
    establishing the task order’s completion date as May 15, 2014 (R4, tab 2 at 2, 7).
    3. Under date of January 25, 2013, the government requested a proposal (RFP)
    for additional work due to design changes at Building 2833 (R4, tab 8 at 1). GSC’s
    proposal submitted in response to the RFP included two fragnet schedules setting forth
    the anticipated impact on the project’s schedule if the government went ahead with the
    additional work (id. at 20-21). GSC’s proposal in the total amount of $59,781.11,
    included a request that 22 days be added to the schedule with a cost of $18,999.42 for
    the additional time of performance required, i.e., extended overhead 1 (id. at 6).
    4. The government accepted GSC’s proposal and issued Modification No. 1A
    to the TO in the amount of $59,781.11, but rather than the 22 days requested, granted
    30 days of time extension. The modification expressly states that it is for all costs
    directly or indirectly attributable to the changes and delays related thereto including
    extended overhead (R4, tab 8 at 25-27). In this regard the modification stated:
    It is understood and agreed that pursuant to the above, the
    contract time is extended the number of calendar days
    stated, and the contract price is increased as indicated
    above, which reflects all credits due the Government and
    all debits due the Contractor. It is further understood and
    agreed that this adjustment constitutes compensation in full
    on behalf of the Contractor and its Subcontractors and
    Suppliers for all costs and markups directly or indirectly
    attributable for the change ordered, for all delays related
    thereto, for all extended overhead costs, and for
    performance of the change within the time frame stated.
    (Id. at 26-27) GSC signed the modification on February 22, 2013 (id. at 25). The
    government’s Price Negotiation Memorandum (PNM) states that the basis for the time
    extension was that design was delayed 30 calendar days by the government’s failure to
    provide as-built drawings to GSC in a timely manner (id. at 23). Modification No. 1A
    extended the contract completion date to June 14, 2014 (id. at 26).
    5. By letter dated May 9, 2013, GSC submitted a letter regarding the
    progressive collapse requirements of the contract. GSC stated the as-built drawings
    had not been made available until sometime after contract award. This had caused a
    delay to the design work, which had been addressed in a modification to the contract.
    (R4, tab 17 at 1) GSC also stated that without the as-built drawings its bid price had
    been based on a proposal it had received from Fibrwrap Construction, which had relied
    on its prior experience with Buildings 2752 and 2754 to prepare the proposal. GSC
    continued, stating they had discovered that much more work was required in the Rip
    Rope buildings than had been required for Buildings 2752 and 2754. (Id.) GSC stated
    it hoped the progressive collapse requirement would be withdrawn from the contract,
    which would result in a credit to the government, otherwise, GSC would submit a
    1   The proposal indicates GSC added Overhead (10%, $1,899.94), Profit (7%, $1,329.96)
    and Bond premium (1%, $189.99) to its proposed costs (id. at 6). Accordingly,
    with respect to the extended overhead GSC was seeking, and ultimately received,
    $22,419.31 ($18, 999.42 + $1,899.94 + $1,329.96 + $189.99) (SOF ¶ 4).
    2
    request for equitable adjustment (REA) of approximately $200,000 for building 2833
    alone (id. at 2).
    6. GSC reiterated that it had received a modification for the delay associated
    with the government’s election to not provide the Rip Rope buildings as-built
    drawings until several months after contract award in its claim submitted May 29,
    2013 (id. at 15). Its claim sought costs associated with the additional reinforcement
    required in Building 2833. The claim did not seek any additional time or any time or
    costs for work in Building 2834. (Id. at 15-16)
    7. By letter dated July 29, 2013, GSC notified the government it had
    encountered what it considered to be differing site conditions (DSC). The letter
    indicated the concrete slabs for Building 2833’s floors were out of plumb with each
    other and that the slabs exceeded the flatness tolerance set forth in the contract. (R4,
    tab 22 at 1) GSC included a cost proposal, totaling $158,921.72 for the two DSC. The
    cost proposal indicated that 2,400 bags of floor leveling compound was needed to
    correct the slab flatness issue. The cost proposal also indicated that a 25-day time
    extension was needed to perform the required corrective work. (Id. at 2)
    8. The government exercised options 1-3 and added the work to TO 007 by
    Modification No. 02, effective August 13, 2013 (R4, tab 10 at 1). The modification
    added 175 calendar days to the task order performance period, extending it to
    December 6, 2014 (id. at 2-3). Although the modification was unilateral, GSC does
    not dispute that the contract completion date was revised to December 6, 2014, by
    Modification No. 02 (gov’t mot. at 2; app. opp’n at 2).
    9. Under date of August 14, 2013, the government sent GSC a RFP for
    removing and replacing a sanitary line and for the work related to alter the metal stud
    framing to account for the edges of each slab being out of plumb (R4, tab 23 at 1, 3).
    GSC submitted a proposal totaling $87,627.67 and requested a 15-day time extension
    in response to the RFP (id. at 5). The proposal included furring out all slab edges to
    make them plumb in the amount of $25,141.00 before markups (id.). GSC also
    submitted a fragnet schedule to support its request for a 15-day time extension (id.
    at 13-14). The parties agreed to a no time change order in the amount of $73,637.52
    for the work, which was added to the TO by Modification No. 1C (id. at 16-17).
    10. By letter dated September 26, 2013, the government requested a proposal
    from GSC for the additional reinforcing work relating to the progressive collapse
    requirements for both of the Rip Rope buildings (R4, tab 24 at 1-3). GSC’s proposal
    in the total amount of $499,931.60 included $81,530.50 before markups for leveling
    the floor slabs, which was based on 1,304 bags of leveling compound (id. at 5, 20).
    During the negotiations of the modification relating to this work, GSC, at the
    government’s request, agreed to remove the costs associated with the floor leveling
    3
    (id. at 31-32). Bilateral Modification No. 04 was executed by the parties on May 15,
    2014, for the additional work associated with the additional reinforcing required to
    comply with the progressive collapse requirement (id. at 34). The government’s PNM
    indicates the floor leveling work associated with Modification No. 04 was required
    due to the increased amount of fiberwrap applied to the slabs to satisfy the progressive
    collapse requirements. (id. at 30-31).
    11. By letter dated February 10, 2015, the contracting officer notified GSC that
    it had failed to complete the project by the contract’s completion date and that the
    government would assess liquidated damages in the amount of $1,029.64 per calendar
    day assessed retroactively from February 5, 2015, until the buildings were turned over 2
    (R4, tab 34). The government conducted the final inspection of building 2834 and
    granted occupancy to the user on June 19, 2015 (R4, tab 19 at 879).3
    12. By letter dated March 3, 2015, the government requested a proposal for
    changes to the fire alarm system. GSC submitted a proposal in the amount of
    $8,393.90 with a 70 calendar day time extension in response. (R4, tab 25 at 1, 5) The
    government issued Modification No. 1G in the amount of $8,393.90 as proposed by
    GSC on March 6, 2015 (id. at 14). The modification was issued unilaterally because
    the parties could not agree on the time required to perform the additional work (id.
    at 11-13). The modification was issued with the understanding that the issue of time
    would be revisited (id. at 15-16). Subsequently, the government issued Modification
    No. 1H granting a 10-day non-compensatory time extension for the changes to the fire
    alarm system (R4, tab 26). This modification was also issued unilaterally. GSC
    declined to sign it and indicated it would provide “a more formal response later in the
    week” (id. at 3). The record includes a response to a request from the government
    made in January 2018 for GSC’s delay analysis relating to the fire alarm changes (R4,
    tab 16). The response, signed by Mr. Jay Grant from GSC discussed the attached
    schedules, which Mr. Grant asserts demonstrates that the fire alarm system changes
    had an impact of 71 calendar days to the overall schedule (id. at 25-39). A comparison
    of the two schedules, found at 26-32 and 33-39 of tab 16 indicates that an activity
    identified as “1G” and named “Fire Alarm Changes” has been added to the amended
    2 Building 2833 had been made available for the government’s use on November 18,
    2014, despite the HVAC system not operating properly (R4, tab 19 at 672).
    The contract does not have separate completion dates for the buildings, a single
    completion date encompasses both buildings (R4, tab 6 at 5, tab 10).
    3 In its motion the government asserts it is undisputed the warranty period commenced
    on June 19, 2015 (gov’t mot. at 23). GSC disputed this in its response,
    asserting Building 2834 was substantially complete in May and that the
    government occupied the building on May 11, 2015 (app. opp’n at 12). The
    government has admitted the project was substantially completed on May 8,
    2015, for purposes of the motion (gov’t reply at 15).
    4
    schedule. The activity is depicted as extending from early March to mid-May. No
    further explanation was provided.
    13. On March 5, 2016, a two-inch water line came apart. Building 2834 was
    flooded with four inches of water in the basement. The base maintenance contractor
    responded to the flood and also noted that a six-inch water main on the first floor was
    leaking badly and contributed to the flooding. (R4, tab 29) The repairs were
    completed on March 10, 2016 (id. at 2).
    14. On March 31, 2016, another leak occurred in Building 2834 and GSC was
    asked to make the necessary repairs. GSC, through a subcontractor, repaired this leak
    on April 2, 2016. On April 3, 2016, the repair failed and the basement was flooded
    with six feet of water and other areas of the building were flooded with as much as two
    feet of water. GSC was again directed by the government to make the necessary
    repairs under the warranty it had provided. (R4, tab 30)
    15. By letter dated April 11, 2016, GSC advised the government that it was
    continuing to assess the cause of the leaking and that it was working to assure the
    government received fully functional items. GSC indicated that its insurance company
    was involved in reviewing the situation. (R4, tab 32)
    16. In July 2016, GSC’s insurance company, BITCO, issued a check in the
    amount of $110,000 to GSC as an advance payment for certain repairs relating to the
    flooding. The check was issued as an accommodation and BITCO reserved all of its
    rights, including the right to seek reimbursement of the payment. (R4, tab 33)
    17. Under date of July 26, 2017, GSC submitted a certified claim to the
    contracting officer for final decision (R4, tab 14). The claim included seven “Issues”
    totaling $1,339,954.11 as follows:
    1) Delay in start of Bldg. 2834 due to a failure to provide
    as-built drawings for existing 2833 Building that was
    outside the power of GSC. GSC requested a thirty (30)
    calendar day time extension and $20,519.37 in extended
    overhead by letter dated January 11, 2013.4
    4   GSC appears to have misstated the date of the letter. The letter enclosed with the
    claim in the record is dated January 31, 2013 (R4, tab 14 at 4). The letter
    includes a cost proposal showing how the cost claimed was calculated and two
    fragnets supporting the 30 days claimed (id. at 5, 7-8). The fragnets are
    identical to the fragnets submitted by GSC to support the request for an
    equitable adjustment that was paid in Modification No. 1A (Cf. R4, tab 14
    at 7-8, tab 8 at 20-21).
    5
    2) Audio Visual Changes. GSC was directed by the user to
    make changes to the audio visual components of 2834 in
    order for 2834 to be accepted. These changes were outside
    GSC’s scope. For these changes, GSC requests a
    $29,689.25 change order per the attached cost breakdown
    from Net Planner and a 21 calendar day time extension
    with extended overhead.
    3) Testing outside GSC’s scope. GSC requests a
    $632,995.61 change order for GSC having to maintain and
    perform testing not required by its contract. This cost is
    substantiated by the partial judgement award, Judge Proper
    January 18, 2016, to GSC for completing HVAC system
    once DYNAMIC was unable to complete. This unduly
    imposed requirement caused substantial hardship to GSC
    and its subcontractors. The HVAC contractor abandoned
    the project and ceased doing business in Georgia as a
    direct result. Attached is an uncollectable judgment
    against the project’s mechanical contractor justifying the
    change order amount. GSC had to complete the project
    acquiring outside forces as no others would take the job
    due to excessive and previously unknown requirements.
    GSC was further burdened by the 120 days these
    requirements added to project completion. GSC is entitled
    to a change order because its losses caused by the testing
    requirements were outside its control and unknown at the
    time GSC entered into its contract.
    4) Existing concrete pads were out over 1” level contrary
    to expected building standards. This unforeseen condition
    forced GSC to install an additional 2400 bags of Ardex at a
    spread rate of 25 sf per bag. GSC requests a change order
    for $158,921.72 per GSC letter dated July 29, 2013.
    5) COE issued unilateral 1G “Fire Alarm Changes.” GSC
    request a 70 day time extension with overhead as requested
    by GSC backup dated March 4, 2015. The unilateral was
    ambiguous but COE took position that it required GSC to
    meet all base requirements for life safety. This resulted in
    confusion loss of efficiency and additional delays to the
    6
    project. Please see attached change order. GSC requests a
    change order for 70 day time with extended overhead.[5]
    6) Basement Flood. GSC was directed to repair a leak to
    2834’s hot water heater. GSC also repaired damages
    caused by the leak at the user’s direction, even though the
    leak was not GSC’s fault, there were damages from
    previous leaks, and the project exceeded the warranty
    period. GSC requests to be reimbursed for the expenses
    incurred in repairing the leak, including its increase
    insurance premium. Please see attached cost breakdown
    estimate including premium increase for damages totaling
    $394,750.68.[6]
    7) GSC is requesting payment of outstanding balance of
    original contract construction costs in the amount of
    $103,077.48. At our expense GSC allowed beneficial
    occupancy of 2833 well before the completion date. This
    resulted in GSC having to maintain 2833 until 2834 was
    occupied by COE.
    (R4, tab 14 at 1-2) The amount claimed for Issue (4) included costs for work
    associated with both leveling the floor slabs and installing furring along the slab edge
    (id. at 18). The pricing, in the amount of $5,506.00, for the furring work was obtained
    from Center Brothers, Inc. via an email dated July 26, 2013 (id. at 26). Center
    Brothers, Inc. subsequently revised the pricing and incorporated it into the price that
    GSC submitted as part of the backup for its REA that resulted in Modification No. 1C
    (R4, tab 23 at 11; see also SOF ¶ 9).
    18. As part of its support of its claim GSC submitted a copy of a judgment in
    the amount of $632,995.61, plus costs and attorney’s fees it had received in the
    Superior Court of Richmond County, Georgia against its subcontractor, Chris Leiser
    5   The claim stated no dollar amount for the extended overhead sought.
    6   This claim Issue was supported with a “Cost Estimate Analysis” breakdown, which
    included a lump sum for the flood repairs in the amount of $303,740.23 and
    $22,500 for the insurance premium increase before markups of 10% each for
    overhead and profit and 1% for additional bond premium (R4, tab 14 at 33).
    We find the total amount claimed for the increase in insurance premium
    element with the markups as claimed is $27,497.25. Although there were
    multiple leak incidents between March and April 2016 appellant’s claim does
    not segregate the costs by incident. (SOF ¶¶ 13-14; R4, tab 14 at 33-34)
    7
    d/b/a Dynamix Mechanical 7 (id. at 12-13). The record includes a copy of the
    complaint filed by GSC against Dynamix, which pleads Dynamix breached the
    subcontract by abandoning performance prior to its completion, requiring GSC to
    engage a replacement subcontractor to complete the work contained within the scope
    of the subcontract agreement and damaging GSC in the amount of $632,995.61 (R4,
    tab 20 at 4). On August 22, 2017, the contracting officer notified GSC that a decision
    on its claim would be issued by February 15, 2018 (R4, tab 15). On October 25, 2017,
    appellant filed a Notice of Appeal with the Board, which was docketed as ASBCA No.
    61380.
    19. By letter dated February 15, 2018, the contracting officer partially found
    merit and partially denied the claim as synopsized below:
    (1) The contracting officer denied the first issue, finding
    GSC had already been compensated in the form of a
    30-day time extension and payment of $20,519.37 via
    Modification No. 1A 8 (R4, tab 2 at 3-5; SOF ¶¶ 3, 4).
    (2) The contracting officer found the second issue had some
    merit, finding GSC was entitled to compensation for additional
    direct costs it had incurred and a non-compensable 21 calendar
    day time extension (R4, tab 2 at 5-7).
    (3) The contracting officer denied the third issue, finding
    the costs claimed, duplicated the amount of a judgment
    GSC had received in a lawsuit against its subcontractor,
    DYNAMIC, for having failed to perform work that GSC
    had pleaded in its complaint against the subcontractor was
    “within the scope of the subcontract” and that GSC had
    provided no explanation for how the government should
    and could be responsible for the subcontractor’s default
    (id. at 7-9).
    7 The record includes references to a GSC subcontractor named DYNAMIC as well.
    Based on GSC’s assertions in its claim we find that Dynamix Mechanical and
    DYNAMIC are one and the same.
    8 The record indicates GSC was actually paid $22,419.31 for extended overhead by
    Modification No. 1A (SOF ¶¶ 3-4). We find the contracting officer conflated
    the amount paid in Modification No. 1A with the amount claimed in 2017,
    which deleted 10% for overhead, which had been claimed and paid in 2013.
    (Id.; R4, tab 14 at 5)
    8
    (4) The contracting officer denied this issue as well (id.
    at 9-12). First, the contracting officer found that the
    furring along the slab edge work had been paid for under
    Modification No. 1C., and with respect to the floor
    leveling work, found that this work had been paid for
    under Modification No. 04. (Id. at 11-12; see also SOF
    ¶ 10) The contracting officer stated that GSC had failed to
    provide any evidence that the work being claimed for
    differed from the work that had been paid for previously
    under the two modifications (id.).
    (5) The contracting officer denied this issue also. The
    contracting officer noted that 10 calendar days had been
    granted for the fire alarm changes under unilateral
    Modification No. 1H. The contracting officer found that
    the fragnet submitted in support of the claim showed the
    fire alarm work would not be finished until the middle of
    May 2015 but that GSC’s own QCR’s (Quality Control
    Report) showed the work was completed no later than
    March 20, 2015.9 The contracting officer also found that
    the claim failed to take into account the 10 calendar day
    time extension that had been granted under Modification
    No. 1H. (Id. at 12-15)
    (6) The contracting officer denied this issue, finding GSC’s
    poor workmanship was the root cause of the flooding.
    Additionally, the contracting officer found GSC had
    submitted no backup to support the claimed insurance
    premium increase. (Id. at 16-22)
    (7) The contracting officer denied this issue finding the
    government was entitled to $127,675.36 due to GSC’s late
    finish. The contracting officer found this amount should be
    reduced by $21,622.44 to account for the 21 day time
    extension the contracting officer found was due GSC for the
    audiovisual changes, claim sub-item (2), but that even with
    this reduction the amount of liquidated damages due the
    government ($106,052.92) exceeded the unpaid contract
    price balance. (Id. at 22-24)
    9   The record includes the Quality Control Reports relied on by the contracting officer
    (R4, tab 18).
    9
    20. In its complaint GSC reiterated the same seven issues set out in its claim
    and sought relief totaling $1,339,954.11, exactly matching the amount claimed (compl.
    ¶¶ 18, 29; SOF ¶ 18).
    21. In its response to the government’s motion for summary judgment, GSC
    withdrew its claim for insurance premium increases, which was part of Issue 6 (app.
    opp’n at 14; SOF ¶ 18).
    22. Additionally, after the government filed its motion, GSC produced a
    settlement agreement between itself and its insurance company (gov’t reply at 13,
    ex. 5). The settlement agreement establishes that GSC received $310,000 from its
    insurance company as a loan for payment of the repairs required to remediate the
    damage caused due to the flooding in building 2834 (gov’t reply, ex. 5). Pursuant to
    the terms of the settlement agreement GSC is not obligated to repay the loan unless
    and to the extent GSC recovers from Roto-Rooter or any other third person (gov’t
    reply, ex. 5 at 3).
    CONTENTIONS OF THE PARTIES
    The government argues appellant has been compensated for much of its claim
    through bilateral modifications to the contract and thus the claim items paid for
    through the modifications are barred by accord and satisfaction. This argument is
    made with respect to Claim Item Nos. 1, 4, 5 (gov’t mot. at 30, 34, 37). The
    government argues appellant has failed to state a claim for which relief may be granted
    with respect to Issue 3 (id. at 32). With respect to Issue 6, the government argues
    appellant caused the flooding, which necessitated the repairs appellant asserts are
    additional work and that in any event appellant has been compensated by its insurance
    company for the repair costs appellant incurred (id. at 40). The government argues it
    is entitled to summary judgment with respect to the claim for the contract balance
    because appellant owes the government liquidated damages that exceed the contract
    balance (id. at 42). With respect to Issue 2, the government acknowledges the claim is
    partially meritorious (id. at 32).
    Appellant opposes the motion, arguing there are material facts in dispute.
    Appellant argues responsibility for the flooding in Building 2834 is disputed.
    Appellant also argues that whether the modifications fully resolved the flooring and
    drawing issues is disputed, as well as the issue of whether appellant is entitled to
    additional time for the added fire alarm work. Appellant further argues there is a
    dispute with respect to whether the government is liable for increased costs related to
    enhance commissioning (app. opp’n at 23-25).
    10
    DECISION
    GSC’s withdrawal of the part of its claim, included in Issue 6, relating to the
    insurance premium increases, deprives the Board of jurisdiction to consider this part of
    the appeal further (SOF ¶ 22). This part of the appeal is dismissed as moot.
    Sygnetics, Inc., ASBCA No. 60357, 18-1 BCA ¶ 37,160; Advanced Powder
    Solutions, Inc., ASBCA No. 61818, 19-1 BCA ¶ 37,425 at 181,897. Accordingly, we
    consider the remaining issues pertaining to the government’s motion.
    Summary judgment is appropriate where there is no genuine dispute as to any
    material fact and the movant has made a prima facie showing with evidence that it is
    entitled to judgment as a matter of law. Enzo Biochem, Inc. v. Applera Corp., 
    599 F.3d 1325
    , 1337 (Fed. Cir. 2010). See also Mingus Constructors, Inc. v. U.S., 
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987); Arko Executive Services, Inc. v. U.S., 
    553 F.3d 1375
    , 1378 (Fed. Cir. 2009); FED. R. CIV. P. 56(a). A material fact is one that might
    affect the outcome of an appeal. Revenge Advanced Composites, ASBCA No. 57111,
    11-1 BCA ¶ 34,698 at 170,883 (citing Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    ,
    248 (1986)). An issue of material fact is “genuine” if the evidence is such that a
    reasonable jury could return a verdict for the non-moving party. Wavetronix v. EIS
    Elec. Integrated Sys., 
    573 F.3d 1343
    , 1354 (Fed. Cir. 2009) (citing 
    Anderson, 477 U.S. at 248
    ). The moving party “bears the initial responsibility of informing
    the . . . court of the basis for its motion, and identifying those portions of ‘the
    pleadings, depositions, answers to interrogatories, and admissions on file, together
    with the affidavits, if any,’ which it believes demonstrate the absence of a genuine
    issue of material fact,” upon which the burden shifts to the nonmoving party to “make
    a showing sufficient to establish the existence of [elements] essential to that party’s
    case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v.
    Catrett, 
    477 U.S. 317
    , 322-23 (1986). The nonmoving party’s failure to show an
    element essential to its case on which it has the burden of proof renders all other facts
    immaterial and entitles the moving party to summary judgment.
    Id. (citing Anderson,
    477 U.S. at 250). We draw all justifiable inferences in favor of the nonmoving party.
    CI², Inc., ASBCA Nos. 56257, 56337, 11-2 BCA ¶ 34,823 at 171,353 (citing
    M. Maropakis Carpentry, Inc. v. U.S., 
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010)). “The
    party opposing summary judgment must show an evidentiary conflict on the record;
    mere denials or conclusory statements are not sufficient.” Mingus 
    Constructors, 812 F.2d at 1390-91
    ; see also Barmag Barmer Maschinefabrik AG v. Murata
    Machinery, Ltd., 
    731 F.2d 831
    , 835-36 (Fed. Cir. 1984) (“With respect to whether
    there is a genuine issue, the court may not simply accept a party’s statement that a fact
    is challenged”). Any fact that is not properly disputed we may consider to be
    admitted. See Rules of the Armed Services Board of Contract Appeals, Rule 7(c)(2),
    “The Board may accept a fact properly proposed and supported by one party as
    undisputed, unless the opposing party properly responds and establishes that it is in
    11
    dispute.” See also Ferguson Propeller, Inc. v. U.S., 
    59 Fed. Cl. 51
    , 58 (2003)
    (“Having failed to specifically dispute the Defendant’s Proposed Findings of
    Uncontroverted Facts, the court deems those facts admitted . . .”); FED. R. CIV. P.
    56(e)(2). Additionally, the Board has discretion to grant partial summary judgment to
    resolve some, but not all, of the issues raised by the moving party. See, e.g., Arctic
    Corner, Inc., ASBCA No. 33347, 92-3 BCA ¶ 25,030 (granting summary judgment
    with regard to 7 of 19 claim items); Hermes Consol., Inc. D/B/A Wyoming Refining
    Co., ASBCA Nos. 52308, 52309, 02-1 BCA ¶ 31,767 (granting partial summary
    judgment on Count I with respect to the measure of recovery for unrecovered
    termination costs and granting summary judgment on Counts II-IV).
    The government asserts there are no genuine disputes as to any material facts.
    For the most part, we agree with the government but disagree in a few instances as set
    forth more fully below. The government’s motion sets forth a detailed statement of
    facts comprising 175 separate paragraphs. Appellant admits 77 of them without
    exception. 10 Appellant admits another 36 but provides additional information, which
    we find fails to dispute the facts asserted and relied on, by the government. 11 The
    remaining 62 are denied, but generally in ways insufficient to establish that a dispute
    actually exists.
    Issue 1: Delay due to lack of as-built drawings
    Appellant argues there are two issues with the as-built drawings, one relating to
    floor drawings, the other progressive collapse and that Modification 1A only resolved
    the floor drawing issue (SUMF ¶¶ 20, 22, 28-31, 36).12 Appellant principally relies on
    the deposition of John Phillips in support of its assertions in this regard. However, the
    deposition transcript cited, ex. 2, is not in the record. Ex. 2 to appellant’s brief is a
    series of Contractor Quality Control Reports. There is an Appendix B to the
    government’s brief, which includes excerpts from Mr. Phillips’ deposition, but does
    not include the pages cited by appellant. We find that appellant has failed to properly
    dispute the facts asserted by the government with respect to this issue. In any event,
    the record establishes that with respect to this sub-claim appellant has received all of
    10 Statement of Undisputed Material Facts (SUMF) ¶¶ 1-5, 7-8, 10-16, 18-19, 21, 32,
    66, 73, 75-80, 88, 90-91, 96, 98-99, 102-106, 108-109, 114-116, 118, 122-133,
    136, 142-146, 150, 152, 156, 158-166, 170-171, 173, and 175 (gov’t mot.
    at 1-28; app. opp’n at 1-15).
    11 SUMF ¶¶ 20, 22, 24-27, 36, 67, 69, 71-72, 74, 81, 87, 89, 92-95, 97, 110, 112, 117,
    119-121, 135, 138-141, 147-149, 151, 169 (gov’t mot. at 4-28; app. opp’n at 4-15).
    12 Appellant’s opposition addresses each of the 175 paragraphs of facts set forth in the
    government’s motion. Most of its argument is set forth in its responses to the
    government’s statement of facts. Rather than cite to page numbers in
    appellant’s brief, we cite the SUMF paragraph numbers.
    12
    the dollars and time claimed (SOF ¶¶ 3-4, 17(1), 19(1)). Appellant has failed to
    dispute these facts. Furthermore, appellant has failed to explain how having received
    all the time and money it claimed with respect to this part of its claim there is anything
    left to possibly dispute. Accordingly, we grant the government’s motion with respect
    to Issue No. 1.
    Issue 2: Audio Visual Changes in Building 2834
    Although the government seeks full summary judgment against the entirety of
    appellant’s claim, the government’s motion includes no facts relating to this issue.
    The government admits the claim is at least partially meritorious and states the
    government is in the process of issuing a modification for it (gov’t mot. at 32, 43).
    The government has provided no further information regarding whether it has issued a
    modification for this claimed additional work and if so, whether appellant has accepted
    same as full compensation for this issue. We find the government has failed to meet
    its burden of proof with respect to Issue 2. Accordingly, we deny the government’s
    motion as it pertains to this issue.
    Issue 3: HVAC Testing
    Appellant summarily denied all of the facts asserted by the government relating
    to this issue, SUMF ¶¶ 38-65, asserting they were irrelevant without any further
    explanation. Appellant asserted the facts relevant to this issue were provided in its
    counter-statement of facts but failed to actually identify any facts, leaving the citation
    blank (app. opp’n at 7). The government argues, based on documents in the record,
    that appellant failed to state a claim because although appellant asserts it was required
    to perform work outside the scope of the contract, appellant has provided no
    documents to support the amount claimed, a default judgment against a subcontractor,
    in which action appellant pleaded the subcontractor had breached its contract with
    appellant by failing to perform contractually required work (gov’t mot. at 33). The
    government argues both of these propositions cannot be true. We find appellant has
    failed to properly dispute the facts asserted by the government, which are sufficient to
    establish appellant has failed to state a claim against the government and grant the
    government’s motion with respect to this issue (gov’t mot. at 33; SOF ¶¶ 17(3), 19(3)).
    Issue 4: Unforeseen condition regarding levelness of concrete pads
    SUMF ¶¶ 66-101 relates to this issue (gov’t mot. at 11-17). This claimed item
    involves two issues, additional furring work required to bring the slabs’ edges into
    vertical alignment and the installation of Ardex floor leveling compound to make the
    13
    slabs acceptably flat 13 (SOF ¶¶ 7, 17(4)). The government argues, it is undisputed that
    both issues have been resolved by bilateral Modifications Nos. 1C and 04 (gov’t mot.
    at 34-37). Appellant argues the modifications did not resolve all of the issues, but
    provides little to dispute the facts asserted by the government, other than this
    conclusory argument. Appellant either admits SUMF ¶¶ 66-78, which relate to the
    furring issue only or adds additional information stating two issues, furring, and floor
    levelness were involved or that it had not seen the government’s PNM relating to
    Modification No. 1C (app. opp’n, SUMF ¶¶ 66-78). We find appellant has not
    properly disputed the facts asserted by the government relating to the furring issue,
    which are supported by documents in the record. Accordingly, we grant the
    government’s motion with respect to the furring issue.
    The flooring issue is another matter. Although not articulated very well, we
    understand appellant is arguing there are two slab levelness issues. One arising from
    the progressive collapse requirements due to the application of fiberwrap material to
    the slabs in some locations and a general levelness issue that may be unrelated to the
    use of fiberwrap. We understand appellant attempts to articulate this where it states in
    response to several of the facts relied on by the government: “there was a broader
    issue of floor levelness beyond the corridors and bays addressed in Modification
    No. 04. See Phillips Dep. Tr. at 67, lines 5-18,” or words to that effect. (App. opp’n,
    SUMF ¶ 81; see also ¶¶ 82-89) The record, however, does not include the part of
    Mr. Phillip’s transcript that appellant cites. The only transcript of Mr. Phillip’s
    deposition in the record is found in Appendix B to the government’s motion.
    Appendix B includes only excerpts of Mr. Phillips’ deposition transcript and it does
    not include the pages cited by appellant. In many, if not most, instances the failure to
    include cited transcript pages in the record could lead to a finding that the non-movant
    has failed to properly dispute the facts asserted by the movant and a ruling in the
    movant’s favor. However, we find the record does include sufficient evidence for us
    to conclude that there may be two separate issues relating to slab levelness (SOF ¶¶ 7,
    10). When appellant first raised the slab levelness issue in July 2013, there was no
    mention of progressive collapse and fiberwrap material being the reason why the slabs
    needed to be levelled. Instead, this appears to be an issue arising from the previous
    construction of the slabs out of tolerance as specified by the American Concrete
    Institute (ACI). The leveling of the slabs that is addressed in Modification No. 04 is
    specifically stated to be attributable to the application of fiberwrap, something that is
    possibly independent and apart from the levelness issue that was initially raised by
    appellant in July 2013. While appellant has not disputed the government’s factual
    assertions as nicely as we would have preferred, we find the record on the issue of slab
    levelness is sufficiently clouded that the better course in the circumstances is to
    exercise our discretion to hold a hearing on this issue. See S.C. Public Serv. Auth.,
    13   Although the Issue 4 narrative appears to describe only the floor leveling work, the
    July 29, 2013 letter cited in support of the claim involves both issues (SOF ¶ 7).
    14
    ASBCA No. 53701, 04-2 BCA ¶ 32,651 at 161,601 citing 
    Anderson, 477 U.S. at 255
    ,
    Blue Cross and Blue Shield Assoc., ASBCA No. 53632, 04-1 BCA ¶ 32,413
    at 160,447. Accordingly, we deny the government’s motion as it relates to the slab
    levelness issue of appellant’s claim.
    Issue 5: 70-day time extension due to fire alarm changes
    GSC seeks a time extension and potentially, the associated, but unquantified,
    extended overhead costs arising from changes made to the fire alarm system. 14 The
    government recognized the original claim had merit, but the parties were not able to
    agree on the amount of time involved in performing the additional work.
    Consequently, the government issued two unilateral modifications, Modification
    Nos. 1G and 1H, for this additional work (SOF ¶ 12). The parties were able to agree
    on the costs for the additional work, which were paid under Modification No. 1G.
    After the work was performed the government recognized and granted appellant a
    10-day non-compensatory time extension for performing the work (id.). The
    government seeks summary judgment, arguing appellant cannot establish entitlement
    and that appellant has been fully compensated by the two modifications (gov’t mot.
    at 37-38). The government asserts appellant has arbitrarily selected a 50-day activity
    that it inserted into its schedule to establish the 70 calendar day time extension it
    seeks and that documents in the record indicate the additional work took much less
    time to perform than the time claimed (gov’t mot. at 38-40). The government also
    argues the deposition testimony of appellant’s accountant undercuts appellant’s claim
    (id.).
    This issue involves SUMF ¶¶ 102-122. We find that if the facts as asserted by
    the government were taken to be true that they would defeat appellant’s claim for
    extended overhead and a time extension beyond that already granted by Modification
    No. 1H. Appellant admitted, without any exception, 12 of these facts. Appellant only
    denied three of the government’s factual assertions, SUMF ¶¶ 107, 111 and 113.
    Appellant admitted but added additional information to the remaining six paragraphs,
    which failed to dispute the facts asserted by the government. Although the fact that
    appellant refused to execute the modifications because it disagreed with the
    government’s assessment of the time required to perform the additional work would
    appear to at least superficially establish that a dispute exists regarding the facts
    associated with this issue. An examination of the assertions with respect to the SUMF
    appellant has ostensibly disputed reveals appellant has failed to dispute the facts
    asserted by the government.
    14   It is not clear from the record before us whether appellant is seeking a compensatory
    or non-compensatory time extension.
    15
    The non-movant must cite specific materials in the record that we, as the fact
    finder could use to find in its favor and this appellant has failed to do. See Optimum
    Corp. v. Emcore Corp., 
    603 F.3d 1313
    , 1319-1320 (Fed. Cir. 2010) (“When a party
    has failed to introduce evidence sufficient to establish the existence of an essential
    element of that party’s case in accordance with the applicable standard of proof,
    summary judgment is properly granted against that party”), citing Novartis Corp. v.
    Ben Venue Labs, Inc., 
    271 F.3d 1043
    , 1046 (Fed. Cir. 2001). To establish its right to
    a time extension, appellant must show that the additional work involved lies on the
    critical path of the schedule. Kinetic Builder’s Inc. v. Peters, 
    226 F.3d 1307
    ,
    1316-1317 (Fed. Cir. 2000) citing Essex Electro Eng’rs, Inc. v. Danzig, 
    224 F.3d 1283
    , 1295-96 (Fed.Cir. 2000), Sauer Inc. v. Danzig, 
    224 F.3d 1340
    , 1345-46 (Fed.
    Cir. 2000). In the three SUMF appellant denied, ¶¶ 107, 111 and 113, appellant
    referenced the backup it had submitted in early March 2015 in support of its proposal,
    which led to Modifications Nos.1G and 1H. This backup included fragnets, one of
    which includes an additional activity, 6-BO009 with a 70-day performance period
    extending from March 5, 2015 to May 13, 2015. Although the fragnet includes
    handwriting stating the addition of the fire alarm changes affects the critical path, the
    record includes nothing more than this conclusory assertion. There is no overall
    schedule, or logic submitted, which would explain how or why the addition of this
    work would affect the critical path. Even more problematic, appellant’s continued
    reliance on its initial submission without more fails to even address, much less put into
    issue, the government’s factual assertions, supported by documents in the record, that
    the work was completed by the end of March 2015, much more quickly than appellant
    contemplated at the time it prepared its proposal and the fragnets. On the record
    before us, the claim is implausible because appellant has failed to produce any
    evidence to counter the government’s factual assertions. Appellant was required to
    produce persuasive evidence and has failed to do so. The record, when considered as a
    whole, could not be reasonably found to favor appellant. Although appellant, as the
    non-movant is entitled to have all reasonable inferences drawn in its favor, we find
    that the factual assertions of the government regarding when the additional work
    required was performed and how much time was involved, is unrebutted except with
    conclusory, unsupported assertions, which leave no reasonable inferences to be drawn
    for appellant. See Matsushita Electric. Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 586-587 (1986). Accordingly, we find SUMF ¶¶ 102-122 have been admitted
    and find the government is entitled to summary judgment with respect to this issue.
    Issue 6: Repair of damages from basement flood
    This issue involves repair costs for two flooding incidents and an increase to
    appellant’s insurance premiums, which total $394,750.68, including $27,497.25
    claimed for the increased insurance premiums (SOF ¶ 17 (6)). As noted above,
    appellant has withdrawn the insurance premium part of its claim. The government
    asserts the first flooding incident was caused by appellant, attributing it to a
    16
    cross-threaded pipe. (SUMF ¶¶ 135-137) Appellant has properly disputed the facts
    asserted by the government relating to the first flooding incident. It has submitted an
    affidavit from its president, Mr. Locke McKnight, in which Mr. McKnight asserts the
    government’s work orders establish that other contractors were working on the
    plumbing in the area where the flooding occurred. The affidavit is accompanied by
    photographs, which Mr. McKnight asserts establish that someone other than appellant
    worked on the piping after appellant had finished its work. We find there is a factual
    dispute regarding the identity of the party responsible for the cross-threaded pipe,
    which makes this issue unsuitable for resolution by motion for summary judgment.
    Although this issue involves an additional flooding incident, because the costs have
    not been segregated and we have found there is a factual dispute regarding the first
    flooding incident, we need not address this additional flooding incident.
    The government also asserts appellant has been paid for the costs appellant
    incurred associated with the flooding by its insurance company and is not obligated to
    repay same and that all of the evidence in the record suggests appellant does not hold
    the government responsible for the flooding (gov’t mot. at 41-42; gov’t reply
    at 13-14). Although not outlined in great detail, the government also argues appellant
    is not legally entitled to be paid twice for the same costs (gov’t reply at 13-14). The
    government’s assertions and argument ignore Mr. McKnight’s assertion that the
    government is responsible for the flooding and the plain language of the settlement
    agreement between appellant and its insurance company, which requires appellant to
    repay the insurance company “to the extent GSC recovers from Roto-Rooter or any
    other third person.” (SOF ¶ 22) (Emphasis added) This includes any potential
    recovery appellant may receive from the government and thus is consistent with
    appellant’s assertion the government is responsible for the flooding. For all of the
    above stated reasons we deny the government’s motion as it relates to this issue as
    modified by appellant’s withdrawal of the increased premium portion of this issue.
    Issue 7: Release of liquidated damages/contract balance
    GSC seeks the payment of the outstanding contract balance. The government
    opposes, arguing it is undisputed it is entitled to liquidated damages in an amount
    exceeding the balance claimed. In support of its argument, the government asserts the
    contract provided for liquidated damages in the amount of $1,029.64 per calendar day,
    that the contract completion date as extended by modifications was February 15, 2015,
    and that the actual completion occurred June 19, 2015, or 124 days late, entitling the
    government to $127,675.36 in liquidated damages. (SUMF ¶¶ 163-172) Appellant
    admitted these facts, except it asserted the government has admitted substantial
    completion occurred on May 8, 2015, and took possession of the building on May 11,
    17
    2015.15 In its reply brief the government admits for purposes of the motion that
    substantial completion occurred on May 8, 2015 (gov’t reply at 15). The government
    states that appellant is entitled to a 21-day time extension for Issue No. 2, which
    extends the contract completion date to March 8, 2015 and that appellant, therefore,
    completed the project 61 calendar days late (id.). The government argues it is thus
    undisputed that it is entitled to $62,808.04 (61 x $1,029.64) in liquidated damages.
    The facts as revised by the government and appellant are undisputed and establish the
    government’s right to liquidated damages in the amount of $62,808.04. Accordingly,
    the government’s motion is granted with respect to Issue No. 7 in this amount.
    CONCLUSION
    The government’s motion is partially granted and partially denied as set forth
    above.
    Dated: June 4, 2020
    CHRISTOPHER M. MCNULTY
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    RICHARD SHACKLEFORD                                OWEN C. WILSON
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    15   Appellant also asserted the government took possession of Building 2833 as early as
    November 17, 2014 (SUMF ¶¶ 172, 174; Counter-Statement of Facts ¶ 10).
    Although this assertion is supported by evidence in the record, see SOF ¶ 11,
    appellant argues the Board should use the date of May 8, 2015, as the date of
    substantial completion in reaching its decision (app. opp’n at 23). We agree
    with appellant due to the HVAC system not working properly when the
    government took possession. Kinetic Builder’s Inc. v. Peters, 
    226 F.3d 1307
    ,
    1315-16 (Fed. Cir. 2000) (“A project should be considered substantially
    completed when it is capable of being used for its intended purpose.”) We find
    that a building without a properly functioning HVAC system is not capable of
    being used for its intended purpose.
    18
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 61380, Appeal of GSC
    Construction, Inc., rendered in conformance with the Board’s Charter.
    Dated: June 5 2020
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    19