U.S. Coating Specialties & Supplies, LLC ( 2017 )


Menu:
  •               ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of--                                 )
    )
    U.S. Coating Specialties & Supplies, LLC    )     ASBCA No. 58245
    )
    Under Contract No. W912EE-10-C-0019         )
    APPEARANCES FOR THE APPELLANT:                    Louis H. Watson, Jr., Esq.
    Watson & Norris, PLLC
    Jackson, MS
    Mr. Earl Washington
    Chief Operation Officer & CEO
    APPEARANCES FOR THE GOVERNMENT:                   Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    John M. Breland, Esq.
    Walker D. Moller, Esq.
    Adam Caudle, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Vicksburg
    OPINION BY ADMINISTRATIVE JUDGE WOODROW ON THE
    GOVERNMENT'S RENEWED MOTION FOR SUMMARY JUDGMENT
    INTRODUCTION
    This appeal arises from the government's termination of the captioned contract
    for default. On 9 April 2015, the Board issued a decision denying the government's
    amended motion to dismiss or, in the alternative, for summary judgment. U.S. Coating
    Specialties & Supplies, LLC, ASBCA No. 58245, 15-1BCA~35,957 (U.S. Coating!).
    The government now files a renewed motion for summary judgment, contending that
    an alleged prior oral agreement between appellant and the Assistant U.S. Attorney
    (AUSA) during appellant's Chapter 11 bankruptcy proceedings is barred by the parol
    evidence rule, and alternatively, the AUSA lacked actual authority to enter into the
    alleged agreement. For the reasons set forth below, we deny the motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 21June2010, the U.S. Army Corps of Engineers (Corps) awarded
    Contract No. W912EE-10-C-0019 (contract) to appellant, U.S. Coating Specialties &
    Supplies, LLC (U.S. Coating) in the amount of$11,383,000 for the construction of a
    U.S. Army Engineer Research and Development Center Information Technology
    Laboratory office building and computer facility in Vicksburg, Mississippi (R4, tab 3
    at 5-6 1).
    2. The contract included the standard Federal Acquisition Regulation (FAR)
    default clause, 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984),
    which provided, in pertinent part:
    (a) If the Contractor refuses or fails to prosecute the work
    or any separable part, with the diligence that will insure its
    completion within the time specified in this contract
    including any extension, or fails to complete the work
    within this time, the Government may, by written notice to
    the Contractor, terminate the right to proceed with the
    work (or the separable part of the work) that has been
    delayed ....
    (c) If, after termination of the Contractor's right to
    proceed, it is determined that the Contractor was not in
    default, or that the delay was excusable, the rights and
    obligations of the parties will be the same as if the
    termination had been issued for the convenience of the
    Government.
    (Id. at 133-34)
    3. On 13 January 2012, during performance of the contract, U.S. Coating
    sought bankruptcy protection, filing a Chapter 11 voluntary petition in the United
    States Bankruptcy Court for the Southern District of Mississippi (Bankruptcy Court)
    (R4, tab 4).
    4. On 24 February 2012, Travelers Casualty and Surety Company of America
    (Travelers), U.S. Coating's surety for the contract, filed a motion ("Dkt. #38") in the
    Bankruptcy Court, seeking relief from the automatic stay imposed by U.S. Coating's
    bankruptcy filing to enforce its rights under a General Agreement of Indemnity
    between Travelers and U.S. Coating (R4, tab 5). Travelers also filed another motion
    ("Dkt. #39") on the same date to compel rejection of the contract, or alternatively, to
    1
    Citations to the Rule 4 file are to the consecutively-numbered pages unless otherwise
    indicated.
    2
    compel U.S. Coating to assume or reject the contract pursuant to 11 U.S.C. § 365
    (supp. R4, tab 1).
    5. On 13 March 2012, Mid State Construction Company, Inc. (Mid State), U.S.
    Coating's subcontractor, filed a response and limited objection to Travelers' motion
    for relief from the automatic stay ("Dkt. #52") (R4, tab 7). Mid State also filed a
    response and limited objection to Travelers' motion to compel on the same date
    ("Dkt. #53") (supp. R4, tab 3).
    6. On 13 March 2012, the AUSA for the Southern District of Mississippi,
    David N. Usry (AUSA Usry), on behalf of the U.S. Attorney, filed responses to
    Travelers' 24 February motions for the United States and the agency. In its response
    and limited joinder in Travelers' motion for relief from the automatic stay ("Dkt.
    #51 "), the United States moved to lift the automatic stay to pursue termination
    proceedings pursuant to FAR Part 49 and allow the Corps to complete the
    construction. (R4, tab 6 at 7) The United States pied that the CO "was proscribed
    from ... determin[ing] whether [U.S. Coating] was defaulted or is likely to default on the
    Contract for failure to make progress" (R4, tab 6 at 7, ~ 26). The United States also
    supported Travelers' motion to compel rejection of the contract, or alternatively, to
    compel U.S. Coating to assume or reject the contract (supp. R4, tab 2).
    7. The Bankruptcy Court of Mississippi issued an order on 30 March 2012,
    directing U.S. Coating, the debtor, to file a motion to assume or reject the contract by
    13 April 2012 and setting a trial on any such motion for 26 April 2012 (supp. R4,
    tab 4).
    8. After obtaining leave from the Bankruptcy Court to file its motion, U.S.
    Coating moved to assume the contract on 17 April 2012 (R4, tab 9). The United States·
    filed a response to the motion on 20 April 2012, demanding proof of U.S. Coating's
    ability to assume the contract at the 26 April 2012 trial. The response was filed by
    AUSA Usry. (R4, tab 12)
    9. Prior to the scheduled 26 April 2012 hearing, U.S. Coating, Travelers, the
    United States, and Mid State advised the Bankruptcy Court that they reached a
    settlement on pending issues set for trial and submitted a proposed order for the
    Bankruptcy Court's approval (R4, tab 20 at 45 2).
    10. Based on the parties' communicated settlement and proposed order, the
    Bankruptcy Court judge issued an order on 25 April 2012, stating in pertinent part:
    2
    Citation is to the original pagination.
    3
    There came on for the Court's consideration for the
    following pleadings:
    A.   Motion for Relief from the Automatic Stay
    [Dkt. #38] ("Automatic Stay Motion") filed by Travelers
    Casualty and Surety Company of America ("Travers"
    [sic]);
    B.    Mid State Construction Company, Inc. 's
    Response and Limited Objection to Travelers Casualty and
    Surety Company of America's Motion for Relief From the
    Automatic Stay [Dkt. #52] filed by Mid State Construction
    Company, Inc. ("Mid State");
    C.     United States of America's Response and
    Limited Joinder in Travelers Casualty and Surety
    Company of America's Motion for Relief from the
    Automatic Stay [Dkt. #51] filed by the United States of
    America on behalf of the Corps of Engineers ("Corps");
    D.    Debtor's Response to Travelers' Motion for
    Relief From the Automatic Stay [Dkt. #59) filed by U.S.
    Coating Specialities [sic] & Supplies, LLC ("Debtor");
    E.    Motion to Assume Executory ("Bonded")
    Contract Held by U.S. Army Corps of Engineers [Dkt.
    #87) ("Motion to Assume") filed by the Debtor;
    F.     Travelers Casualty and Surety Company of
    American's [sic] Objection to Motion to Assume [Dkt.
    #83);
    G.    Mid State Construction Company, Inc. 's
    Objection to Motion to Assume Executory Contract [Dkt.
    #84]; and
    H.     United States of America's Response to
    Debtor's Motion to Assume Executory ("Bonded")
    Contract [Dkt. #99).
    The Court, being fully advised in the premises and
    having considered the settlement of the foregoing
    pleadings as reflected below, finds that cause exists
    4
    pursuant to 11 U.S.C. § 362(d)(l) to grant Travelers and
    the Corps relief from the automatic stay and finds that the
    Motion to Assume should be denied and that the contract
    ("Contract") between the Debtor and the Corps ... should be
    deemed rejected.
    IT IS, THEREFORE, ORDERED that the Contract
    is hereby rejected as a matter of law.
    IT IS FURTHER ORDERED that the automatic
    stay is hereby terminated in favor of the Corps and
    Travelers with respect to the Contract and General
    Agreement of Indemnity ('"GAI").
    IT IS FURTHER ORDERED that this Order does
    not adjudicate or waive any respective rights and/or
    defenses of Travelers, the Corps, or Mid State with respect
    to the Contract, the Bonded Project, the GAI, or the
    performance and payment bonds issued by Travelers on
    the project.
    IT IS FURTHER ORDERED that, because the
    Automatic Stay Motion was sufficient to afford reasonable
    notice of the material provisions of the agreement between
    the parties and opportunity for hearing, the provisions of
    Fed. R. Bankr. P. 400l(d)(l)-(3) do not apply and the
    agreement is approved without further notice.
    ORDERED that the Stay of execution of Fed. R.
    Bankr. P. 400l(a)(3) is hereby waived. SO ORDERED.
    (R4, tab 13) The order was "AGREED TO and APPROVED AS TO FORM" by
    AUSA Usry, U.S. Coating's bankruptcy counsel, and representatives for Travelers,
    and Mid State (id. at 3).
    11. Following the issuance of the Bankruptcy Court's 25 April 2012 order, the
    contracting officer (CO), Jeri H. McGuffie (CO McGuffie), terminated the contract for
    default on the same date, asserting that U.S. Coating's consent to rejection of the
    contract constituted an anticipatory repudiation of the contract (R4, tab 2).
    12. On 30 April 2012, U.S. Coating formally filed a motion in the Bankruptcy
    Court to vacate the 25 April 2012 order. In its motion, U.S. Coating asserted that its
    consent to the settlement was based on representations made by AUSA Usry that the
    5
    Corps would terminate the contract for "reasons other than default" (R4, tab 15). The
    United States, Travelers, and Mid State filed responses to U.S. Coating's motion to
    vacate the 25 April 2012 order (R4, tabs 16-18).
    13. The Bankruptcy Court held a hearing on U.S. Coating's motion to vacate
    on 17 May 2012. Ruling from the bench, the Bankruptcy Court denied U.S. Coating's
    motion, holding that U.S. Coating's contentions were insufficient to set aside the
    25 April 2012 order. The Bankruptcy Court did not address the propriety of the
    Corps' termination of the contract for default. (R4, tab 20) The Bankruptcy Court
    subsequently issued a written Final Judgment based on the reasons articulated at the
    hearing (R4, tab 19).
    14. On 20 July 2012, U.S. Coating timely appealed from the CO's 25 April
    2012 final decision, terminating the contract for default.
    15. The Corps filed a motion to dismiss or, in the alternative, for summary
    judgment in this appeal, which was later amended, that was the subject of our
    9 April 2015 decision in US. Coating I, 15-1BCAiJ35,597 at 175,705. In our
    decision, the Board struck U.S. Coating's affirmative claims in its amended complaint
    and denied the remainder of the Corps' motion. 
    Id. at 175,707-08.
    16. On 21January2016, the Corps filed a renewed motion for summary
    judgment in this appeal. In support of its renewed motion, the Corps submitted the
    affidavits of CO McGuffie and AUSA Usry. CO McGuffie's affidavit stated in
    pertinent part:
    2. I was the Government Procuring Contracting Officer
    who awarded and administered the contract (number
    W9 l 2EE- l O-C-0019) that is the subject of this appeal.
    3. My authority as the duly authorized Contracting Officer
    under the subject Contract was never delegated to or
    usurped by the Assistant United States Attorney who
    represented the Corps in the bankruptcy proceeding that
    involved U.S. Coating and implicated contract number
    W9 l 2EE- l O-C-0019.
    4. Because of the Contractor's actions endangering
    performance on the contract, I had clear justification for
    termination for default. Due to the significant financial
    and contractual ramifications a termination for
    convenience would have presented to the Corps and our
    customer, I never would have agreed to terminate the
    6
    contract for convenience. The Assistant United State[s]
    Attorney had no authority granted to him on the subject
    contract. Had the Assistant United State[ s] Attorney
    advised or recommended a termination for
    convenience, which he did not, I would not have
    entertained such a recommendation.
    (Gov't reply, ex. L) AUSA Usry's affidavit stated in pertinent part:
    2. I represented the United States Army Corps of
    Engineers ("the Corps") in the Chapter 11 bankruptcy
    proceedings that involved the Corps' contract, number
    W912EE-10-B-001 l,l31with U.S. Coating Specialties &
    Supplies, LLC ("U.S. Coating"), the debtor ....
    3. I had conversations with U.S. Coatings' counsel in the
    bankruptcy proceedings, Herb Irvin, and
    representatives of the debtor on multiple occasions
    during the course of the bankruptcy proceedings.
    4. During my discussions and negotiations in the
    bankruptcy proceedings with debtor's counsel and
    debtor's representatives, I never promised anyone that
    the Corps would terminate the contract for convenience
    if U.S. Coating rejected the contract in bankruptcy.
    5. During my discussions and negotiations in the
    bankruptcy proceedings with debtor's counsel and
    debtor's representatives, I never did state or otherwise
    imply that I had any authority whatsoever to bind the
    Corps to terminate the contract for convenience.
    (Gov't reply, ex. M)
    17. In its opposition to the Corps' renewed motion for summary judgment,
    U.S. Coating relies on three affidavits of its employees - President and CEO,
    Mr. Earl J. Washington; Ms. Velma Day; and Mr. Alden Brooks - originally submitted
    3
    The referenced contract number appears to be a typographical error. The correct
    reference is Contract No. W912EE-10-C-0019. The referenced number,
    W912EE-10-B-001 l, pertains to Invitation for Bid No. W912EE-10-B-001 l
    (see gov't reply, ex. K).
    7
    in the earlier US. Coating I proceedings. Mr. Washington's affidavit stated in
    pertinent part:
    3. I never consented to a termination by default. I agreed
    to lift the automatic stay on the condition that U.S.
    Coating would be terminated only by convenience. I
    held this discussion with Travelers' legal counsel, the
    Respondent's legal counsel, and U.S. Coating's legal
    counsel, Herb Irvin, on April 24, 2012.
    (Gov't reply, ex. I) Ms. Day's affidavit stated that telephone discussions between U.S.
    Coating's counsel, Herb Irvin, and AUSA Usry took place on 24 April 2012, and there
    were discussions about the automatic stay being lifted to allow discussions about a
    termination for convenience (id., ex. G). Mr. Brooks'· affidavit stated that he received
    a telephone call on 24 April 2012 to attend a meeting to discuss a resolution that would
    allow for a termination of the contract for convenience. Mr. Brooks stated that U.S.
    Coating's counsel and AUSA Usry exchanged messages and it was his understanding
    that all parties agreed to terminate the contract for convenience. (Id., ex. H)
    DECISION
    Summary Judgment Standards
    The guidelines for summary judgment are well established; the granting of
    summary judgment is appropriate where there are no genuine issues of material fact
    and the movant is entitled to judgment as a matter of law. Celotex Corp. v. Catrett,
    
    477 U.S. 317
    , 322 (1986); DIRECTV Grp., Inc. v. United States, 
    670 F.3d 1370
    , 1374
    (Fed. Cir. 2012). The movant has the burden to establish that there are no material
    facts in dispute. A material fact is one which may affect the outcome of the case.
    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986). At the summary judgment
    stage, we do not resolve controversies, weigh evidence, or make determinations of
    credibility. 
    Id. at 253.
    All reasonable inferences are drawn in favor of the
    non-movant. 
    Id. at 25
    5. A movant is entitled to judgment as a matter of law if the
    non-movant "fails to make a showing sufficient to establish the existence of an
    element essential to [the non-movant's] case, and on which [the non-movant] will bear
    the burden of proof at trial." Celotex 
    Corp., 477 U.S. at 322
    .
    Discussion
    In US. Coating I, we concluded that summary judgment for the Corps was
    premature, stating that appellant should be given an opportunity to demonstrate that
    "its consent to the rejection of the contract was based upon an agreement with the
    government to terminate the contract, not for default, but for convenience." US.
    8
    Coating I, 15-1 BCA ~ 35,957 at 175,708. In its renewed motion for summary
    judgment, the Corps advances two new theories to bar U.S. Coating's introduction of
    an alleged prior oral agreement to terminate the contract for convenience for the
    purposes of contesting the propriety of the default termination. First, it contends that
    U.S. Coating's allegation of a prior agreement is barred by the parol evidence rule.
    Second, it contends that, even if the allegation is assumed true, the AUSA, whose
    representations U.S. Coating relies upon, lacked the requisite actual authority to bind
    the government to such an agreement.
    For the reasons set forth below, we reject both of the government's theories and
    deny the government's renewed motion for summary judgment.
    Parol Evidence Rule
    The Corps contends that there is no genuine issue of material fact that the
    Bankruptcy Court's 25 April 2012 order is a fully or partially integrated agreement,
    and therefore, the parol evidence rule prohibits U.S. Coating from introducing
    extrinsic evidence of an alleged prior oral agreement to contradict the terms of the
    parties' agreement. It asserts that the order was drafted, reviewed, and consented to by
    representatives of the parties involved prior to the Bankruptcy Court's issuance, and
    U.S. Coating does not contest that the order is an integrated agreement. (Gov't br.
    at 4; gov't reply at 16-17) The Corps also argues that the 25 April order expressly
    rejected the contract under bankruptcy law and that while the order does not contain
    terms pertaining to termination of the contract, the order stated that the Corps did not
    waive any rights with respect to the contract (gov't br. at 5; gov't reply at 15).
    In opposition, U.S. Coating contends that there are material factual disputes
    surrounding the 25 April order and the Corps' arguments "lack any evidentiary
    foundation" (app. opp'n at 7 of 8). It argues that it consented to the order in exchange
    for a termination of the contract for convenience and detrimentally relied on the
    AUSA's representations, citing to the affidavits of its employees previously submitted
    in US. Coating I (id. at 1-2, 7 of 8). U.S. Coating also contends that summary
    judgment is still premature because, while it has conducted written discovery, it has
    not orally deposed any witnesses (id. at 7 of 8).
    The parol evidence rule is a rule of substantive law that prohibits consideration
    of extrinsic evidence to alter the terms of a written agreement that "has been adopted
    by the parties as an expression of their final understanding." Barron Bancshares, Inc.
    v. United States, 
    366 F.3d 1360
    , 1375 (Fed. Cir. 2004) (citing David Nassif Assocs. v.
    United States, 
    557 F.2d 249
    , 256 (Ct. Cl. 1977)). Therefore, a writing that is final and
    complete is an integrated agreement, and the effect of integration is the inadmissibility
    of prior or contemporaneous agreements to modify or contradict the terms of the
    agreement. See David Nassif 
    Assocs., 557 F.2d at 256
    ; RESTATEMENT (SECOND) OF
    9
    CONTRACTS§§ 213, 215 (Am. Law Inst. 1981). Where a fully or completely
    integrated agreement exists, the writing cannot be supplemented with evidence of
    consistent or inconsistent additional terms or prior agreements that cover the same
    subject matter. Rumsfeldv. Freedom NY, Inc., 
    329 F.3d 1320
    , 1328 (Fed. Cir. 2003);
    RESTATEMENT (SECOND) OF CONTRACTS§§ 214, 216~
    In this appeal, the parties largely dispute whether the Bankruptcy Court's
    25 April 2012 order was intended to be a completely integrated agreement. A writing
    that is signed by both parties "and apparently complete on its face, may be decisive of
    the issue in the absence of credible contrary evidence." RESTATEMENT (SECOND) OF
    CONTRACTS § 210. An integration clause creates a strong presumption that the writing
    is purported to be a completely integrated agreement. Freedom 
    NY, 329 F.3d at 1328
    .
    On its face, the 25 April order contains no integration clause, nor does it contain
    express language indicating finality and completeness (SOF ,-i 10). The Corps
    concedes that the order does not contain express terms addressing termination of the
    contract (gov't br. at 5; gov't reply at 15).
    In the absence of unequivocal language indicating finality and completeness,
    we may examine the writing itself as well as the circumstances surrounding its
    execution, including the negotiations that produced it. David Nassif Assocs., 557 F .2d
    at 256; see also RESTATEMENT (SECOND) OF CONTRACTS§ 210 ("But a writing cannot
    of itself prove its own completeness, and wide latitude must be allowed for inquiry
    into circumstances bearing on the intention of the parties."). To ascertain whether the
    25 April 2012 order is a complete or partially integrated agreement, we must examine
    the parties' negotiations prior to and contemporaneous with the issuance of the order.
    See RESTATEMENT§ 209(2) ("Whether there is an integrated agreement is to be
    determined by the court as a question preliminary ... to application of the parol evidence
    rule.").
    The current record is incomplete to reach these determinations. As we
    concluded in our previous opinion, there are genuine issues of material fact regarding
    whether there was a separate oral agreement with the government to terminate the
    contract for convenience. US. Coating I, 15-1 BCA ,-i 35,957 at 175,708. Such an
    agreement, if it existed, would contradict directly the government's contention that the
    bankruptcy order is an integrated agreement. It also would call into question whether
    the contracting officer properly exercised her discretion in terminating the contract for
    default. 
    Id. Therefore, appellant
    should be given an opportunity to demonstrate that
    "its consent to the rejection of the contract was based upon an agreement with the
    government to terminate the contract, not for default, but for convenience." 
    Id. Finally, the
    Corps' emphasis on the parol evidence rule glosses over the
    implausibility of its position. It is hard to imagine why U.S. Coating would agree to
    settle the bankruptcy litigation in exchange for a termination for default. Indeed, U.S.
    10
    Coating's president, Mr. Earl Washington, stated in his affidavit that his agreement to
    the bankruptcy order was based on his understanding that such an order was necessary
    to proceed with negotiations with the Corps to allow the addition of a subcontractor to
    assist U.S. Coating in completing the contract. US. Coating I, 15-1 BCA, 35,957
    at 175,705 (citing R4, tab 20 at 23-30). Indeed, the Corps gives us no reason to doubt
    Mr. Washington's testimony that "I have not consented to any termination, and I will
    not consent to any termination" (R4, tab 20 at 33).
    Actual Authority
    Alternatively, the Corps argues that even if U.S. Coating's allegation of a prior
    oral agreement with the AUSA to terminate the contract for convenience were true,
    there is no genuine issue of material fact that the AUSA lacked actual authority to bind
    the government, and therefore, the agreement is unenforceable (gov't br. at 6-7). It
    contends that the requisite authority to make changes and determinations affecting the
    contract resides with the CO, and authority to terminate the contract for reasons other
    than default was not delegated to the AUSA, citing to J.H. Strain & Sons, Inc.,
    ASBCA No. 34432, 88-3 BCA, 20,909 for support (id. at 6-7; gov't reply at 9-10
    n.4). The Corps asserts that the AUSA never communicated or implied that he had
    authority to promise a termination of the contract for convenience and U.S. Coating
    has failed to present sufficient facts proving the AUSA either made the alleged
    agreement or had actual authority (gov't reply at 9-13). It also argues that prior to the
    25 April 2012 order, U.S. Coating was well aware that the CO was unwilling to
    terminate the contract for convenience or entertain U.S. Coating's attempts to propose
    a substitution of contractors. It maintains that the AUSA possesses no express
    authority under the regulations to terminate a contract for convenience, and that his
    authority during the bankruptcy proceedings was limited to settling claims arising
    under U.S. Coating's bankruptcy filing. (Gov't br. at 6-7; gov't reply at 9)
    Like its arguments regarding the parole evidence rule, U.S. Coating primarily
    argues that the Corps' actual authority theory lacks evidentiary foundation. It
    contends that it detrimentally relied on the AUSA's representations, and the record
    reflects that the "sole purpose" of its consent of the 25 April 2012 order was in
    exchange for a termination of the contract for convenience. U.S. Coating also alleges
    that while it has conducted written discovery it should be entitled to further discovery
    because it has not deposed any witnesses. (App. opp'n at 7 of 8)
    The Corps' argument regarding the authority possessed by AUSA Usry misses
    the point, because it fails to acknowledge the statutory delegation of settlement
    authority to the U.S. Department of Justice pursuant to 28 U.S.C. § 516. As a result of
    the bankruptcy filing, litigation at the Bankruptcy Court was within the control and
    purview of the Department of Justice, whose officers, under the supervision of the
    Attorney General, are tasked to conduct and supervise all litigation on behalf of the
    11
    United States and its agencies. See 28 U.S.C. §§ 516-520; Hughes Aircraft Co. v.
    United States, 
    534 F.2d 889
    , 901 (Ct. Cl. 1976) ("[U]nless otherwise provided by law,
    the Attorney General is charged by statute with exclusive and plenary power to
    supervise and conduct all litigation to which the U.S. is a party.").
    U.S. Coating's bankruptcy filing imposed an automatic stay pursuant to
    11 U.S.C. § 362(a), prohibiting the CO from commencing administrative actions or
    proceedings against U.S. Coating. Martel Truck & Tractor Serv., Inc., ENG BCA
    No. 6191, 96-2 BCA ~ 28,368 at 141,649. Therefore, the Corps could not terminate
    the contract for default absent permission from the Bankruptcy Court. 
    Id. at 141,650.
    The government acknowledged this constraint in its filings before the Bankruptcy
    Court, when it stated that the bankruptcy stay prevented it from "determin[ing]
    whether [U.S. Coating] was defaulted or is likely to default on the Contract for failure
    to make progress so as to endanger performance" (SOF ~ 6). While the Corps suggests
    that the CO could have pursued a termination of the contract for the government's
    convenience without violating the stay, it does not cite to any case law to support this
    assertion.
    The Corps cites to a Board decision, J.H. Strain & Sons, 88-3 BCA ~ 20,909, to
    support its contention that the alleged agreement was not binding because
    CO McGuffie, as the person authorized to make decisions related to the contract, did
    not delegate her authority to the AUSA. The Corps reliance on this decision is
    misplaced. In J.H. Strain, the Board concluded that a settlement agreement,
    negotiated by an engineer trial attorney but not approved by the CO, was
    unenforceable against the government. The engineer trial attorney, as a limited agent
    of the CO under the applicable procurement regulations, lacked authority to settle
    without delegation from the CO. 
    Id. at 105,
    702. In this appeal, the AUSA, as the
    authorized representative of the Attorney General, possesses the exclusive authority to
    settle matters in litigation before the United States bankruptcy courts. Because the
    AUSA's authority is exclusive, the question of whether the CO has delegated her
    authority is irrelevant.
    The Corps also contends that the applicable regulations contained within
    28 C.F .R. Part 0, Subpart Y, do not delegate authority to an AUSA to terminate a
    contract for convenience. Again, this argument misses the point that the AUSA, as the
    authorized representative of the Attorney General, possesses the exclusive authority to
    settle litigation before the United States bankruptcy courts. Subject to limitations, the
    regulations, in effect at the time of the Bankruptcy Court's 25 April 2012 order,
    redelegated authority to U.S. Attorneys to initiate suits, accept or reject compromises,
    and take any other action necessary to protect the interests of the United States. This
    specific suit and compromise authority may be further redelegated in writing to
    AUSAs. See 28 C.F.R. §§ 0.160, 0.168; 28 C.F.R. Pt. 0, Subpt. Y, App., sections I
    and 4 of Directive No. 1-10. There is no dispute that AUSA Usry, acting on behalf of
    12
    the U.S. Attorney, negotiated and settled matters arising from the Bankruptcy Court's
    25 April 2012 order which, according to the Corps, is the parties' settlement
    agreement. "A settlement agreement.. .arises when a claimant relinquishes its right to
    litigate its claim." Massie v. United States, 166 F .3d 1184, 1188 (Fed. Cir. 1999).
    U.S. Coating relies on the existence of an alleged prior agreement to terminate
    the contract for convenience to challenge the propriety of the default termination, and
    matters arising under the 25 April 2012 order served as the underlying basis for the
    termination. Although U.S. Coating has not adequately informed the Board reasons
    why additional discovery consisting of oral depositions of witnesses was necessary to
    its opposition (see FED. R. C1v. P. 56(d)), we conclude that the Corps is not entitled to
    judgment as a matter of law on the factual record and further development is needed.
    See NL.R.B. v. Smith Indus., Inc., 
    403 F.2d 889
    , 893 (5th Cir. 1983) (court should
    deny summary judgment if facts and circumstances have not been sufficiently
    developed to make a correct determination of the question oflaw). In particular, U.S.
    Coating should have an opportunity to fully develop the facts surrounding the parties'
    negotiations at the Bankruptcy Court. See Monarch Assurance P.L.C. v. United States,
    
    244 F.3d 1356
    , 1365 (Fed. Cir. 2001) (while commenting that likelihood of proving
    actual authority was remote, the Court granted additional discovery because, on
    balance, possible harm and appearance of unfairness outweighed inconvenience to the
    government).
    CONCLUSION
    The government's renewed motion for summary judgment is denied.
    Dated: 6 April 2017
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    13
    I concur
    ``
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 58245, Appeal of U.S.
    Coating Specialties & Supplies, LLC, rendered in conformance with the Board's
    Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    14