Blanchard's Contracting, LLC ( 2021 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                   )
    )
    Blanchard’s Contracting, LLC                  )    
    ASBCA No. 62508
    )
    Under Contract No. N40080-19-C-2026           )
    APPEARANCE FOR THE APPELLANT:                      Mr. Quentin W. Blanchard
    President/CEO
    APPEARANCES FOR THE GOVERNMENT:                    Craig D. Jensen, Esq.
    Navy Chief Trial Attorney
    Daniel J. Monahan, Esq.
    Senior Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE O’CONNELL
    The government moves to dismiss this appeal in part because appellant did not
    submit certain issues to the contracting officer that it has raised at the Board. The Board
    grants the motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. The parties entered into the above-referenced design-build contract in the
    amount of $523,513.60 on June 25, 2019. It required appellant, Blanchard’s Contracting,
    LLC (Blanchard), to furnish relocatable buildings. As modified, the contract provided
    for completion by July 31, 2020. (R4, tab 3 at 1, tab 4 at 1, 6, 49, tab 18)
    2. On April 17, 2020, Blanchard submitted a claim to the contracting officer (CO)
    in the amount of $73,304. It contended that the government had delayed the project from
    June 25 to October 22, 2019, or 119 days, at a rate of $616 per day. (R4, tab 20) The
    claim does not explain why Blanchard contends it was delayed, other than to state that the
    government did not issue a notice to proceed.
    3. The CO denied the claim on May 6, 2020. She professed not to understand
    what the claim was about. She observed that the period for which Blanchard claims to
    have been delayed corresponded almost exactly with the design phase of the project
    (which she said Blanchard completed on October 17, 2019). She stated that Blanchard’s
    project manager was “heavily involved” in this process and that “[w]e never received any
    concern.” The CO determined that the Navy had not delayed the project but that
    Blanchard subsequently caused 138 days of delay due to problems with its heating,
    ventilation, and air conditioning (HVAC) design between October 30, 2019, and
    March 16, 2020. (R4, tab 21)
    4. Blanchard filed a timely appeal on May 9, 2020.
    5. On August 12, 2020, Blanchard filed a motion for summary judgment. It stated
    in the motion that it had attached an amended claim at tab 9 to the motion (mot. at 2).
    The amended claim repeated Blanchard’s demand for the $73,304 sought in the original
    claim. In addition, it sought $50,000 for meeting with government officials and
    producing drawings (the “drawing claim”). It further sought $173,712 for delay from
    October 23, 2019 (the day after the first delay claim ended) to the revised completion
    date of July 31, 2020 (the “second delay claim”). (Mot., tab 9) The motion states: “the
    delays were caused by internal government issues relating to changes the end user require
    [sic] e.g. HVAC Upgrades, Electrical Upgrades, additional research for cubical layout
    additional requirements and increased requirement regarding number of personnel the
    new room will accommodate . . .” and references modification A00001, which extended
    the contract completion date from March 20 to July 31, 2020 (mot. at 2).
    6. The Board conducted a status conference on September 24, 2020. A
    memorandum of the conference call authored by the previous judge stated that the Board
    would hold Blanchard’s summary judgment motion in abeyance until appellant had
    conducted sufficient discovery to support the motion. The Board also directed Blanchard
    to file a chronological list of events that reflect the government actions that delayed its
    performance.
    7. On October 7, 2020, the Navy filed a motion to dismiss for lack of jurisdiction
    Blanchard’s drawing claim and the second delay claim because, it contends, Blanchard
    never submitted these issues to the CO in a claim.
    8. Blanchard filed a response to the motion on October 9, 2020. It did not dispute
    the Navy’s contention that neither the drawing claim nor the second delay claim had been
    submitted to the CO. However, it contended without elaboration that the claim(s) is
    “related” to the initial claim (app. resp. at 1), but it is not clear if it makes this contention
    with respect to just the second delay claim or the drawing claim as well. The response
    contains a chronological list as the Board ordered during the September 24 status
    conference but it is not illuminating as to the specific government actions that caused
    delays. The closest it gets is a reference to tab B-4 to its response, which it describes as
    “Government Changes that delayed the project are field changing the contract” (app.
    resp. at 4). Tab B-4 contains a potpourri of documents (emails, letters, subcontractor
    change order requests, requests for information, drawings), on a variety of issues (for
    example, fire alarms, electrical issues, and cuts to walls), many of which are internal to
    appellant and its subcontractors. However, due to the absence of a clear narrative
    2
    explaining how these events delayed the project, appellant’s position with respect to the
    specific causes of either the first or second delay claim remains unclear.
    DECISION
    The Contract Disputes Act (CDA) provides that “[e]ach claim by a contractor
    against the Federal Government relating to a contract shall be submitted to the contracting
    officer for a decision.” 
    41 U.S.C. § 7103
    (a)(1). For the Board to possess jurisdiction
    under the CDA, “the contractor must submit a proper claim—a written demand that
    includes (1) adequate notice of the basis and amount of a claim and (2) a request for a
    final decision.” M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1328
    (Fed. Cir. 2010). In addition, the contractor must have received the CO’s final decision,
    or a deemed denial, on that claim. 
    Id.
     A contractor who has appealed to the Board may
    increase the amount of its claim but may not pursue new claims not presented to the CO.
    Santa Fe Engineers, Inc. v. United States, 
    818 F.2d 856
    , 858 (Fed. Cir. 1987).
    The Court of Appeals for the Federal Circuit has stated that two claims may be
    considered the “same” for CDA jurisdictional purposes if “they arise from the same
    operative facts, claim essentially the same relief, and merely assert differing legal
    theories for that recovery.” Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365 (Fed.
    Cir. 2003). In Scott Timber, the Federal Circuit characterized the claim submitted to the
    CO and the claim the plaintiff pursued in court as presenting “slightly different legal
    theories” but held that they could be treated as the same claim for jurisdictional purposes.
    Scott Timber, 
    333 F.3d at 1366
    .
    More recently, the Federal Circuit has held that “we should treat requests as
    involving separate claims if they either request different remedies (whether monetary or
    non-monetary) or assert grounds that are materially different from each other factually or
    legally.” K-Con Bldg. Sys., Inc. v. United States, 
    778 F.3d 1000
    , 1005 (Fed. Cir. 2015)
    (emphasis by the Court). Similarly, in Lee’s Ford Dock, Inc. v. Secretary of the Army, the
    Court of Appeals held that a “claim is new when it ‘present[s] a materially different factual
    or legal theory’ of relief.” 
    865 F.3d 1361
    , 1369 (Fed. Cir. 2017) (quoting K-Con, 778 F.3d
    at 1006). In Lee’s Ford, the Court held that the Board lacked jurisdiction when the
    contractor had presented to the CO a claim for reformation based on mutual mistake and
    frustration of purpose but at the Board had pursued a claim for knowing misrepresentation
    by nondisclosure. Id. at 1369-70. The Federal Circuit has also emphasized that this rule is
    not so rigid that a party is precluded from adding factual details or legal argumentation in
    the course of litigating the claim. K-Con, 778 F.3d at 1006.
    Applying this test to the current matter, we conclude that appellant’s drawing
    claim is clearly a new claim because it is not a delay claim but rather a claim for
    additional or changed work that arises from operative facts involving creation of
    drawings (SOF ¶ 5) that were not presented to the contracting officer. E.g., Santa Fe
    3
    Engineers, 
    818 F.2d at 859
     (contractor that had presented claim to CO for impact costs
    related to three change orders could not pursue a claim at the Board for “total job
    disruption” due to the collective nature of all the changes on the project). The drawing
    claim is dismissed for lack of jurisdiction.
    With respect to delay, the government states in its brief that “the factual and legal
    underpinnings of Appellant’s April 17, 2020 claim are not clear,” but it has not moved to
    dismiss that first delay claim (mot. at 3). Because the Navy has not moved to dismiss, the
    Board will not address that claim.
    With respect to the second delay claim, Blanchard apparently contends that the
    basis for that delay claim is “HVAC Upgrades, Electrical Upgrades, additional research
    for cubical layout additional requirements and increased requirement regarding number
    of personnel the new room will accommodate” (SOF ¶ 5). None of these assertions were
    brought to the attention of the CO in a claim and, as a result, she never had the
    opportunity to consider them and resolve them prior to litigation. They also involve a
    different period of time than the submitted claim. Accordingly, the Board lacks
    jurisdiction to consider the second delay claim. 
    41 U.S.C. § 7103
     (a)(1); K-Con,
    778 F.3d at 1006; Maropakis, 
    609 F.3d at 1328
    .
    CONCLUSION
    The government’s motion is granted. The drawing claim and the second delay
    claim are dismissed for lack of jurisdiction.
    Dated: February 22, 2021
    MICHAEL N. O’CONNELL
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    4
    I concur                                           I concur
    RICHARD SHACKLEFORD                                OWEN C. WILSON
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62508
    , Appeal of
    Blanchard’s Contracting, LLC, rendered in conformance with the Board’s Charter.
    Dated: February 23, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 62508

Judges: O'Connell

Filed Date: 2/22/2021

Precedential Status: Precedential

Modified Date: 3/17/2021