Sauer Incorporated ( 2022 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                    )
    )
    Sauer Incorporated                             )   
    ASBCA No. 62395
    )
    Under Contract No. W91278-07-D-0030            )
    APPEARANCE FOR THE APPELLANT:                      Gina P. Grimsley, Esq.
    Counsel
    APPEARANCES FOR THE GOVERNMENT:                    Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Laura J. Arnett, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, Savannah
    OPINION BY ADMINISTRATIVE JUDGE STINSON ON
    GOVERNMENT’S MOTION FOR RECONSIDERATION
    The government requests reconsideration of our April 16, 2021, decision denying
    the government’s motion for summary judgment and granting, in part, the cross-motion
    for summary judgment filed by appellant Sauer Inc. (Sauer). Sauer, Inc., 
    ASBCA No. 62395
    , 
    21-1 BCA ¶ 37,845
    . Sauer appealed the denial of its claim challenging the
    government's assessment of liquidated damages, based upon appellant’s substantial
    completion of the Task Order. We granted appellant’s motion, in part, based upon
    appellant’s completion of Phases I and II of the Task Order. Appellant’s motion was
    denied, in part, due to material issues of fact regarding substantial completion of Phase III
    of the Task Order, as well as issues regarding proper apportionment of the liquidated
    damages rate. Familiarity with that decision is presumed. For the reasons stated below,
    the government’s motion for reconsideration is denied.
    DISCUSSION
    “Motions for reconsideration do not afford litigants the opportunity to take a
    ‘second bite at the apple’ or to advance arguments that properly should have been
    presented in an earlier proceeding.” Dixon v. Shinseki, 
    741 F.3d 1367
    , 1378 (Fed. Cir.
    2014). “But if we made mistakes in our findings of fact or conclusions of law, or by
    failing to consider an appropriate matter, reconsideration may be appropriate.” Supreme
    Foodservice GMBH, 
    ASBCA No. 57884
     et al., 
    20-1 BCA ¶ 37,716
     at 183,090 (citation
    omitted).
    I. The Government’s Contentions
    The government alleges four errors in our decision:
    I. The Board mistakenly concluded that it possesses
    jurisdiction to consider the reasonableness and enforceability
    of the liquidated damages (LD) rate incorporated into the
    contract.
    II. The Board failed to appreciate that Sauer waived any
    argument as to the reasonableness and enforceability of the
    LD rate incorporated into the contract.
    III. The Board erred when it concluded, as a matter of law,
    that the LD rate is unenforceable.
    IV. The Board erred in re-writing the contract to adopt
    phased LDs when the parties never agreed to any such
    provision.
    (Gov’t mot. at 2)
    II. Reasonableness and Enforceability of the Liquidated Damages Rate
    The government’s first assignment of error is based upon the suggestion that we
    made a determination regarding the “reasonableness and enforceability” of the specific
    liquidated damages rate incorporated in the task order. 1 The government’s argument is
    based upon a false premise. Our decision did not address, let alone determine, whether
    the actual liquidated damages rate imposed by the task order was reasonable, nor did we
    decide whether we had jurisdiction to determine the reasonableness of the rate. Our
    decision held, in the first instance, that the government had failed to meet its burden of
    proof to establish the propriety of imposing liquidated damages under the circumstances
    of this appeal, based upon Board precedent holding that assessment of the full amount of
    1
    In its reply brief filed in support of its motion for summary judgment, the government
    argued that “Sauer’s certified claim dated 6 September 2019 does not raise the
    issue of the reasonableness of the liquidated damages rate,” and “does not question
    the rate, how it was calculated, or whether it was reasonable in light of the phased
    nature of the project” (gov’t reply at 7). The government argued also that
    appellant’s “claim does not assert any facts regarding the rate which would put the
    government on notice that the reasonableness of the rate or how it was calculated
    was in dispute,” and that “Sauer’s claim challenging the liquidated damages rate
    presents a materially different factual and legal theory of relief.” 
    Id.
    2
    daily liquidated damages after substantial completion of the first two phases of a contract
    is unenforceable as a penalty. Sauer, 
    21-1 BCA ¶ 37,845
     at 183,757 (citing Dick Pacific
    Constr. Co., 
    ASBCA No. 57675
     et al., 
    16-1 BCA ¶ 36,196
     at 176,641).
    The government’s argument on reconsideration ignores the statement in our
    opinion which provided “[o]ur decision on the parties’ cross-motions for summary
    judgment turns not on the reasonableness of the liquidated damages rate as established by
    the government pre-award (nor are we able to decide that factual dispute on summary
    judgment), but, rather, on the government’s failure to apportion its liquidated damages at
    the time it assessed those damages.” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,759-60. As to the
    issue of whether the Board had jurisdiction to consider appellant’s challenge to the
    reasonableness or enforceability of the actual, daily rate established by the parties in the
    task order, our decision recognized, as noted by the government, “that appellant’s
    complaint does not address the reasonableness of the government’s liquidated damages
    rate.” 
    Id. at 183,760
    . We noted also that “Board Rule 6(d) provides for amendment of
    pleadings ‘upon conditions fair to both parties,’” and that, “[g]iven our decision here,
    appellant must decide what additional steps, if any, are necessary to properly tee up its
    affirmative defense for resolution in this appeal.” 
    Id.
     Our suggestion that appellant
    consider what steps, if any, were necessary to properly assert its affirmative defense, was
    stated in the context of the government’s jurisdictional challenge to appellant’s
    arguments regarding assessment of liquidated damages, which the government argued
    were not properly before us.
    Subsequent to the issuance of our decision, appellant filed a separate motion
    seeking leave to file several affirmative defenses, including one challenging the
    reasonableness of the government’s set daily rate. We address in a separate opinion the
    issues raised by appellant in its motion for leave filed pursuant to Board Rule 6(b), as
    well as the government’s response in opposition to that motion, including whether we
    have jurisdiction to consider appellant’s challenge to the reasonableness of the specific
    rate set forth in the task order.
    III. Appellant’s Alleged Waiver of the Reasonableness and Enforceability of the
    Liquidated Damages Rate
    The government argues that appellant did not challenge enforceability of
    liquidated damages until the filing of its cross-motion for summary judgment (gov’t mot.
    at 2). The government is mistaken. In its claim submitted to the contracting officer,
    appellant challenged the enforceability of liquidated damages, arguing that, because
    appellant had substantially completed the project, assessment of liquidated damages was
    improper. Sauer, 
    21-1 BCA ¶ 37,845
     at 183,752. In briefing on the parties’ cross-
    motions for summary judgment, appellant established, and the government did not
    dispute, that prior to the government’s decision to impose liquidated damages, appellant
    had completed Phases I and II of the three-phase project, and that, according to the
    3
    contractor’s calculations, Phase I alone accounted for 98 percent of the project work. 2
    Based upon these and other undisputed facts, we granted partial summary judgment to
    appellant, finding “that the government has failed to reference sufficient evidence
    demonstrating that a reasonable fact finder could decide in favor of the government on
    the issue of substantial completion of Phases I and II.” 
    Id. at 183,756
    .
    The government argues that appellant waived its right to challenge the
    reasonableness of the actual rate by failing to lodge a protest prior to award, stating “[i]f
    Sauer thought that the liquidated damages rate was unenforceable or unreasonable, it
    should have raised it prior to contract award” (gov’t mot. at 8). In addition to
    respondent’s jurisdictional argument that appellant’s challenge to the enforceability or
    reasonableness of the liquidated damages rate is a new claim, in its motion for
    reconsideration, the government suggests that appellant waived that defense because it
    was not asserted in its complaint (id. at 6-7). The government states, “should the Board
    find, as it did in its April 16, 2021 decision, that Sauer’s challenge to the enforceability
    and reasonableness of the liquidated damages rate is an affirmative defense that is
    permissible without submission of a claim to the contracting officer, Sauer has waived
    the assertion of that defense” (id. at 6). As discussed above, although our decision
    recognized the reasonableness of the liquidated damages rate as a potential affirmative
    defense, our decision did not decide whether we had jurisdiction to determine the
    reasonableness of the specific liquidated damages rate set forth in the task order.
    Respondent cites our decision in Trade West Construction, Inc., 
    ASBCA No. 61068
    , 
    20-1 BCA ¶ 37,713
     at 183,080, for the proposition that “[a] party may waive
    an affirmative defense by failing to assert it,” and complains that our decision in Trade
    West “did not ‘tee up its affirmative defense for resolution in th[e] appeal,’ as it did for
    Sauer” (gov’t mot. at 6-7). Respondent’s reliance upon that decision is misplaced as the
    facts in that appeal present a quite different scenario than those presented here. Trade
    West concerned a contractor claim for additional costs based upon an alleged change to
    the contract requiring more work. At the Board, the government sought denial of the
    claim based upon several grounds, including appellant’s alleged lack of notice pursuant
    2
    Statement of Fact (SOF) ¶ 22 provides “that 98.7 percent of the total construction-
    related costs were placed in Phase I, construction of the new headquarters
    building.” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,752 (citing app. Statement of
    Undisputed Material Facts No. 3; R4, tabs 3.03, 3.07; app. mot. at ex. 1).
    SOF ¶ 22 also stated that “[a]lthough the government ‘denies’ this allegation, it
    does not state why appellant's determination is incorrect. Rather, the government
    ‘notes that the costs associated with the respective schedule activities were
    assigned by Sauer in its schedule, not determined by the government’” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,752 (citing gov’t resp. to app. Statement of undisputed
    Material Facts No. 3).
    4
    to the Changes clause - an issue that has no application to a government claim for
    liquidated damages. Trade West, 
    20-1 BCA ¶ 37,713
     at 183,080. 3
    We rejected the government’s argument, detailing the many ways that the
    government was on notice of the contractor’s changed-condition claim, despite the
    contractor submitting no formal notice to the government. 
    Id.
     We found also that the
    government failed to offer any record evidence that it was prejudiced by the passage of
    time, and “[e]ven assuming appellant failed to provide the requisite Changes clause
    notice, the government waived any objection it may have had to appellant’s claim based
    upon that lack of notice,” because the contracting officer failed to raise the issue of lack
    of notice in the final decision as a basis for denying the claim, and the government failed
    to plead lack of notice as an affirmative defense. 
    Id.
     The government’s failure to address
    notice in its final decision or in its answer was additional evidence that the government
    was on notice of the claim, despite the lack of any formal notice required by the Changes
    clause. 
    Id.
     That simply is not the situation here.
    As stated above, we will address in a separate decision whether we have
    jurisdiction to consider the affirmative defense as to the reasonableness of the rate
    established by the task order.
    IV. Our Decision Properly Held that Assessment of Liquidated Damages was
    Improper Based Upon Completion of Phases I and II of the Task Order
    The government argues that we committed error when we “concluded, as a matter
    of law, that the LD rate is unenforceable” (gov’t mot. at 2). According to the
    government, we erred in our “reading Dick Pacific as establishing a rule of law rather
    than resting its conclusion upon a factual finding,” and that while we “concluded that the
    LD rate assessed in Dick Pacific was unenforceable in that case, the Board [in Dick
    Pacific] specifically rested that conclusion upon the factual finding that the ‘daily rate
    bears no reasonable relation to the probable loss that would be incurred by the
    government after substantial completion of the first two contract items’” (id. at 10).
    Our decision in Dick Pacific both recognized, and applied, a rule of law based
    upon factual findings, specifically that the daily liquidated damages rate set forth in the
    3
    Respondent also suggests that “the situation is more problematic” because “this
    liquidated damages rate has been apparent to Sauer since January 12, 2011, when
    the Request for Proposals was issued, prior to contract award” (gov’t mot. at 7).
    Other than note the passage of time, respondent does not allege, let alone establish,
    how the passage of time has prejudiced the government. Moreover, appellant here
    was not put on notice that the government was going to assess liquidated damages
    (where the contractor already had completed two phases of the Contract), until
    project work was mostly complete.
    5
    contract should be apportioned based upon substantial completion of certain portions of
    the project, as indicated by their warranty dates. Dick Pacific, 
    16-1 BCA ¶ 36,196
    at 176,640. Our decision in this appeal applied that same rule of law to undisputed
    factual findings regarding completion of phases I and II of the task order. Specifically,
    we held that “[t]he government’s assessment of the full amount of daily liquidated
    damages after substantial completion and acceptance of the first two phases is
    unenforceable.” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,758. To be clear, the rule of law
    espoused in Dick Pacific applies equally to this appeal because, in both this appeal and in
    Dick Pacific, the “‘daily rate bears no reasonable relation to the probable loss that would
    be incurred by the government after’ substantial completion of the first two contract
    items.” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,757 (quoting Dick Pacific, 
    16-1 BCA ¶ 36,196
    at 176,641). 4
    The government argues also, that “[s]imply put, Sauer’s claim for remission of
    liquidated damages was based solely on a disagreement with USACE about when
    substantial completion occurred, not the unreasonableness or unenforceability of the rate
    itself” (gov’t mot. at 5). The government then concludes “[t]hus appropriately, the
    Contracting Officer’s Final Decision (COFD) was limited to the allegations set forth in
    Sauer’s claim, concluded that the government is entitlement [sic] to the liquidated
    damages assessed, and discussed when each phase of the three-phase project had been
    completed” (id.). As noted in our decision, however, the contracting officer’s final
    decision failed completely to address the issue of substantial completion as raised by
    appellant in its claim. Indeed, we found that “[t]he contracting officer did not address
    appellant’s argument that assessment of liquidated damages after substantial completion
    of the Project was inappropriate. Rather, the contracting officer assessed liquidated
    damages ‘[i]n accordance with FAR 52.211-12’ based upon appellant’s ‘failure to
    complete the work within the contract duration’ (R4, tab 2.02 at 7).” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,752 (SOF ¶ 25).
    Respondent argues also that “contrary to the analysis required by the Federal
    Circuit, the Board did not analyze how the liquidated damage figure was arrived at, nor
    did it analyze whether the liquidated damages were reasonable at the time that the
    contract was awarded” (gov’t mot. at 11 (citing K-Con Bldg. Sys., Inc. v. United States,
    
    778 F.3d 1000
    , 1008)). The government’s argument puts the cart before the horse, as our
    decision here did not turn on the reasonableness the liquidated damages rate, nor did we
    decide whether we had jurisdiction to consider that issue. Indeed, the government admits
    as much, stating that “based upon the limited factual findings reached at this stage, the
    Board could not have done so, as the question of whether an LD amount bears a
    reasonable relationship to the foreseeable actual damages suffered by delayed completion
    of the project is a question of fact, which the Board has not yet reached” (gov’t mot.
    at 11-12).
    4
    See also our discussion of Dick Pacific set forth in section V of this decision.
    6
    Notwithstanding its position that rate reasonableness was not, and could not be
    decided at this state of the litigation (a position with which we agree), the government’s
    motion submits additional documentary information in an attempt to establish the
    reasonableness of the liquidated damages rate set forth in the contract, arguing that “[t]he
    reasonableness of the liquidated damages [rate] is evaluated at the time of contract
    formation” (gov’t mot. at 12). As we already have held, however, “[o]ur decision on the
    parties’ cross-motions for summary judgment turns not on the reasonableness of the
    liquidated damages rate as established by the government pre-award (nor are we able to
    decide that factual dispute on summary judgment), but, rather, on the government’s
    failure to apportion its liquidated damages at the time it assessed those damages.” Sauer,
    
    21-1 BCA ¶ 37,845
     at 183,759-60.
    The government argues, that “without reaching a determination as to when the
    project was substantially completed, in the next section of the decision the Board held
    that the amount of liquidated damages assessed per day for this project must necessarily
    be reduced” (gov’t mot. at 8-9). The government misreads our decision. Although, it
    accurately quotes a portion of our decision, stating “as to the issue of substantial
    completion of the Project vis-a-vis Phase III, we are constrained at this point in the
    litigation from making a determination whether it occurred on December 20, 2013, or
    at some point prior to that date,” (id. at 8), there we were addressing only the issue of
    Phase III substantial completion. 5 Earlier in our decision, we had held, as admitted by
    the government, that Phases I and II were complete (indeed, not just substantially
    complete). Sauer, 
    21-1 BCA ¶ 37,845
     at 183,757-58. The factual issue we were unable
    to reach concerned Phase III of the task order, which, according to appellant’s
    calculations, comprised less than two percent of appellant’s construction-related costs.
    Sauer, 21- 
    1 BCA ¶ 37,845
     at 183,752 (see SOF ¶ 23).
    As to the government’s argument that the contract is not substantially complete
    because the government has not received all the benefits for which it contracted, those
    “benefits” relate solely to work performed in Phase III. The government is free to argue
    those benefits as they pertain to Phase III and the issue of substantial completion of that
    phase. The government argues also, “[b]ecause the Board cannot assess whether the
    parking lot is necessary for the government to achieve substantial completion, it is
    impossible, at this stage of the proceedings, for the Board to conclude that the LD rate
    assessed was unenforceable” (gov’t mot. at 9). The government is incorrect. The
    liquidated damages rate is unenforceable as to Phases I and II. It may very well be
    enforceable as to Phase III, with an apportioned amount of the task order’s specified rate
    properly assessed in the event Phase III was not substantially complete. Our decision
    5
    Concerning Phase III, we held that factual issues remained regarding the extent of work
    left to be completed, such that we were unable to make a determination of
    substantial completion vis-a-vis that phase. Sauer, 
    21-1 BCA ¶ 37,845
     at 183,757.
    7
    contains no determination as to what portion of the liquidated damages may properly be
    enforced. A determination as to substantial completion of Phase III first must be made.
    V. Our Decision Did Not Rewrite Contract Terms
    The government argues that our decision improperly rewrote terms of the contract
    (id. at 13-15). According to the government, our decision “recognized that the contract
    did not set a different liquidated damages rate for each phase of the contract, (Decision
    at 15), yet holds that the government ‘should have’ done so, and ultimately, rules as if the
    government did have phased liquidated damages” (id. at 14). As support, the government
    cites George Hyman Const. Co. v. United States, 
    832 F.2d 574
    , 581 (Fed. Cir. 1987), for
    the proposition that courts lack authority to re-write contracts and insert words into a
    contract to which the parties never agreed (gov’t mot. at 14-15). The government
    misreads our decision, as we did not rewrite any terms of the contract. Rather we held
    that “[t]he government’s assessment of the full amount of daily liquidated damages after
    substantial completion and acceptance of the first two phases is unenforceable.” Sauer,
    
    21-1 BCA ¶ 37,845
     at 183,758.
    The origin of appellant’s critique arises out of an argument set forth in its motion
    for summary judgment, wherein the government cited American Int’l Contractors, Inc.,
    ASBCA Nos. 60948, 61166, 
    18-1 BCA ¶37,061
    , “as an example of when the government
    did not include separate liquidated damages rates for each phase of a contract, even
    though the FAR provides a contracting officer ‘the authority to revise the liquidated
    damages clause to provide for different rates for separate parts of the work’ (gov’t reply
    at 15).” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,758. In responding to the government’s
    argument, we found that the government’s reliance upon American Int’l Contractors as
    support for its not including separate liquidated damages for each project phase was
    “misplaced, as the Board there did not reach the issue of whether the contracting officer
    should have exercised the authority set forth in FAR 11.503(b) and should have included
    different liquidated damages rates for each contract phase.” 
    Id.
     6
    However, in distinguishing American Int’l Contractors from the current appeal,
    we did not thereby rewrite the liquidated damages clause to conform with the
    requirements of FAR 11.503(b). Rather, we stated that “the plain wording of that
    provision suggests that when the government issued RFP Revision No. 02 to provide for
    phased construction with corresponding completion dates, the government should have
    revised paragraph (a) of FAR 52.211-12 ‘to state the amount of liquidated damages for
    6
    FAR 11.503(b) provides “[i]f the contract specifies more than one completion date for
    separate parts or stages of the work, revise paragraph (a) of the clause
    [FAR 52.211–12, LIQUIDATED DAMAGES—CONSTRUCTION] to state the
    amount of liquidated damages for delay of each separate part or stage of the
    work.” 
    48 C.F.R. §11.503
    (b).
    8
    delay of each separate part or stage of the work,’” and “[t]he fact that the government did
    not follow FAR 11.503(b) here is yet an additional argument in favor of a finding that
    apportionment of the liquidated damages rate is appropriate in this appeal.” 
    Id.
    Our decision that apportionment of the liquidated damages is appropriate in this
    appeal was based, not on American Int’l Contractors or the instructions set forth in
    FAR 11.503(b), but rather upon our precedent in Dick Pacific, and the well-established
    principle set forth in that decision which instructs “that liquidated damages may not be
    assessed past substantial completion.” Dick Pacific, 
    16-1 BCA ¶ 36,196
     at 176,640
    (citing Ellis Environmental Group, LLC, 
    ASBCA No. 55375
    , 
    08-2 BCA ¶ 33,918
    at 167,847). Indeed, our decision in Dick Pacific did not involve any change to the actual
    rate amount set forth in the contract at time of award. Rather, in that decision we found
    that apportionment of the rate was appropriate based upon substantial completion of two
    of the three project phases, noting that “[a]ll of the information needed to apportion the
    liquidated damages was available during the formation process,” specifically the
    percentage of the contract price as it pertained to each phase. Dick Pacific, 
    16-1 BCA ¶ 36,196
     at 176,640. Accordingly, in Dick Pacific, we instructed that “[i]n the quantum
    proceeding the parties may apply these [percentage] rates using the substantial
    completion dates.” 
    Id. at 176,641
    . We held that “[t]he $2,298 daily rate bears no
    reasonable relation to the probable loss that would be incurred by the government after
    the Rev B Infield and Strat Ramp are substantially complete,” and that “allowing the
    daily rate of $2,298 to run after the Rev B Infield and Strat Ramp are substantially
    complete results in a penalty.” 
    Id.
     We held also that “assessing the full amount of daily
    liquidated damages after substantial completion of the Rev B Infield and Strat Ramp is
    unenforceable.” 
    Id.
     7
    Our holding in Dick Pacific applies equally to this appeal. The project here
    likewise was divided into three phases, yet the task order specified only one liquidated
    damages rate. In our decision, we noted that “[a]lthough the issue of substantial
    completion is a question of fact, the record establishes beyond cavil that at the very least
    appellant substantially completed Phases I and II, given that the government admits
    Phases I and II were complete.” Sauer, 
    21-1 BCA ¶ 37,845
     at 183,757-58. We noted
    also it was undisputed that appellant completed the first two phases prior to the task
    order’s deadline for completion of the project, with only Phase III remaining. Sauer,
    21- 
    1 BCA ¶ 37,845
     at 183,751. Here, as in Dick Pacific, the daily rate specified in the
    task order “bears no reasonable relation to the probable loss that would be incurred by the
    government after” Phases I and II “are substantially complete,” and “allowing the daily
    rate . . . to run after” Phases I and II “are substantially complete results in a penalty.”
    7
    Dick Pacific involved extension of existing airfield and pavement, and construction of a
    clear water rinse facility (CWRF), with the project divided into three construction
    phases - an Infield Ramp Rev B (Rev B Infield), an Airlift/Strat Ramp Expansion
    (Strat Ramp), and the CWRF. 
    16-1 BCA ¶ 36,196
     at 176,603-06.
    9
    Dick Pacific, 
    16-1 BCA ¶ 36,196
     at 176,641. As with our decision in Dick Pacific, our
    decision here was based upon unrefuted facts establishing that the vast portion of the
    phased task order work already had been completed.
    The government challenges our holding, suggesting that completion of the parking
    lots somehow justifies imposition of the entire amount of liquidated damages because
    “the Project was not substantially complete without a parking lot” (gov’t mot. at 9). The
    actual amount of liquidated damages properly assessed waits to be determined. The
    government still has the ability to argue the importance of the parking lots going forward
    in determining the proper amount of liquidated damages. However, as we already have
    held, “[t]he government’s assessment of the full amount of daily liquidated damages after
    substantial completion and acceptance of the first two phases is unenforceable.” Sauer,
    
    21-1 BCA ¶ 37,845
     at 183,758.
    CONCLUSION
    For the reasons stated above, the government’s motion for reconsideration is
    denied.
    Dated: March 2, 2022
    DAVID B. STINSON
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    RICHARD SHACKLEFORD                               OWEN C. WILSON
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    10
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62395
    , Appeal of Sauer
    Incorporated, rendered in conformance with the Board’s Charter.
    Dated: March 3, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    11
    

Document Info

Docket Number: ASBCA No. 62395

Judges: Stinson

Filed Date: 3/2/2022

Precedential Status: Precedential

Modified Date: 3/22/2022