Fluor Intercontinental, Inc. ( 2022 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of -                                  )
    )
    Fluor Intercontinental, Inc.                  ) ASBCA Nos. 62550, 62672
    )
    Under Contract No. W912BU-11-D-0003           )
    APPEARANCES FOR THE APPELLANT:                   James A. Hughes, Jr., Esq.
    Hughes Law PLC
    Arlington, VA
    Andrea L. Reagan, Esq.
    Donald M. Yenovkian II, Esq.
    R. Austin Kusnir, Esq.
    Counsels
    APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Kyle A. Guess, Esq.
    John A. Skarbek, Esq.
    John R. Lockard, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Norfolk
    OPINION BY ADMINISTRATIVE JUDGE HERZFELD
    ON THE GOVERNMENT’S MOTION TO DISMISS AND
    APPELLANT’S MOTION FOR SUMMARY JUDGMENT
    Respondent, the United States Army Corps of Engineers, moves to dismiss part of
    appellant Fluor Intercontinental, Inc.’s (Fluor) complaint for failure to state a claim upon
    which relief may be granted. In particular, the agency seeks to dismiss Fluor’s attempt to
    recover subcontractor Blanchard Machinery Company’s (Blanchard) termination costs
    because Blanchard estimated some of its costs using an inapplicable cost principle. Fluor
    cross-moves for summary judgment, asserting that Fluor’s decision to settle with
    Blanchard was reasonable and, thus, should be awarded all its costs from settling with
    Blanchard. We find that Fluor has plausibly pleaded a claim for recovery of its
    subcontractor costs, but that there is a genuine dispute of material fact as to whether and
    what amount of its costs were reasonable. Thus, we deny both motions.
    .
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS
    On December 3, 2010, the Corps of Engineers awarded an electrical support
    services multiple-award task order contract to Fluor (Contract) and to a competitor,
    Inglett and Stubbs Intercontinental (Inglett & Stubbs), for a base one-year period and
    four, one-year option periods (R4, tab 3 at 93, tab 2 at 8). On February 14, 2011, Fluor
    entered a subcontract with Blanchard Machinery Company (Blanchard) using a basic
    ordering agreement (Subcontract) following from a teaming agreement to pursue the
    Contract (first amended compl. ¶¶ 10-12; app. supp. R4, tab 13 at 307-59 (basic ordering
    agreement); app. supp. R4, tab 13 at 297-306 (teaming agreement)).
    With a closing date of September 25, 2012, the Corps of Engineers issued a task
    order solicitation and Fluor submitted a proposal to quickly provide leased generators to
    operate and maintain a 30 megawatt power plant at the airfield in Bagram, Afghanistan
    (first amended compl. ¶ 24; R4, tab 10 at 232-33). On February 4, 2013, the Corps of
    Engineers awarded Fluor task order 10 (Task Order) under the Contract and issued a
    notice to proceed (first amended compl. ¶¶ 4, 29; R4, tab 2 at 42-46). On February 27,
    2013, Fluor issued a purchase order to Blanchard to lease generators, switches, and
    control panels to meet the Task Order requirements (codifying a “verbal/facsimile”
    agreement on February 18, 2013) (first amended compl. ¶ 17; app. supp. R4, tab 13
    at 406-69). Because Fluor would need to provide the government power generating
    capacity within 60-120 days of the notice to proceed, Fluor had previously authorized
    Blanchard to purchase, ready, and ship the equipment in September 2012, which
    Blanchard did (first amended compl. ¶¶ 26-27; app. supp. R4, tab 13 at 95 (indicating the
    generator acquisition dates); R4, tab 8 at 181 (acknowledging that Blanchard shipped the
    generators to Dubai)).
    On February 27, 2013, the Corps of Engineers issued a stop-work order to Fluor
    (first amended compl. ¶ 5; R4, tab 4 at 109). On March 18, 2021, Inglett & Stubbs filed a
    protest with the Government Accountability Office (GAO) challenging the award of the
    Task Order to Fluor (R4, tab 11 at 248; first amended compl. at 9 n.3). On April 12,
    2013, GAO dismissed the protest after the Corps of Engineers took corrective action
    (R4, tab 11 at 282-83). While taking corrective action, the Corps of Engineers realized
    that it failed to timely exercise the options under the Contract and, thus, could not use the
    Contract as a vehicle to issue task orders to obtain these services (R4, tab 6 at 141).
    On May 24, 2013, the Corps of Engineers terminated Fluor’s Task Order for
    convenience (first amended compl. ¶ 5; R4, tab 6 at 143-46). As part of the convenience
    termination notice, the Corps of Engineers directed Fluor to cease all activities and
    discussed procedures for submitting a termination settlement proposal (R4, tab 6
    at 143-46). Additionally, the Corps of Engineers specifically reminded Fluor of the
    contractor’s obligations to its subcontractors: “You remain liable to your subcontractors
    and suppliers for proposals arising because of the termination of their subcontracts or
    2
    orders. You are requested to settle these settlement proposals as promptly as possible.
    For purposes of reimbursement by the Government, settlements will be governed by the
    provisions of Part 49” (R4, tab 6 at 144).
    The Contract incorporated by reference two Federal Acquisition Regulation (FAR)
    standard termination for convenience provisions: (1) FAR 52.249-1, TERMINATION
    FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (SHORT FORM)
    (APR 1984); and (2) FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE
    GOVERNMENT (FIXED-PRICE) (MAY 2004) (first amended compl. ¶ 72; R4, tab 2
    at 31). Additionally, the Contract included two clauses requiring Fluor to flow down
    certain other FAR and Defense Federal Acquisition Regulation Supplement (DFARS)
    clauses to subcontractors providing commercial items: (1) FAR 52.244-6,
    SUBCONTRACTS FOR COMMERCIAL ITEMS (APR 2010); and (2) DFARS
    252.244-7000, SUBCONTRACTS FOR COMMERCIAL ITEMS AND COMMERCIAL
    COMPONENTS (DOD CONTRACTS) (AUG 2009) (first amended compl. ¶ 59; R4,
    tab 2 at 30-31). FAR 52.244-6 otherwise discourages flowing down more clauses in
    commercial items subcontracts, but states, “Contractor may flow down to subcontracts
    for commercial items a minimal number of additional clauses necessary to satisfy its
    contractual obligations.” FAR 52.244-6(c)(2).
    Fluor flowed down the two commercial items subcontract clauses to Blanchard in
    the purchase order (first amended compl. ¶ 20; app. supp. R4, tab 13 at 423). 1 However,
    as permitted by these two clauses, Fluor also flowed down the short form Termination for
    Convenience clause to Blanchard as part of the Subcontract, including the entire FAR
    provision:
    As prescribed in the FAR 49.502(a)(1), insert the following:
    “The Contracting Off[ic]er, by written notice, may terminate
    this contract, in whole or in part, when it is in the
    Government’s best interest. If this contract is terminated, the
    rights, duties, and obligations of the parties, including
    compensation to the Contractor, shall be in accordance with
    Part 49 of Federal [A]cquisition [Regulation] in effect on the
    date of the award of this contract.”
    (First amended compl. ¶ 15 (quoting DFARS 52.249-1); app. supp. R4, tab 13 at 318
    (same)) The Subcontract included several forms with terms and conditions, including an
    1
    The supplemental appellant’s Rule 4 file includes two tabs labeled as “13.” We have
    labeled the second as “13.2” for ease of reference. Also, we use the pdf page
    numbers for appellant’s supplemental Rule 4 file because appellant did not add
    page numbers as we generally require. ASBCA Rule 4(c) (“Any documents
    without internal page numbers shall have page numbers added.”).
    3
    additional termination for convenience clause that promised any termination payment
    “shall be promptly and mutually agreed to” by Fluor and Blanchard (first amended
    compl. ¶ 16; app. supp. R4, tab 13 at 330).
    Fluor submitted a termination settlement proposal (dated December 19, 2013) to
    the Corps of Engineers seeking $5,179,655 in termination costs (first amended compl.
    ¶ 42; R4, tab 13; app. supp. R4, tab 13.2 at 4, tab 15 at 1). Among other settlement costs,
    the termination settlement proposal included Blanchard’s termination settlement proposal
    of $3,370,768 as “settlements with subcontractors” (first amended compl. ¶ 42; app.
    supp. R4, tab 13.2 at 4, tab 15 at 1; R4, tab 13 at 332).
    The Corps of Engineers referred the termination settlement proposal to the
    Defense Contract Audit Agency (DCAA) to audit the proposal; Fluor and Blanchard
    answered questions and provided additional information to DCAA over the next several
    months (first amended compl. ¶ 42; R4, tab 8). In July 2014, while the DCAA audited
    the proposal (including Blanchard’s costs), Fluor’s complaint alleges that Fluor paid
    Blanchard $3,116,991.20 based on Blanchard’s termination settlement proposal (leaving
    an unpaid balance due of $253,776.80) (first amended compl. ¶ 46). The Corps of
    Engineers denies, for lack of information, the allegation that Fluor made a settlement
    payment to Blanchard (answer ¶ 46). 2
    On December 15, 2015, DCAA issued an audit report of Fluor’s termination
    settlement proposal, attaching DCAA’s earlier November 10, 2015 separate audit report
    of Blanchard’s termination settlement proposal (first amended compl. ¶¶ 54-55; R4,
    tab 8). The DCAA questioned $3,013,324 of Fluor’s $5,179,655 termination settlement
    proposal, which resulted in DCAA opining that Fluor had demonstrated $2,166,331 in
    allowable costs:
    RESULTS OF
    AUDIT
    Cost Element       Settlement Proposal     Questioned Difference
    Direct Material                    $511,506             - $511,506
    Direct Labor                        338,093      101,391   236,702
    Other Costs                          73,296             -    73,296
    Subcontractors                    3,370,768    2,374,480   966,288
    G&A                                  63,994             -    63,944
    Profit                              741,572      537,453   204,119
    Settlement Expenses                  80,426             -    80,426
    2
    We refer to the answer to the first amended complaint as the “answer” throughout this
    opinion.
    4
    Total                            $5,179,655       $3,013,324 $2,166,331
    (First amended compl. ¶ 70; R4, tab 8 at 163)
    The “subcontractors” category in the audit report related to Blanchard’s costs and
    DCAA broke down its audit of those costs as follows:
    RESULTS OF AUDIT
    Cost Element        Settlement Proposal Questioned Difference
    Material/Equipment                 $675,513            - $675,513
    Shipping and Storage                367,824     161,692   206,132
    Technician (Labor)                   11,182            -    11,182
    Equipment Depreciation               1,634,527     1,634,527          -
    Overhead                               316,977       316,977          -
    Cost of Money                          112,374       112,374          -
    Profit                                 231,406       148,909     82,496
    Settlement Expenses                     20,965             -     20,965
    Total                            $3,370,768       $2,374,479   $966,289
    (First amended compl. ¶ 67; R4, tab 8 at 165, 178)
    Blanchard’s termination settlement proposal included equipment costs (first
    amended compl. ¶ 36; app. supp. R4, tab 13 at 10). Blanchard calculated its costs for the
    generators and related equipment using five-year straight-line depreciation (first
    amended compl. ¶ 40; app. supp. R4, tab 13 at 12). Blanchard’s proposal referenced
    FAR 31.205-11 – the cost principle for depreciation – and noted that it used the Internal
    Revenue Service “depreciable lives and calculated on a straight-line basis” (app. supp.
    R4, tab 13 at 12; first amended compl. ¶ 40). Fluor asserts that Blanchard’s depreciation
    amount excluded any subcontractor or prime contractor mark-ups and that Blanchard
    and Fluor incurred and should have received overhead and profit for the depreciation
    costs disallowed under the profits and overhead categories above (first amended compl.
    ¶¶ 68, 71).
    During the audit, Blanchard’s then-chief financial officer (CFO) communicated
    with the DCAA auditor, explaining Blanchard’s decision to use depreciation to value the
    costs of the generators and equipment (although we have not found a copy of the
    communication in the Rule 4 files, but the agency’s answer admits to the text of the
    communication incorporated in the complaint) (first amended compl. ¶ 39; answer ¶ 39).
    DCAA questioned why Blanchard did not use the rental rate for the equipment rather
    5
    than deriving the cost through depreciation (first amended compl. ¶ 39; answer ¶ 39).
    Blanchard asserted that it used depreciation over other approaches based on its
    “interpretation of the guidelines relating to contracts that are terminated for convenience
    by the government, our agreement and discussions with Fluor and discussions with our
    advisors” (first amended compl. ¶ 39; answer ¶ 39). But, Blanchard provided DCAA an
    estimate of the rental rate of $6,224,103 (a rate that Blanchard’s current CFO attests to in
    an affidavit attached to appellant’s brief) (first amended compl. ¶ 39; answer ¶ 39;
    app. resp., Dalys Johnson aff. ¶ 8). Fluor pleads that Blanchard “understated” its costs by
    using the lower depreciation-based settlement proposal of $3,370,768 instead of the
    $6 million rental rate (first amended compl. ¶ 41). Fluor alleges that Blanchard used
    depreciation as an approach that “best approximated the cost it would incur in disposing
    of the power equipment” (first amended compl. ¶ 40). Given that Blanchard’s proposal
    used cost estimates, Fluor alleges that it considered the rental rates (and lower
    depreciation cost) as a basis for finding Blanchard’s termination costs reasonable and for
    paying Blanchard’s termination costs in July 2014 (first amended compl. ¶¶ 45-46).
    DCAA recommended denial of Blanchard’s equipment depreciation costs based
    on the requirements of the depreciation cost principle – FAR 31.205-11 (first amended
    compl. ¶ 58; R4, tab 8 at 180-81). DCAA acknowledged, “In reviewing the supporting
    documentation and inquiry with the subcontractor, we determined that the generators
    were shipped from the U.S. to Dubai and held in storage without being turned on for this
    subcontract” (R4, tab 8 at 181; see first amended compl. ¶¶ 37-38). Nevertheless, DCAA
    quoted FAR 31.205-11(c), which states that “allowable depreciation shall not exceed the
    amount used for financial accounting purposes, and shall be determined in a manner
    consistent with the depreciation policies and procedures followed in the same segment on
    non-government business” (R4, tab 8 at 180-81 (quoting FAR 31.205-11(c)); first
    amended compl. ¶ 58). DCAA found that Blanchard “including depreciation costs in
    excess of what they had recorded for financial accounting purposes caused this material
    noncompliance” (R4, tab 8 at 181; first amended compl. ¶ 62). Fluor’s complaint states
    that Blanchard uses a declining balance depreciation method (not straight-line) for
    Federal tax purposes and “did not depreciate the equipment in its accounting records
    other than for tax purposes” (first amended compl. ¶¶ 58, 62; R4, tab 8 at 181).
    Ultimately, Fluor reduced its termination proposal from $5,179,655 to $5,106,772
    (first amended compl. ¶ 70 n.5; app. supp. R4, tab 46 at 1). In 2018, the Corps of
    Engineers paid Fluor $2,166,331 (the amount recommended by DCAA as allowable),
    leaving an unpaid and disputed amount of $2,940,441 (first amended compl. ¶¶ 70 n.5,
    82; app. supp. R4, tab 46 at 2; R4, tab 3 at 95). On September 18, 2018, Fluor requested
    a contracting officer’s determination regarding the unpaid and disputed amount (first
    amended compl. ¶ 77; answer ¶ 77; notice of appeal at 2 (
    ASBCA No. 62550
    )). The
    Corps of Engineers never responded and Fluor appealed the deemed denial to the Board
    on May 22, 2020 (
    ASBCA No. 62550
    ) (first amended compl. ¶ 6). On July 30, 2020, the
    Corps of Engineers’ contracting officer adopted the reasoning of DCAA’s audit report
    6
    and issued a final decision denying Fluor’s $2,940,441 claim (first amended compl. ¶ 7;
    R4, tab 3). On September 9, 2020, Fluor appealed the contracting officer’s final decision
    (
    ASBCA No. 62672
    ).
    In its complaint, Fluor noted that its original termination settlement proposal had
    included certain estimated costs because, for example, Blanchard had not disposed of the
    generators and other equipment (first amended compl. ¶ 50). In its complaint and in the
    Johnson Affidavit attached to its opening brief, Fluor now provides new claim amounts
    based on Blanchard’s actual costs (which it did not have at the time of its termination
    settlement proposal) as evidence that its settlement with Blanchard was reasonable (first
    amended compl. ¶¶ 61-66; Johnson aff. ¶¶ 5-7.7). Comparing these January 2021 actual
    costs with the prior settlement proposal and the Corps of Engineers’ payment of those
    costs renders the following table:
    RESULTS OF AUDIT
    Cost Element            Jan. 2021            Settlement       Questioned Allowed
    Actual Costs           Proposal                    & Paid
    Material/Equipment              $1,766,347              $675,513             - $675,513
    Shipping and Storage               312,366               367,824      161,692   206,132
    Technician (Labor)                  11,182                11,182             -   11,182
    Equipment Depreciation                   0             1,634,527    1,634,527         -
    Overhead                           316,977               316,977      316,977         -
    Cost of Money                      883,464               112,374      112,374         -
    Profit                             231,406               231,406      148,909    82,496
    Settlement Expenses                 20,965                20,965             -   20,965
    Total                            $3,542,706          $3,370,768     $2,374,479   $966,289
    (First amended compl. ¶¶ 61-67, 76; Johnson aff. ¶¶ 5-7.7; R4, tab 8 at 165, 178)
    Although Fluor’s complaint and the Johnson affidavit both include the new $1,766,347 in
    actual material/equipment costs, only the complaint indicates that these “costs were
    slightly offset by a net gain of $586,000 resulting from the eventual sale of the
    generators;” the Johnson affidavit’s calculation does not discuss this potential mitigating
    amount (first amended compl. ¶ 61). The Corps of Engineers’ answer denies Fluor’s
    allegations regarding the increased costs to the material/equipment and cost of money
    (answer ¶¶ 50, 61-66, 82).
    When the Corps of Engineers filed its answer to the amended complaint, it also
    moved to partially dismiss the appeals. Fluor cross-moved for summary judgment.
    7
    DECISION
    Fluor Has Plausibly Pleaded a Claim for its Subcontractor Settlement Costs
    The Corps of Engineers moves to partially dismiss Fluor’s complaint for failure to
    state a claim for recovery of its subcontractor Blanchard’s costs of supplying generators
    and other equipment. The Corps of Engineers asserts that FAR Part 31’s cost principles
    apply because the Contract used termination provisions prescribed by FAR Part 49
    (including the requirement to consider the cost principles in assessing termination costs)
    and that they preclude Fluor from obtaining the recovery it seeks. Despite conceding the
    applicability of FAR Part 49 in its complaint and flowing down a FAR Part 49
    termination clause into the Subcontract, Fluor asserts in its response to the government’s
    motion that it entered a commercial items subcontract with Blanchard resulting in the
    applicability of FAR Part 12 and inapplicability of the cost principles. As discussed
    below, we disagree. However, even though FAR Part 12 does not apply, when we apply
    the cost principles under FAR Part 31 and the fairness principle under FAR Part 49, Fluor
    has plausibly pleaded a claim to recover its subcontractor termination settlement costs.
    A.     Standard of Review
    The Board’s rules do not include an equivalent to FED. R. CIV. P. 12(b)(6) or
    12(c), but we permit motions to dismiss for failure to state a claim upon which relief may
    be granted. Kamaludin Slyman CSC, 
    ASBCA No. 62006
    , 
    21-1 BCA ¶ 37,849
    at 183,789. “To survive a motion to dismiss, a complaint must contain sufficient factual
    matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft
    v. Iqbal, 
    556 U.S. 662
    , 678 (2009) (quoting Bell Atlantic Corp. v. Twombly, 
    550 U.S. 544
    , 570 (2007)). “A claim has facial plausibility when the [complaint] pleads factual
    content that allows the [Board] to draw the reasonable inference that the [respondent] is
    liable for the misconduct alleged.” 
    Id.
     Plausibility requires more than alleging facts
    “merely consistent with” the requested relief. Id.; Kamaludin Slyman, 
    21-1 BCA ¶ 37,849
     at 183,789. However, we look at the facts and do “not countenance dismissal of
    a complaint for imperfect statement of the legal theory supporting the claim asserted.”
    Johnson v. City of Shelby, 
    574 U.S. 10
    , 11 (2014).
    The Board “must accept well-pleaded factual allegations as true and must draw all
    reasonable inferences in favor of the claimant.” Kellogg Brown & Root Servs., Inc. v.
    United States, 
    728 F.3d 1348
    , 1365 (Fed. Cir. 2013). We are not limited to the four-
    corners of the complaint, but look also to the contractor’s or government’s claim – the
    wellspring of our jurisdiction – and look at “matters incorporated by reference or integral
    to the claim, items subject to judicial notice, matters of public record, orders, items
    appearing in the record of the case, and exhibits attached to the complaint whose
    authenticity is unquestioned,” as appropriate. 5B CHARLES A. WRIGHT & ARTHUR R.
    MILLER, FED. PRAC. & PROC. CIV. § 1357 (3d ed.); see also A&D Auto Sales, Inc. v.
    8
    United States, 
    748 F.3d 1142
    , 1147 (Fed. Cir. 2014); Kamaludin Slyman, 
    21-1 BCA ¶ 37,849
     at 183,789. 3
    B.     Fluor’s Termination Costs, Including its Subcontractor Blanchard’s Costs,
    Are Subject to the Standards in FAR Part 49, Not FAR Part 12
    “A contractor’s entitlement to compensation in a termination for convenience is
    determined by those applicable clauses of the FAR that are incorporated into the contract
    at issue.” Campus Mgmt. Corp., 
    ASBCA No. 59924
    , 
    17-1 BCA ¶ 36,727
     at 178,876.
    Here, as noted above, the Contract incorporates two termination clauses deriving from
    FAR Part 49: (1) FAR 52.249-1, TERMINATION FOR THE CONVENIENCE OF
    THE GOVERNMENT (FIXED-PRICE) (SHORT FORM) (APR 1984); and (2)
    FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT
    (FIXED-PRICE) (MAY 2004) (first amended compl. ¶ 72; R4, tab 2 at 31). As
    pertinent here, the long-form termination for convenience clause (52.249-2) states: “The
    cost principles and procedures of part 31 of the Federal Acquisition Regulation, in effect
    on the date of this contract, shall govern all costs claimed, agreed to, or determined
    under this clause.” FAR 52.249-2(i); FAR 49.113 (“The cost principles and procedures
    in the applicable subpart of part 31 shall, subject to the general principles in 49.201,
    (a) be used in asserting, negotiating, or determining costs relevant to termination
    settlements under contracts with other than educational institutions, . . .”). Unlike the
    FAR clauses in the Contract, the commercial items clause excludes the use of the cost
    principles in assessing terminations: “The Contractor shall not be required to comply
    with the cost accounting standards or contract cost principles for this purpose.”
    FAR 52.212-4(l). Typically, “the commercial items clause’s recovery is price based,
    while the standard clause’s recovery is cost based.” ESCGov, Inc., 
    ASBCA No. 58852
    ,
    
    17-1 BCA ¶ 36,772
     at 179,186.
    Fluor seeks to avoid application of FAR Part 31, asserting that its Subcontract
    purchased commercial items from Blanchard and, therefore, the commercial items
    termination clause governs Fluor’s recovery of its termination costs here (app. resp.
    at 13-15). However, the Contract does not include the commercial items terms and
    conditions clause (FAR 52.212-4) with the commercial items termination provision. Nor
    3
    Although the government submitted an answer here and was certainly not precluded
    from doing so, we do wish to underscore that it had the option of requesting a
    delay in filing that pleading until after we had resolved the pending motion.
    Under the Federal Rules of Civil Procedure (which do not bind us, but are
    helpful), typically “the filing of a motion that only addresses part of a complaint
    suspends the time to respond to the entire complaint, not just to the claims that are
    the subject of the motion.” Fed. Contracting, Inc. v. United States, 
    128 Fed. Cl. 788
    , 797 (2016) (quoting 5B Charles A. Wright & Arthur R. Miller, Fed. Prac. &
    Proc. Civ. § 1346 (3d ed.)); FED. R. CIV. P. 12(a)(4)(A); RCFC 12(a)(4)(A).
    9
    did Fluor include the commercial items termination provision in its Subcontract with
    Blanchard. Instead, Fluor included the short form of the FAR Part 49 fixed-price
    termination provision, which states terminations for convenience “shall be in accordance
    with Part 49 of Federal [A]cquisition [Regulation] in effect on the date of the award or
    this contract.” (First amended compl. ¶ 15 (quoting DFARS 52.249-1); app. supp. R4,
    tab 13 at 318 (same)) Indeed, in contrast to its briefs, Fluor’s complaint explicitly
    acknowledges, “FAR Part 49 applies to the termination of Task Order 10 of the Contract”
    (first amended compl. ¶ 22). 4
    Fluor counters that the Contract required Fluor to flow down, as it did, two
    Commercial Items provisions to any commercial items subcontract: (1) FAR 52.244-6,
    SUBCONTRACTS FOR COMMERCIAL ITEMS (APR 2010); and (2) DFARS
    252.244-7000, SUBCONTRACTS FOR COMMERCIAL ITEMS AND COMMERCIAL
    COMPONENTS (DOD) CONTRACTS (AUG 2009) (first amended compl. ¶¶ 20, 59;
    R4, tab 2 at 30-31; app. supp. R4, tab 13 at 423; app. resp. at 15 n.1). And Fluor notes
    that the Corps of Engineers’ answer admitted that these clauses were in the Contract and
    Blanchard provided commercial services (answer ¶ 59; app. resp. at 13). However,
    neither clause includes a termination provision nor requires a prime contractor to flow
    down FAR 52.212-4 (which includes the commercial items termination provision). To
    the contrary, that FAR clause specifically permits a prime contractor to “flow down to
    subcontracts for commercial items a minimal number of additional clauses necessary to
    satisfy its contractual obligations.” FAR 52.244-6(c)(2). And, as noted above, regardless
    of Fluor’s current characterization of the Subcontract, Fluor flowed down the standard
    short form termination provision to Blanchard (FAR 52.249-1) instead of the commercial
    items termination provision.
    4
    Fluor’s concession in its complaint that FAR Part 49 applies and Fluor’s choice of using
    the FAR Part 49 termination provision in the Subcontract instead of FAR Part 12’s
    termination provision distinguishes this appeal from JKB Solutions & Services,
    LLC v. United States, 
    18 F.4th 704
     (Fed. Cir. 2021), where the Federal Circuit did
    not apply the termination provision in the contract. The footnotes tell the story of
    that appeal. There, for purposes of summary judgment, the government did not
    contest that the contract provided non-commercial services rather than commercial
    items (which, by definition, included commercial services). 
    Id.
     at 710 n.2.
    Because the government conceded the contract did not provide commercial items,
    the Federal Circuit concluded that the commercial items termination provision
    incorporated in the contract did not apply. 
    Id. at 706-08
    . The contractor asserted
    that it could pursue breach damages without any termination provision. The Court
    of Federal Claims, however, never assessed whether the Christian doctrine
    required incorporation of another termination for convenience clause and the
    Federal Circuit remanded for consideration of that issue. 
    Id. at 707
    , 708 n.1
    (discussing G.L. Christian Assocs. v. United States, 
    312 F.2d 418
     (Ct. Cl. 1963)).
    10
    Nonetheless, Fluor asserts that our decision in SWR should govern, but that
    decision (as Fluor recognizes) related to a termination of a commercial items prime
    contract that included FAR 52.212-4, not a prime contract or subcontract without it.
    SWR, Inc., 
    ASBCA No. 56708
    , 
    15-1 BCA ¶ 35,832
     at 175,204 (“The contract also
    contained FAR 52.212-4 . . . .”). Fluor’s complaint conceded the applicability of
    FAR Part 49 and the Contract and Subcontract both used termination provisions derived
    from FAR Part 49 (not FAR Part 12). Fluor cannot now avoid FAR Part 49’s application
    of the FAR Part 31 cost principles in assessing its termination settlement costs.
    Ultimately, we must apply the termination provisions in the Contract, which does not
    incorporate the Commercial Items termination provision but instead the standard
    termination provisions and principles of FAR Part 49. Campus Mgmt. Corp., 
    17-1 BCA ¶ 36,727
     at 178,876.
    C.     Notwithstanding the Applicability of FAR Parts 31 and 49 to This Contract,
    Fluor Has Pleaded a Claim for Blanchard’s Termination Costs Relating to
    the Generators and Equipment
    A termination for convenience of a task order in a non-commercial items contract
    effectively converts a fixed-price contract into a cost-reimbursement contract, which
    entitles a contractor to recover allowable costs and reasonable profit. Envtl. Safety
    Consultants, Inc., 
    ASBCA No. 58343
    , 
    15-1 BCA ¶ 35,906
     at 175,522; Best Foam
    Fabricators, Inc. v. United States, 
    38 Fed. Cl. 627
    , 638 (1997). “The regulations
    provide that the cost principles in Part 31.2 of the Federal Acquisition Regulations
    (‘FAR’) are to ‘be used in asserting, negotiating, or determining costs relevant to
    termination settlements,’ but they are subject to the general fairness principles of section
    49.201(a).” Nicon, Inc. v. United States, 
    331 F.3d 878
    , 885 (Fed. Cir. 2003) (quoting
    FAR 49.113(a)); Best Foam, 38 Fed. Cl. at 638 (“Allowability is determined using the
    cost principles set forth in FAR part 31, subject to the general principle that the
    contractor should be compensated fairly for the work terminated.”). FAR Part 31’s cost
    principles permit recovery of “allowable” costs that comply “with all of the following
    requirements: (1) Reasonableness. (2) Allocability. (3) [Cost Accounting Standards or
    generally accepted accounting principles]. (4) Terms of the contract. (5) Any limitations
    set forth in this subpart.” Geren v. Tecom, Inc., 
    566 F.3d 1037
    , 1040 (Fed. Cir. 2009)
    (quoting FAR 31.201-2).
    FAR 49.201(a) states, “A settlement should compensate the contractor fairly for
    the work done and the preparations made for the terminated portions of the contract,
    including a reasonable allowance for profit.” FAR 49.201(a); SWR, Inc., 
    15-1 BCA ¶ 35,832
     at 175,223. “The standard for termination settlement proposals recognizes . . .
    that the settlement may need to be based upon estimates.” Phoenix Data Solutions LLC,
    
    ASBCA No. 60207
    , 
    18-1 BCA ¶ 37,164
     at 180,922. “The use of business judgment, as
    distinguished from strict accounting principles, is the heart of a settlement.”
    FAR 49.201(a); see also Codex Corp. v. United States, 
    226 Ct. Cl. 693
    , 698 (1981)
    11
    (reconciling “the strict standard of allowable costs . . . and the fairness concept . . . is a
    matter primarily within the discretion of the Board of Contract Appeals”). “Although the
    burden is on the contractor to show entitlement to a larger settlement amount, . . . the
    overall purpose of a termination for convenience settlement is to fairly compensate the
    contractor and to make the contractor whole for the costs incurred in connection with the
    terminated work.” Nicon, 
    331 F.3d at 885
    .
    1.     Fluor Has Plausibly Alleged a Claim Based on the Termination Cost
    Principle and Need Not Rely on the Depreciation Cost Principle
    Here, the Corps of Engineers’ motion to dismiss relates to the fifth element of
    allowability – limitations in FAR Part 31. FAR 31.201-2(a)(5). In particular, the Corps
    of Engineers asserts that Fluor has failed to plausibly plead a claim for recovery of
    Blanchard’s costs for the generators and other equipment because Blanchard’s
    termination settlement proposal estimated those costs using the depreciation cost
    principle – FAR 31.205-11 (gov’t mot. at 7-9). And, because Blanchard estimated its
    costs based on the depreciation cost principle (FAR 31.201-11), the Corps of Engineers
    asserts that Fluor may only recover its subcontractor termination settlement costs with
    Blanchard under that cost principle or not at all (gov’t mot. at 6-9; gov’t reply at 2-5).
    As reflected in Fluor’s complaint, strict adherence to the depreciation cost
    principle would result in no recovery, as DCAA recommended and the contracting officer
    concluded (first amended compl. ¶¶ 7, 58; R4, tab 3; tab 8 at 180-81). For a
    subcontractor not governed by the Cost Accounting Standards such as Blanchard,
    “allowable depreciation shall not exceed the amount used for financial accounting
    purposes, and shall be determined in a manner consistent with the depreciation policies
    and procedures followed in the same segment on non-Government business.”
    FAR 31.205-11(c). Fluor acknowledges that Blanchard calculated its generator costs
    using straight-line depreciation, but Blanchard uses the declining balance depreciation
    method for Federal tax purposes, and “did not depreciate the equipment in its accounting
    records other than for tax purposes” (first amended compl. ¶¶ 58, 62; R4, tab 8 at 181).
    Thus, Blanchard’s termination settlement proposal that calculated generator costs using
    depreciation was inconsistent with its normal depreciation policies and procedures. 5
    5
    The Corps of Engineers relies on a General Services Board of Contract Appeals
    (GSBCA) decision, which applied the depreciation cost principle
    (FAR 31.205-11) to bar a contractor’s attempt to recover on property that had
    already been fully depreciated. Herman B. Taylor Constr. Co. v. Gen. Servs.
    Admin., GSBCA No. 15421, 
    03-2 BCA ¶ 32,320
     at 159,906. In Taylor
    Construction, the GSBCA dealt with a different issue under the depreciation cost
    principle – that a contractor cannot recover a rental charge for fully depreciated
    equipment without the government’s agreement. 
    Id.
     (citing FAR 31.205-11(1)
    and Union Boiler Works, Inc. v. Caldera, 
    156 F.3d 1374
    , 1376 (Fed. Cir. 1998)).
    12
    Fluor counters, however, that it is not relying on the depreciation cost principle
    (which Blanchard merely used to estimate its costs) but the termination cost principle –
    FAR 31.205-42 – and the Contract’s Termination for Convenience contract clause
    (FAR 52.249-2) that permits recovery of costs from subcontractor settlements (app. resp.
    at 15-16; app. reply at 3-6). The termination cost principle states, “Subcontractor claims,
    including the allocable portion of the claims common to the contract and to other work of
    the contractor, are generally allowable.” FAR 31.205-42(h). The Contract’s long-form
    termination for convenience clause permits Fluor to recover “[t]he cost of settling and
    paying termination settlement proposals under terminated subcontracts that are properly
    chargeable to the terminated portion of the contract . . . .” FAR 52.249-2(g)(2)(ii). “A
    prime seeking to recover the costs of settling with a sub under the ‘settled and paid’
    clause . . . need not strictly prove the allowability, reasonableness, and allocability of all
    of the sub’s costs.” Morrison Knudsen Corp. v. Fireman’s Fund Ins. Co., 
    175 F.3d 1221
    ,
    1252 (10th Cir. 1999). The FAR also states that the termination contracting officer must
    evaluate whether the settlement “was arrived at in good faith, is reasonable in amount,
    and is allocable to the terminated portion of the contract . . . .” FAR 49.108-3(c). Thus,
    allowability of a contractor’s costs in settling a subcontractor’s claim depends on “the
    reasonableness and prudence of the settlement, including the competence and good faith
    with which the negotiations were conducted[,] and the adequacy of the information upon
    which the settlement was based.” Gen. Dynamics Land Sys., Inc., 
    ASBCA No. 52283
    ,
    
    02-1 BCA ¶ 31,659
     at 156,411.
    Fluor alleges (and the Corps of Engineers admits) that Blanchard informed DCAA
    during the audit that Blanchard had estimated its costs using the depreciation principle
    and Blanchard would have used other methods to calculate its costs had it believed it
    could (first amended compl. ¶ 39; answer ¶ 39). Blanchard informed DCAA those other
    methods (such as charging the rental rate or using declining-balance depreciation) would
    have resulted in higher cost estimates (first amended compl. ¶ 39; answer ¶ 39). Fluor
    alleges that Blanchard used its estimate mainly because it more closely approximated
    what it expected to cost to dispose of the generators and other equipment (first amended
    compl. ¶ 40). Even DCAA acknowledged that Blanchard had purchased and timely
    shipped the equipment to the Middle East, where it sat ready for performance prior to
    termination (R4, tab 8 at 181; first amended compl. ¶¶ 37-38). Indeed, Fluor alleges that
    Blanchard’s actual costs of disposing of the equipment closely approximated its
    estimated costs provided to DCAA (first amended compl. ¶¶ 61-66). Fluor alleges that it
    acted reasonably in settling with Blanchard because the actual costs incurred by
    Blanchard match the amount Fluor and Blanchard had already provided the Corps of
    We note first that GSBCA cases are not binding upon us except to the degree that
    we find them to be persuasive authority. Moreover, here, the equipment was new
    and had not been depreciated, so this particular aspect of the cost principle is not
    relevant to these appeals. Nor did the costs at issue relate to settlement of a
    subcontractor’s costs, as here.
    13
    Engineers and DCAA in the estimated costs in the termination settlement proposal (first
    amended compl. ¶¶ 50, 61-66).
    Based on all these allegations, we believe that Fluor has plausibly pleaded a claim
    for recovery of its subcontractor costs even though Fluor seeks to demonstrate the
    reasonableness of recovery based on the actual increased costs incurred rather than the
    estimates provided in Blanchard’s termination settlement proposal. Johnson, 574 U.S.
    at 11; Phoenix Data, 
    18-1 BCA ¶ 37,164
     at 180,922 (noting that termination settlements
    may be “based on estimates”); Raytheon Co., 
    ASBCA No. 57743
     et al., 
    17-1 BCA ¶ 36,724
     at 178,847 (“An increase (or reduction) on appeal in the amount claimed does
    not constitute a new claim under the CDA as long as the nature of the claim and basic
    operative facts are essentially the same.”), aff'd, 
    940 F.3d 1310
     (Fed. Cir. 2019).
    Termination settlements must balance strict application of the cost principles with
    assuring fairness to the contractor terminated for convenience. Nicon, 
    331 F.3d at 885
    ;
    FAR 49.201(c) (“Cost and accounting data may provide guides, but are not rigid
    measures, for ascertaining fair compensation.”). Fluor plausibly alleges Blanchard
    incurred costs for obtaining, shipping, and storing the equipment, and Fluor should not
    shoulder the costs of the government’s convenience termination decision for following
    the agency’s direction to settle these costs with its subcontractor. Nicon, 
    331 F.3d at 885
    ;
    Jacobs Eng’g Grp., Inc. v. United States, 
    434 F.3d 1378
    , 1381 (Fed. Cir. 2006) (“A
    contractor is not supposed to suffer as the result of a termination for convenience of the
    Government, nor to underwrite the Government's decision to terminate.” (Citation
    omitted)); (R4, tab 6 at 144 (termination letter reminding Fluor of obligation to
    “promptly” settle with subcontractors)) Fluor should be permitted to provide evidence to
    prove its well-pleaded allegations.
    2.     Fluor Has Plausibly Alleged Notice to the Agency Regarding its
    Subcontractor Settlement
    The Corps of Engineers asserts that, even if Fluor was permitted to show the
    reasonableness of its settlement with its subcontractor Blanchard, Fluor cannot recover
    because Fluor failed to obtain contracting officer approval under FAR 49.108-3 prior to
    paying its subcontractor to settle its termination proposal (gov’t reply at 5-6 n.6).
    FAR 49.108-3(b)(2) states that a termination contracting officer “shall require that . . .
    [t]he prime contractor submit, for approval or ratification, all termination settlements
    with subcontractors.” FAR 49.108-3(b)(2); Parson Global Servs., Inc. ex rel. Odell Int’l,
    Inc. v. McHugh, 
    677 F.3d 1166
    , 1172 (Fed. Cir. 2012) (recognizing that FAR 49.108-3
    “allows prime contractors to settle with subcontractors and then submit these settlements
    to the TCO for approval”); Lockheed Martin Corp. v. England, 
    424 F.3d 1199
    , 1201
    (Fed. Cir. 2005) (noting that a prime contractor’s proposed termination settlement with a
    subcontractor would not “become final until approved or ratified by the Termination
    Contracting Officer”).
    14
    In December 2013, Fluor provided Blanchard’s 474-page termination settlement
    proposal as part of Fluor’s termination proposal, listing the total amount of Blanchard’s
    settlement proposal of $3,370,768 as “settlements with subcontractors” (first amended
    compl. ¶ 42; app. supp. R4, tab 13.2 at 4, tab 15 at 1, tab 13 (Blanchard termination
    settlement proposal)). Fluor has adequately alleged that Blanchard’s termination
    settlement proposal provided the Corps of Engineers with sufficient information to meet
    the requirements of FAR 49.108-3. H.J. Lyness Constr., Inc. v. United States, 
    121 Fed. Cl. 287
    , 295 (2015) (denying claim based on FAR 49.108-3 where “[t]he documentation
    submitted to GSA at the time of the audit was insufficient to support the award of
    subcontractor settlement costs, and Plaintiff has failed to provide the Court with any
    additional documentation that could supplement the record on the issue”), aff’d, 652 F.
    App’x 972 (Fed. Cir. 2016). Indeed, as noted above, DCAA’s audit report (which was
    not issued until December 2015 – two years after Fluor submitted its termination
    settlement proposal) verified that Blanchard incurred costs by purchasing, shipping, and
    housing the generators in the Middle East in preparation for this Contract (R4, tab 8
    at 181; first amended compl. ¶¶ 37-38).
    Moreover, Fluor has alleged that it entered a settlement agreement with Blanchard
    in July 2014 for the subcontractor’s termination costs eight months after submitting its
    termination settlement proposal to the Corps of Engineers in December 2013 (first
    amended compl. ¶ 46). Indeed, Fluor alleged that it acted reasonably by not awaiting the
    two-year-long DCAA audit by “promptly” settling as the Corps of Engineers directed
    Fluor when the agency terminated the Task Order in May 2013 (and as Fluor promised
    Blanchard in the Subcontract) (first amended compl. ¶ 16; app. supp. R4, tab 13 at 330;
    R4, tab 6 at 144). Thus, Fluor has plausibly pleaded that it met its obligation under
    FAR 49.108-3 and has appealed the contracting officer’s decision denying recovery of its
    settlement with Blanchard. Whether Fluor should recover its subcontractor settlement
    costs remains a question of disputed fact that we look at next.
    The Current Record Does Not Establish Fluor’s Costs and, Thus, We Deny
    Summary Judgment in its Favor
    A.     Standard of Review
    Board Rule 7(c) permits summary judgment motions and “looks to Rule 56 of the
    Federal Rules of Civil Procedure for guidance.” ASBCA Rule 7(c)(2). FED. R. CIV.
    P. 56 requires granting “summary judgment if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    FED. R. CIV. P. 56(a). “[A]t the summary judgment stage the judge’s function is not
    himself to weigh the evidence and determine the truth of the matter but to determine
    whether there is a genuine issue for trial.” Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    ,
    249 (1986).
    15
    “At the summary judgment stage, facts must be viewed in the light most favorable
    to the nonmoving party only if there is a ‘genuine’ dispute as to those facts.” Scott v.
    Harris, 
    550 U.S. 372
    , 380 (2007). The nonmovant must “do more than simply show that
    there is some metaphysical doubt as to the material facts” to defeat a summary judgment
    motion. 
    Id.
     (quoting Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    ,
    586-87 (1986)). Finally, on summary judgment, we apply the “substantive evidentiary
    standard of proof that would apply at the trial on the merits.” Anderson, 
    477 U.S. at 252
    .
    B.     There is a Genuine Dispute of Material Fact Regarding the Reasonableness
    and Amount of Costs Relating to Fluor’s Settlement with Blanchard
    For convenience termination costs, the “claimant bears the burden of proving the
    fact of loss with certainty, as well as the burden of proving the amount of loss with
    sufficient certainty so that the determination of the amount of damages will be more than
    mere speculation.” Lisbon Contractors, Inc. v. United States, 
    828 F.2d 759
    , 767 (Fed.
    Cir. 1987) (quoting Willems Indus., Inc. v. United States, 
    295 F.2d 822
    , 831 (Ct. Cl.
    1961)); Envtl. Safety Consultants, 
    15-1 BCA ¶ 35,906
     at 175,522. Fluor’s summary
    judgment motion and the extant record do not suffice to establish an absence of a genuine
    dispute of material fact as to the reasonableness and amount of Fluor’s costs in settling
    with Blanchard. 6
    Fluor asserts in its complaint that it paid Blanchard $3,116, 991.20 to settle, but
    the record includes nothing to support that allegation (first amended compl. ¶ 46). Fluor
    relies on the Corps of Engineers’ citation of Fluor’s complaint as the basis for finding this
    fact undisputed (app. resp. at 18; gov’t mot. at 4). The agency clearly treated that fact as
    undisputed only for purposes of its motion to dismiss, where it “must accept well-pleaded
    factual allegations as true” to prevail. Kellogg Brown & Root, 728 F.3d at 1365. In fact,
    the Corps of Engineers’ answer denies, for lack of information, the allegation that Fluor
    made a settlement payment to Blanchard (answer ¶ 46). Fluor must do more than simply
    rely on its pleadings to demonstrate the fact and amount of settlement, particularly where
    the Corps of Engineers’ answer denies it. While Blanchard’s estimated costs in its
    termination settlement proposal and allegation of subcontractor settlement and payment
    assisted Fluor in surviving dismissal, the current record lacks sufficient evidentiary proof
    to demonstrate an undisputed material fact necessary for summary judgment.
    6
    Typically, Fed. R. Civ. P. 56 “requires the nonmoving party to go beyond the pleadings
    and by her own affidavits, or by the ‘depositions, answers to interrogatories, and
    admissions on file,’ designate ‘specific facts showing that there is a genuine issue
    for trial.’” Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 324 (1986) (quoting Fed. R.
    Civ. P. 56(e)). Because Fluor has failed to show an absence of a genuine dispute
    of material fact, the Corps of Engineers’ has prevailed despite its unsupported
    responses that “upon information and belief” Fluor’s allegations were not true.
    16
    Additionally, the record is unclear whether Fluor acted reasonably in settling with
    Blanchard for the alleged amount. “Cost reasonableness is a ‘question of fact.’” Kellogg
    Brown & Root, 728 F.3d at 1360 (quoting Gen. Dynamics Corp. v. United States,
    
    410 F.2d 404
    , 409 (Ct. Cl. 1969)). “The standard of assessing reasonableness is flexible”
    and we “consider many fact-intensive and context-specific factors.” 
    Id.
     at 1360 (citing
    FAR 31.201-3). Fluor has alleged that it acted reasonably in settling with Blanchard
    because Blanchard’s actual costs, including costs of capital, justified the estimates
    provided in the termination settlement proposal provided to DCAA (first amended compl.
    ¶¶ 61-66). For factual support, Fluor relies solely on an affidavit of Blanchard’s current
    chief financial officer to explain the actual costs Blanchard incurred in disposing of the
    generators and other equipment (app. resp., Johnson aff. ¶¶ 5-7.7). However, the record
    includes no back-up documentation that is necessary to justify the reasonableness of these
    actual incurred costs. “A reference in a claim is inadequate to constitute a showing
    sufficient that no reasonable trier of fact could find other than for appellant.” Orbital
    Sciences Corp., 
    ASBCA No. 50171
    , 
    00-1 BCA ¶ 30,860
     at 152,344. Fluor must provide
    more than just its allegations in its claim or complaint and may not simply rely on alleged
    costs “asserted under oath by a company official” but must provide some documentation
    supporting its termination costs. First Division Design, LLC, 
    ASBCA No. 60049
    , 
    18-1 BCA ¶ 37,201
     at 181,102.
    Moreover, Fluor’s complaint alleges that Blanchard’s actual incurred “costs were
    slightly offset by a net gain of $586,000 resulting from the eventual sale of the
    generators;” but the affidavit’s calculation does not discuss this potential mitigating
    amount and whether it impacts Blanchard’s actual costs (first amended compl. ¶ 61).
    Even a terminated party has a duty of mitigation. Ind. Mich. Power Co. v. United States,
    
    422 F.3d 1369
    , 1375 (Fed. Cir. 2005) (“Mitigation is appropriate where a reasonable
    person, in light of the known facts and circumstances, would have taken steps to avoid
    damage.”). If Blanchard actually mitigated these costs, then that potentially impacts the
    reasonableness of any settlement and the agency’s liability to reimburse Fluor.
    Ultimately, at this time, Fluor has failed to provide sufficient evidentiary proof to
    demonstrate an absence of a genuine dispute of material fact. In response to the agency’s
    motion to dismiss Fluor stated, “There is a genuine issue of material fact regarding the
    actual costs incurred by Blanchard resulting from the termination for convenience”
    (app. resp. at 12). We agree, and think this statement equally applies to Fluor’s motion
    for summary judgment. Fluor may very well have evidence to show that it acted
    reasonably, but Fluor neither provided undisputed evidence with its summary judgment
    motion nor has it yet included such evidence in any supplements to the Rule 4 file. Thus,
    we deny Fluor’s motion for summary judgment.
    17
    CONCLUSION
    For the foregoing reasons, we deny the Corps of Engineers’ motion to partially
    dismiss Fluor’s appeal and deny Fluor’s motion for summary judgment.
    Dated: March 29, 2022
    DANIEL S. HERZFELD
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    RICHARD SHACKLEFORD                              J. REID PROUTY
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 62550, 62672, Appeals of
    Fluor Intercontinental, Inc., rendered in conformance with the Board’s Charter.
    Dated: March 29, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    18