Korte Construction Company ( 2023 )


Menu:
  •                   ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                )
    )
    Korte Construction Company                 )   
    ASBCA No. 63148
    )
    Under Contract No. W912BV-19-C-0017        )
    APPEARANCE FOR THE APPELLANT:                  Michael E. Wilson, Esq.
    Greenfelder, Hemker & Gale, P.C.
    St. Louis, MO
    APPEARANCES FOR THE GOVERNMENT:                Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Lauren M. Williams, Esq.
    Thomas R. Alford, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Tulsa
    OPINION BY ADMINISTRATIVE JUDGE STINSON
    ON THE PARTIES’ MOTIONS FOR SUMMARY JUDGMENT
    Appellant Korte Construction Company (Korte) appeals a contracting officer’s
    October 22, 2021, final decision denying Korte’s August 24, 2021, claim requesting
    the government rescind its unilateral contract modification assessing a credit of
    $493,639.43, in direct and indirect costs for a deductive change to contract work. We
    have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 
    41 U.S.C. §§ 7101-7109
    . The parties submitted opposing motions for summary judgment,
    responsive and reply briefs, as well as exhibits to be considered in deciding this
    appeal. 1 For the reasons stated below, appellant’s motion for summary judgment is
    denied and the government’s motion for summary judgment is granted.
    1
    “App. mot.” refers to appellant’s March 20, 2023, motion for summary judgment;
    “gov’t mot.” refers to the government’s March 20, 2023, motion for summary
    judgment; “app. resp.” refers to appellant’s May 10, 2023, response to the
    government’s motion for summary judgment; “gov’t resp.” refers to the
    government’s May 10, 2023, response to appellant’s motion for summary
    judgment; “app. reply” refers to appellant’s June 9, 2023, reply brief; and
    “gov’t reply” refers to its June 9, 2023, reply in support of its motion for
    summary judgment.
    SYNOPSIS
    This appeal presents the issue of whether the government is entitled to a credit
    under a deductive change request where the contractor alleges it did not include in its
    cost proposal amounts required to perform work that is the subject of the deductive
    change request. Korte offers evidence that its mechanical subcontractor, who
    submitted a bid for the work that was incorporated into the contractor’s cost proposal,
    determined that the work was not required under the contract, and, accordingly, did not
    price that work.
    Korte now seeks to use as a shield the fact that, through incorporation of its
    subcontractor’s bid into its cost proposal, Korte’s contract price did not include the
    cost to perform work covered by the deductive change order and, as such, the
    government is not entitled to a credit for the work not performed. While it is true that,
    for certain purposes, a subcontractor’s interpretation will be imputed to a contractor if
    it proves that the subcontractor relied upon that interpretation in submitting its bid, the
    defect in Korte’s armor is that the contractor is not protected if the interpretation by
    the subcontractor is indefensible, and here, the evidence Korte offers in its motion for
    summary judgment establishes that its subcontractor recognized pre-award an
    ambiguity in the contract regarding whether the work was required to be performed
    but did not seek clarification regarding that work. Korte suggests that reference to the
    work in the solicitation was simply a scrivener’s error, one it admittedly had
    knowledge of during the solicitation process. However, Korte’s motion for summary
    judgment admits knowledge of an ambiguity in the solicitation, one which appellant
    was required to raise with the government pre-award but failed to do so.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
    The parties submitted a Joint Stipulation of Material Facts (JSMF) in support of
    their motions for summary judgment. Our statement of facts relies upon, and adopts,
    certain of the parties’ JSMF, as set forth below.
    RFP Phase 1
    1. On October 11, 2018, the government issued the Phase 1 Request for
    Proposals (RFP) for Solicitation No. W912BV-18-R-0047 (JSMF ¶ 1; R4, tab 3). The
    Phase 1 RFP sought design-build proposals for a new KC-46A Depot Fuel Hangar
    project at Tinker Air Force Base and contemplated award of a firm fixed-price contract
    as part of a two-phase competitive solicitation (JSMF ¶ 2; R4, tab 3 at COE R4 3-
    0001).
    2. The Phase 1 RFP included specification section 00 21 00, INSTRUCTIONS,
    CONDITIONS AND NOTICES TO OFFERORS (R4, tab 3 at COE R4 3 - 0004).
    2
    Paragraph 1.4, which provided information regarding offerors’ questions and
    comments, instructed that “[a]ll contractual matters, questions and or comments
    relative to these documents should be submitted via Bidder Inquiry in ProjNet” (id.
    at COE R4 3 - 0005).
    3. The Phase 1 RFP included specification section 00 22 20, PHASE 2
    DESIGN-BUILD SELECTION PROCEDURES AND BASIS OF AWARD (R4, tab 3
    at COE R4 3 - 0036). Paragraph 3.8, TAB A – DEVIATIONS, EXCEPTIONS, AND
    ASSUMPTIONS, stated, in part:
    Should the Offeror have any questions related to specific
    terms and conditions, these must be resolved prior to
    submission of the offer. Notwithstanding the above, if
    deviations and exceptions are included with the offer, the
    Offeror shall list and describe in detail the deviations
    and/or exceptions under Tab A.
    (Id. at COE R4 3 - 0041) (underlining in original) 2
    4. The Phase 1 RFP included specification section 01 10 05.00 setting forth a
    statement of work and mechanical requirements for the project (R4, tab 3 at COE R4 3
    - 0187). Paragraph 4 of section 01 10 05.00 set forth specifications regarding heating,
    ventilation, and air conditioning systems (id. at COE R4 3 - 0193). Paragraph 4.4.4 set
    forth requirements for the “Air cooled chiller,” stating, “[t]he Tinker Air Force Base
    existing chilled water loop will be utilized to provide cooling to the facility” (id.
    at COE R4 3 - 0198). Paragraph 4.4.5 set forth specifications regarding the chilled
    water system (id.). Paragraph 4.5 set forth specifications regarding piping and
    paragraph 4.5.1 set forth specifications regarding chilled water piping (id. at COE R4 3
    - 0199).
    Korte’s Mechanical Engineer and Subcontractor
    5. Charles E. Jarrell Contracting Company d/b/a Jarrell Mechanical (Jarrell or
    Jarrell Mechanical) was part of Korte’s design-build team for the Project and the
    mechanical subcontractor. Jarrell was “delegated the responsibility for preparing the
    drawings for Korte’s proposals for the Project to design team members” and as “the
    mechanical engineering firm of record, in this case, Jarrell, was responsible for
    determining whether chilled water piping was required.” (App. mot. at 2 (app. facts
    ¶ 3) (citing app. mot. ex., Feb. 23, 2023, D. Brauer dep. 35:14-17, 37:24-38:2, 51:19-
    53:9, 75:22-76:5, 76:9-77:18 , 79:13-80:3)) (see also app. resp. ex., May 10, 2023,
    2
    The RFP Phase 2 specifications included a similar provision (JSMF ¶ 8; R4, tab 6
    at COE 6 - 0013, 0020).
    3
    M. Jarrell decl. at 1) The government’s Statement of Genuine Issues of Material Fact
    responds to appellant’s Facts submission ¶ 3, denying the allegations and stating,
    “[p]aragraph 3 characterizes the responsibilities of Korte’s subcontractors with which
    the Government has no contractual relationship. In addition, this is not material for
    resolution of this Appeal” (gov’t resp. at 3). In the context of a motion for summary
    judgment, the government’s stated objection is wholly insufficient as a basis to
    properly challenge or controvert the facts set forth by appellant in paragraph 3.
    6. Korte states that “[d]uring the Project solicitation stage, Jarrell Mechanical’s
    project team interpreted the solicitation documents including the concept drawings as
    not calling for any chilled water improvements” (app. May 10, 2023, Statement of
    Additional Material Facts ¶ 11) (citing app. mot. ex., Feb. 23, 2023, M. Jarrell
    dep. 24:6-13, 33:12-35:7, 40:1-41:10, 42:4-22; R4, tab 45; Feb. 23, 2023, D. Brauer
    dep. 77:6-18; Mar. 20, 2023, D. Brauer decl. ¶ 4). The government’s response to
    appellant’s Statement of Additional Material Facts ¶ 11 states “[t]he Government is
    without sufficient information to admit or deny what Korte’s subcontractor, Jarrell
    Mechanical’s project team interpreted; therefore, denies” (gov’t reply at 6). In the
    context of a motion for summary judgment, the government’s stated objection is
    wholly insufficient as a basis to properly challenge or controvert the facts set forth in
    paragraph 11.
    7. On November 13, 2018, Korte submitted a Phase 1 proposal and on
    January 7, 2019, submitted a revised Phase 1 proposal (JSMF ¶¶ 4-5; R4, tabs 15-16).
    RFP Phase 2
    8. On January 29, 2019, the government issued RFP Amendment No. 0003,
    which included the RFP Phase 2 revised solicitation dated January 17, 2019 (JSMF
    ¶ 6; R4, tab 6 at COE R4 6 - 0001-0002).
    9. RFP Phase 2 included a revision to section 01 10 05.00 (STATEMENT OF
    WORK – MECHANICAL REQUIREMENTS, specifically paragraph 4.4.4, deleting
    the following statement (as it appeared in RFP Phase 1), “Air cooled chiller: The
    Tinker Air Force Base existing chilled water loop will be utilized to provide cooling to
    the facility” (see SOF ¶ 4), and replacing it with “Air cooled chiller: A single air-
    cooled chiller may be provided” (R4, tab 6 at COE R4 6 – 0196, 0209).
    10. Another revision to section 01 10 05.00 was the addition of a new
    paragraph 4.5.6, which stated, “[e]xtend the base wide chilled water, hot water, and
    compressed air piping to the slab edge of the hangar. Provide connection location for
    future projects” (JSMF ¶ 7; R4, tab 6 at COE R4 6 – 0198, 0211). This new provision
    also was included in subsequent revisions to RFP Phase 2, specifically, (1) RFP
    Amendment No. 0005, issued on February 21, 2019, included the same information set
    4
    forth in the same numbered paragraph 4.5.6 (JSMF ¶ 17; R4, tab 8 at COE R4 8 -
    0218), (2) RFP Amendment No. 0007, issued on March 8, 2019, included the same
    information, but it appeared in a new paragraph 4.4.11.6 (JSMF ¶ 20; R4, tab 44
    at COE R4 44 - 0150) (see also R4, tab 12 at COE R4 12 – 0218), and (3) RFP
    Amendment No. 0009, dated May 9, 2019, included the same information, again in
    paragraph 4.4.11.6, and was “issued to provide clarification between subsequent
    amendments, provide a comprehensive document of changes from [sic] Amendment
    0007 and Amendment 0008, and incorporate new revisions into the solicitation” (R4,
    tab 12 at COE R4 12 - 0001).
    RFP Phase 2 Drawings
    11. RFP Phase 2 included numerous schematic drawings, several of which
    depicted three parallel lines labeled “CW” running east to west, located north of the
    hangar, specifically, Contract Drawing CG101, the Conceptual Grading and Drainage
    Plan (R4, tab 6 at COE R4 6 - 0901, tab 8 at COE R4 8 - 0862, tab 12 at COE R4 12 -
    0859, tab 44 at COE R4 44 - 0791) and Contract Drawing CU101, the Conceptual
    Civil Utility Plan (R4, tab 6 at COE R4 6 - 0909, tab 8 at COE R4 8 - 0870, tab 12
    at COE R4 12 - 0867, tab 44 at COE R4 44 - 0799; see also JSMF ¶ 11). In its briefs,
    the government assigns the term “chilled water” to the demarcation “CW,” although
    that specific acronym is not set forth or defined in Contract Drawings CG101 and
    CU101 (gov’t mot. at 2 n.1; see R4, tab 6 at COE R4 6 - 0901 (Contract Drawing
    CG101) and COE R4 6-0909 (Contract Drawing CU101)).
    12. Various other lines appear on Contract Drawing CG101, some of which
    have a keynote number pointing to them. An information box on the righthand side of
    the drawing, titled “Sheet Keynotes,” includes four keynotes with descriptions. Lines
    without a keynote also appear on this drawing. Among the lines without a keynote are
    the three parallel lines labeled “CW” running east to west, located north of the hangar
    between two boxes which likewise have no corresponding keynote. (JSMF ¶ 14; R4,
    tab 6 at COE R4 6 - 0901).
    13. Various other lines appear on Contract Drawing CU101, some of which
    have a keynote number pointing to them. A box on the righthand side of the drawing
    titled “Sheet Keynotes” includes sixteen keynotes with descriptions. Lines without a
    keynote also appear on this drawing. Among the lines on this sheet without a keynote
    pointing to them are the three parallel lines labeled “CW” running east to west, located
    north of the hangar between two boxes which likewise have no corresponding keynote.
    Under the moniker “General Sheet Notes” appears the statement: “Refer to sheet
    C-001 and C-002 for general civil notes, legends, and abbreviations.” (JSMF ¶ 15; R4,
    tab 6 at COE R4 6 - 0909).
    5
    14. Contract Drawing C-001, Abbreviations and Existing Conditions Legend,
    includes underneath the moniker “Existing Conditions Legend, Continued” the
    following two symbols: “—12" CWS1—” and “—12" CWR1—”, with the following
    descriptions: “Chilled Water Supply” and “Chilled Water Return.” Also included
    under “Abbreviations” are CWR and CWS, with the following description: “Chilled
    Water Return” and “Chilled Water Supply.” (JSMF ¶ 12; R4, tab 6 at R4 6 - 0884; see
    also JSMF ¶ 28)
    15. Contract Drawing C-002, Civil Legend, sets forth two columns, one titled
    “Proposed” and another to the right titled “Description.” Symbols for various lines
    such as “force main,” “fire water line,” “industrial waste,” “sanitary sewer,” “storm
    sewer,” “natural gas line,” “compressed air line,” and “water line,” are included among
    the civil legends. The columns on this sheet do not include the words “chilled water.”
    (JSMF ¶ 13; R4, tab 6 at COE R4 6 - 0885)
    16. The solicitation incorporated by reference FAR 52.243-4, Changes
    (JUN 2007). The solicitation also incorporated by reference FAR 52.236-21
    Specifications and Drawings for Construction (FEB 1997), which stated, in part:
    (a) . . . In case of difference between drawings and
    specifications, the specifications shall govern. In case of
    discrepancy in the figures, in the drawings, or in the
    specifications, the matter shall be promptly submitted to
    the Contracting Officer, who shall promptly make a
    determination in writing. Any adjustment by the
    Contractor without such a determination shall be at its own
    risk and expense. The Contracting Officer shall furnish
    from time to time such detailed drawings and other
    information as considered necessary, unless otherwise
    provided.
    (JSMF ¶¶ 38-39; R4, tab 12 at COE R4 12 - 0049; see also R4, tab 26 at COE R4 26 -
    0013)
    Inquires of Other Offerors Through ProjNet
    17. On February 6, 2019, an offeror submitted the following inquiry (question
    no. 7829421) through the ProjNet system: “RFP section 01 10 05.00 00, 4.5.6 requires
    relocation of the campus chilled and hot water pipes. The civil plans do not show any
    existing campus chilled or hot water pipes. Can drawings of the existing pipes be
    provided?” (R4, tab 49 at COE R4 49 - 0017) On February 27, 2019, the government
    provided the following response to question no. 7829421: “The CHWS and CHWR
    lines shown are per the FY 15 Support Infrastructure project and show the lines routed
    6
    north in order to avoid the Fuel Hangar footprint. The awarded-Contractor must
    confirm this is the case prior to design and construction.” (Id.)
    18. On February 19, 2019, an offeror submitted the following inquiry (question
    no. 7851655) through the ProjNet system: “In the RFP Phase I document (Section
    011005 paragraph 4.4.4) it states ‘The Tinker Air Force Base existing chilled water
    loop will be utilized to provide cooling to the facility’. The same paragraph in the
    Phase 2 solicitation states that ‘a single air cooled chiller may be provided.’ Please
    advise if the TAFB existing chilled water loop is to be utilized or is a new chiller to be
    provided?” (R4, tab 50 at COE R4 50 - 0007) On March 14, 2019, the government
    provided the following response to question no. 7851655: “Reference amendment”
    (id.).
    19. On February 19, 2019, an offeror submitted the following inquiry (question
    no. 7851662) through the ProjNet system: “If there is a district heating and cooling
    system on base, and we utilize this, are we still obligated to provide a treatment system
    for the makeup water to chilled water, heating water, and condenser water systems
    (section 011005 paragraph 4.8) at the Fuel Hangar and the Depot Maintenance
    Hangar?” (R4, tab 50 at COE R4 50 - 0007). On March 14, 2019, the government
    provided the following response to question no. 7851662: “Provide chilled water
    system and hot water system at the building per RFP documents” (id.).
    20. On February 19, 2019, an offeror submitted the following inquiry (question
    no. 7851659) through the ProjNet system: “In the RFP Phase I document (Section
    011005 paragraph 4.6.3.1) it states 'Heating for the building shall be provided by
    existing hot water boiler(s) from the Tinker AFB hot water loop'. The sam [sic]
    paragraph in the Phase 2 solicitation states that ‘Heating for the building shall be
    provided by packaged natural gas fire high efficiency condensing type hot water boiler
    (s)’. Please advise it [sic] the existing hot water loop is to be utilized or if new boilers
    are required.” (R4, tab 50 at COE R4 50 - 0007) On March 14, 2019, the government
    provided the following response to question no. 7851659: “Provide new boiler system
    per RFP and amendments” (id.).
    21. On March 15, 2019, an offeror submitted the following inquiry (question
    no. 7893440) through the ProjNet system: “RFP states: Extend the base wide chilled
    water, hot water, and compressed air piping to the slab edge of the hangar. Are we
    required to extend CHW and HW to the hangar if we are not utilizing either service for
    this facility?” (JSMF ¶ 22; R4, tab 14) On April 8, 2019, the government provided
    the following response to question no. 7893440: “Extend the base wide systems per
    the RFP” (JSMF ¶ 23; id.).
    7
    Korte’s RFP Phase 2 Proposals
    22. On May 31, 2019, appellant submitted its RFP Phase 2 technical proposal,
    and on July 18, 2019, submitted its revised RFP Phase 2 proposal (JSMF ¶¶ 33-34; R4,
    tabs 20-23). Both of Korte’s RFP Phase 2 proposals included annotated versions of
    drawings contained in the solicitation that included three parallel lines labeled “CW”
    running east to west, located north of the hangar (R4, tab 20 at COE R4 20 – 0074
    (Proposal Drawing C-208, Grading Plan); R4, tab 20 at COE R4 20 - 0081 (Proposal
    Drawing C-215, Utility Plan); R4, tab 23 at COE R4 23 - 0074 (Proposal Drawing C-
    208, Grading Plan); R4, tab 23 at COE R4 23 - 0081 (Proposal Drawing C-215, Utility
    Plan)). Korte’s May 31, 2019, RFP Phase 2 Technical proposal, Tab A, and RFP
    Phase 2 Price proposal, Tab B, both state: “The Korte Company is not proposing any
    deviations, exceptions or assumptions to the terms or conditions of the Solicitation for
    the KC-46A Fuel Maintenance Hangar at Tinker Air Force Base” (JSMF ¶ 33; R4,
    tab 20 at COE R4 20 - 0005, tab 21 at COE R4 21 - 0015). Korte’s July 18, 2019,
    revised RFP Phase 2 proposal, Tab A, states: “The Korte Company is not proposing
    any deviations, exceptions or assumptions to the terms or conditions of the Solicitation
    for the KC-46A Fuel Maintenance Hangar at Tinker Air Force Base” (JSMF ¶ 35; R4,
    tab 23 at COE R4 23 - 0005).
    Contract Award
    23. On September 27, 2019, the government awarded Korte Contract
    No. W912BV-19-C-0017 in the amount of $72,827,332.00 (JSMF ¶ 37; R4, tabs 25-
    26).
    Government’s Request for Proposal/Korte’s Response
    24. By letter dated September 14, 2020, the government requested Korte
    submit a request for proposal (RFP-0002) to perform work identified as “Breathing Air
    & Chilled Water Changes” pursuant to the contract’s Changes clause (JSMF ¶ 40; R4,
    tab 28 at COE R4 28 - 0001). Specifically, the government requested Korte (1)
    “[e]xtend the existing separate breathing air system . . . past the new apron and be
    capped and or valved appropriately for future connections,” (2) “[i]nstall new Utilities
    Valve Vault for 14" Chilled Water Supply (CHWS or CW) and 14" Chilled Water
    Return (CHWR or CW),” (3) “[i]nstall 2 - 14" Underground Chilled Water (CW)
    mains from the FY15 mechanical building to the new Utilities Valve Vault,” and (4)
    “[r]emove 1 - 14" Underground Chilled Water (CW) main line. . . . Line to be
    removed runs from the new valve vault (NW of central plant) and extends past the new
    apron for future connection. RFP sheet CU101 indicated a total of 3 main lines
    required, but only 2- 14" mains lines are needed.” (Id. at COE R4 28 - 0002)
    8
    25. By letter dated October 12, 2020, Korte responded to the government’s
    request (JSMF ¶ 43). Regarding the “Chilled Water Supply/Return & Vault,” Korte
    (1) proposed to install new Utilities Valve Vault for 14" Chilled Water Supply and 14"
    Chilled Water Return, (2) stated that the “[i]nstalled vault will contain bubble-tight
    and air-tight manual butterfly valves,” (3) stated it would “provide water/moisture
    blow down for the BA line and a small line of flow bypass on the west end of the new
    14" Chilled Water mains in the valve box,” (4) proposed to install 2 – 14"
    Underground Chilled Water (CW) mains from the FY15 mechanical building to the
    new Utilities Valve Vault, (5) proposed to remove 1 – 14" Underground Chilled Water
    (CW) main line, (6) stated that “[t]he line to be removed runs from the new Valve
    Vault NW of Central Plant and extends past the new apron for future connection, and
    (7) “acknowledge[d] that RFP sheet CU101 indicated a total of 3 required main lines,
    but only 2 – 14" main lines are needed” (R4, tab 30 at COE R4 30 - 0001-0002).
    Korte did not contest that “CW” denotes “chilled water” (R4, tab 30 at COE R4 30 -
    0001).
    26. By email dated November 3, 2020, the government discussed Korte’s
    proposal for RFP-0002, noting that the proposal did not include a credit for the three
    12" lines shown in the RFP drawings and stating that there should have been a credit
    for approximately 1,618LF of 12" chilled water line. The government also stated that
    “[t]here is one vault shown at the edge of the pavement, so there should only be two
    additional vaults in your proposal.” (JSMF ¶ 47; R4, tab 31 at COE R4 31 - 0001-
    0002)
    Disagreement Regarding Proposal Work
    27. By email dated November 17, 2020, Korte submitted a response to the
    government’s November 3, 2020, email, and included as an attachment a copy of a
    November 6, 2020, letter to Korte from Jarrell which stated, in part, “[t]he 3 lines
    labeled ‘CW’ on drawing CU101 of the RFP were not included in the original
    scope/pricing. These lines were not noted with what they were nor were any sizes
    indicated. On drawing C-001 of the RFP, the abbreviations list does not show
    anything for ‘CW’. It does list chilled water return as ‘CWR’ and chilled water supply
    as ‘CWS’.” (JSMF ¶ 48; R4, tab 33 at COE R4 33 - 0001, 0003-0004)
    28. By email dated November 18, 2020, the government responded to Korte’s
    November 17, 2020, email, stating, in part, “we are going to need more details on why
    things in the RFP were not included in writing so that I can provide that to our KO. As
    of now, just because it was forgotten or not added is not justification enough.” (JSMF
    ¶ 49; R4, tab 31 at COE R4 31 - 0003, tab 2 at COE R4 32 - 0003)
    29. By email also dated November 18, 2020, Korte responded:
    9
    I don’t believe anyone is claiming to have forgotten the
    CW lines. There are 3 lines shown as CW with no other
    indication as to what they are. All other utilities have key
    notes and direction with the RFP writer’s intent. With no
    direction provided our subsequent proposal did not indicate
    any work to take place making the assumption that they
    were either existing or not needed.
    (Id.) Korte’s November 18, 2020, email also states that no vaults were budgeted for
    the Project (id.).
    30. By email to Korte dated December 1, 2020, the government stated, in part:
    In regards to the chilled water lines, the RFP states (01 10
    05.00.00 “4.4.11.6) “Extend the base wide chilled water,
    hot water, and compressed air piping to the slab edge of
    the hangar. Provide connection location for future
    projects.” The legend on C-0001 [sic] indicated that the
    existing chilled water line was 12" and CU101 showed the
    location of the chilled water lines. The legend shows 12"
    lines and 14" lines are needed. So a cost for increasing
    from 12" to 14" would be acceptable. However, since only
    2 lines are required and 3 lines are shown, a credit would
    be due to the government for one line (deduction of a 12"
    line as shown). No credit was provided in your proposal
    for the deduction of this line. Please update the proposal
    accordingly.
    (JSMF ¶ 50; R4, tab 31 at COE R4 31 - 0001-0002)
    31. By email dated December 11, 2020, Korte responded to the government’s
    December 1, 2020, email, stating, in part, “[w]ith regard to the chilled water line there
    is not clear direction in the RFP requiring us to install these [sic] line as there are for
    other utilities and infrastructure. The type and size you [sic] referencing for these are
    from other locations and other pages within the RFP and no clear direction or
    reference where they should be shown on CU-101. Proper direction is just simply not
    provided.” (JSMF ¶ 51; R4, tab 31 at COE R4 31 - 0001, tab 32 at COE R4 32 - 0001)
    Jarrell’s Interpretation of the Solicitation Requirements
    32. Included as an attachment to Korte’s December 11, 2020, email was a letter
    dated December 8, 2020, from Jarrell Mechanical to Korte. The letter stated, in part:
    10
    The legend on C-001 that is being referred to is labeled as
    “Existing Conditions Legend”. Anything listed in this
    legend would be referring to existing items, not new items.
    This legend does indeed have symbols for 12" chilled
    water supply and 12" chilled water return. Again, these
    would be referring to existing piping, not new piping.
    Also, none of the drawings in the RFP show this existing
    12" piping. We are not understanding how a symbol for
    existing 12" piping implies that any new piping is also to
    be 12". The email also states that drawing CU-101 showed
    the location of the chilled water lines. In fact, CU-101
    does not show any chilled water lines. The government is
    saying that the 3 lines labeled “CW” are chilled water
    lines. The legends and abbreviations on C-001 do not list a
    “CW”, therefore how is one to know that lines labeled
    “CW” are chilled water?
    Since the lines were not properly identified or sized on the
    RFP drawings, the Korte team did not include them in the
    project bid. Based on this, there is no credit to give for any
    chilled water lines or vaults.
    (R4, tab 31 at COE R4 31 - 0009)
    33. During his deposition, Mr. Jarrell testified that paragraph 4.4.11.6
    (previously paragraph 4.5.6 (SOF ¶ 10)), was “poorly worded and unbiddable.”
    Specifically, Mr. Jarrell testified that the provision is “poorly written . . . since there's
    no base wide chilled water or no base wide hot water, and we knew that at the time.
    We have no idea how to size the piping, even if it did exist, because we don't know the
    size of the future projects. And we don't know which slab edge to go to, because
    there's four slab edges. So I would define that as unbiddable and very poorly worded
    and, honestly, a leftover from the Phase One RFP before they changed it from base
    wide system to independent systems.” (App. mot. ex., Feb. 23, 2023, M. Jarrell dep.
    at 33-34)
    34. Regarding his actions subsequent to reading paragraph 4.4.11.6 (previously
    paragraph 4.5.6 (SOF ¶ 10)), Mr. Jarrell stated:
    We discussed it verbally with Korte. We did research
    locally on the base to see -- well, first, we researched the
    floor plan of the base to see where the base wide chilled
    water and hot water system were. Determined they didn't
    exist. Determined the compressed air system did exist.
    11
    Included the compressed air system to get to the new
    hanger and talked verbally with Korte and included the
    condensed units and the hot water boilers as you pointed
    out in our proposal earlier.
    (App. mot. ex., Feb. 23, 2023, M. Jarrell dep. at 34-35) Mr. Jarrell confirmed that
    these discussions took place “before the contract was awarded” (id. at 35). Regarding
    whether he took any steps to inquire from the government about this “unbiddable and
    very poorly worded” solicitation provision, Mr. Jarrell stated: “Questions were asked
    and not answered clearly. I have no idea who asked them. I don't know if Korte did
    that after our discussion or if somebody else asked them. (Id. at 35) Regarding the
    government’s response to the March 15, 2019, question submitted by another offeror
    through the ProjNet system (SOF ¶ 21), Mr. Jarrell stated his belief that the response
    “was a poor answer,” that “the RFP is vague,” and that “the proposal reviewer was
    being lazy and not trying to figure out why the question was being asked” (app. mot.
    ex., Feb. 23, 2023, M. Jarrell dep. at 23:1-24:5; see app. mot. at 12).
    Deletion of Chilled Water Lines and Unilateral Modification No. P00004
    35. By letter dated February 12, 2021, the government issued RFP-0008
    pursuant to the Changes clause, requesting Korte “submit a proposal for accomplishing
    the revised work listed as TG012, Delete Chilled Water Lines, on page 2” (JSMF
    ¶ 55). Page 2 of the February 12, 2021, letter, included reference to Part C, CHANGE
    IN CONTRACT SPECIFICATIONS, which stated:
    SECTION 01 10 05.00.00 paragraph 4.4.11.6 "Extend the
    base wide chilled water, hot water, and compressed air
    piping to the slab edge of the hangar. Provide connection
    location for future projects." shall be revised to "Extend the
    base wide hot water, and compressed air piping to the slab
    edge of the hangar. Provide connection location for future
    projects."
    (Id. ¶ 57)
    36. By email dated March 26, 2021, the government transmitted Modification
    No. P00004 to Korte for signature. The email noted that “[t]he Government requested
    a proposal from Korte for this action, but did not receive one.” (JSMF ¶ 61; R4,
    tab 41) By letter dated March 31, 2021, Korte informed the government it would not
    execute Modification No. P0004 because “a credit is not due” (JSMF ¶ 62; R4, tab 42).
    On April 20, 2021, the Contracting Officer issued unilateral Modification No. P00004,
    decreasing the contract price by $493,639.43 (JSMF ¶ 63; R4, tab 27).
    12
    37. By letter dated May 19, 2021, Korte informed the government that it did
    not agree that the government’s issuance of unilateral Modification No. P00004 was
    proper and requested that the modification be deleted (JSMF ¶ 64; R4, tab 43). The
    letter also referenced the March 15, 2019, question (discussed in SOF ¶ 21 above),
    inquiring about the reference to extending “the base wide chilled water, hot water, and
    compressed air piping to the slab edge of the hangar . . . .” (R4, tab 43 at COE R4 43 -
    0002; see also JSMF ¶ 65). Regarding that question, appellant asserts that it “was not
    able to send a follow up question due to the USACE response was past the Proj[N]et
    Question period” (id.).
    Korte’s Claim and Request for Recission of Modification
    38. By letter dated August 24, 2021, Korte submitted a request “for a final
    written decision of the Contracting Officer on Korte’s claim that the USACE’s
    April 21, 2021 unilateral modification adopting a credit of $493,639.43 should be
    rescinded” (JSMF ¶ 66; R4, tab 2 at COE R4 2 - 0001). The letter stated, in part:
    [T]he RFP for Phase II made it clear that rather than have
    the fuel hangar tie into a base wide chiller system per the
    terms of the Phase I RFP, the fuel hangar was to have its
    own single air-cooled chiller and system. Thus, the RFP
    for Phase II unambiguously provides that there will be no
    need for chilled water piping running to and from the fuel
    hangar. Moreover, since there is no base wide chilled
    water system, terms purporting to extend such a
    non-existing system are obviously the product of a
    scrivener’s mistake—one which was recognized during the
    development of Korte’s pricing—and cannot have any
    force and effect.
    In developing Korte’s pricing for the proposal dated
    July 18, 2019, Korte included pricing for the estimated cost
    to furnish and install the air-cooled chiller referenced in
    section 4.4.4 of the Phase II of the RFP, and to furnish and
    install associated piping for the hangar’s system.
    However, in formulating our price, neither Korte nor its
    mechanical and plumbing subcontractor included any costs
    for furnishing or installing chilled water piping beyond the
    fuel hangar because piping to a non-existent base wide
    chiller system was obviously not needed or required.
    As our mechanical subcontractor points out, RFP
    section 01 10 05.00, paragraph 4.4 describes options for
    13
    the cooling system. The section describes a stand-alone
    cooling system with either a condensing unit or a packaged
    air-cooled chiller. Our mechanical subcontractor utilized
    and relied on that information in developing its pricing.
    Korte, in turn, relied on that pricing from the mechanical
    subcontractor in providing its proposed price to the
    USACE.
    Our mechanical contractor thereafter learned that section
    010 10 05.00, paragraph 4.4.11.6 discusses extending the
    base chilled water to the slab edge of the hangar for future
    connections. Our mechanical subcontractor recognized
    that this must be a mistake. In this regard, a base wide
    chilled water system is not required for the cooling system
    of the Fuels Hangar. The fact that no such base wide
    chilled water system was contemplated as part of the
    present project is reinforced by the fact that the RFP
    provided no information on: (1) any tie in locations for
    any such base chilled water system; (2) where the base
    chilled water would be required in the future; (3) at which
    slab edge the base chilled water pipes should be
    terminated; or (4) the size or capacity of the future base
    chilled water needs.
    (R4, tab 2 at COE R4 2 - 0001-0002)
    39. Korte’s claim challenged only the government’s entitlement to a credit for
    the alleged deductive change. It did not include a challenge to the amount assessed by
    the government ($493,639.43) decreasing the contract price via unilateral Modification
    No. P00004. (Id.)
    Contracting Officer’s Final Decision
    40. By letter dated October 22, 2021, the contracting officer issued a final
    decision denying Korte’s claim that the government’s “unilateral modification
    adopting a credit of $493,639.43 should be rescinded” (R4, tab 1 at COE R4 1 - 0001).
    The contracting officer noted that “Korte’s claim does not request the payment of
    money in a sum certain, but instead appears to be requesting interpretation of contract
    terms or other relief arising under or relating to the Contract.” The final decision
    stated, in part:
    It is the Government’s position that the Solicitation
    required installation of three 12" chilled water lines.
    14
    However, if Korte believed there was an obvious mistake
    or error in the Solicitation and was aware of that at the
    time it prepared its proposal, as it alleges in its claim,
    Korte was responsible for bringing that purported patent
    ambiguity to the Contracting Officer’s attention during the
    Solicitation process.
    (R4, tab 1 at COE R4 1 - 0001, 0007-0008)
    DECISION
    I. Standard of Review
    “Summary judgment is appropriate if there is no genuine issue as to any
    material fact and the moving party is entitled to judgment as a matter of law.” First
    Commerce Corp. v. United States, 
    335 F.3d 1373
    , 1379 (Fed. Cir. 2003); FED. R. CIV.
    P. 56(a). “The moving party bears the burden of establishing the absence of any
    genuine issue of material fact and all significant doubt over factual issues must be
    resolved in the opposing party's favor.” Bubble Room, Inc. v. United States, 
    159 F.3d 553
    , 561 (Fed. Cir. 1998). A party challenging a motion for summary judgment “must
    set forth specific facts showing that there is a genuine issue for trial.” Anderson v.
    Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986) (quoting First Nat’l Bank of Ariz. v.
    Cities Serv. Co., 
    391 U.S. 253
    , 288 (1968)). It does not matter that the parties have
    cross-moved for summary judgment, both claiming that there exists no material issue
    of fact. Osborne Constr. Co., 
    ASBCA No. 55030
    , 
    09-1 BCA ¶ 34,083
     at 168,513
    (“[e]ach cross-motion is evaluated separately on its merits, and all reasonable
    inferences are drawn in favor of the defending party; the Board is not bound to ‘grant
    judgment as a matter of law for one side or the other’” (quoting Mingus Constructors,
    Inc. v. United States, 
    812 F.2d 1387
    , 1391 (Fed. Cir. 1987))).
    II. Burden of Proof
    This appeal involves a deductive change request, which is considered a
    government claim. States Roofing Corp., 
    ASBCA No. 55507
    , 
    09-1 BCA ¶ 34,094
    at 168,571. The government bears the burden of establishing that the work upon
    which it seeks a credit was required by the contract and that it is “entitled to an
    equitable adjustment for a deductive change to reflect the cost savings to the
    contractor.” C.H. Hyperbarics, Inc., 
    ASBCA No. 49375
     et al., 
    04-1 BCA ¶ 32,568
    at 161,150; see Fru-Con Const. Corp., ASBCA Nos. 53544, 53794 
    05-1 BCA ¶ 32,936
     at 163,165 (“The requirement that a contractor claimant must shoulder the
    burden of establishing the fundamental facts of liability, causation and resultant injury
    relating to a claim for which it sees [sic] recovery applies with equal efficacy to claims
    brought by the government”). The government likewise has “the burden of proof as to
    15
    the amount of the credit to which it is entitled for the deductive change.” States
    Roofing, 
    09-1 BCA ¶ 34,094
     at 167,573 (citing Nager Elec. Co. v. United States, 
    194 Ct. Cl. 835
    , 853, 
    442 F.2d 936
    , 946 (1971)).
    III. Contentions of the Parties
    The government seeks a deductive change for certain work deleted from the
    contract. The parties disagree as to whether the deleted work was, in fact, a
    requirement of the contract. According to the government, the plain language of the
    contract, when read as a whole, unambiguously required installation of three chilled
    water lines. The government labels as unreasonable Korte’s interpretation of the
    contract that the water lines were not required. (Gov’t mot. at 23) The government
    argues in the alternative that Korte’s pre-award interpretation of the contract regarding
    the water lines created a patent ambiguity in the contract, giving rise to a duty to
    inquire, which appellant failed to carry out (id.). The government states that it relied
    upon an independent government estimate to determine the amount of the credit and
    that “Korte has not questioned the amount of the credit and does not dispute the
    Government’s estimated value of the cost of removing the requirement to install in the
    three lines” (gov’t mot. at 29). 3
    Korte maintains that the contract did not require installation of the three water
    lines (app. mot. at 1). According to appellant, the government is not entitled to a credit
    for the deductive change because appellant, through its mechanical subcontractor,
    read/understood the contract prior to award as not requiring installation of chilled
    water lines and appellant thereby did not include in its proposal any costs for such
    work (app. resp. at 53-54). Korte states that, because it did not include the cost of
    installing chilled water lines in its proposal, there are no costs to be deducted from the
    contract or reimbursed to the government (id. at 55). Korte also argues that its
    interpretation is reasonable, and that the government’s contrary interpretation is
    unreasonable (app. mot. at 25; app. resp. at 25).
    IV. The Interpretation of Korte’s Mechanical Subcontractor Pre-Award
    Created an Ambiguity Regarding Work the Contractor was Required to
    Perform
    A contract “is ambiguous if it is susceptible of more than one reasonable
    interpretation. It is patently ambiguous if the ambiguity should be apparent to a
    reasonable person in the claimant's position.” Dick Pacific/GHEMM, JV, 
    ASBCA No. 55806
    , 
    07-2 BCA ¶ 33,711
     at 166,903. “If there is a patent ambiguity,
    inconsistency or mistake, the contractor must inquire about it prior to submitting its
    3
    Our review of Korte’s ASBCA filings uncovered no instance wherein Korte disputed
    the government estimate or questioned the government’s credit amount.
    16
    bid or proposal.” 
    Id.
     The origin of this doctrine resides “in the policy of ensuring that
    two negotiating parties (whether private or governmental) do what they are able to do
    to clear up patent ambiguities or defects before formation, thus helping to reduce
    future litigation and allowing expeditious contract formation.” Boeing Co. v. United
    States, 
    968 F.3d 1371
    , 1380 (Fed. Cir. 2020).
    The doctrine of contra proferentem does not apply where the contractor knew of
    the alleged ambiguity before submitting its bid. James A. Mann, Inc. v. United States,
    
    210 Ct. Cl. 104
    , 122, 
    535 F.2d 51
    , 61 (1976) (the degree to which an ambiguity was
    “patently obvious” or “not glaring” is irrelevant where the contractor was aware of the
    ambiguity prior to submitting its bid); Meridian Eng’g Co. v. United States, 
    885 F.3d 1351
    , 1361-62 (Fed. Cir. 2018) (contractor asserting breach of contract claim who
    alleges that documents were ambiguous on their face had a duty to seek clarification of
    any such patent ambiguity before submitting its offer or bid and cannot rely upon that
    discrepancy as a basis for a subsequent claim); Edward L. Kolbar Co., 
    ASBCA No. 15520
    , 
    73-2 BCA ¶ 10,063
     at 47,201 (subcontractor knowledge of ambiguity
    when bidding placed upon it the burden of inquiry).
    There is no legitimate dispute that the RFP Phase 2 documents included
    reference to chilled water piping, i.e., contract drawings with three parallel lines
    running east to west labeled “CW” (SOF ¶¶ 13, 22). Although, as Korte notes, the
    drawings did not include a definition of “CW” (SOF ¶ 11) or include reference to
    chilled water in the drawing containing a “Civil Legend” (SOF ¶ 15), other drawings
    defined similar terms, including “CWR” (Chilled Water Return) and CWS (Chilled
    Water Supply) (SOF ¶ 14). Moreover, it is undisputed the RFP Phase 2 specification
    included a new paragraph 4.5.6, which required the contractor to “[e]xtend the base
    wide chilled water, hot water, and compressed air piping to the slab edge of the
    hangar. Provide connection location for future projects.” (SOF ¶ 10) In addition to
    raising issues regarding which side of the slab edge the pipes were to be extended and,
    later, how wide the pipes were required to be (SOF ¶¶ 10, 32), appellant argues now
    that “[t]here was simply no good reason to extend chilled water piping from the slab
    edge of the hangar per the above-quoted SOW . . . when there was no apparent need
    for chilled water piping in the first place” and “it was absurd to read the SOW
    statement as extending something that was non-existent” (emphasis in original)
    (app. mot. at 27). Korte’s chosen course of action - to simply ignore the import of the
    actual language that Korte viewed as “absurd” - in no way justifies Korte’s decision to
    make no inquiry regarding the meaning of the new specification paragraph 4.5.6, or
    the government’s reference in that specification to “future projects.”
    The record establishes that Korte’s subcontractor recognized pre-award an
    ambiguity in the solicitation documents regarding installation of chilled water lines,
    although rather than seeing a relatively limited set of ambiguities, chose (and, let there
    be no mistake, it was a choice) to interpret the contract to its benefit (SOF ¶¶ 6, 32-34,
    17
    38; app. resp. at 9; app. reply at 21). Specifically, Korte states that “[d]uring the
    Project solicitation stage, Jarrell Mechanical’s project team interpreted the solicitation
    documents including the concept drawings as not calling for any chilled water
    improvements” (SOF ¶ 6). Korte also asserts that “[t]he determination of the scope of
    mechanical improvements belonged to the party responsible for mechanical
    engineering, namely Jarrell Mechanical,” and that “Jarrell Mechanical reviewed the
    solicitation documents and concluded that chilled water improvements were not
    required” (app. reply at 9-10) (citing app. resp. at 53-54).
    Appellant’s August 24, 2021, claim likewise admits knowledge of the
    ambiguity discovered during development of Korte’s pricing, stating, “since there is
    no base wide chilled water system, terms purporting to extend such a non-existing
    system are obviously the product of a scrivener’s mistake—one which was recognized
    during the development of Korte’s pricing—and cannot have any force and effect”
    (SOF ¶ 38). However, appellant’s suggestion that the solicitation’s reference to a
    base-wide chilled water system was simply a “scriveners mistake” ignores the fact that
    the referenced specification clause – which Korte labels as “purporting to extend such
    a non-existing system” – was not a remanent of the RFP Phase 1, as Korte suggests,
    but was added to the solicitation with the issuance of RFP Phase 2, as new
    specification paragraph 4.5.6 (later paragraph 4.4.11.6) (SOF ¶ 10), along with
    changes to paragraph 4.4.4, “Air cooled chiller” (SOF ¶ 9). 4
    During his deposition, Mr. Jarrell stated that paragraph 4.4.11.6 was “a leftover
    from the Phase One RFP before they changed it from base wide system to independent
    systems” (SOF ¶ 33). Inasmuch as paragraph 4.5.6 (later paragraph 4.4.11.6) was not
    included in RFP Phase 1 and was added with RFP Phase 2 (SOF ¶ 10), it is not
    properly characterized as a “leftover,” having been added to the solicitation
    requirements with issuance of RFP Phase 2 (SOF ¶ 9). Moreover, appellant’s attempt
    to justify ignoring this provision by labeling it as a scrivener’s error violates the well-
    established rule that “[w]hen interpreting the contract, the document must be
    considered as a whole and interpreted so as to harmonize and give reasonable meaning
    to all of its parts.” NVT Techs., Inc., v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir.
    2004) (citation omitted).
    4
    RFP Phase 2 deleted the following statement (as it appeared in RFP Phase 1) “Air
    cooled chiller: The Tinker Air Force Base existing chilled water loop will be
    utilized to provide cooling to the facility” (see SOF ¶ 4) and replaced it with
    “Air cooled chiller: A single air-cooled chiller may be provided” (SOF ¶ 9).
    New paragraph 4.5.6 stated that that the contractor should “[e]xtend the base
    wide chilled water, hot water, and compressed air piping to the slab edge of the
    hangar,” and “[p]rovide connection location for future projects” (SOF ¶ 10).
    18
    During his deposition, Mr. Jarrell also testified about internal discussions that
    took place “before the contract was awarded” (SOF ¶ 33). Mr. Jarrell stated that
    specification paragraph 4.4.11.6 was “poorly worded and unbiddable” (id.).
    Specifically, Mr. Jarrell stated that the provision is “poorly written . . . since there’s no
    base wide chilled water or no base wide hot water, and we knew that at the time. We
    have no idea how to size the piping, even if it did exist, because we don’t know the
    size of the future projects. And we don't know which slab edge to go to, because
    there's four slab edges. So I would define that as unbiddable and very poorly worded.”
    (Id.) Mr. Jarrell’s conclusion that the solicitation provision was “unbiddable” was
    reason enough for appellant to seek clarification from the government. See Santa Fe
    Eng’rs, Inc., 
    ASBCA No. 23523
    , 
    92-1 BCA ¶ 24,420
     at 121,901 (appellant who
    considered reference in contract drawing to be “‘un-biddable’ at bid time and did not
    bid anything for [the work]” had an affirmative obligation to raise the issue with the
    government prior to submitting its bid); Newsom v. United States, 
    230 Ct. Cl. 301
    ,
    304, 
    676 F.2d 647
    , 650 (1982) (“The existence of a patent ambiguity in itself raises the
    duty of inquiry, regardless of the reasonableness vel non of the contractor's
    interpretation. . . . The court may not consider the reasonableness of the contractor's
    interpretation, if at all, until it has determined that a patent ambiguity did not exist”).
    “A subcontractor's interpretation will be imputed to a contractor if the
    contractor proves that the subcontractor relied upon the interpretation in its bid to the
    contractor, and that the contractor incorporated the subcontractor's bid or the
    subcontractor's price was comparable to that of others and the contractor's bid reflected
    those estimates.” M.A. Mortenson Co., 
    ASBCA No. 53146
     et al., 
    05-1 BCA ¶ 32,846
    at 162,771; Caddell Constr. Co., Inc., 
    ASBCA No. 35368
    , 
    90-1 BCA ¶ 22,263
    at 111,846 (pre-award knowledge and understanding of subcontractor who provided
    input for certain contract work imputed to appellant where record contained no
    evidence indicating appellant’s pre-award understanding regarding that work); S/G
    Constr., Inc., 
    ASBCA No. 38477
    , 
    89-3 BCA ¶ 22,234
     at 111,781 (pre-award
    knowledge and understanding of subcontractor who provided bid input for a portion of
    work imputed to appellant). Korte’s readily admits that its cost estimate relied upon
    Jarrell Mechanical’s determination of the required work as set forth in the solicitation
    (SOF ¶ 38; app. resp. at 54) and “that both Korte and Jarrell Mechanical construed the
    drawings and the specifications during the solicitation period as not calling for any
    chilled water improvements” (app. reply at 21). 5
    5
    The government argues that appellant “has not demonstrated that it relied on Jarrell’s
    interpretation before award rather than during performance,” and that “Korte is
    inconsistent on when it interpreted whether the chilled water lines were a
    contract requirement” (gov’t reply at 20). However, for the purpose of deciding
    the parties’ motions for summary judgment, we consider appellant’s statements
    to be judicial admissions regarding the issue of Korte’s knowledge of the
    ambiguity created by Jarrell’s interpretation of the solicitation. See Raytheon
    19
    Korte cites WPC Enters., Inc. v. United States, 
    163 Ct. Cl. 1
    , 5-6, 
    323 F.2d 874
    ,
    876-77 (1963), for the proposition that “any claimed ambiguity or claimed discrepancy
    about whether Korte’s scope of work encompassed three chilled water lines and a pipe
    vault cannot be viewed objectively as an obvious error in drafting, a gross discrepancy,
    or an inadvertent but glaring gap” (app. mot. at 33). WPC addresses the situation
    where both the government and the contractor proffer reasonable interpretations of a
    contract and, in the absence of an obvious error or glaring error, the contract is
    interpreted against the government as drafter. That is not the situation here, as Korte’s
    own interpretation of the contract recognized the patent ambiguity. Indeed, appellant’s
    argument in its motion for summary judgment that the ambiguity “cannot be viewed
    objectively as an obvious error in drafting,” contradicts the statement in Korte’s claim
    that the “terms purporting to extend such a non-existing system are obviously the
    product of a scrivener’s mistake—one which was recognized during the development
    of Korte’s pricing” (SOF ¶ 38).
    In its responsive brief, appellant admits that this appeal “represents one of those
    atypical, if not rare, instances where the scrivener included words that, considering the
    circumstances, are impossible of performance and cannot be given any sensible
    meaning in the context of this project,” labeling the reference to “chilled water” in
    paragraph 4.5.6 as “plainly superfluous” (app. resp. at 42). Viewed objectively,
    appellant was not, therefore, free to simply ignore the specification provision it
    considered superfluous. Santa Fe Eng’rs, Inc., ASBCA Nos. 22090, 22194, 
    79-1 BCA ¶ 13,647
     at 66,967 (“A basic tenet of contract interpretation is that every effort
    must be made to give meaning to each provision and not to accept an interpretation
    which will render any part of the contract meaningless, inexplicable or render it
    useless or superfluous. These factors should have caused appellant to question the
    reasonableness of its interpretation and to have sought clarification from the
    contracting officer”).
    In an attempt to downplay the import of the reference to “CW” on certain
    contract drawings (SOF ¶¶ 12, 22), Korte states that the letters “CW” “are smaller than
    the other lettering on the plan sheet and are not readily discernable when viewing the
    pdf of that plan sheet on the computer in the normal ‘100%’ size text mode” (app. mot.
    at 5; see also app. mot. at 25 (“CW” lettering is “difficult to read in normal computer
    mode”)). Even assuming that the reference to “CW” appears smaller than other
    markings and thereby more difficult to read, this does not excuse appellant from
    Co., 
    ASBCA No. 57743
     et al., 
    16-1 BCA ¶ 36,335
     at 177,147 (distinguishing
    between judicial admissions and evidentiary admissions). Put another way,
    Korte’s assertions regarding its reliance upon Jarell’s interpretation were
    contrary to its own interests and we will consider them here in ruling against
    Korte.
    20
    attempting to understand its import, nor does it somehow cast the information as less
    important or less relevant than other, larger markings or information set forth on the
    drawings. See Natkin and Co., ASBCA Nos. 26072, 29071 
    84-2 BCA ¶ 17,469
    at 87,044 (where contract drawings are “difficult to read” it is incumbent upon the
    contractor to resolve “the matter by inquiry prior to submitting its proposal”).
    In Ghemm-Manson-Osberg, 
    ASBCA No. 16217
    , 
    71-2 BCA ¶ 9,136
     at 42,364,
    we held that, even assuming the contract was ambiguous and that both parties’
    interpretations were reasonable, the contractor could not prevail because the record
    established that the contractor’s subcontractor recognized an ambiguity. We stated,
    “[t]he ambiguity, if we were to consider the contract terms ambiguous, was not the
    result of a subtle lack of clarity in specifying the desired performance but was patent
    and glaring to appellant's subcontractor and was or should have been obvious to
    appellant itself.” The same is true here. We find there is no genuine issue of material
    fact regarding appellant’s and its subcontractor’s interpretation of the solicitation as
    containing an ambiguity, of which appellant and its subcontractor admittedly were
    aware prior to award, and that appellant has not presented sufficient evidence upon
    which a reasonable factfinder could find that appellant’s or its subcontractor’s
    interpretation of the solicitation did not create an ambiguity.
    V. Korte and its Subcontractor Failed to Inquire from the Government About
    the Ambiguity Pre-Award
    A patent ambiguity “triggers a duty to inquire.” NVT Techs., 370 F.3d at 1162.
    Although the duty to seek clarification of patent ambiguities or defects does not
    require the contractor to “ferret out hidden or subtle errors in the specifications,” White
    v. Edsall Constr. Co., 
    296 F.3d 1081
    , 1085 (Fed. Cir. 2002), the ambiguity here
    required no ferreting out of hidden or subtle specification errors. As we discuss below,
    uncontroverted record evidence establishes that, at bottom, Korte, through its
    mechanical subcontractor Jarrell, was aware of the ambiguity or defect in the contract
    documents and chose to interpret it without consultation from the government. See
    Dynamic Sys. Tech., Inc., 
    ASBCA No. 63037
    , 
    23-1 BCA ¶ 38,274
     at 185,863
    (contractor assumed the risk “[b]y submitting a proposal based upon information it
    considered to be erroneous, and by failing to take avenues available to it to challenge
    the solicitation language prior to submitting its proposal”).
    A. Neither Appellant Nor its Subcontractor Made an Inquiry to the
    Government
    Where a contractor has knowledge of an ambiguity in the contract, it “imposes
    upon it a duty to inquire of the government,” which “tends to deter a bidder, who
    knows (or should know) of a serious problem in interpretation, from consciously
    taking the award with a lower bid (based on the less costly reading) with the
    21
    expectation that he will then be able to cry ‘change’ or ‘extra’ if the procuring officials
    take the other view after the contract is made.” Lebolo-Watts Constructors 01 JV,
    LLC, 
    ASBCA No. 59740
     et. al., 
    21-1 BCA ¶ 37,789
     at 183,433 (emphasis added)
    (quoting S.O.G. of Ark. v. United States, 
    212 Ct. Cl. 125
    , 131, 
    546 F.2d 367
    , 371
    (1976). That the inquiry must be made to the government makes sense, as the
    requirement “that a contractor, before bidding, should attempt to have the Government
    resolve a patent ambiguity in the contract's terms is a major device of preventive
    hygiene; it is designed to avoid just such post-award disputes as this by encouraging
    contractors to seek clarification before anyone is legally bound.” S.O.G. of Ark., 
    212 Ct. Cl. at 131
    , 
    546 F.2d at 370-71
    .
    Korte offers no evidence that it made any inquiry regarding the import of
    specification paragraph 4.5.6 (later paragraph 4.4.11.6) (SOF ¶ 10). It alleges instead
    that Mr. Jarrell “made the inquiry” (app. resp. at 43). According to Korte, Mr. Jarrell
    conducted an “investigation of pre-existing utility lines at Tinker AFB,” and
    “confirmed via available base documents that no base-wide or campus chilled water
    system or hot water existed . . . .” (id.). Mr. Jarrell’s “investigation” examining
    “available base documents” does not equate to making an inquiry of the government
    about the contract requirements given Mr. Jarrell’s interpretation of specification 4.5.6.
    Regarding Mr. Jarrell’s actions upon reading paragraph 4.5.6, Mr. Jarrell stated:
    We discussed it verbally with Korte. We did research
    locally on the base to see -- well, first, we researched the
    floor plan of the base to see where the base wide chilled
    water and hot water system were. Determined they didn't
    exist. Determined the compressed air system did exist.
    Included the compressed air system to get to the new
    hanger and talked verbally with Korte and included the
    condensed units and the hot water boilers as you pointed
    out in our proposal earlier.
    (SOF ¶ 34) Mr. Jarrell’s conversations with Korte likewise do not equate to making an
    inquiry from the government. On the issue of whether Mr. Jarrell took any steps to
    inquire from the government about what he termed an “unbiddable and very poorly
    worded” solicitation provision (SOF ¶ 34), Mr. Jarrell stated “[q]uestions were asked
    and not answered clearly. I have no idea who asked them. I don't know if Korte did
    that after our discussion or if somebody else asked them.” (Id.) Mr. Jarrell’s
    statements on this issue are not evidence upon which a reasonable factfinder could find
    that appellant or its subcontractor raised the issue with the government, and appellant
    offers no other evidence to support a finding that it raised the issue with the
    government.
    22
    Appellant’s failure to inquire is compounded by the solicitation’s inclusion of
    FAR 52.236-21, which, in case of discrepancies in the drawings or specifications,
    requires the contractor to promptly notify the contracting officer in writing and that
    “[a]ny adjustment by the Contractor without such a determination shall be at its own
    risk and expense” (SOF ¶ 16).6 Likewise, paragraph 3.8 of the specifications warned
    Korte that should it “have any questions related to specific terms and conditions, these
    must be resolved prior to submission of the offer,” and that any deviations or
    exceptions included in an offer shall be listed and described in detail in the deviations
    in TAB A (SOF ¶ 3). Both of Korte’s Phase 2 technical proposals (original and
    revised) stated in TAB A that “[t]he Korte Company is not proposing any deviations,
    exceptions or assumptions to the terms or conditions of the Solicitation for the KC-
    46A Fuel Maintenance Hangar at Tinker Air Force Base” (SOF ¶ 22).
    Korte argues that paragraph 4.4.11.6 suggests the existence of what it terms a
    “patent discrepancy,” stating “Jarrell Mechanical decided to investigate, after reading
    the ‘extend’ clause, to confirm there was no base wide chilled water” (app. reply at 22
    (citing app. resp. at 8 n.31)). Appellant alleges “[a]s to that patent discrepancy (i.e., an
    impossibility), the duty to investigate was met,” and “[a]s for the three ‘no keynote’
    lines on Drawing CU101, Jarrell Mechanical properly interpreted them as not calling
    for any improvements because the keynote/keynote designation protocol was followed
    as to those three lines” (id.). 7 Appellant then concludes, stating “[t]hose three “no
    keynote” lines did not constitute a patent ambiguity” (id.). We disagree. Whether
    termed a “patent discrepancy” or a “patent ambiguity,” Korte offers no evidence that it
    made any inquiry from the government about its subcontractor’s interpretation of the
    solicitation. Mr. Jarrell’s “investigation” likewise does not constitute making such an
    inquiry. We find that Korte has not presented sufficient evidence upon which a
    reasonable factfinder could find that appellant (or its subcontractor) properly inquired
    from the government about the ambiguity in the solicitation identified by its
    subcontractor prior to contract award.
    6
    We note also that the order of precedence clause here provides that in the event there
    is a difference between the drawings and the specifications, the specifications
    shall govern (SOF ¶ 16). Here, the provision requiring the contractor to
    “[e]xtend the base wide chilled water, hot water, and compressed air piping to
    the slab edge of the hangar,” and “[p]rovide connection location for future
    projects” is set forth in the RFP Phase 2 specifications (SOF ¶ 10).
    Accordingly, any argument that appellant could ignore the import of that
    specification provision in the context of determining the contract requirements
    is misplaced.
    7
    In its December 8, 2020, letter, Jarrell Mechanical likewise suggests that “[s]ince the
    lines [labeled ‘CW’] were not properly identified or sized on the RFP drawings,
    the Korte team did not include them in the project bid (SOF ¶ 32).
    23
    B. Submissions by Other Offerors Through the ProjNet System Do Not Satisfy
    Appellant’s Duty to Inquire
    Korte also suggests that its duty to inquire was satisfied by other offerors who
    submitted Requests for Information (RFI) through the ProjNet system (app. resp.
    at 51-52). One such RFI noted the solicitation requirement that the contractor
    “[e]xtend the base wide chilled water, hot water, and compressed air piping to the slab
    edge of the hangar,” and inquired “[a]re we required to extend CHW [chilled water]
    and HW [hot water] to the hangar if we are not utilizing either service for this
    facility?” (SOF ¶ 21) To which the government responded “[e]xtend the base wide
    systems per the RFP” (id.). Appellant labels the government’s response “unhelpful,”
    stating that it “clarifies nothing and reflects an unwillingness to provide to the offerors
    a better understanding of what USACE desired in terms of the systems referenced in
    the SOW” (app. resp. at 52).
    Appellant’s argument that the government’s response was “unhelpful” and
    “clarifies nothing” is of no moment. It is beyond cavil that “when an offeror attempts,
    but the government's response fails, to resolve an ambiguous solicitation provision, the
    offeror has the duty to continue to seek to resolve that ambiguity.” Phoenix Mgmt.,
    Inc., 
    ASBCA No. 57234
    , 
    11-1 BCA ¶ 34,734
     at 171,005 (citing Community Heating &
    Plumbing Co. v. Kelso, 
    987 F.2d 1575
    , 1580 (Fed. Cir. 1993) (it is not enough under
    the duty to inquire that a contractor merely make an initial inquiry); Beacon Constr.
    Co. of Mass. v. United States, 
    161 Ct. Cl. 1
    , 6-7, 
    314 F.2d 501
    , 504 (1963) (offeror has
    a duty to “call attention to an obvious omission in specification, and make certain that
    the omission was deliberate”); General Dynamics - National Steel and Shipbuilding
    Co., 
    ASBCA No. 61524
    , 
    22-1 BCA ¶ 38,067
     at 184,824 (“if the government's
    response to that initial inquiry fails to address and resolve the ambiguity, the contractor
    is obligated to request further clarification”). The reason for this requirement to seek
    further clarification of such ambiguities is “to prevent contractors from taking
    advantage of the government, protect other bidders by assuring that all bidders bid on
    the same specifications, and materially aid the administration of government contracts
    by requiring that ambiguities be raised before the contract is bid, thus avoiding costly
    litigation after the fact.” Community Heating, 
    987 F.2d at 1580
    .
    Korte cites two additional RFIs that touch on the issue of heating and cooling
    systems (app. resp. at 51-52) (SOF ¶¶ 18-19). However, we find that these RFIs do
    not address specifically the expressed understanding of appellant’s subcontractor
    regarding the existence a base-wide chilled water system or the requirement to install
    or extend chilled water lines (nor does appellant claim to be one of the offerors who
    submitted any of the RFIs). Indeed, these RFIs cited by appellant assume the
    existence of an existing or base wide chilled water system (SOF ¶¶ 18-19; see also
    SOF ¶ 21).
    24
    Korte argues that “any further inquiry on that topic would have been futile”
    (app. resp. at 53) (although appellant offers no evidence that it made any such inquiry,
    relying instead on RFIs submitted by other offerors). As support for its argument,
    Korte cites the Court of Federal Claims’ decision in Allied Tech. Grp., Inc., v. United
    States, 
    39 Fed. Cl. 125
     (1997). 8 In that case, the plaintiff and one other contractor
    submitted questions to the government that directly addressed the ambiguity presented
    in the solicitation and the government responded both times that “[t]he solicitation is
    clear on its face.” 
    Id. at 141
    . The court held that the government could not rely upon
    the doctrine of patent ambiguity, stating “[o]nce ambiguities have been identified, in
    this case by the plaintiff, and clarification has been genuinely sought, the
    inconsistencies must be interpreted against the . . . drafter. 
    Id. at 142
    . That simply is
    not the situation presented in this appeal. Aside from the non-binding nature of that
    decision on this Board, appellant has presented no evidence that there was any inquiry
    of the government regarding appellant’s subcontractor’s specific interpretation of the
    solicitation requirements prior to contract award. Moreover, as discussed above,
    decisions of this tribunal make clear that an offeror has the obligation to continue to
    pursue issues such as this where the government’s response fails to address the issue
    presented.
    We note that one additional RFI cited by appellant in its opening brief inquired
    about “relocation of the campus chilled and hot water pipes,” stating that “[t]he civil
    plans do not show any existing campus chilled or hot water,” and asking “[c]an
    drawings of the existing pipes be provided?” (SOF ¶ 17). To which the government
    responded, “[t]he CHWS and CHWR lines shown are per the FY 15 Support
    Infrastructure project and show the lines routed north in order to avoid the Fuel Hangar
    footprint,” and instructed that “[t]he awarded-Contractor must confirm this is the case
    prior to design and construction” (id.). Appellant fails to discuss the import of this
    RFI, or whether its subcontractor even considered the government’s response
    regarding the CHWS or CHWR lines as depicted on the FY 15 Support Infrastructure
    project. 9
    8
    We note that decisions of the Court of Federal Claims, are “neither binding upon this
    tribunal, nor are they even binding in other matters pending before the Court of
    Federal Claims.” Northrop Grumman Corp., 
    ASBCA No. 62165
    , 
    21-1 BCA ¶ 37,922
     at 184,180 n.8) (citing C.R. Pittman Constr. Co., Inc., 
    ASBCA No. 57387
     et al., 
    15-1 BCA ¶ 35,881
     at 175,427 n.6 (Court of Federal Claims
    decisions are not binding precedent for the ASBCA); Zaccari v. United States,
    
    142 Fed. Cl. 456
    , 462 n.6 (2019) (“Decisions of the United States Court of
    Federal Claims do not bind the court in this matter but may provide persuasive
    authority”).
    9
    Although Korte included this RFI question and response in the “Facts” portion of its
    opening brief (app. mot. at 10-11) and made passing reference to the RFI in its
    25
    Korte cites Caraco Constr. Co., ASBCA Nos. 28431, 32408, 
    86-3 BCA ¶ 19,245
     at 97,326, for the proposition that “when the particular subject in the RFP is
    ambiguous, and that matter is brought to the government’s attention, the curt reply to
    simply follow what the RFP requires is ‘unhelpful’” (app. mot. at 34). In that appeal,
    however, the Board found that appellant’s president questioned the government about
    the specific ambiguity that was the basis of its claim and the government promised to
    arrange a meeting between appellant and the Chief of Engineering and Environmental
    Planning to discuss appellant’s concern. However, that appointment never took place
    and ultimately appellant was told to bid the item at issue as set forth in the drawings
    and specifications. 
    Id. at 97,324
    . The Board noted also that both the government
    engineer who developed the specifications and drawings, and the former Chief of
    Engineering and Environmental Planning who signed the contract drawing at issue,
    agreed with the interpretation proffered by appellant. 
    Id. at 97,326
    . Here, Korte offers
    no evidence that it specifically inquired from the government about its subcontractor’s
    interpretation of the solicitation, or its conclusions as to what work was required (or
    that a meeting to discuss the issue with government representatives was promised but
    never arranged). 10 What is certain, however, is that the RFIs cited by appellant neither
    addressed nor responded to the specific interpretation of the solicitation proffered by
    appellant’s subcontractor. We find that appellant has not presented sufficient evidence
    upon which a reasonable factfinder could find that RFIs submitted by other offerors
    addressed the specific ambiguity identified by appellant’s subcontractor or otherwise
    satisfied appellant’s duty to inquire.
    VI. Whether Appellant Included in its Pricing the Cost of Installing Chilled
    Water Lines is not Controlling to the Outcome of this Appeal
    There is some facial appeal to appellant’s argument that the government is not
    entitled to a credit for deletion of work regarding the chilled water lines requirement
    because, according to appellant, its price did not include the cost of installing those
    lines. See Norcoast-Beck Aleutian, A Joint Venture, 
    ASBCA No. 25469
    , 
    81-1 BCA ¶ 15,072
     at 74,550 (“the salient criterion of liability for a deductive change is whether
    the change causes a ‘decrease in the Contractor's cost of . . . performance of any part of
    the work,’ and the fact that the Government incurs no expense or damages because of
    the change is irrelevant to the issue”). However, this Board long ago expressly
    reply brief (app. reply at 13), Korte offered no specific discussion or analysis of
    the RFI itself.
    10
    Regarding the March 15, 2019, RFI discussed above (SOF ¶ 21), Korte’s May 19,
    2021, letter to the government states that appellant “was not able to send a
    follow up question due to the USACE response was past the Proj[N]et Question
    period” (SOF ¶ 37). However, this does not excuse appellant’s failure to timely
    raise the issue in the first instance.
    26
    rejected such an argument that “since appellant did not include the costs for the
    disputed items in its bid, the Government has already received the savings from the
    use of the less costly course of performance; therefore to permit a downward
    adjustment would penalize appellant for being competitive and reward the
    Government with a windfall.” G & C Enters., Inc., 
    ASBCA No. 36618
    , 
    89-2 BCA ¶ 21,609
     at 108,785-86. In Bruce Anderson Co., Inc., ASBCA No., 
    ASBCA No. 29412
    , 32247, 
    89-2 BCA ¶ 21,872
     at 110,037-38, citing G & C Enters., we
    expanded upon the reasoning for such a holding, stating “[w]e are not unmindful of the
    equity considerations which seem to flow from situations such as this. If one simply is
    swayed by the plea that nothing was included in the bid to cover the work so that it is
    inequitable to demand a return of money, one loses sight of several cogent factors.”
    
    Id. at 110,037
    . One such factor is protection of “[t]he competitive bidding system,”
    for which we noted, “[a]ny bidder who omits, for any reason, costs that would
    otherwise be included, gets the benefit of a bid lower than it otherwise would be, but
    runs the risk of a later change in contract price. Such a bidder's trade-off for the risks
    involved is the greater likelihood of contract award.” 
    Id. at 110,038
     (quoting Hof
    Constr., Inc., GSBCA No. 7027, 
    84-3 BCA ¶ 17,571
     at 78,563 (dissenting opinion)).
    Our holding is consistent with the Court of Appeals for the Federal Circuit
    decision in Triax Pacific, Inc. v. West, 
    130 F.3d 1469
    , 1475 (Fed. Cir. 1997), which
    recognized that the purpose of the court-made rule of patent ambiguity, “is designed to
    ensure, to the greatest extent possible, that all parties bidding on a contract share a
    common understanding of the scope of the project.” As noted by the Federal Circuit,
    this “objective is particularly important in government contracts, in which significant
    post-award modifications are limited by the government's obligation to use
    competitive bidding procedures and by the risk of prejudice to other potential
    contractors.” 
    Id.
    27
    CONCLUSION
    Given our findings herein, we need not address the remaining arguments
    offered by the parties regarding the plain language of the contract or the
    reasonableness of the parties’ respective interpretations of the contract requirements.
    The government’s motion for summary judgment is granted, and appellant’s motion
    for summary judgment is denied. The appeal is denied.
    Dated: October 26, 2023
    DAVID B. STINSON
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                            I concur
    RICHARD SHACKLEFORD                                 J. REID PROUTY
    Administrative Judge                                Administrative Judge
    Acting Chairman                                     Vice Chairman
    Armed Services Board                                Armed Services Board
    of Contract Appeals                                 of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 63148
    , Appeal of Korte
    Construction Company, rendered in conformance with the Board’s Charter.
    Dated: October 27, 2023
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    28
    

Document Info

Docket Number: 63148

Filed Date: 10/26/2023

Precedential Status: Precedential

Modified Date: 11/18/2023