RLB Contracting, Inc. ( 2023 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                   )
    )
    RLB Contracting, Inc.                         )    
    ASBCA No. 62779
    )
    Under Contract No. W9126G-17-C-0043           )
    APPEARANCES FOR THE APPELLANT:                     Michael H. Payne, Esq.
    Casey J. McKinnon, Esq.
    Cohen Seglias Pallas Greenhall
    & Furman, P.C.
    Philadelphia, PA
    APPEARANCES FOR THE GOVERNMENT:                    Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Clark Bartee, Esq.
    Engineer Trial Attorney
    U.S. Army Corps of Engineers District,
    Galveston
    OPINION BY ADMINISTRATIVE JUDGE SWEET
    This appeal involves dredging work that appellant RLB Contracting, Inc. (RLB)
    performed for the United States Army Corps of Engineers (Corps or USACE) in the
    Gulf Intracostal Waterway (GIWW), Texas Main Channel, San Antonio Bay, Texas.
    While performing that work, RLB struck the Tomcat West Pipeline (Pipeline)—a
    submerged natural gas pipeline—causing an explosion that damaged the dredger, and
    allegedly delayed completion of the contract. The Corps imposed liquidated damages.
    RLB submitted a claim to the contracting officer (CO) seeking a time extension and
    remission of the liquidated damages due to the purported excusable delays of defective
    specifications, differing site conditions, and a breach of the duty of good faith and fair
    dealing. After the CO denied that claim, RLB filed this appeal. The Corps moves for
    summary judgment on all of RLB’s causes of action. We grant that motion and
    dismiss this appeal for the reasons discussed below.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    I. The Pipeline
    1. The Pipeline was a natural gas pipeline owned by Genesis Energy (Genesis)
    that crossed the GIWW (R4, tabs 1 at 39, 10 at 277, 282-83).
    2. In a November 2016 email chain (Email Chain), Corps personnel expressed
    concerns that the Pipeline and another pipeline were not adequately buried to -24 feet
    MLWW, 1 and thus at risk of an accidental strike (app. resp. ex. 1 at 814-16).
    3. As a result, on November 23, 2016, the Corps forwarded its concerns to
    Morris P. Herbert, Inc. (Herbert)—an engineering firm (app. resp. ex. 1 at 812-13;
    SAGIMF ¶ 31; RSAGIMF ¶ 31). 2 Herbert forwarded the Corps’ concerns to Genesis
    on November 23, 2016, with an email stating that the Corps was directing Genesis to
    lower the pipelines as soon as possible (id. at 812).
    4. On November 29, 2016, Herbert wrote to the Corps that “[t]he pipeline will
    be lowered to minimum 24 feet MLLW as directed by USACE.” (app. resp. ex. 1
    at 809).
    5. On March 23, 2017, Herbert sent the Corps an as-built drawing (Genesis As-
    Built Drawing) and stated that “[a]s shown on the drawing, the pipeline was lowered
    as directed by USACE Operations” (app. resp. ex. 6 at 917). The Genesis As-Built
    1
    “MLLW” stands for Mean Lower Low Water and means the “average of the lower
    low water height of each tidal day observed over the National Tidal Datum
    Epoch.” See
    https://tidesandcurrents.noaa.gov/datum_options.html#:~:text=MLLW*,the%
    20National%20Tidal%20Datum%20Epoch.
    2
    “SUMF” refers to the Corps’ statement of undisputed material fact. “RSUMF” refers
    to RLB’s response to the SUMF. “SAGIMF” refers to RLB’s statement of
    additional genuine issues of material fact. “RSAGIMF” refers to the Corps’
    response to the SAGIMF.
    2
    Drawing indicated as follows:
    (gov’t reply ex. 2 at 919). As the Genesis As-Built Drawing’s bottom drawing shows,
    the Pipeline was adequately buried to at least -24 feet MLWW for all of the 325-foot
    distance between the setbacks (id.). 3 That 325-foot distance was wider than the 300-
    foot dredging area in this appeal (R4, tab 1 at 38-39).
    II. The 0043 Contract
    6. On April 7, 2017, the Corps issued Solicitation W9126G-17-B-0011, which
    resulted in the award of Contract No. W9126G-17-C-0043 (0043 Contract) to RLB on
    3
    RLB’s suggestion that the Genesis As-Built Drawing showed that Genesis only
    lowered the Pipeline across the 125-foot channel is incorrect (app. resp. at 7).
    The Genesis As-Built Drawing bottom drawing showed that Genesis lowered
    the Pipeline to at least -24 feet MLWW not just across the channel, but also
    between the “set back” lines (gov’t reply ex. 2 at 919). Those “set back” lines
    are 325 feet apart based upon: (1) the horizontal graphic scale; and (2) the fact
    that those two “set back” lines were just to the right of STA 671 +22 and STA
    674 + 53, respectively, which corresponded to the ends of the set backs that
    were 325 feet apart on the top drawing (125-foot channel, plus 100-foot slopes
    on setbacks on both sides) (id.).
    3
    June 2, 2017 (R4, tab 1 at 6-7). The 0043 Contract was for the dredging of the GIWW
    (id. at 12, 38).
    7. The 0043 Contract specification 1.8 assigned the task of locating pipelines
    and utilities crossings the dredging area to RLB, stating that:
    It is the Contractor’s responsibility to investigate the
    location of utility crossings. The Contractor shall take
    precautions against damages which can result from
    dredging operations in the vicinity of the utility crossings.
    If damage occurs as a result of dredging operations, the
    Contractor will be required to suspend dredging until the
    damage is repaired and approved. Costs of these repairs
    and downtime of the dredge and attendant plant shall be at
    the Contractor’s expense.
    (R4, tab 1 at 48). Similarly, the 0043 Contract incorporated by reference Federal
    Acquisition Regulation (FAR) 52.236-9 (PROTECTION OF EXISTING
    VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
    IMPROVEMENTS) (April 1984) (id. at 64), which stated, inter alia, that “[t]he
    Contractor shall protect from damage all existing improvements and utilities . . . at or
    near the work site . . . the locations of which are made known to or should be known
    by the Contractor.” 
    48 C.F.R. § 52.236-9
    (b).
    8. The 0043 Contract specification 1.8.1 stated that:
    There are pipelines and or utilities which are within the
    work limits. The following pipeline/utilities cross the
    area(s) to be dredged:
    Approximate     Permit    Description              Owner
    Station         No.
    1101+763        16247     One 2 and 7/8-inch       General Atlantic
    pipeline                 Resources, Inc.
    One 4 and 1/2-inch
    pipeline
    1102+281        7461/     One 12-inch pipeline     Houston Pipe Line Co.
    3371
    1108+419        16715     One 24-inch Pipeline     Northern Natural Gas Co.
    EVERY EFFORT HAS BEEN MADE TO GIVE ALL
    PERTINENT DETAILS ON THE LOCATION OF
    PIPELINES/UTILITIES. THE DATA FURNISHED
    4
    ON THE PLANS ARE BELIEVED TO BE
    SUBSTANTIALLY CORRECT. HOWEVER, THE
    EXACT LOCATIONS MAY VARY FROM THAT
    SHOWN: THEREFORE THE CONTRACTOR
    SHALL COOPERATE WITH THE RESPECTIVE
    OWNERS TO ESTABLISH THE ACTUAL
    POSITION OF THE PIPELINES/UTILITIES. THE
    U.S. ARMY CORPS OF ENGINEERS PERMITS OF
    THE RESPECTIVE PIPELINES AND PREVIOUS
    SURVEYS ARE AVAILABLE UPON REQUEST
    FROM THE CORPUS CHRISTI RESIDENT
    OFFICE.
    THE FOLLOWING IS FURNISHED FOR
    INFORMAITON ON VERIFYING PIPELINE
    OWNERSHIP:
    Lonestar Notification Center
    1-713-223-4567 or 1-800-669-
    8344 Texas 811
     (Dig-Tess)
    1/800-344-8377
    (R4, tab 1 at 48-49 (emphasis in original)). Similarly, the 0043 Contract required RLB
    to “[v]erify with the utility owner the size, depth, coordinates, and transported material
    of any pipelines buried within the area of work” (id. at 188).
    9. Although the table above did omit the Pipeline, two drawings in the 0043
    Contract—drawings C-19 and C-20—showed the Pipeline crossing Section No. 17 of
    the dredging area (R4, tab 1 at 38-39).
    10. The 043 Contract incorporated by reference FAR 52.236-21
    (SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION) (Feb. 1997) (R4,
    tab 1 at 65), which stated, inter alia, that “[a]nything mentioned in the specifications
    and not shown on the drawings or shown on the drawings and not mentioned in the
    specifications, shall be of like effect as if shown or mentioned in both” 
    48 C.F.R. § 52.236-21
    (a).
    11. The 043 Contract required RLB to complete performance within 115
    calendar days of the notice to proceed (R4, tab 1 at 28). The 043 Contract included a
    liquidated damages clause under FAR 52.211-12, which required RLB to pay $1,673
    for each calendar day of delay (id.). However, the 043 Contract also incorporated by
    reference FAR 52.249-10 (DEFAULT (FIXED-PRICE CONSTRUCTION)) (April
    5
    1984) (id. at 65), which stated that RLB shall not be charged with liquidated damages
    if “the delay in completing the work arises from unforeseeable causes beyond the
    control and without the fault or negligence of the Contractor” 
    48 C.F.R. § 52.249
    -
    10(b)(1).
    III. Performance
    12. The Corps issued the notice to proceed on June 8, 2017 (R4, tab 3 at 248),
    making the contract completion date (CCD) October 1, 2017 (SUMF ¶12; RSUMF ¶
    12).
    13. RLB did not cooperate with Genesis to establish the actual position of the
    Pipeline prior to dredging, or request the Pipeline permit or surveys from the Corps
    (Hernandez Decl. ¶¶ 9-10; gov’t mot. at ex. 1; SUMF ¶ 18; RSUMF ¶ 18).
    14. On April 17, 2018, the Jonathon King Boyd—one of RLB’s dredgers—
    struck the Pipeline while performing dredging in Section No. 17, causing a gas plume
    to ignite and damage the Jonathon King Boyd (R4, tabs 4 at 251; 10 at 277).
    15. During a telephone call on April 18, 2018, Randy Boyd of RLB informed
    Christopher Frabotta—Chief of the Corps’ Navigation Branch—“you know Chris, the
    pipeline was clearly marked on the plans and this one’s on us. It’s on my guys; well
    it’s on me. My guys should have performed better coordination” (R4, tab 4 at 251). 4
    16. RLB claims that, due to the damage, it was unable to perform dredging
    work between April 17, 2018 and December 21, 2018 (R4, tab 11 at 289). RLB
    completed the dredging work on April 17, 2019 (R4, tab 14 at 313). 5
    4
    While RLB calls the above statement self-serving, it is not hearsay because it was an
    opposing party’s statement. FED. R. EVID. 801(d)(2). Moreover, RLB did not
    raise a genuine issue of material fact regarding that statement by submitting
    contradictory evidence, such as a declaration from Mr. Boyd (app. resp. at 2-3).
    5
    The Corps points to a July 16, 2019 National Transportation Safety Board (NTSB)
    report’s probable cause findings regarding the accident (R4, tab 10). However,
    “[n]o part of a report of the [National Transportation Safety] Board relating to
    an accident or an investigation of an accident may be admitted into evidence or
    used in a civil action for damages resulting from a matter mentioned in the
    report.” 
    49 U.S.C. § 1154
    (b); see also In re Air Crash Disaster at Sioux City,
    Iowa, 
    780 F.Supp. 1207
    , 1208-11 (N.D. Ill. 1991). Because we find in favor of
    the Corps anyway, we assume without deciding that that statute precludes our
    consideration of the NTSB report’s findings regarding probable cause.
    6
    IV. Procedural History
    17. On July 2, 2020, RLB submitted a certified claim to the CO (R4, tab 11
    at 288-301).
    18. On October 30, 2020, the CO issued a final decision, denying the claim
    (R4, tab 14 at 308-19).
    19. This appeal followed. The complaint alleges that RLB is entitled to a time
    extension of 363 days and remission of liquidated damages in the amount of $585,550
    due to the excusable delays of the Corps providing defective specifications, RLB
    encountering differing site conditions, and the Corps breaching its duty of good faith
    and fair dealing (compl. ¶¶ 33-52, WHEREFORE clause).
    DECISION
    The Corps properly imposed liquidated damages under the 0043 Contract
    because there is no genuine issue of material fact suggesting that there was excusable
    delay. Where—as here (SOF ¶ 11)—a contract authorizes the imposition of liquidated
    damages, the government may impose reasonable liquidated damages for delays,
    unless a contractor can show that the delays were excusable. Ken Laster Co., 
    ASBCA No. 61292
    , 
    20-1 BCA ¶ 37,659
     at 182,855. The government bears the initial burden of
    proving that the contractor failed to meet the CCD, and that the period of time for
    which the government assessed liquidated damages was correct. 
    Id.
     If the
    government makes such a showing, then the burden shifts to the contractor to show
    that its failure to timely complete the work was excusable. 
    Id.
    Here, RLB does not dispute the Corps’ showing that RLB failed to meet the
    CCD, and that the period of time for which the Corps assessed liquidated damages was
    correct (see generally app. resp. 9-18). Rather, RLB argues that that delay was
    excusable because the Corps provided defective specifications, there were differing
    site conditions, and the Corps breached its duty of good faith and fair dealing (id.). As
    discussed below, RLB has failed to raise a genuine issue of material fact suggesting
    that there were defective specifications, differing site conditions, or a breach of the
    duty of good faith and fair dealing.
    I. Summary Judgment Standard
    We grant summary judgment only if there is no genuine issue as to any material
    fact, and the moving party is entitled to judgment as a matter of law. Celotex Corp. v.
    Catrett, 
    477 U.S. 317
    , 322-23 (1986) (internal citations omitted). All significant doubt
    over factual issues must be resolved in favor of the party opposing summary judgment.
    Mingus Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987). In
    7
    deciding summary judgment motions, we do not resolve controversies, weigh
    evidence, or make credibility determinations. Anderson v. Liberty Lobby, Inc.,
    
    477 U.S. 242
    , 255 (1986). Moreover, we draw all reasonable inferences in favor of the
    non-movant. 
    Id.
     A genuine issue of material fact arises when the non-movant
    presents sufficient evidence upon which a reasonable fact-finder, drawing the requisite
    inferences and applying the applicable evidentiary standard, could decide the issue in
    favor of the non-movant. C Sanchez & Son, Inc. v. United States, 
    6 F.3d 1539
    , 1541
    (Fed. Cir. 1993).
    II. Defective Specifications Claim
    RLB has failed to raise a genuine issue of material fact suggesting that the
    Corps provided defective specifications. As we have recognized:
    When the government provides a contractor with defective
    specifications, the government is deemed to have breached
    the implied warranty that satisfactory contract performance
    will result from adherence to the specifications, and the
    contractor is entitled to recover all of the costs proximately
    flowing from the breach.
    Essex Electro Engineers, Inc. v. Danzig, 
    224 F.3d 1283
    , 1289 (Fed. Cir. 2000). A
    contractor may not prevail on a defective specifications claim when it has assumed the
    risk of performance, such as when the government uses specific—as opposed to
    general—exculpatory language. Commercial Constr. Corp., 
    ASBCA No. 24087
    , 
    80-1 BCA ¶ 14,312
     at 70,532. In order to establish a defective specifications claim, the
    contractor bears the burden of establishing the fundamental facts of liability, causation,
    and resulting injury. Wunderlich Contracting Co. v. United States, 
    351 F.2d 956
    , 968
    (Ct. Cl. 1965). As discussed below, RLB has failed to raise a genuine issue of material
    fact regarding either liability or causation.
    A. Liability
    RLB has not presented sufficient evidence upon which a reasonable fact-finder
    could decide the issue of liability in its favor. RLB first argues that specification 1.8.1
    was defective because it omitted the Pipeline from the identified known pipelines and
    utility crossings the dredging areas (app. resp. at 11; see also SOF ¶ 8). However, we
    must read a contract as a whole. Medlin Constr. Group, Ltd. V. Harvey, 
    449 F.3d 1195
    , 1200 (Fed. Cir. 2006); A.R. Mack Constr. Co., 
    ASBCA No. 49526
    , 
    97-1 BCA ¶ 28,742
     at 143,464. In particular, even if a specification omits a condition, the
    contract nevertheless accurately discloses the condition if the contract contains a
    FAR 52.236-21 clause and drawings that accurately disclose the condition. Hobbs
    Constr. & Develop., Inc., 
    ASBCA No. 299910
    , 
    91-1 BCA ¶ 23,518
     at 117,933;
    8
    FAR 52.236-21. Here, the 0043 Contract contained a FAR 52.236-21 clause, which
    stated that “[a]nything . . . shown on the drawings and not mentioned in the
    specifications, shall be of like effect as if shown or mentioned in both” (SOF ¶ 10).
    Moreover, drawings C-19 and C-20 accurately disclosed that the Pipeline crossed the
    dredging area (SOF ¶ 9). Therefore, read as a whole, the 0043 Contract accurately
    disclosed that the Pipeline crossed the dredging area, despite specification 1.8.1’s
    omission of the Pipeline from the list of pipelines and utilities crossing the dredging
    area.
    RLB next points to specification 1.8.1’s statement that “every effort has been
    made to give all pertinent details on the location of pipelines/utilities. The data
    furnished on the plans are believed to be substantially correct[.]” RLB argues that that
    statement was defective because the Email Chain and the Genesis As-Built Drawing
    show that the Corps knew that the Pipeline was not adequately buried to -24 feet
    MLLW over the 300 feet dredging area, and failed to disclose that information to
    RLB. (App. resp. at 11-12 (quoting SOF ¶ 8) (emphasis omitted)) However, the
    Email Chain at most raises a genuine issue of material fact suggesting that the Corps
    knew in November 2016 that the Pipeline was not adequately buried (SOF ¶ 2). It is
    not reasonable to infer from that fact that the Corps knew when it issued the
    solicitation and awarded the 0043 Contract on April 7, 2017 and June 2, 2017,
    respectively, that the Pipeline was not adequately buried because there is no genuine
    issue of material fact but that: (1) in the Email Chain, the Corps—through Herbert—
    directed Genesis to lower the Pipeline as soon as possible in November 2016
    (SOF ¶ 3); (2) Herbert confirmed to the Corps on March 23, 2017 that “the pipeline
    was lowered as directed by USACE Operations” (SOF ¶ 5); and (3) Herbert provided
    the Corps on March 23, 2017, the Genesis As-Built Drawing, showing that Genesis
    adequately buried the Pipeline to at least -24 feet MLWW for all of the 325 feet of the
    GIWW channel, slopes, and setbacks—which was wider than the 300 feet dredging
    area (SOF ¶ 5). Thus, RLB has failed to raise a genuine issue of material fact
    suggesting that the Corps knew when it issued the solicitation and awarded the 0043
    Contract that the Pipeline was inadequately buried.
    In any event, RLB’s defective specifications claim would fail because there is
    no genuine issue of material fact but that RLB assumed the risk of determining the
    Pipeline’s location and depth, and specification 1.8.1 used specifically exculpatory
    language regarding any representations as to the Pipeline’s location and depth. RLB
    assumed the risk of determining the Pipeline’s location and depth through
    specification 1.8.1, which stated that “the contractor shall cooperate with the
    respective owners to establish the actual position of the pipelines/utilities” (SOF ¶ 8
    (emphasis omitted)). Similarly, specification 1.8 stated that:
    It is the Contractor’s responsibility to investigate the
    location of utility crossings. The Contractor shall take
    9
    precautions against damages which can result from
    dredging operations in the vicinity of the utility crossings.
    If damage occurs as a result of the dredging operations, the
    Contractor will be required to suspend dredging until the
    damage is repaired and approved. Costs of these repairs
    and downtime of the dredge and attendant plant shall be at
    the Contractor’s expense.
    (SOF ¶ 7). Likewise, the 0043 Contract required RLB to “[v]erify with the utility
    owner the size, depth, coordinates, and transported material of any pipelines buried
    within the area of work,” and provided that “[t]he Contractor shall protect from
    damage all existing . . . utilities . . . at or near the work site.” (SOF ¶¶ 7-8). Further,
    specification 1.8.1 used specific exculpatory language, stating that “the exact locations
    [of pipelines and utilities] may vary from that shown.” (SOF ¶ 8 (emphasis omitted)).
    Because there is no genuine issue of material fact but that RLB assumed the risk of
    determining the Pipeline’s location and depth, and specification 1.8.1 used specifically
    exculpatory language, RLB’s defective specifications claim must fail. Commercial
    Constr., 
    80-1 BCA ¶ 14,312
     at 70,532. 6
    B. Causation
    Nor has RLB presented sufficient evidence upon which a reasonable fact-finder
    could decide that any defective specifications caused the injury. First, RLB does not
    even argue—let alone presents sufficient evidence upon which a reasonable fact-finder
    could decide—that any inadequate burial of the Pipeline caused the accident (app. br.
    9-10).
    On the contrary, there is no genuine issue of material fact but that RLB’s failure
    to satisfy its duty to determine the Pipeline’s location and depth caused the accident.
    As discussed above, the 043 Contract required RLB to determine the Pipeline’s
    location and depth (SOF ¶¶ 7-8). However, RLB failed to determine the Pipeline’s
    location and depth (SOF ¶ 13).
    There is no genuine issue of material fact but that it was that failure by RLB to
    determine the Pipeline’s location and depth that cause the injury. As Mr. Boyd of
    RLB acknowledged after the accident that “the pipeline was clearly marked on the
    6
    We do not enforce specific exculpatory language if the parties did not contemplate
    enforcement, or enforcement would be inconsistent with some other significant
    contract provision. Commercial Constr., 
    80-1 BCA ¶ 14,312
     at 70,532. RLB
    does not argue that the parties did not contemplate enforcement of the specific
    exculpatory language, or that such enforcement would be inconsistent with
    some other significant contract provision (see generally app. resp.).
    10
    plans and this one’s on us. It’s on my guys; well it’s on me. My guys should have
    performed better coordination” (SOF ¶ 15). Therefore, there is no genuine issue of
    material fact but that RLB’s failure to fulfill its contractual duty to determine the
    Pipeline’s location and depth—and not any defective specifications—caused the
    injury. As a result, the Corps is entitled to judgment as a matter of law on RLB’s
    defective specifications claim.
    III. Differing Site Conditions Claim
    There is no genuine issue of material fact suggesting that there were differing
    site conditions. The elements of a type I 7 differing site conditions claim are that:
    (1) the contract contained a positive indication of the conditions at the site; (2) the
    contractor reasonably interpreted and relied upon the indicated site conditions; (3) the
    conditions encountered were materially different from those indicated; (4) the
    conditions encountered were reasonably unforeseeable based upon the information
    available to the contractor at the time of bidding; and (5) the differing site conditions
    were the sole cause of the contractor’s injury. Nova Group, Inc., 
    ASBCA No. 55408
    ,
    
    10-2 BCA ¶ 34,533
     at 170,321 (citing H.B. Mac, Inc. v. United States, 
    153 F.3d 1338
    ,
    1345 (Fed. Cir. 1998); Stuyvesant Dredging Co. v. United States, 
    834 F.2d 1576
    , 1581
    (Fed. Cir. 1987)).
    Here, RLB has failed to present sufficient evidence upon which a reasonable
    fact-finder could decide that there was a positive indication in the 0043 Contract as to
    the Pipeline’s depth (app. resp. at 10-16). Rather, RLB complains that the 0043
    Contract failed to disclose that the Pipeline was inadequately buried (id. at 16).
    However, because establishing a differing site conditions claim requires a positive
    indication, the absence of an indication in the 0043 Contract regarding the Pipeline’s
    depth does not support a differing site conditions claim. See David Boland, Inc.,
    
    ASBCA No. 61923
     et al., 
    21-1 BCA ¶ 37,822
     at 183,656 (holding that the absence of
    an indication in a contract regarding the state of a utility line did not support a
    differing site conditions claim).
    Moreover, RLB has failed to present sufficient evidence upon which a
    reasonable fact-finder could decide that the conditions encountered were reasonably
    unforeseeable based upon the information available to RLB at the time of bidding.
    If—as RLB alleges—the Genesis As-Built Drawing showed that the Pipeline was
    inadequately buried (which is not the case) (app. resp. at 7, 11-12, 16), then the
    purported fact that the Genesis As-Built drawing showed the Pipeline was
    7
    Given RLB’s allegation that actual conditions differed materially from those
    indicated in the 0043 Contract, (compl. ¶ 49), it is clear that RLB is bringing a
    type I—and not a type II—differing site conditions claim. See Dennis T. Hardy
    Elec., Inc., 
    ASBCA No. 47770
    , 
    97-1 BCA ¶ 28,840
     at 143,870.
    11
    inadequately buried would have been reasonably foreseeable based upon the
    information available to RLB because the Genesis As-Built Drawing was available to
    RLB. As specification 1.8 stated, “the U.S. Army Corps of Engineers permits of the
    respective pipelines and previous surveys are available upon request from the Corpus
    Christi Resident Office.” (SOF ¶ 8 (emphasis omitted)) Further, as discussed above,
    RLB could have—and indeed was contractually required to—determine the Pipeline’s
    depth by contacting Genesis (SOF ¶¶ 7-8). Thus, there is no genuine issue of material
    fact suggesting that the conditions encountered were reasonably unforeseeable based
    upon the information available to RLB at the time of bidding. See Control, Inc. v.
    United States, 
    294 F.3d 1357
    , 1365 (Fed. Cir. 2002) (holding that a differing site
    conditions claim related to a pipeline failed when a reasonably prudent contractor
    would have inquired about the pipeline’s location).
    Finally, there is no genuine issue of material fact suggesting that that failure to
    disclose the Pipeline’s depth was the sole cause of RLB’s injury. Rather, as discussed
    above, there is no genuine issue of material fact but that RLB’s failure to fulfill its
    contractual duty to determine the Pipeline’s depth caused the injury (SOF ¶¶ 7-8, 13).
    As a result, the Corps is entitled to judgment as a matter of law on RLB’s differing site
    conditions claim.
    IV. The Duty of Good Faith and Fair Dealing Claim
    There is no genuine issue of material fact suggesting that the Corps breached its
    duty of good faith and fair dealing. “Every contract imposes upon each party a duty of
    good faith and fair dealing in its performance and enforcement.” Metcalf v. United
    States, 
    742 F.3d 984
    , 990 (Fed. Cir. 2014) (internal citation omitted). However, a
    party cannot use an implied duty of good faith and fair dealing to expand another
    party’s contractual duties beyond those in the contract, or to create duties inconsistent
    with the contract’s provisions. Agility Pub. Warehousing Co. KSCP v. Mattis, 
    852 F.3d 1370
    , 1384 (Fed. Cir. 2017) (internal citation omitted).
    Here, RLB argues that the Corps breached its duty of good faith and fair
    dealing by failing to disclose its knowledge that the Pipeline was inadequately buried,
    despite the Corps’ representation that it would “give all pertinent details on the
    location of pipelines” and utilities and that the “data furnished on the plans are
    believed to be substantially correct” (app. resp. at 14-15; see also SOF ¶ 8). However,
    as discussed above, there is no genuine issue of material fact suggesting that the Corps
    knew that the Pipeline was inadequately buried at the time of the solicitation and
    contract award (SOF ¶ 5). In any event, RLB cannot use the duty of good faith and
    fair dealing to impose upon the Corps a duty to disclose the Pipeline’s depth because
    that would create a duty inconsistent with the 0043 Contract, which—as discussed
    above—imposed upon RLB a duty to determine the Pipeline’s depth (SOF ¶¶ 7-8).
    12
    Therefore, the Corps is entitled to judgment as a matter of law on RLB’s breach of the
    duty of good faith and fair dealing claim.
    CONCLUSION
    For the foregoing reasons, the motion for summary judgment is granted and we
    dismiss this appeal.
    Dated: June 15, 2023
    JAMES R. SWEET
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                            I concur
    RICHARD SHACKLEFORD                                 J. REID PROUTY
    Administrative Judge                                Administrative Judge
    Acting Chairman                                     Vice Chairman
    Armed Services Board                                Armed Services Board
    of Contract Appeals                                 of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62779
    , Appeal of RLB
    Contracting, Inc., rendered in conformance with the Board’s Charter.
    Dated: June 16, 2023
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    13
    

Document Info

Docket Number: 62779

Filed Date: 6/15/2023

Precedential Status: Precedential

Modified Date: 11/18/2023