Conservation Law Foundation v. ExxonMobil Corporation ( 2021 )


Menu:
  •              United States Court of Appeals
    For the First Circuit
    No. 20-1456
    CONSERVATION LAW FOUNDATION, INC.,
    Plaintiff, Appellant,
    v.
    EXXON MOBIL CORPORATION, EXXONMOBIL OIL CORPORATION, EXXONMOBIL
    PIPELINE COMPANY,
    Defendants, Appellees.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Mark L. Wolf, U.S. District Judge]
    Before
    Howard, Chief Judge,
    Thompson, Circuit Judge,
    and Katzmann,* Judge.
    Ian David Coghill, with whom Christopher M. Kilian,
    Conservation Law Foundation, Allan Kanner, and Kanner & Whiteley,
    LLC were on brief, for appellant.
    William Thomas Marks, with whom Theodore V. Wells, Jr., Daniel
    J. Toal, Jamie D. Brooks, Kannon K. Shanmugam, William T. Marks,
    Paul, Weiss, Rifkind, Wharton & Garrison LLP, Deborah E. Barnard,
    Jessica R. Early, and Holland & Knight LLP were on brief, for
    appellees.
    *  Of the United States Court of International Trade, sitting by
    designation.
    July 1, 2021
    THOMPSON, Circuit Judge.        Conservation Law Foundation,
    a not-for-profit organization focusing on the conservation and
    protection of New England's environment, has filed suit against
    ExxonMobil Corporation, ExxonMobil Oil Corporation, and ExxonMobil
    Pipeline Company (collectively, "ExxonMobil").             The Foundation's
    complaint alleges violations of the Clean Water Act ("CWA"), 33
    U.S.C. § 1251 et seq., and the Resource Conservation and Recovery
    Act ("RCRA"), 42 U.S.C. § 6901 et seq., at ExxonMobil's petroleum
    storage   and   distribution    terminal    in    Everett,   Massachusetts.
    After denying in part ExxonMobil's motion to dismiss, the district
    court granted ExxonMobil's motion to stay proceedings under the
    so-called doctrine of primary jurisdiction, a doctrine "concerned
    with   promoting   proper     relationships      between   the   courts   and
    administrative     agencies    charged     with    particular     regulatory
    duties," so that the U.S. Environmental Protection Agency ("EPA")
    could weigh in.     United States v. W. Pac. R.R., 
    352 U.S. 59
    , 63
    (1956).   The case has remained stayed ever since.           The Foundation
    appealed the stay order, maintaining that the district court erred
    because, in the context of this case, the doctrine of primary
    jurisdiction is inapt.      ExxonMobil, on the other hand, argues that
    the district court correctly applied the doctrine, but that even
    if it did not we lack appellate jurisdiction to review the stay
    - 3 -
    order.1   For the following reasons, we find that we do have
    appellate jurisdiction to review the order and, upon that review,
    that the district court improperly stayed the case.
    I.   Background
    A.   The Permit
    Pursuant to a permit issued by EPA under the National
    Pollutant Discharge Elimination System program, see 33 U.S.C.
    § 1342(a), ExxonMobil may discharge stormwater, groundwater, and
    certain other waters (such as potable water used to wash trucks or
    garage floors) from its Everett terminal into the Island End River,
    a small tributary of Boston's Mystic River.    See City of Taunton
    v. EPA, 
    895 F.3d 120
    , 124 (1st Cir. 2018) (explaining the permit
    process more).   ExxonMobil's permit originally became effective on
    1  It is often remarked that jurisdiction is "a word of many, too
    many, meanings." Fort Bend Cty. v. Davis, 
    139 S. Ct. 1843
    , 1848
    (2019) (quoting Kontrick v. Ryan, 
    540 U.S. 443
    , 454 (2004)). This
    case requires us to discuss two of the word's uses. The first,
    the doctrine of primary jurisdiction, is a bit of a misnomer.
    "Properly understood, the doctrine is not jurisdictional per se,
    but rather is a means of procuring 'harmony, efficiency, and
    prudence' in areas of overlapping judicial and administrative
    concern." Nat'l Tank Truck Carriers, Inc. v. Burke, 
    608 F.2d 819
    ,
    821 (1st Cir. 1979) (quoting Mashpee Tribe v. New Seabury Corp.,
    
    592 F.2d 575
    , 580 n.1 (1st Cir. 1979)); see also United States v.
    Lahey Clinic Hosp., Inc., 
    399 F.3d 1
    , 18 (1st Cir. 2005)
    (explaining that the primary jurisdiction doctrine "does not
    implicate the subject matter jurisdiction of the federal court"
    (quoting P.R. Mar. Shipping Auth. v. Fed. Mar. Comm'n, 
    75 F.3d 63
    ,
    67 (1st Cir. 1996))).    By contrast, when it comes to appellate
    jurisdiction, a court of appeals "must verify [that] it has that
    jurisdiction before addressing the merits of any appeal." Conille
    v. Council 93, Am. Fed'n of State, Cty. & Mun. Emps., 
    935 F.3d 1
    ,
    5 (1st Cir. 2019).
    - 4 -
    January 1, 2009 and superseded a prior permit issued in March 2000.
    EPA later modified the permit.           Permits issued under the National
    Pollutant Discharge Elimination System program may not exceed five
    years, so ExxonMobil's permit for the Everett terminal expired on
    January 1, 2014.         See 33 U.S.C. § 1342(a)(3), (b)(1)(B).                   By
    regulation,       however,    the    conditions   of     an   EPA-issued    permit
    "continue in force" until the effective date of a new permit if,
    as here, the permittee has submitted a timely application and
    through no fault of its own a new permit has not yet issued.                     40
    C.F.R. § 122.6(a); 5 U.S.C. § 558 ("When the licensee has made
    timely and sufficient application for a renewal or a new license
    in accordance with agency rules, a license with reference to an
    activity     of   a   continuing      nature   does    not    expire   until     the
    application has been finally determined by the agency.").                  EPA has
    yet to act on ExxonMobil's application, so the conditions of the
    prior permit remain in effect.
    B.   Procedural History
    In September 2016, the Foundation filed this action
    under the citizen suit provisions of the CWA, 33 U.S.C. § 1365,
    and RCRA, 42 U.S.C. § 6972.              The operative complaint contains
    principally two sets of allegations:              first, that ExxonMobil has
    failed to comply with its discharge permit and thus violated the
    CWA;   and    second,    that       ExxonMobil    "has    contributed      and   is
    contributing to past and present handling, storage, treatment,
    - 5 -
    transportation, or disposal of solid and hazardous wastes which
    may present an imminent and substantial endangerment to health or
    the environment in violation of RCRA."
    In March 2019, after hearing argument on ExxonMobil's
    motion to dismiss, the district court granted the motion as to
    three of the fifteen counts in the complaint but denied the motion
    as to the others.        All but one of the surviving counts allege
    violations of the CWA.         Some of those counts allege ExxonMobil
    violated    the   CWA   by   discharging     pollutants    from   the    Everett
    terminal in excess of the limits set out in the permit or in
    violation of Massachusetts Surface Water Quality Standards, which
    itself violates the permit.       Another count alleges that ExxonMobil
    violated the CWA by failing to develop, implement, and maintain a
    Storm Water Pollution Prevention Plan ("stormwater plan") that is
    designed to reduce or prevent the discharge of pollutants in
    stormwater while accounting for harsher precipitation events and
    increased    flooding    generally    attributable        to   climate    change
    ("climate change factors").        Other counts allege that ExxonMobil
    violated the CWA by failing to prepare the stormwater plan "in
    accordance with good engineering practices" as required by the
    permit since it did not account for the climate change factors,
    or because the stormwater plan failed to "identify potential
    sources of pollution that may reasonably be expected to affect the
    quality" of the stormwater discharges, as required by the permit,
    - 6 -
    since the stormwater plan did not account for the climate change
    factors.    Still more counts allege ExxonMobil violated the CWA
    because, in violation of the permit, the stormwater plan failed to
    "describe and ensure implementation of practices which will be
    used to reduce the pollutants and assure compliance with this
    permit"    and   also   fails   to     identify   "all   pollutant    sources"
    including "all areas where spills . . . could occur" and the
    "expected   drainage"    for    each    of   those   pollutants,     since   the
    stormwater plan did not account for the climate change factors.
    Another count alleges that ExxonMobil violated the CWA because,
    among other reasons, the stormwater plan did not contain "spill
    prevention and response procedures," as required by the permit,
    which accounted for the climate change factors.               Another count
    alleges a CWA violation because the permit required ExxonMobil to
    report any relevant facts it either did not previously submit or
    that it submitted incorrectly, and that ExxonMobil failed to do so
    as to facts relating to the climate change factors.           Another count
    describes a similar obligation as to the stormwater plan and
    alleges that ExxonMobil failed to amend or update the stormwater
    plan with information relating to the climate change factors.                 It
    also alleges that ExxonMobil failed to "properly operate and
    maintain" the Everett terminal or to "take all reasonable steps to
    minimize" certain discharges having "a reasonable likelihood of
    adversely affecting human health or the environment" (in violation
    - 7 -
    of the permit) since it did not account for the climate change
    factors.   The complaint also alleges that ExxonMobil made certain
    certifications that were improper for many of the reasons already
    discussed, in violation of the permit.
    The final count relates to RCRA.             It alleges that
    ExxonMobil violated –– and continues to violate -- RCRA at its
    Everett    terminal   because    it     "has   contributed    or . . .   is
    contributing to the past or present handling, storage, treatment,
    transportation, or disposal of any solid or hazardous waste which
    may present an imminent and substantial endangerment to health or
    the environment" largely because it has failed to account for the
    climate change factors.       42 U.S.C. § 6972(a)(1)(B).
    The   Foundation     seeks   injunctive   relief    to   prevent
    further violations of the CWA and RCRA as well as declaratory
    relief under the CWA.     It also seeks civil penalties amounting to
    tens of thousands of dollars per day per violation for each day
    starting in 2009.      Finally, it seeks costs of the litigation,
    including attorney and expert witness fees, and all other relief
    permitted by law.
    After the district court ruled on the motion to dismiss,
    ExxonMobil moved to stay the case under the doctrine of primary
    jurisdiction until EPA issued a decision on ExxonMobil's pending
    permit renewal application for the Everett terminal.            ExxonMobil
    maintained that EPA's decision would likely resolve "most, if not
    - 8 -
    all, of the disputed issues" in the case.               The district court
    granted ExxonMobil's motion.          Conservation Law Found., Inc. v.
    ExxonMobil Corp., 
    448 F. Supp. 3d 7
    , 12 (D. Mass. 2020).                 While
    recognizing that the doctrine of primary jurisdiction "must be
    applied   sparingly,   especially      in    citizen   suits    authorized    by
    Congress,"    it   reasoned   that    this    case   involved    "a   rare   set
    circumstances" justifying application of the doctrine.                 
    Id.
       We
    will detail its reasoning as it pertains to our analysis later.
    The Foundation timely appealed the stay order.
    II.    Discussion
    A.   Appellate Jurisdiction
    The parties dispute whether we even have jurisdiction to
    hear this case.        Generally speaking, we only have appellate
    jurisdiction to review "final decisions of the district courts."
    28 U.S.C. § 1291; see Commonwealth Sch., Inc. v. Commonwealth Acad.
    Holdings LLC, 
    994 F.3d 77
    , 82 (1st Cir. 2021).           A district court's
    order is final if it "ends the litigation on the merits and leaves
    nothing for the court to do but execute the judgment."                Caribbean
    Mgmt. Grp., Inc. v. Erikon LLC, 
    966 F.3d 35
    , 40 (1st Cir. 2020)
    (quoting Whitfield v. Municipality of Fajardo, 
    564 F.3d 40
    , 45
    (1st Cir. 2009)).      That might seem like an uneasy match for an
    order granting a stay -- the decision we are asked to review --
    since a stay is the "postponement or halting of a proceeding."
    Stay, Black's Law Dictionary (11th ed. 2019).            Indeed, "most stay
    - 9 -
    orders do not constitute final appealable decisions within the
    meaning of 28 U.S.C. § 1291."           Nat'l R.R. Passenger Corp. v.
    Providence & Worcester R.R. Corp., 
    798 F.2d 8
    , 9 (1st Cir. 1986).
    Sometimes, however, a stay bears "special features . . .
    that make the district court's action something other than what it
    seems," not just "an ordinary postponement of court action."
    Hartford Fin. Sys., Inc. v. Fla. Software Servs., Inc., 
    712 F.2d 724
    , 726 (1st Cir. 1983) (Breyer, J.).        The Foundation argues that
    this case entails such a stay, because the stay order has rendered
    the Foundation "effectively-out-of-court."               See Moses H. Cone
    Mem'l Hosp. v. Mercury Constr. Corp., 
    460 U.S. 1
    , 10 (1983).             The
    Foundation focuses on the length of the stay, emphasizing that the
    case has been pending since 2016, that the district court granted
    the stay on March 21, 2020, and that the district court's order
    stayed the case indefinitely pending issuance of a new permit by
    EPA (though the district court set a check-in date for over a year-
    and-a-half after its order (November 1, 2021)).
    ExxonMobil   tells   us    that   the   key   consideration   for
    determining whether a stay order renders a party "effectively out
    of court" is not the indefiniteness of the stay but whether the
    stay "require[s] all or an essential part of the federal suit to
    be litigated in a state forum" or some other forum.          Moses H. Cone,
    
    460 U.S. at 10 n.11
    .       Several "effectively-out-of-court" cases
    have   focused   on   situations     where   the   federal    court   stayed
    - 10 -
    proceedings while a state court was resolving an identical issue
    and where the state court's judgment would have bound the parties
    in the federal litigation.    See In re Urohealth Sys., Inc., 
    252 F.3d 504
    , 507 (1st Cir. 2001) (citing Moses H. Cone, 
    460 U.S. at 10 & n.11
    ); Quackenbush v. Allstate Ins., 
    517 U.S. 706
    , 713 (1996)
    (explaining that the stay order in Moses H. Cone was appealable
    because the stay "put the litigants 'effectively out of court,'
    and because its effect was 'precisely to surrender jurisdiction of
    a federal suit to a state court'" (quoting Moses H. Cone, 
    460 U.S. at 10 n.11
    )).     In those situations, a party would lose the
    opportunity to litigate that same issue in federal court.
    As ExxonMobil acknowledges, however, that is not the
    only circumstance our circuit has recognized as rendering a party
    "effectively out of court."    See Rojas-Hernandez v. P.R. Elec.
    Power Auth., 
    925 F.2d 492
    , 495 (1st Cir. 1991) ("[W]e note that
    this Court has not interpreted the appealability rule in Moses H.
    Cone to turn solely on the preclusive effects of the state court
    judgment.").   Indeed, the approach we have taken -- treating stay
    orders that impose lengthy or indefinite delays as appealable as
    final orders under § 1291, even absent any risk that another
    proceeding will have res judicata effect on the federal case, id.
    - 11 -
    -- is the approach adopted by several courts of appeals to have
    considered the issue.2
    In   Rojas-Hernandez,    for     example,      which   is    binding
    precedent in our circuit, there was ambiguity about whether the
    appellant was a party to state-court proceedings which concerned
    an issue identical to one he had initiated litigation on in federal
    court. 
    925 F.2d at 494
    –95. Accordingly, there was ambiguity about
    whether the state-court judgment there would have had preclusive
    effect in the federal-court proceedings.          
    Id.
         And if the state-
    court   judgment   were   not   binding    in   federal    court,      then   the
    appellant would not be "effectively out of court" in the way
    ExxonMobil suggests is necessary, because the appellant would get
    2  The Second, Fifth, Ninth, Eleventh, and Federal Circuits agree
    that stay orders imposing lengthy or indefinite delays are
    appealable as final orders under § 1291. See King v. Cessna
    Aircraft Co., 
    505 F.3d 1160
    , 1165 (11th Cir. 2007) (holding that
    "a stay order that is immoderate and involves a protracted and
    indefinite period of delay is final and appealable under 28 U.S.C.
    § 1291"); see also XPO Logistics, Inc. v. Elliott Cap. Advisors,
    LP, 
    673 F. App'x 85
    , 86 (2d Cir. 2016) (unpublished); Occidental
    Chem. Corp. v. La. Pub. Serv. Comm'n, 
    810 F.3d 299
    , 307-09 (5th
    Cir. 2016); Stanley v. Chappell, 
    764 F.3d 990
    , 995 (9th Cir. 2014);
    Spread Spectrum Screening LLC v. Eastman Kodak Co., 
    657 F.3d 1349
    ,
    1354 (Fed. Cir. 2011). But see Crystal Clear Commc'ns v. Sw. Bell
    Tel. Co., 
    415 F.3d 1171
    , 1176 (10th Cir. 2005) (explaining that,
    "[i]f a stay merely delays litigation and does not effectively
    terminate proceedings, it is not considered a final decision");
    see also Strausser v. Twp. of Forks, 
    460 F. App'x 115
    , 119 (3d
    Cir. 2012).    Other circuits have not yet articulated a clear
    position on this query. See, e.g., Clark v. Adams, 
    300 F. App'x 344
    , 351 (6th Cir. 2008) (unpublished); Phyllis Schlafly Revocable
    Tr. v. Cori, 
    924 F.3d 1004
    , 1010 (8th Cir. 2019); Belize Soc. Dev.
    Ltd. v. Gov't of Belize, 
    668 F.3d 724
    , 730 (D.C. Cir. 2012).
    - 12 -
    to    litigate    his     entire     case   in   federal    court   after    all.
    Nevertheless, we found we had jurisdiction in Rojas-Hernandez
    because   the     appellant    was    "effectively    out    of   court"    for   a
    different reason:         "the indefinite unnecessary delay inherent in
    the stay order."        
    Id. at 495
     (quoting Nat'l R.R. Passenger Corp.,
    
    798 F.2d at 10
    ).        Even though the state court had set a trial date,
    we determined that the appellant was subject to an indefinite
    delay:
    The stay in this case . . . [creates] a delay
    tied not into the usual considerations of the
    federal court's calendar but rather to those
    arising   in   the   state  proceeding. . . .
    Whether or not the trial in the commonwealth
    court takes place in the near future, [as
    scheduled,] plaintiff's trial has already been
    delayed almost a year since the entry of the
    district court order . . . , and further
    delays may arise while an opinion is awaited
    and an appeal taken.
    
    Id.
       We also recognized that if the state-court proceedings turned
    out not to be binding (as we had assumed), then the stay would not
    even have preserved any judicial resources.                
    Id.
    We think the situation here mirrors that in Rojas-
    Hernandez.       See, e.g., Occidental Chem. Corp. v. La. Pub. Serv.
    Comm'n, 
    810 F.3d 299
    , 307 (5th Cir. 2016) (finding that a decision
    to stay a case under the primary jurisdiction doctrine rendered
    the plaintiff "effectively out of court" where the agency had taken
    no action since the entrance of the stay and, after nearly two
    years, there was "no indication" of when it might take action);
    - 13 -
    Johnson & Johnson, Inc. v. Wallace A. Erickson & Co., 
    627 F.2d 57
    ,
    62 (7th Cir. 1980) (taking a similar approach in a case where the
    court ordered plaintiff to initiate patent reissue proceedings
    with the PTO and stayed patent infringement case pending resolution
    of   those   proceedings,   resulting     in   delay    that   was   for    an
    "indefinite period, and possibly forever").            ExxonMobil tries to
    distinguish this case on the facts, pointing out that EPA has
    represented that the agency is trying to issue a new permit by
    October 2021.    Even if EPA can deliver by its proposed issuance
    date   (over    eight    years   since     ExxonMobil      submitted       its
    application), the Foundation will have endured the stay for over
    a year and a half.      This is so even though the district court is
    requiring the parties in November 2021 to report their views on
    whether the stay should be lifted if EPA has not by that point
    issued the permit.      ExxonMobil contends that this check-in date
    makes the delay not so "indefinite," but the mere fact that the
    district court may reconsider its stay order after over a year and
    a half does not mean that the stay's duration is definite for
    purposes of our appellate jurisdiction.           But see Cheyney State
    Coll. Faculty v. Hufstedler, 
    703 F.2d 732
    , 735–36 (3d Cir. 1983)
    (concluding a stay order was not indefinite where the district
    court asked for an update on administrative proceedings within
    ninety days and where the district court agreed to reconsider its
    order on that date).
    - 14 -
    ExxonMobil    maintains        that    we    should       render        a    party
    "effectively out of court" due to "indefinite" delay in more
    limited    circumstances,       such    as    where       there       is   not    even       the
    possibility of an eventual return to federal court.                              See, e.g.,
    Crystal Clear Commc'ns, Inc. v. Sw. Bell Tel. Co., 
    415 F.3d 1171
    ,
    1177 (10th Cir. 2005) (explaining that a party was not "effectively
    out of court" since the "referral of a discrete issue to a federal
    agency under the doctrine of primary jurisdiction leaves open the
    possibility of an eventual return to federal court"). Our caselaw,
    however,   espouses     a   broader     view        --    in    Rojas-Hernandez,             for
    example,   we    contemplated     that       the    appellant         would      eventually
    return to federal court, 
    925 F.2d at 495
     -- and, subject to only
    rare exceptions, we are bound by our circuit's prior decisions,
    see United States v. Barbosa, 
    896 F.3d 60
    , 74 (1st Cir. 2018).
    For an indefinite stay to confer appellate jurisdiction
    under § 1291, the stay must also be unnecessary.                           See Miccosukee
    Tribe of Indians of Fla. v. S. Fla. Water Mgmt. Dist., 
    559 F.3d 1191
    , 1197 (11th Cir. 2009) (explaining that suspended-animation
    stays   are    appealable    when      they    are       "pending       the     outcome      of
    proceedings      that   [are]     unlikely          to    control          or    to       narrow
    substantially     the   claims    or    unresolved             issues      in   the       stayed
    lawsuit");      Rojas-Hernandez,       
    925 F.2d at 495
         (describing          the
    appellant as effectively-out-of-court because of the "indefinite
    unnecessary delay inherent in the stay order" (quoting Nat'l R.R.
    - 15 -
    Passenger Corp., 
    798 F.2d at 10
    )).      That requires us to review the
    likely outcome of the stay, an approach that "contrasts with the
    usual situation in which we first ascertain that jurisdiction
    exists and only then proceed to the merits."         Cheyney State Coll.
    Faculty, 
    703 F.2d at 735
    .          We will explain why the stay is
    unnecessary in the next section.
    Accordingly, we find that we have jurisdiction to hear
    this appeal.3
    B.   The Stay Order
    The district court granted ExxonMobil's motion for a
    stay under the doctrine of primary jurisdiction.            As we mentioned
    earlier,   the   doctrine    "applies   where   a   claim    is   originally
    cognizable in the courts, and comes into play whenever enforcement
    of the claim requires the resolution of issues which, under a
    regulatory scheme, have been placed within the special competence
    3  The Foundation provides two alternative bases for hearing this
    case. First, it argues that the stay order is final because it
    falls within the collateral order doctrine laid out in Cohen v.
    Beneficial Indus. Loan Corp., 
    337 U.S. 541
     (1949).      Second, it
    argues that we have jurisdiction under 28 U.S.C. § 1651 to issue
    a writ of mandamus, a "'drastic and extraordinary' remedy 'reserved
    for really extraordinary causes.'" Cheney v. U.S. Dist. Ct. for
    D.C., 
    542 U.S. 367
    , 380 (2004) (quoting Ex parte Fahey, 
    332 U.S. 258
    , 259–260 (1947)). Because we find appellate jurisdiction over
    the stay order because the Foundation is "effectively out of
    court," we need not discuss these alternatives further. See, e.g.,
    Moses H. Cone, 
    460 U.S. at 8 n.6
     ("[A] court of appeals has no
    occasion to engage in extraordinary review by mandamus 'in aid of
    [its] jurisdictio[n],' 28 U.S.C. § 1651, when it can exercise the
    same review by a contemporaneous ordinary appeal." (second and
    third alterations in original)).
    - 16 -
    of an administrative body."         W. Pac. R.R., 
    352 U.S. at 64
    .           The
    doctrine guides a court in deciding when those issues should be
    resolved in the first instance by the agency.             See PHC, Inc. v.
    Pioneer Healthcare, Inc., 
    75 F.3d 75
    , 80 (1st Cir. 1996).                   The
    doctrine    exists     to   promote     "national     uniformity      in    the
    interpretation and application of a federal regulatory regime" and
    "to avoid the possibility that a court's ruling might disturb or
    disrupt the regulatory regime of the agency in question."                   Am.
    Auto. Mfrs. Ass'n v. Mass. Dep't of Envtl. Prot., 
    163 F.3d 74
    , 81
    (1st Cir. 1998).
    The district court found a stay appropriate until EPA
    renews ExxonMobil's permit for the Everett terminal.             It reasoned
    that   determining    permit     conditions   fell   squarely   under      EPA's
    authority, that EPA was better suited than the court to determine
    the scientific and policy issues raised by ExxonMobil's need to
    consider the climate change factors, that EPA's renewal of the
    permit might moot the Foundation's request for injunctive relief,
    and that resolving the case on the merits would take at least as
    long   as   EPA's    projected    timeline    for    renewing   the   permit.
    Conservation Law Found., Inc., 448 F. Supp. 3d at 12.
    1.     Primary Jurisdiction and Citizen Suits
    The Foundation brought this action under the citizen
    suit provisions of the CWA and RCRA, and the Foundation argues
    that suits brought under those provisions bar courts from applying
    - 17 -
    the primary jurisdiction doctrine.            Citizen suits "function as a
    form of statutory enforcement in addition to, or in conjunction
    with,   enforcement     by     an    administrative      agency    or   other
    governmental entity."     Chico Serv. Station, Inc. v. Sol P.R. Ltd.,
    
    633 F.3d 20
    , 27 (1st Cir. 2011) (quoting Esso Standard Oil Co.
    (P.R.) v. Rodríguez–Pérez, 
    455 F.3d 1
    , 5 n.2 (1st Cir. 2006)).             In
    other words, citizen suit provisions demonstrate circumstances
    where Congress wanted to allow individuals to bring lawsuits, even
    where an agency has some authority.              The primary jurisdiction
    doctrine, on the other hand, is a form of abstention, that is, "a
    prudential mechanism that allows federal courts to take note of
    and weigh significant and potentially conflicting interests that
    were not –– or could not have been –– foreseen by Congress at the
    time that it granted jurisdiction for a given class of cases to
    the courts."   
    Id. at 31
    ; see United States v. Culliton, 
    328 F.3d 1074
    , 1082 (9th Cir. 2003) ("Whether the doctrine of primary
    jurisdiction applies in any particular situation depends on 'the
    extent to which Congress, in enacting a regulatory scheme, intends
    an administrative body to have the first word on issues arising in
    juridical proceedings.'" (quoting United States v. Gen. Dynamics
    Corp., 
    828 F.2d 1356
    , 1362 (9th Cir. 1987))).             We ourselves have
    previously   recognized      some   tension    between   citizen   suits   and
    Burford abstention.     See generally Chico, 
    633 F.3d at 30-31
    .
    - 18 -
    In Chico, we examined whether Burford abstention, a type
    of abstention related to the doctrine of primary jurisdiction, was
    applicable to a suit brought under RCRA's citizen suit provision.
    
    633 F.3d at 30
    .    We began our abstention discussion by taking note
    of a bedrock principle:
    Abstention occupies an uneasy position in the
    jurisprudence of federal court jurisdiction.
    As the common refrain goes, "federal courts
    have a 'virtually unflagging obligation . . .
    to exercise the jurisdiction given them.'"
    Ankenbrandt v. Richards, 
    504 U.S. 689
    , 705
    (1992) (quoting Colo. River Water Conservation
    Dist. v. United States, 
    424 U.S. 800
    , 817
    (1976)); United States v. Fairway Capital
    Corp., 
    483 F.3d 34
    , 44 (1st Cir. 2007) (same).
    This all but unyielding duty to exercise
    jurisdiction rests on the "the undisputed
    constitutional principle that Congress, and
    not the Judiciary, defines the scope of
    federal      jurisdiction      within      the
    constitutionally permissible bounds."      New
    Orleans Pub. Serv., Inc. v. Council of New
    Orleans (NOPSI), 
    491 U.S. 350
    , 359 (1989); see
    also Cohens v. Virginia, 
    19 U.S. 264
    , 404
    (1821) (federal courts "have no more right to
    decline the exercise of jurisdiction which is
    given, than to usurp that which is not").
    Chico, 
    633 F.3d at 28-29
    .    In our consideration of the abstention
    issue before the court, we observed that most courts to consider
    the issue, under either Burford abstention or the doctrine of
    primary jurisdiction, had found abstention improper.           
    Id. at 30
    .
    We then explained that Congress had recognized in RCRA's citizen
    suit   provision   "the   specific   clash   of   interests"    we   were
    considering with respect to abstention, and we thought abstention
    - 19 -
    might "threaten[] an 'end run around RCRA,' and would substitute
    our judgment for that of Congress about the correct balance between
    respect   for    state   administrative    processes    and   the    need   for
    consistent and timely enforcement of RCRA."            
    Id. at 31
     (quoting
    PMC, Inc. v. Sherwin–Williams Co., 
    151 F.3d 610
    , 619 (7th Cir.
    1998)).   Nevertheless, we declined to categorically rule out the
    possibility of abstention in RCRA in citizen suits.           
    Id.
         Instead,
    we   expressed     our   view   that    the     "circumstances      justifying
    abstention will be exceedingly rare."           
    Id. at 32
    .
    Reasoning by analogy, the Foundation argues that the
    circumstances justifying the doctrine of primary jurisdiction
    should be exceedingly rare -- and, in fact, nonexistent -- when a
    suit is brought under the citizen suit provisions of the CWA and
    RCRA.   Because we find abstention improper in the circumstances of
    this particular case, however, we need not determine whether the
    doctrine of primary jurisdiction doctrine is, as the Foundation
    urges, inapplicable to every case brought under the citizen suit
    provisions of the CWA and RCRA.        See Baykeeper v. NL Indus., Inc.,
    
    660 F.3d 686
    , 695 (3d Cir. 2011) (finding abstention improper while
    declining to impose a general rule as to the applicability of the
    primary jurisdiction doctrine to cases brought under citizen suit
    provisions).     We now explain why we find abstention improper here.
    2.     Review
    To start, we must decide what standard we ought to apply
    - 20 -
    in reviewing the stay order, but the parties have hardly discussed
    this issue.     Our caselaw does not readily provide an answer.
    Compare U.S. Pub. Interest Research Grp. v. Atl. Salmon of Me.,
    LLC, 
    339 F.3d 23
    , 34 (1st Cir. 2003) (suggesting that a district
    court has some discretion over whether to stay a case under the
    primary jurisdiction doctrine), with Newspaper Guild of Salem,
    Local 105 of Newspaper Guild v. Ottaway Newspapers, Inc., 
    79 F.3d 1273
    , 1283 (1st Cir. 1996) ("We review de novo the district court's
    implicit   jurisdictional   finding     that   the   Guild's   claims    fall
    within the primary jurisdiction of the NLRB."); see also U.S. Pub.
    Interest Research Grp., 
    339 F.3d at 34
     ("[A] refusal in this case
    to make a primary jurisdiction reference prior to the state's
    issuance of the permit was neither a mistake of law nor an abuse
    of discretion.").   And other circuit courts are split over whether
    to review decisions about the application of the doctrine of
    primary    jurisdiction   for   abuse   of   discretion   or   without   any
    deference to the district court.        See Chlorine Inst., Inc. v. Soo
    Line R.R., 
    792 F.3d 903
    , 908 (8th Cir. 2015) (collecting cases);
    see generally Nicholas A. Lucchetti, One Hundred Years of the
    Doctrine of Primary Jurisdiction:        But What Standard of Review Is
    Appropriate for It?, 59 Admin. L. Rev. 849 (2007).             For present
    purposes, we assume -- favorably to ExxonMobil -- that our review
    is for abuse of discretion.      "Abuse occurs when a material factor
    deserving significant weight is ignored, when an improper factor
    - 21 -
    is relied upon, or when all proper and no improper factors are
    assessed, but the court makes a serious mistake in weighing them."
    Indep. Oil & Chem. Workers of Quincy, Inc. v. Procter & Gamble
    Mfg. Co., 
    864 F.2d 927
    , 929 (1st Cir. 1988).
    Although there is "[n]o fixed formula" for applying the
    primary jurisdiction doctrine, W. Pac. R.R., 
    352 U.S. at 64,
     we
    have recognized three principal factors that guide whether to defer
    a matter to an agency:
    (1) whether the agency determination l[ies] at
    the heart of the task assigned the agency by
    Congress; (2) whether agency expertise [i]s
    required to unravel intricate, technical
    facts; and (3) whether, though perhaps not
    determinative, the agency determination would
    materially aid the court.
    Massachusetts v. Blackstone Valley Elec. Co., 
    67 F.3d 981
    , 992
    (1st Cir. 1995) (quoting Mashpee Tribe, 
    592 F.2d at 581
    ).             We may
    also consider whether referral to the agency promotes "national
    uniformity in the interpretation and application of a federal
    regulatory regime."      Am. Auto. Mfrs. Ass'n, 
    163 F.3d at 81
    ; see
    also Blackstone, 
    67 F.3d at 992
    .
    As a reminder, the district court stayed the case until
    EPA issues its new permit for ExxonMobil's Everett terminal.             As
    to   the   first   Blackstone   factor,    the   district   court   sensibly
    determined that issuing a permit and determining its terms lie at
    the heart of EPA's assigned task.         See 33 U.S.C. § 1342; Arkansas
    v. Oklahoma, 
    503 U.S. 91
    , 105 (1992) ("Congress has vested in the
    - 22 -
    [EPA] Administrator broad discretion to establish conditions for
    NPDES permits.").
    As to the second Blackstone factor, the district court
    explained   that   --   because   the   complaint   focuses   heavily   on
    ExxonMobil's alleged failure to account for the climate change
    factors -- it would have to determine "whether and to what extent
    climatologists believe weather patterns in Boston are changing,
    and how prudent industrial engineers would respond to such changes"
    in order to grant the requested relief.       Conservation Law Found.,
    Inc., 448 F. Supp. 3d at 22.       We assume for the sake of argument
    that agency expertise would be helpful to unravel which climate
    models most accurately capture the effects of the climate change
    factors.    Cf. BASF Wyandotte Corp. v. Costle, 
    598 F.2d 637
    , 655
    (1st Cir. 1979) ("[T]he choice of statistical methods is a matter
    best left to the sound discretion of the [EPA] Administrator."
    (quoting FMC Corp. v. Train, 
    539 F.2d 973
    , 986 (4th Cir. 1976)));
    but see Me. People's All. v. Mallinckrodt, Inc., 
    471 F.3d 277
    , 293
    (1st Cir. 2006) ("[F]ederal courts have proven, over time, that
    they are equipped to adjudicate individual cases, regardless of
    the complexity of the issues involved.        Federal courts are often
    called upon to make evaluative judgments in highly technical areas
    (patent litigation is an excellent example).").
    We now turn to the third Blackstone factor -- whether
    the agency determination would materially help the court.               Of
    - 23 -
    course, were we to weigh each of the Blackstone factors equally,
    the first two factors might outweigh the third even if the agency
    determination underlying the stay were completely unrelated to an
    issue before the court.       But that is obviously not what is meant.
    "[T]he doctrine of primary jurisdiction is not a doctrine of
    futility; it does not require resort to 'an expensive and merely
    delaying administrative proceeding when the case must eventually
    be decided on a controlling legal issue wholly unrelated to
    determinations for the ascertainment of which the proceeding was
    sent to the agency.'"         Local Union No. 189, Amalgamated Meat
    Cutters & Butcher Workmen of N. Am., AFL-CIO v. Jewel Tea Co., 
    381 U.S. 676
    , 686 (1965) (quoting Fed. Mar. Bd. v. Isbrandtsen Co.,
    
    356 U.S. 481
    , 521 (1958) (Frankfurter, J., dissenting)).                  So, the
    third factor can outweigh the other factors, and sometimes greatly
    so.   See     U.S.   Pub.   Interest   Research      Grp.,   
    339 F.3d at 34
    (explaining    that    whether   to    apply   the    doctrine     of     primary
    jurisdiction "usually depends on whether a reference will advance
    the sound disposition of the court case and whether failure to
    refer will impair the statutory scheme or undermine the agency to
    which the reference might be made").
    The third Blackstone factor is especially salient in
    this case.     Whether and on what terms EPA issues the permit for
    the Everett terminal seems to us largely irrelevant to whether
    ExxonMobil has violated the conditions of the permit currently in
    - 24 -
    effect.4   And it is wholly speculative whether the issuance of the
    permit will illuminate EPA's beliefs as to the best climate change
    models or how good engineers would respond to them, even if it
    must publish a draft permit, provide detailed explanations for the
    permit's conditions, and respond to public comments. See 40 C.F.R.
    §§ 124.7, 124.8, 124.11, 124.13, 124.17.      The stay also seems
    unlikely to aid in the national uniformity of the meaning of terms
    at issue in ExxonMobil's permit or the appropriate scope of climate
    change regulations since EPA is not tasked with interpreting them.
    See Astiana v. Hain Celestial Grp., Inc., 
    783 F.3d 753
    , 761 (9th
    Cir. 2015) ("Common sense tells us that even when agency expertise
    4  See, e.g., Sierra Club, Inc. v. Granite Shore Power LLC, No.
    19-CV-216-JL, 
    2019 WL 8407255
    , at *13 (D.N.H. Sept. 13, 2019) ("At
    its core, the EPA's current permit adjudication concerns the
    content and scope of [the facility's] future permit conditions.
    This is a very different determination than whether [the facility]
    is operating in compliance with its current permit conditions."
    (citation omitted)) (denying motion to stay citizen suit alleging
    violations of existing NPDES permit under primary jurisdiction
    doctrine notwithstanding pending permit renewal proceeding);
    Student Pub. Interest Research Grp. of N.J., Inc. v. Fritzsche,
    Dodge & Olcott, Inc., 
    579 F. Supp. 1528
    , 1537-38 (D. N.J. 1984),
    aff’d, 
    759 F.2d 1131
     (3d Cir. 1985) ("Defendant's argument confuses
    two events: the present citizen's suit, to enforce an existing
    NPDES permit; and a renewal application") (rejecting argument that
    citizen suit alleging violation of NPDES permit should be stayed
    pending permit reissuance); Ill. Pub. Interest Research Grp., 835
    F. Supp. at 1076 (finding primary jurisdiction inapplicable where
    citizen suit seeks enforcement of existing permit terms); cf.
    Student Pub. Interest Research Grp. of N.J., Inc. v. Monsanto Co.,
    
    600 F. Supp. 1479
    , 1483 (D.N.J. 1985) ("The pendency of a [permit]
    modification proceeding does not excuse violations of a permit
    prior to actual modification:     a modification request does not
    stay existing permit limitations.").
    - 25 -
    would be helpful, a court should not invoke primary jurisdiction
    when the agency is aware of but has expressed no interest in the
    subject matter of the litigation."); see also Student Pub. Interest
    Research Grp. of N.J., Inc. v. Monsanto Co., 
    600 F. Supp. 1479
    ,
    1483 (D.N.J. 1985) ("[W]hatever uniformity the EPA hoped to achieve
    presumably was expressed through the issuance of permits.").5
    After all, ExxonMobil has represented that its permit application
    seeks the issuance of a permit that is similar "in all material
    aspects" to the one currently in effect.
    For these reasons, we find unconvincing the district
    court's rationale that EPA's determination on the permit could
    render "most of th[e] case moot" since the Foundation has sought
    injunctive relief and since the new permit might cover some or all
    of the behavior the Foundation seeks to enjoin.    Conservation Law
    Found., Inc., 448 F. Supp. 3d at 24.       The district court also
    reasoned that even if the new permit did "not directly address
    climate change," it would "generate a fuller administrative record
    to which [it could] refer to discern the meaning of particular
    terms" in the permit.   Id. at 23.   That may be so, but we are not
    5  EPA is well aware of this litigation. In fact, EPA's statements
    in this case have expressly discounted concerns with any regulatory
    interference (indicating in a letter filed in this matter that the
    threat that "rulings in this case could be contrary to EPA's
    programs" is no greater than that "present in most private
    environmental litigation"). Further, EPA was invited to comment
    on this lawsuit and expressly declined to do so.
    - 26 -
    satisfied that a stay awaiting EPA's decision on ExxonMobil's
    permit for this reason would "materially" help the district court.6
    After considering the Blackstone factors, we balance
    them "against the potential for delay inherent in the decision to
    refer an issue to an administrative agency."                        Am. Auto. Mfrs.
    Ass'n, 
    163 F.3d at 81
    .7          Since the Blackstone factors do not weigh
    in   favor   of   the     stay    envisioned    by    the   district        court,   any
    potential    delay      only     furthers   our      view    that     the    stay    was
    unjustified.      We add that, despite the district court ruling on
    ExxonMobil's motion to dismiss in March 2019, the parties have not
    even begun discovery.            The district court explained that, in its
    view,   even      under     an    "ambitious,        and    perhaps    unrealistic,
    schedule," discovery and briefing on summary judgment would take
    6  We can imagine much more salient agency determinations, though
    we do not suggest that a stay to refer such determinations to EPA
    would satisfy the Blackstone factors or that it would be proper
    for the district court on remand to refer such determinations to
    the agency at this stage of the litigation. EPA's determination
    would much more likely aid the district court if, for example, it
    were to consider the meaning of the terms as used in ExxonMobil's
    permit whose terms are currently in effect.
    7  In American Automobile Manufacturers, we advised that where
    delay would potentially be too great to justify a referral, a
    district could, for example, "refer a matter to an administrative
    agency, explicitly providing, however, that if the agency fails to
    rule within a reasonable amount of time, the court would either
    vacate the referral order and decide the matter itself, or issue
    an order under 5 U.S.C. § 706(1), which authorizes courts to
    'compel agency action . . . unreasonably delayed.'" 
    163 F.3d at 82
    . There, we stayed proceedings to afford one of the parties the
    opportunity to obtain a ruling from EPA, but we warned that if no
    agency ruling was forthcoming in 180 days, we would decide the
    issues in the case without EPA's guidance. 
    Id. at 86
    –87.
    - 27 -
    over a year.    Conservation Law Found., Inc., 448 F. Supp. 3d at
    26.   Although the district court foresaw the issuance of the new
    permit as mooting many of the issues in the case, it is unclear
    how, as it believed, "deferring to the EPA until at least October
    2021 [w]ould not delay the resolution of the issues involved in
    this case."    Id.   Even if EPA issues ExxonMobil's permit by EPA's
    proposed deadline and even if the permit moots the Foundation's
    request for injunctive relief, the parties would still have to
    begin discovery on the counts alleging past violations.          Indeed,
    the district court held that the Foundation's complaint adequately
    alleged that ExxonMobil was or is contributing to an "imminent and
    substantial    endangerment   to    health   or   the   environment"   in
    violation of RCRA.      42 U.S.C. § 6972(a)(1)(B).       And that count
    does not even involve consideration of the permit's terms.
    In conclusion, we think the district court erred in
    granting a stay under the doctrine of primary jurisdiction until
    EPA issues a new permit for ExxonMobil's Everett terminal.
    III.     Conclusion
    For the foregoing reasons, we vacate the stay order and
    remand for proceedings not inconsistent with this opinion.         Costs
    to the appellant.
    - 28 -
    

Document Info

Docket Number: 20-1456P

Filed Date: 7/1/2021

Precedential Status: Precedential

Modified Date: 7/1/2021

Authorities (41)

basf-wyandotte-corp-v-douglas-m-costle-as-administrator-environmental , 598 F.2d 637 ( 1979 )

Student Public Interest Research Group of New Jersey, Inc. ... , 600 F. Supp. 1479 ( 1985 )

hartford-financial-systems-inc-v-florida-software-services-inc , 712 F.2d 724 ( 1983 )

cheyney-state-college-faculty-and-e-sonny-harris-and-arthur-m-bagley-and , 703 F.2d 732 ( 1983 )

Ex Parte Fahey , 332 U.S. 258 ( 1947 )

Federal Maritime Board v. Isbrandtsen Co. , 78 S. Ct. 851 ( 1958 )

New Orleans Public Service, Inc. v. Council of City of New ... , 109 S. Ct. 2506 ( 1989 )

Crystal Clear Communications, Inc. v. Southwestern Bell ... , 415 F.3d 1171 ( 2005 )

esso-standard-oil-company-puerto-rico-a-puerto-rico-corporation-v , 455 F.3d 1 ( 2006 )

34-contcasfed-cch-75252-34-contcasfed-cch-75364-united-states , 828 F.2d 1356 ( 1987 )

the-newspaper-guild-of-salem-local-105-of-the-newspaper-guild-v-ottaway , 79 F.3d 1273 ( 1996 )

The Independent Oil and Chemical Workers of Quincy, Inc. v. ... , 864 F.2d 927 ( 1988 )

United States v. James M. Culliton , 328 F.3d 1074 ( 2003 )

SPREAD SPECTRUM SCREENING LLC v. Eastman Kodak Co. , 657 F.3d 1349 ( 2011 )

National Railroad Passenger Corporation D/B/A Amtrak v. ... , 798 F.2d 8 ( 1986 )

King v. Cessna Aircraft Co. , 505 F.3d 1160 ( 2007 )

Baykeeper v. NL Industries, Inc. , 660 F.3d 686 ( 2011 )

Chico Service Station, Inc. v. Sol Puerto Rico Ltd. , 633 F.3d 20 ( 2011 )

Fmc Corporation v. Russell E. Train , 539 F.2d 973 ( 1976 )

Belize Social Development Ltd. v. Government of Belize , 668 F.3d 724 ( 2012 )

View All Authorities »