The University of Notre Dame (USA) in England v. TJAC Waterloo, LLC ( 2022 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 21-1558
    THE UNIVERSITY OF NOTRE DAME (USA) IN ENGLAND,
    Plaintiff, Appellee,
    v.
    TJAC WATERLOO, LLC; ZVI CONSTRUCTION CO., LLC,
    Defendants, Appellants.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Allison D. Burroughs, U.S. District Judge]
    Before
    Barron, Chief Judge,
    Lipez and Gelpí, Circuit Judges.
    Richard E. Briansky, with whom Amy B. Hackett and Peckar &
    Abramson, P.C. were on brief, for appellants.
    John A. Tarantino, with whom Nicole J. Benjamin and Adler
    Pollock & Sheehan, P.C. were on brief, for appellee.
    September 13, 2022
    GELPÍ,   Circuit Judge.              This is an appeal from       the
    district court's confirmation of a foreign arbitral tribunal's
    assessment   of   damages    in     a    contractual    dispute   relating   to
    construction defects.       The underlying arbitration concerns joint
    liability claims made by appellee The University of Notre Dame
    (USA) in England ("Notre Dame") against appellants TJAC Waterloo,
    LLC ("TJAC") and ZVI Construction Co., LLC ("ZVI"), respectively
    the seller and renovator of a dormitory that Notre Dame had agreed
    to purchase.      In a previous decision, we affirmed the district
    court's   confirmation      of    the    arbitrator's     liability     judgment
    against TJAC and ZVI.       See Univ. of Notre Dame (USA) in Eng. v.
    TJAC Waterloo, LLC (Notre Dame I), 
    861 F.3d 287
    , 296 (1st Cir.
    2017).     Now,    TJAC   and     ZVI    challenge     the   district   court's
    confirmation of certain damages awarded to Notre Dame, arguing
    that Notre Dame's petition for judicial confirmation of these
    awards is time-barred.           Because appellants' contentions in this
    building-defect dispute rest on shaky foundations, we affirm.
    - 2 -
    I.        Background1
    Upon purchasing from TJAC the building that ZVI had
    renovated, Notre Dame became aware of numerous defects.                        The
    ensuing dispute was submitted to arbitration, and the parties
    agreed to bifurcate the proceedings, first trying the liability
    elements   of        Notre     Dame's      breach-of-contract       claim,     and
    subsequently litigating issues of "quantum" (i.e., damages) for
    any breach found during the liability phase.               
    Id. at 290
    .
    In Notre        Dame I,       we addressed the finality of the
    arbitrator's judgment of joint liability against TJAC and ZVI
    following the conclusion of the first phase of the arbitration.
    861 F.3d at 289.      TJAC and ZVI argued that the district court erred
    in   confirming      the   arbitrator's      liability     award   because    that
    judgment -- only pertaining to the first stage of the bifurcated
    proceedings     --    lacked       the   requisite     finality    for   judicial
    confirmation      under      the    United       Nations   Convention    on   the
    Recognition and Enforcement of Foreign Arbitral Awards, June 10,
    1958, 21 U.S.T. 2517, 330 U.N.T.S. 38 (the "New York Convention").2
    1   As this is the second time a dispute                 relating to the
    underlying arbitration has made its way to this               court, see Notre
    Dame I, 861 F.3d at 287, we assume the reader's               familiarity with
    our earlier opinion, and rehearse here only the               facts and travel
    necessary to contextualize the instant appeal.
    2   The New York Convention is implemented in domestic law
    by chapter two of the Federal Arbitration Act ("FAA").     See 
    9 U.S.C. §§ 201-08
    .
    - 3 -
    Notre Dame I, 861 F.3d at 291.          We disagreed, holding that the
    same standard of finality applicable under domestic law applies to
    proceedings pursuant to the New York Convention and reiterating
    our previous determination that "a bifurcated liability judgment
    may qualify as final when the arbitrating parties have formally
    agreed to litigate liability and damages in separate, independent
    stages." Id. at 291-92 (citing Hart Surgical, Inc. v. Ultracision,
    Inc., 
    244 F.3d 231
    , 235-36 (1st Cir. 2001)).                On de novo review,
    see Cytyc Corp. v. DEKA Prods. Ltd. P'ship, 
    439 F.3d 27
    , 32 (1st
    Cir. 2006), we affirmed the district court's finding that the
    arbitrator's     liability   judgment     was      indeed    final   and     thus
    susceptible to judicial confirmation.           Notre Dame I, 861 F.3d at
    293.
    While the parties litigated judicial confirmation of the
    liability awards (issued by the arbitrator as Awards No. 1 and No.
    2),    the   arbitration   continued    to   the    quantum     phase   of   the
    proceedings. Between 2016 and 2020, the arbitrator issued a series
    of damages awards concerning various costs that stemmed from the
    breach established at the liability stage:
    •    Award No. 3 ("An Expert Determination on Quantum") -- Dated
    September 20, 2016; regarding the preliminary "Cost of Works"
    to remediate the deficiencies in the building under contract;
    no amount was awarded.
    - 4 -
    •   Award No. 4 ("An Expert Determination on Quantum") -- Dated
    April 11, 2017; regarding the final cost of works; the amount
    awarded was £1,781,048.44.
    •   Award No. 5 ("Decisions") -- Dated July 27, 2017; regarding
    certain additional and ancillary costs of work items not
    covered by Award No. 4; the amount awarded was £957,450.00.
    •   Award      No.   6   ("Expert   Determination   Award   No.   6
    (Amended)") -- Dated December 5, 2018; regarding interest due
    on Awards No. 4 and 5; the amount awarded was £328,001.37 +
    £269.52 per day (beginning on November 30, 2018).
    •   Award No. 7 ("Expert Determination Award No. 7 -- Decisions
    as to VAT") -- Dated March 31, 2020; concerning costs relating
    to the value-added tax (VAT) previously paid by Notre Dame as
    well as remaining outstanding items (e.g., expert fees and
    interest); the amount awarded was £547,699.00 + £5,040.00 +
    £65,723.00 (interest through August 1, 2018) + £60.02 per day
    (beginning on August 2, 2018).
    On May 15, 2020, Notre Dame moved for the district court
    to confirm these awards and enter summary judgment in its favor.
    TJAC and ZVI opposed the motion, arguing that Award No. 4 was, for
    purposes of judicial confirmation, final upon issuance and that
    Notre Dame's request for confirmation of Award No. 4 was thus time-
    barred.   Because the FAA provides that a party to an arbitration
    may apply for judicial confirmation "[w]ithin three years after an
    - 5 -
    arbitral award falling under the [New York] Convention is made,"
    see 
    9 U.S.C. § 207
    , and Award No. 4 was issued on April 11, 2017,
    TJAC       and    ZVI   posited    that     the   statute     of   limitations     for
    confirmation of the award expired on April 11, 2020.                     Similarly,
    TJAC and ZVI argued that Award No. 6 was partially ineligible for
    judicial         confirmation     insofar    as   it   granted     interest   on   the
    (putatively unconfirmable) Award No. 4.
    The district court disagreed, holding that Award No. 4
    was not a final award eligible for judicial confirmation upon
    issuance.         Instead, the court held that the three-year statute of
    limitations for judicial confirmation only began to run upon the
    issuance of Award No. 7 on March 31, 2020, as it was only at this
    time that the arbitrator had "issued a decision as to all th[e]
    sub-categories" of awards, and therefore arrived at a "final
    comprehensive           damages   determination"       that      "definitively     and
    comprehensively settl[ed] the parties' dispute regarding damages."
    Univ. of Notre Dame (USA) in Eng. v. TJAC Waterloo, LLC (Notre
    Dame II), No. 16-CV-10150, 
    2021 WL 2827442
    , at *3 (D. Mass. July
    7, 2021).        Accordingly, the court granted Notre Dame's request for
    judicial confirmation.3           Id. at *5.      TJAC and ZVI timely appealed.
    3  TJAC and ZVI also contested the confirmability of Award
    No. 7 on the ground that it ran afoul of the "revenue rule," which
    constrains judicial enforcement of recognition of foreign revenue
    rules. The district court rejected this argument, Notre Dame II,
    
    2021 WL 2827442
    , at *3-4, and appellants do not raise the issue on
    appeal.
    - 6 -
    II.     DISCUSSION
    A. The Finality Requirement
    We review the district court's decision to confirm Notre
    Dame's damages awards de novo.              Cytyc Corp., 
    439 F.3d at 32
    .
    Federal courts are generally loath to disturb arbitral awards,
    deferring to arbitrators if they are "even arguably construing or
    applying the contract and acting within the scope of [their]
    authority."         
    Id.
       (alteration      in    original)   (quoting     United
    Paperworkers Int'l Union v. Misco, Inc., 
    484 U.S. 29
    , 38 (1987)).
    As we have recognized, '[j]udicial review of binding arbitration
    awards is necessarily limited so as to "maintain[] arbitration's
    essential virtue of resolving disputes straightaway."'                 Farnsworth
    v. Towboat Nantucket Sound, Inc., 
    790 F.3d 90
    , 99 (1st Cir. 2015)
    (second alteration in original) (quoting Hall St. Assocs. v.
    Mattel, Inc., 
    552 U.S. 576
    , 588 (2008)).
    The FAA provides that, "[w]ithin three years after an
    arbitral award falling under the [New York] Convention is made,"
    a party may seek judicial confirmation of the award.             9 U.S.C § 207
    (emphasis added).         Appellants suggest that, because Award No. 4
    was   issued   on    April   11,    2017   and    Notre   Dame   did    not   seek
    confirmation until May 2020, the language of 
    9 U.S.C. § 207
    precludes confirmation.        But this textual argument overlooks the
    relationship between the meaning of "is made" in § 207 and the
    Convention requirement that an award be "binding" to be confirmed.
    - 7 -
    Confirmation under 
    9 U.S.C. § 207
     is mandatory unless
    "one of the grounds for refusal or deferral of recognition or
    enforcement of the award specified in the said Convention" applies.
    
    Id.
           One    such     exception     provides       that    "[r]ecognition       and
    enforcement of the award may be refused" if "[t]he award has not
    yet become binding on the parties."                    New York Convention art.
    V(1)(e).        Because    an   award    can    only    be    subject    to    judicial
    confirmation if it is binding on the parties, we do not think an
    award can be "made" under § 207 until the award is binding on the
    parties.        Interpreting "is made" to require only that a foreign
    arbitral award "is issued" by an arbitrator would permit the
    statute    of     limitations    to     run    even    where    the     "non-binding"
    exception to confirmation in Article V(1)(e) prevented the winning
    side from securing judicial confirmation of the issued award.                       See
    New York Convention art. V(1)(e).
    Our conclusion that an award "is made" within the meaning
    of 
    9 U.S.C. § 207
     when it becomes binding on the parties is
    consistent with our precedent in the context of domestic arbitral
    awards, see Hart Surgical, 
    244 F.3d at 233, 235
     (interpreting "is
    made" in 
    9 U.S.C. § 9
     to mean "is made final"), and flows directly
    from our reasoning in Notre Dame I, 861 F.3d at 291.                          There, we
    held that the New York Convention's textual requirement that a
    foreign     arbitral        award       be     "binding"        is      "conceptually
    indistinguishable" from the judicially constructed requirement
    - 8 -
    that a domestic arbitral award be "final" to be subject to judicial
    confirmation under the FAA.         861 F.3d at 291.      We observed that
    this interpretation was "in harmony with cases from outside this
    circuit that have addressed the Convention standard for judicial
    confirmation with the domestic law vocabulary," id., and cited in
    support of this equivalence the Ninth Circuit's observation that
    "[t]he not-binding defense in the Convention's Article V(1)(e) may
    be invoked when an action to confirm or enforce an arbitration
    award is filed before the award has become final," id. (citing
    Ministry of Def. & Support for the Armed Forces of the Islamic
    Republic of Iran v. Cubic Def. Sys., Inc., 
    665 F.3d 1091
    , 1100
    (9th Cir. 2011)), and district courts' equation of the requirements
    of 'binding' and 'final,' 
    id.
     (citing Ecopetrol S.A. v. Offshore
    Expl. & Prod. LLC, 
    46 F. Supp. 3d 327
    , 336 (S.D.N.Y. 2014), and
    Daum Glob. Holdings Corp. v. Ybrant Digit. Ltd., No. 13 CIV. 03135,
    
    2014 WL 896716
    ,   at   *2   (S.D.N.Y.   Feb.   20,   2014)).   The   key
    consideration in this case, therefore, is when the damages awards
    became binding on the parties.       And, as we concluded in Notre Dame
    I, it was appropriate to scrutinize foreign arbitral awards "by
    the familiar finality standard that[,] '[n]ormally, an arbitral
    award is deemed "final" provided it evidences the arbitrators'
    intention to resolve        all claims submitted in the demand for
    arbitration.'"    
    Id.
     (second alteration in original) (quoting Hart
    Surgical, 
    244 F.3d at 233
    ).
    - 9 -
    In   a    different     context,    the    Second        Circuit   in
    Seetransport Wiking Trader Schiffarhtsgesellschaft MBH & Co. v.
    Navimpex Centrala Navala, 
    989 F.2d 572
     (2d Cir. 1993), held that
    a foreign arbitral award is "made" for FAA purposes when it is
    "originally decided by the arbitrators," rather than when the
    appeals process provided by the arbitral forum state has been
    exhausted.    
    Id. at 581
     (holding that § 207's three-year statute of
    limitations was triggered by the issuance of the "final award" by
    a   French   arbitral    tribunal,    rather    than    upon    the    subsequent
    dismissal of an appeal before the Court of Appeal of Paris,
    whereupon the award "became final" as a matter of French law).
    TJAC and ZVI cite Seetransport for the proposition that
    the statute of limitations for foreign arbitral awards begins to
    run when an award is "decided by the arbitrator and issued."                    We
    see   no   daylight,    however,     between    Seetransport's        "originally
    decided by the arbitrators" test and our own intent-based approach
    to determining arbitral finality.         Indeed, the Seetransport court
    explicitly contrasted a previous "interim award issued" by the
    arbitrator (which did not trigger § 207's statute of limitations)
    with the arbitrator's "final award" (which did).               
    989 F.2d at 574
    .
    It was thus only upon issuance of the latter, which definitively
    and comprehensively resolved the claims at bar, that the award was
    "made" and "decided by the arbitrators."               
    Id. at 581
    .       As such,
    the Second Circuit deemed this decree a "final award" in much the
    - 10 -
    same way as we ordinarily understand arbitral finality -- that is,
    reflecting     the    "arbitrators'       intention   to    resolve   all   claims
    submitted in the demand for arbitration."               Notre Dame I, 861 F.3d
    at 291 (quoting Hart Surgical, 
    244 F.3d at 233
    ).4
    Having established this legal background, we now proceed
    to evaluate the parties' arguments about when the awards became
    final.
    B. The Interim Arbitral Awards Were Not Final
    On appeal, TJAC and ZVI contest the district court's
    determination that the damages awards only became final on March
    31,   2020,    at    which   time   the    arbitrator      issued   Award   No.    7,
    resolving      the    last    remaining      subcategory       of   damages       and
    "definitively and comprehensively settling the parties' dispute
    4   Moreover, our reading of Seetransport as incorporating
    an arbitral intent standard of finality is in harmony with the
    Second Circuit's jurisprudence in the domestic arbitral context.
    There, the Second Circuit held that an arbitral award that fails
    to conclusively dispose of a separate independent claim -- and is
    thus "nonfinal" as a question of arbitral intent -- does not
    trigger the one-year statute of limitations established by 
    9 U.S.C. § 9
    . See Kerr-McGee Refin. Corp. v. M/T Triumph, 
    924 F.2d 467
    ,
    471 (2d Cir. 1991) (questioning "whether the one-year limitation
    should apply to a party seeking confirmation of an award that does
    not end the arbitration, since such a rule 'will make arbitration
    more complicated, time consuming and expensive,'" but holding that
    the court "need not resolve this issue" because "the Partial Final
    Award did not finally dispose of a separate independent claim,
    thus rendering the one-year limitation inapplicable in any event"
    (citation omitted)); see also Photopaint Techs., LLC v. Smartlens
    Corp., 
    335 F.3d 152
    , 158 (2d Cir. 2003) (noting that "section
    207 . . . is analogous to section 9 of the FAA," rendering
    precedent concerning § 207 "difficult to distinguish" from cases
    concerning § 9 (citing Seetransport, 
    989 F.2d at 580-81
    )).
    - 11 -
    regarding damages."       Notre Dame II, 
    2021 WL 2827442
    , at *3.
    Appellants argue that Award No. 4 was, in fact, a final arbitral
    award, for which the FAA's three-year statute of limitations for
    judicial confirmation began to run on April 11, 2017.          Because
    Notre Dame moved for judicial confirmation on May 15, 2020,
    appellants contend that the award (and, derivatively, the portion
    of Award No. 6 granting interest on Award No. 4) is no longer
    judicially confirmable.     In support of their argument, appellants
    place great emphasis on language in Award No. 4 referring to the
    arbitrator's "final views" and stating that the "[d]eterminations
    herein served are final Quantum sums." Seizing on these two usages
    of the word "final," and suggesting that the parties intended for
    each interim damages award to be confirmable upon issuance, TJAC
    and ZVI argue that the district court erred in determining that
    the interim award was nonfinal, such that confirmation in this
    case would not be barred by the statute of limitations, because it
    did not resolve all outstanding damages claims.      On this telling,
    although various claims remained to be adjudicated when Award No.
    4 was issued, the award was sufficiently discrete and definitive
    --   and   its   "plain   language"   adequately   probative   of   the
    arbitrator's intent -- to be final upon issuance.
    Careful examination of the awards at issue leads us to
    conclude otherwise.       TJAC and ZVI first encounter a formidable
    obstacle in their attempts to evade judicial confirmation upon
    - 12 -
    confronting our circuit's well-worn finality standard, by which we
    "[n]ormally" deem an award final if it reflects the arbitrator's
    intent    to    resolve   "all   claims   submitted   in   the    demand    for
    arbitration."         Notre Dame I, 861 F.3d at 291 (alteration in
    original) (quoting Hart Surgical, 
    244 F.3d at 233
    ).              By its plain
    terms, Award No. 4 did not purport to resolve every claim submitted
    to arbitration.       Instead, Award No. 4 only addressed certain "Cost
    of Works" damages resulting from TJAC and ZVI's breach of contract,
    explicitly disclaiming a comprehensive resolution and noting that
    multiple "Heads of Claim" were "yet to be decided."              Nor did the
    various     damages    awards    correspond   to   different     findings    of
    liability at the first stage of the arbitration.                 Rather, all
    damages flowed from the same, singular liability determination on
    the breach-of-contract claim asserted by Notre Dame.             Against this
    backdrop, we proceed to assess whether TJAC and ZCI                   furnish
    sufficient reason for us to deviate from our                "general rule"
    regarding arbitral finality.        See Hart Surgical, 
    244 F.3d at 233
    .
    TJAC and ZVI's suggestion that the parties nonetheless
    agreed for the seriatim damages awards to be considered final upon
    issuance -- akin to their prior agreement to bifurcate the arbitral
    proceedings into separate and binding liability and damages phases
    -- does not suffice to surmount the hurdle posed by our finality
    standard.      Noting the district court's finding that "[w]ithin the
    damages phase, the parties asked the [arbitrator] to adjudicate
    - 13 -
    multiple damages sub-categories," Notre Dame II, 
    2021 WL 2827442
    ,
    at *3, TJAC and ZVI assert that the parties entered into a "unique
    agreement" under which the arbitrator would grant a series of
    "discrete,   final    and   confirmable   interim   awards"   during   the
    damages phase.   But TJAC and ZVI do not offer evidence that any
    such express or implied agreement ever existed, and we find none
    in the record.        The fact that the parties intended for the
    arbitrator to assess multiple types of damages flowing from the
    breach of contract, and that these damages were adjudicated in a
    piecemeal fashion, does not evidence an intention or agreement
    that the individual damage awards would be separately confirmable
    upon issuance.       There is no parallel here to the situation we
    encountered in Notre Dame I, where the parties agreed to bifurcate
    the arbitration into separate liability and damages stages.             It
    was only in light of that agreement that the arbitrator issued its
    "binding decision[] as to [l]iability."5        See Notre Dame I, 861
    F.3d at 290, 292 n.2; see also Hart Surgical, 
    244 F.3d at
    235
    5    This agreement, moreover, reflected our longstanding
    recognition of the "legitimacy of requesting bifurcation in
    foreign as well as domestic arbitral determinations" and deferring
    to the "arbitrator's understanding of finality on a bifurcated
    component" of the arbitration.    Notre Dame I, 861 F.3d at 293.
    This precedent does not support the disaggregation of a damages
    proceeding within a bifurcated arbitration into separate and
    independently final sub-proceedings.       To the contrary, our
    decision in Notre Dame I reflected an understanding that the
    quantum phase of the arbitration would consist of one "separate
    proceeding to assess damages," not multiple. Id. at 292.
    - 14 -
    (noting   that   "the     definiteness     with   which    the   parties   have
    expressed an intent to bifurcate is an important consideration" in
    determining whether an award is final).
    Just as we find no joint agreement between the parties
    regarding the finality of the interim damages awards, neither do
    we discern any such intent on the part of the arbitrator.                  TJAC
    and ZVI contrast Award No. 4's statement that the "[d]eterminations
    herein served are final Quantum sums," with language in Award No.
    3, concerning the same subcategory of damages, labeling that award
    "preliminary     views"    rather   than    a   "[f]inal   [d]etermination."
    However, appellants' entreaties to follow the arbitrator's "plain
    language" ignore the following lines in Award No. 4, which advise
    that "[t]he Awards are to be read together" and that multiple
    damages subcategories were "yet to be decided."              In other words,
    as the district court recognized, the arbitrator only viewed his
    damages determination as "comprehensive" and therefore "final"
    once all the awards had issued.            Notre Dame II, 
    2021 WL 2827442
    ,
    at *3.
    From that perspective, the arbitrator's admonition to
    read the damages awards in tandem reveals a very different picture
    of the arbitrator's intent from that depicted by TJAC and ZVI.
    Consider, for example, appellants' claim that "each Award (Nos. 4,
    5, 6 and 7) resolved separate discrete issues finally and forever,"
    being thereby "discrete, final, and confirmable" upon issuance.
    - 15 -
    In language mirroring Award No. 4, Award No. 5 states that it is
    a   "final    [d]ecision,"   according      to   which    the   arbitrator's
    "preliminary views are now amended & final."              Among the damages
    assessed in Award No. 5 was an ongoing interest award granted to
    Notre Dame, assessed at a daily rate of £117.48.                According to
    appellants'    theory   of   the   case,    this    award   was   final   and
    confirmable on July 27, 2017, the date of its issuance.              But in
    Award No. 6, issued on December 5, 2018, the arbitrator revised
    his previous interest determination from Award No. 5, reassessing
    the same ongoing interest expense to accrue at a daily net rate of
    £269.52.     The fact that the arbitrator saw fit to subsequently
    amend the damages already granted in Award No. 5 -- notwithstanding
    that the award was labeled "final," and that over sixteen months
    had elapsed in between awards -- is at odds with appellants'
    assertion that the arbitrator intended for the interim damages
    awards to "definitively and forever resolve claims between the
    parties."
    We see no evidence that the arbitrator regarded Award
    No. 4 any differently from Award No. 5.            It is, indeed, TJAC and
    ZVI's position that Awards No. 4 and 5 are of the same nature,
    each   being     sufficiently      "specific     and     discrete"   to    be
    "independently confirmable" upon issuance.             This claim, however,
    is contradicted in the arbitrator's subsequent modification of
    Award No. 5, well over a year after its initial issuance.            Read in
    - 16 -
    context          of   the    overall    seriatim       award     process,      then,    the
    arbitrator's bare use of the word "final" in these awards did not
    constitute a term of art or otherwise evince an intent to issue a
    definitive, confirmable award.6                 See Publicis Commc'n v. True N.
    Commc'ns Inc., 
    206 F.3d 725
    , 728 (7th Cir. 2000) ("The content of
    a[n] [arbitral] decision -- not its nomenclature -- determines
    finality.")            Rather, it merely indicates that the arbitrator,
    having come to an interim (and amendable) decision on one set of
    issues, intended to move on to evaluate the next subcategory of
    damages to be considered in the proceedings. As the district court
    noted, the fact that the arbitrator followed a "piecemeal approach"
    to evaluating the various damages -- all flowing from the same
    breach of contract and grouped together for apparent purposes of
    administrative convenience -- "does not . . . suggest that each
    time       the    [arbitrator]       decided     a     particular       component,      that
    decision was a final arbitral award."                      Notre Dame II, 
    2021 WL 2827442
    , at *3.
    Given      that   neither    the     parties'    conduct      during    the
    arbitration           nor   the    arbitrator's       treatment    of    the   individual
    6  By way of contrast, we further note that the arbitrator
    termed the liability award at issue in Notre Dame I a "binding
    [d]ecision" that "cannot be changed," echoing the terminology for
    arbitral finality employed by the New York Convention. See Notre
    Dame I, 861 F.3d at 293; New York Convention art. V(1)(e).     No
    comparable language can be found in the interim damages awards at
    issue.
    - 17 -
    damages award evinces an understanding that the awards at issue
    would be final upon issuance, we find the out-of-circuit caselaw
    that TJAC and ZVI recite regarding the confirmability of interim
    damages awards to be inapposite.   To be sure, as we have previously
    noted, "[s]everal circuits have recognized exceptions to th[e]
    general rule" of arbitral finality, according to which "an arbitral
    award is deemed 'final' provided it evidences the arbitrators'
    intention to resolve    all claims submitted in the demand for
    arbitration."   Hart Surgical, 
    244 F.3d at 233
     (quoting Fradella v.
    Petricca, 
    183 F.3d 17
    , 19 (1st Cir. 1999)).      We have recognized
    one such exception (announced in Hart Surgical and applied in Notre
    Dame I) that a "partial award" on liability, in a bifurcated
    proceeding agreed upon by the parties, can be final for purposes
    of judicial confirmation.    However, while our ordinary rule with
    respect to arbitral finality is not ironclad, it does not follow
    that an arbitration -- once cleaved into two stages -- can be yet
    further   fractured   into   multifarious   sub-proceedings,   each
    producing separate and immediately confirmable final awards.
    At a minimum, the cases cited by TJAC and ZVI require
    that an award "finally and definitively dispose[] of a separate
    independent claim" in order to be confirmable.   Metallgesellschaft
    A.G. v. M/V Capitan Constante, 
    790 F.2d 280
    , 283 (2d Cir. 1986);
    accord Zeiler v. Deitsch, 
    500 F.3d 157
    , 169 (2d Cir. 2007); Rocket
    Jewelry Box, Inc. v. Nobel Gift Packaging Inc., 
    157 F.3d 174
    , 176
    - 18 -
    (2d Cir. 1998); Kerr-McGee Refin. Corp. v. M/T Triumph, 
    924 F.2d 467
    , 471 (2d Cir. 1991); Ecopetrol S.A. v. Offshore Expl. & Prod.
    LLC, 
    46 F. Supp. 3d 327
    , 337 (S.D.N.Y 2014).   Moreover, given that
    judicial confirmation of interim awards constitutes an exception
    to the ordinary rule governing arbitral finality, these cases often
    involve other factors -- such as the peculiar character of the
    arbitration, express agreements between litigants, or unusually
    exigent circumstances -- that are not present here.      See, e.g.,
    Zeiler, 
    500 F.3d at 169
     (finding certain interim awards to be final
    given the "unique character of th[e] arbitration, as agreed by the
    parties"); Publicis Commc'n, 
    206 F.3d at 729
     (construing an order
    as immediately confirmable because "the order was necessary to
    prevent the final award from becoming meaningless"); see also Hall
    Steel Co. v. Metalloyd Ltd., 
    492 F. Supp. 2d 715
    , 719-20 (E.D.
    Mich. 2007) (cataloguing caselaw and tracing a "common feature" in
    many cases where "courts have found it appropriate to confirm
    interim awards," viz., "that the party seeking confirmation was
    seeking an immediate need for relief").
    As we have just explained, Award No. 4 did not "finally
    and definitively" resolve a claim, Metallgesellschaft A.G., 
    790 F.2d at 283
    , and the parties had no agreement to treat the various
    damages awards as independently final and confirmable.     Further,
    as established supra, the damages do not correspond to 'separate'
    and 'independent' claims, id., but rather all flow from the same
    - 19 -
    breach of contract established at the liability stage.                As such,
    regardless of whether there are circumstances outside of the
    bifurcated liability award context where certain interim awards
    may be immediately confirmable, we do not face such a situation
    here.
    *      *     *
    "The primary purpose served by the arbitration process
    is expeditious dispute resolution."                 Fradella, 
    183 F.3d at 19
    .
    "Arbitration loses some of its luster, though, when one party
    refuses to abide by the outcome and the courts are called in after
    all for enforcement."           Publicis Commc'n, 
    206 F.3d at 729
    .           TJAC
    and ZVI have now twice come to us in attempts to avoid judicial
    confirmation.        They urge us to deviate from our ordinary approach
    to arbitral finality, instead adopting a rule that would force
    litigants in arbitral proceedings to run to the courthouse upon
    the issuance of interim awards lest they lose their right to
    judicial confirmation.
    Nothing in the awards in question, our precedents, or
    the principles that animate our liberal approach to arbitration
    compels such an outcome.              Indeed, we have previously noted the
    risk of "creat[ing] situations at the arbitration level in which
    [a   party]    may    forfeit    an    appeal . . . by     waiting   until   all
    arbitration proceedings are complete."              Hart Surgical, 
    244 F.3d at 236
    .    Similarly, we have admonished that district courts should
    - 20 -
    not be held "open as an appellate tribunal during an ongoing
    arbitration   proceeding,    since    applications   for   interlocutory
    relief result only in a waste of time, the interruption of the
    arbitration proceeding, and . . . delaying tactics in a proceeding
    that is supposed to produce a speedy decision."             
    Id. at 233
    (quoting Michaels v. Mariform Shipping, S.A., 
    624 F.2d 411
    , 414
    (2d Cir. 1980)).      We find that Award No. 4 was not confirmable
    upon issuance, and that the three-year statute of limitations
    established by 
    9 U.S.C. § 207
     only began to run upon the issuance
    of the final arbitral award in March 2020.7      As such, Notre Dame's
    motion for judicial confirmation was not time-barred.
    III.    CONCLUSION
    Affirmed.    Costs awarded to appellee.
    7    Because we find that Notre Dame's motion for judicial
    confirmation of Award No. 4 was timely, we need not consider TJAC
    and ZVI's argument that the portion of Award No. 6 granting
    interest on Award No. 4 was time-barred.
    - 21 -