Allco Renewable Energy Ltd. v. Massachusetts Electric Co. ( 2017 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 17-1296
    ALLCO RENEWABLE ENERGY LIMITED,
    Plaintiff, Appellant,
    v.
    MASSACHUSETTS ELECTRIC COMPANY, agent of National Grid;
    ANGELA M. O'CONNOR, individually and in her official capacity as
    Chairperson of the DPU; JOLETTE A. WESTBROOK, individually and
    in her official capacity as Commissioner of the DPU;
    ROBERT HAYDEN, individually and in his official capacity as
    Commissioner of the DPU; JUDITH JUDSON, individually and in her
    official capacity as Commissioner of the MDER,
    Defendants, Appellees.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Patti B. Saris, U.S. District Judge]
    Before
    Torruella, Thompson, and Barron,
    Circuit Judges.
    Eric L. Christensen, with whom Cairncross & Hempelmann, P.S.,
    Thomas Melone, and Allco Renewable Energy Limited were on brief,
    for appellant.
    Michael Kunselman, with whom Alston & Bird LLP, Anthony J.
    Marchetta, and Day Pitney LLP were on brief, for appellee
    Massachusetts Electric Company d/b/a National Grid.
    Timothy J. Casey, Assistant Attorney General, Government
    Bureau, with whom Maura Healey, Attorney General of Massachusetts,
    was on brief, for state appellees O'Connor, Westbrook, Hayden, and
    Judson.
    November 13, 2017
    -2-
    TORRUELLA, Circuit Judge.                This case arises from the
    efforts of Allco Renewable Energy Limited ("Allco") to enforce
    section      210   of   the    Public     Utility       Regulatory    Policies    Act
    ("PURPA"), 16 U.S.C. § 824a-3, against Massachusetts Electric
    Company d/b/a National Grid ("National Grid").                   The district court
    dismissed Allco's claim against National Grid because section 210
    does   not    provide    a    private     right    of    action    against    utility
    companies     (such     as    National    Grid).         The   district   court   was
    correct, so we affirm that dismissal.                     Allco also appeals the
    district court's denial of its motion for additional relief against
    various      Massachusetts      Department        of    Public    Utilities    (MDPU)
    officials      (collectively,      the     "state        defendants")     after   the
    district      court      invalidated       certain        MDPU     regulations     as
    inconsistent with PURPA.           The district court did not abuse its
    discretion in doing so, so we affirm that decision as well.
    I.     BACKGROUND
    A.
    We begin with an overview of the statutory scheme at the
    heart of this case.          Congress passed PURPA in 1978 in response to
    the ongoing energy crisis that plagued the nation.                            FERC v.
    Mississippi, 
    456 U.S. 742
    , 745 (1982).                 Section 210 of PURPA seeks
    to lessen the United States' reliance on oil and natural gas by
    encouraging the development of energy-efficient cogeneration and
    -3-
    small power production facilities.                  
    Id. at 750
    .           See 16 U.S.C.
    § 824a-3.    "Cogeneration facilities capture otherwise-wasted heat
    and turn it into thermal energy; small power-production facilities
    produce    energy    (fewer    than    80    megawatts)        primarily      by    using
    'biomass, waste, renewable resources, geothermal resources, or any
    combination thereof.'"         Portland Gen. Elec. Co. v. FERC, 
    854 F.3d 692
    , 695 (D.C. Cir. 2017) (quoting 
    16 U.S.C. § 796
    (17)).                        Both of
    these     categories     of    facilities          are    known      as     "qualifying
    facilities" ("QFs") under PURPA.
    Congress     found      that    traditional        electric      utilities'
    reluctance to transact with these nontraditional facilities posed
    an obstacle to facilitating their development.                    FERC, 
    456 U.S. at 750
    .    It sought to address this by requiring utilities to do so.
    Thus,    section     210(a)    of    PURPA       directed      the   Federal       Energy
    Regulatory Commission ("FERC") to promulgate rules mandating that
    electric utilities purchase energy from QFs.                      16 U.S.C. § 824a-
    3(a).    Those rules, section 210(b) specified, were not to "provide
    for a rate which exceeds the incremental cost to the electric
    utility of alternative electric energy."                  Id. § 824a-3(b).          PURPA
    defines "incremental cost" as "the cost to the electric utility of
    the    electric     energy    which,   but        for    the   purchase      from    such
    cogenerator or small power producer, such utility would generate
    or purchase from another source."                Id. § 824a-3(d).         In accordance
    -4-
    with    this    directive,       FERC    promulgated       regulations      requiring
    utilities to purchase electricity from QFs "at a rate equal to the
    utility's full avoided cost."            Am. Paper Inst. v. Am. Elec. Power
    Serv.    Corp.,    
    461 U.S. 402
    ,    405-06       (1983)     (citing     18 C.F.R.
    292.304(b)(2)).          Crucially,      given    section       210's   purpose,   the
    avoided cost rate "usually exceeds the market price for wholesale
    power."    Portland Gen., 854 F.3d at 695.                  Additionally, section
    210(f)    of     PURPA    instructs      state        regulatory     authorities     to
    implement these FERC rules.               16 U.S.C. § 824a-3(f); see also
    Portland Gen., 854 F.3d at 695 ("Under PURPA, state utility
    commissions are responsible for calculating the avoided-cost rates
    for utilities subject to their jurisdiction").
    Key to this case is understanding PURPA's framework for
    enforcing its requirement that states implement FERC's PURPA-
    implementing rules.          Sections 210(g)-(h) of PURPA create "an
    overlapping scheme of federal and state judicial review of state
    regulatory action taken pursuant to PURPA."                       Greenwood ex rel.
    Estate of Greenwood v. N.H. Pub. Utils. Comm'n, 
    527 F.3d 8
    , 10 n.1
    (1st Cir. 2008).          First, PURPA allows a QF to petition FERC to
    bring an enforcement action against a state on the grounds that
    the state has failed to properly implement PURPA.                             16 U.S.C.
    § 824a-3(h).        With    respect      to     private        enforcement,    PURPA's
    enforcement      scheme    contemplates         two    types    of   private    actions
    -5-
    against   a     state   utility    regulatory    agency:      "implementation"
    challenges and "as-applied" challenges.              Exelon Wind 1, L.L.C. v.
    Nelson, 
    766 F.3d 380
    , 388 (5th Cir. 2014); Power Res. Grp., Inc.,
    v. Pub. Util. Comm'n of Tex., 
    422 F.3d 231
    , 234-35 (5th Cir. 2005).
    Implementation challenges involve claims that a state
    agency    has   failed    to   properly      implement      FERC's   regulations
    governing the purchase of energy from QFs.               Power Res. Grp., 
    422 F.3d at 235
    .       As-applied challenges, meanwhile, involve claims
    that a utility has failed to abide by a state's regulations
    implementing PURPA.       See Portland Gen., 854 F.3d at 698 (citing
    16 U.S.C. § 824a-3(g)(2)).           While federal district courts have
    exclusive jurisdiction over implementation challenges, only state
    courts may hear as-applied challenges.                Id.     Additionally, an
    individual seeking to bring an implementation challenge may only
    do so after having petitioned FERC to bring an implementation
    enforcement action, and only if FERC has not initiated an action
    within    sixty    days   of      receiving    the    petition.        16 U.S.C.
    § 824a-3(h)(2)(B).
    Finally, and crucially, PURPA's text does not make any
    reference to the possibility of a QF bringing any sort of action
    against a utility in federal court.
    -6-
    B.
    On March 28, 2011, Allco offered to sell National Grid
    the entire generation output from eleven of its solar energy
    generating QFs located in Massachusetts.                These QFs all have a
    production capacity between one and thirty megawatts.                Consistent
    with Mass. Code Regs. § 8.03(1)(b)(2), Allco offered to negotiate
    a purchase agreement with National Grid.                 On April 18, 2011,
    National Grid declined to negotiate a contract with Allco, but
    offered instead to purchase Allco's energy under its standard power
    purchase contract.       The methodology for arriving at the price rate
    in National Grid's standard contract complied with the relevant
    MDPU regulations governing that calculation.              See 220 Mass. Code
    Regs. § 8.05(2)(a).
    On August 3, 2011, Allco, pursuant to 220 Mass. Code
    Regs.   §   8.03(1)(c),     petitioned     the   MDPU    to    investigate   the
    reasonableness      of   National   Grid's    response    to    Allco's   offer.
    Allco further requested a declaration that National Grid was
    legally obligated to purchase energy from Allco's QFs for a term
    of twenty-five years, at the rate of its avoided costs, calculated
    using the rate-forecasting methodology the MDPU employed in a
    specific 2010 proceeding.           The MDPU denied that petition on
    July 22,    2014,    finding   National      Grid's   offer     to   Allco   both
    reasonable and consistent with its regulations.
    -7-
    In response, Allco petitioned the FERC to bring an
    enforcement     action     against     MDPU       on    the    grounds   that   MDPU's
    regulations clashed with PURPA.                  FERC declined to do so.         Under
    PURPA,   that    allowed      Allco    to    sue       the    MDPU.    See    16 U.S.C.
    § 824a-3(h)(2)(B).
    C.
    On October 6, 2015, Allco sued National Grid and the
    state    defendants      in   the     District         of    Massachusetts.      Allco
    contended that the MDPU regulations at issue conflicted with FERC's
    regulations implementing PURPA.              Specifically, it maintained that
    the MDPU regulations ran afoul of 18 C.F.R § 292.304(d)(2) in
    denying QFs the option of calculating the utility's avoided costs
    either "at the time of delivery" or "at the time the obligation is
    incurred."      Allco also sought a declaration that National Grid had
    a "legally enforceable obligation" to buy the output of Allco's
    QFs for a twenty-five-year term, at the rate of National Grid's
    long-term avoided costs.            Finally, Allco requested damages from
    National Grid for its lost income.                National Grid moved to dismiss
    Allco's complaint for failure to state a claim.                       Allco moved for
    summary judgment of its claims against National Grid and the state
    defendants.
    Meanwhile, at the district court's request, FERC filed
    an amicus brief.         In that brief, FERC "decline[d] to provide a
    -8-
    definitive opinion as to the specific question of whether [MDPU's]
    regulations    are   consistent     with   PURPA,     or   with   FERC's
    implementation of PURPA."     In lieu of taking a definitive stance
    on any of the questions before the court, the brief only generally
    discussed those issues in broad terms.
    The district court granted Allco's motion for summary
    judgment of its challenge to the MDPU's regulations.           It denied
    Allco's motion for summary judgment of its claim for damages and
    declaratory relief against National Grid.           Finally, it granted
    National Grid's motion to dismiss those claims.       Specifically, the
    district court concluded that Allco did not have a private cause
    of action to enforce National Grid's obligation to purchase its
    QFs' output.   Allco Renewable Energy Ltd. v. Mass. Elec. Co., 
    208 F. Supp. 3d 390
    , 395-97 (D. Mass. 2016).      The district court then
    denied Allco's motions for reconsideration and additional relief
    against the state defendants.      Allco appeals the district court's
    dismissal of its claims against National Grid and denial of further
    relief against the state defendants.
    Lastly,    after   the   district   court   struck   down   its
    regulations as inconsistent with PURPA, the MDPU initiated a
    rulemaking to satisfactorily replace those regulations.
    -9-
    II.    ALLCO'S EFFORTS TO SUE NATIONAL GRID TO ENFORCE PURPA'S
    "MUST-BUY" OBLIGATION
    Allco contends that under PURPA, National Grid has "an
    obligation to purchase all energy offered by Allco," and that it
    may sue National Grid to enforce that obligation.
    As an initial matter, section 210 of PURPA expressly
    authorizes three types of enforcement actions: (1) implementation
    challenges by FERC against states in federal court, 16 U.S.C.
    § 824a-3(h)(2)(A); (2) implementation challenges by QFs against
    states in federal court, id. § 824a-3(h)(2)(B); and (3) as-applied
    challenges by QFs against utilities in state court, id. § 824a-
    3(g).       Allco contends that section 210 also implicitly allows QFs
    to    sue    utilities   in   federal   court   to   enforce   the   must-buy
    obligation.
    Alexander v. Sandoval, 
    532 U.S. 275
     (2001), guides our
    analysis.       There, the Supreme Court held that "private rights of
    action to enforce federal law must be created by Congress."              
    Id. at 286
    .      When a statute does not contain an express private cause
    of action, courts "must interpret the statute Congress has passed
    to determine whether it displays an intent to create not just a
    private right but also a private remedy."            
    Id.
     (emphasis added).
    Statutory intent is dispositive, and "[w]ithout it, a cause of
    action does not exist and courts may not create one, no matter how
    desirable that might be as a policy matter, or how compatible with
    -10-
    the statute."       
    Id. at 286-87
    .    In other words "a private right of
    action under federal law is not created by mere implication, but
    must be 'unambiguously conferred.'"                Armstrong v. Exceptional
    Child Center, Inc., 
    135 S. Ct. 1378
    , 1387-88 (2015) (plurality
    opinion) (quoting Gonzaga Univ. v. Doe, 
    536 U.S. 273
    , 283 (2002)).
    Additionally, certain factors cut against finding an
    implied private cause of action in a given statute, such as the
    existence of other express enforcement provisions.                The Court in
    Sandoval explained that the "express provision of one method of
    enforcing a substantive rule suggests that Congress intended to
    preclude others."         
    532 U.S. at 290
    .       Indeed, "[s]ometimes [that]
    suggestion     is    so    strong   that    it    precludes   a   finding   of
    congressional intent to create a private right of action, even
    though other aspects of the statute . . . suggest the contrary."
    
    Id.
     (citation omitted); see also Bonano v. East Caribbean Airline
    Corp., 
    365 F.3d 81
    , 85 (1st Cir. 2004) (holding that Congress's
    express provision of a solitary private right of action under the
    Federal Aviation Act weighed against finding additional implied
    rights).     This is doubly so when a statute's express enforcement
    scheme is complex, and when agencies play a role in enforcing the
    statute.     See Armstrong, 
    135 S. Ct. at 1385
     (2015) ("The sheer
    complexity associated with enforcing § 30(A), coupled with the
    express provision of an administrative remedy . . . shows that the
    -11-
    Medicaid Act precludes private enforcement of § 30(A) in the
    courts.").
    Allco, therefore, faces an uphill battle in asserting
    that section 210 implicitly provides a private right of action
    apart from the enforcement mechanisms it expressly contemplates.
    Nonetheless, Allco makes copious arguments to the effect that
    Congress must have intended to give QFs a right to enforce PURPA's
    "must-buy" obligation against utility companies.    We consider its
    principal arguments in turn.
    First, Allco points to the Supreme Court's comment in
    FERC v. Mississippi that states may satisfy their obligations under
    section 210 of PURPA, among other ways, "by resolving disputes on
    a case-by-case basis."      
    456 U.S. at 751
    .     This language, it
    furthers, implicitly recognized a private right of action against
    utilities.
    It is difficult to see how recognizing that states may
    resolve disputes on a case-by-case basis amounts to recognizing a
    private right of action against a utility in federal court.      As
    National Grid suggests, it makes most sense to understand that
    language as referring to state court adjudication of as-applied
    challenges.     In any event, this line cannot suffice to satisfy
    Sandoval's demand for indicia of Congressional intent to create a
    private right.
    -12-
    Second, Allco, citing Transamerica Mortgage Advisors,
    Inc. v. Lewis, 
    444 U.S. 11
    , 19 (1979), argues that when Congress
    "addresses contract-like rights . . . it intends the customary
    legal incidents attendant to those rights to be available[,]
    including suit."   Thus, because PURPA obligates National Grid to
    purchase energy from Allco's QFs, Congress must have intended to
    give QFs the means of enforcing that contract-like obligation.
    However,   Transamerica's   holding     only   addressed   Congressional
    declarations that "certain contracts are void," in which case "the
    customary legal incidents of voidness would follow."          
    Id.
       Yet,
    Allco avers that the Second and Ninth circuits have extended
    Transamerica beyond the context of voidness.            See First Pac.
    Bancorp, Inc. v. Helfer, 
    224 F.3d 1117
    , 1123 (9th Cir. 2000);
    Oneida Indian Nation v. Cty. of Oneida, 
    719 F.2d 525
    , 535 (2d Cir.
    1983).
    But, this argument is unavailing because no contract
    exists between Allco and National Grid.        Section 210 of PURPA does
    not create a contract.      Rather, it merely creates an obligation
    to enter into a contract at a regulation-specified cost rate.
    Here, Allco and National Grid never agreed upon a cost rate, nor
    has any regulation or court set that rate.       Indeed, Allco does not
    allege breach of contract, not could it, given that no contract
    exists.    Unlike in the cases Allco cites, this case does not
    -13-
    involve a contract or other enforceable obligation from which any
    "customary legal incidents" could follow.
    Third,    Allco    highlights     that   section      210   of    PURPA
    contains "rights-creating language," in addition to an intent to
    confer those rights on a specific class of persons. Nothing, it
    furthers, indicates that Congress intended to leave those rights
    unenforceable.       However, Allco inverts the proper analysis.                We
    don't   look   for   indicia    that    Congress     meant   to   leave      rights
    unenforceable.       Rather, a right of action only exists where
    Congress has clearly intended one.             Sandoval, 
    532 U.S. at 286
    .
    Further, while rights-creating language is a necessary condition
    to finding a private remedy, it is alone insufficient to support
    an implied remedy.       Bonano, 
    365 F.3d at
    84 (citing Gonzaga, 
    536 U.S. at 283-84
    ). Also relevantly, the court in Sandoval considered
    the case of language of this sort.            It indicated that the notion
    that Congress typically provides an express remedy at the exclusion
    of all others can even overcome language "making the would-be
    plaintiff a member of the class for whose benefit the statute was
    enacted."      Sandoval, 
    532 U.S. at 290
     (internal quotation marks
    omitted).
    Thus, Allco fails to show that Congress, by way of
    section 210's rights-creating language, intended to create an
    additional remedy to those it established expressly.
    -14-
    Fourth, Allco argues that the district court's failure
    to find a private federal cause of action against utilities places
    QFs with a capacity of over 30MW (which Allco's are not) in a "no
    man's land" where they have no remedy.           Congress, it argues, could
    not have intended this result.            Allco bases this argument on
    subsection 210(h)(1)'s provision that            subsection 210(g)'s state
    court adjudication process does not apply to the "operations" of
    QFs that are subject to FERC jurisdiction under part II of the
    Federal Power Act (FPA).        This includes QFs with a production
    capacity of greater than 30MW.      
    18 C.F.R. § 292.601
    (b).
    But, as National Grid correctly highlights, subsection
    210(h)(1)   specifically    provides      that    in   cases    of    regulatory
    overlap between PURPA and the FPA, the challenged PURPA regulation
    "shall be treated as a rule under the [FPA]."              As a result, the
    FPA's   enforcement   scheme    would     be   available       to    QFs   with   a
    production capacity of greater than 30MW.               Under the FPA, any
    person may file a complaint with FERC, 
    18 C.F.R. § 385.206
    (a), and
    FERC's decision is subject to judicial review in the D.C. Circuit,
    16 U.S.C. § 825l(b).    This is far from the remedy-less "no man's
    land" that Allco alleges.      In fact, the very case that Allco relies
    on in making this argument describes the process by which QFs with
    a production capacity of greater than 30MW may obtain judicial
    -15-
    review of PURPA regulations that overlap with FPA regulations.
    See Portland Gen., 854 F.3d at 697-700.
    Fifth, Allco maintains that failing to find a private
    remedy against National Grid leaves it stranded in another "no
    man's land," where it must "wait and hope that the MDPU takes some
    action that would be compliant with PURPA."
    Allco overstates the irregularity and gravity of this
    situation.    The district court entered its order invalidating the
    MDPU's regulations on September 23, 2016.             In response, the MDPU
    commenced a rulemaking on March 21, 2017 to promulgate PURPA-
    compliant regulations.          The MDPU sought public comment until
    April 28, 2017.         Allco's eagerness for the MDPU to conclude this
    process so that it may enter into a contract with National Grid
    under the resulting PURPA-compliant regulations is understandable.
    Yet, waiting for the MDPU to promulgate those regulations does not
    quite amount to a "no man's land."              Allco's rhetorical flourish
    ignores the mundane and commonplace nature of waiting for an agency
    to conclude a rulemaking process.           Indeed, at any given moment,
    countless men (among others) can be found in this land of awaiting
    finalized agency rules.         Allco's temporary visit there does not
    show that Congress meant to give it a private right under PURPA.
    As   the    MDPU   points   out,    as   soon   as   it   finishes
    promulgating the regulations in question, Allco is free to submit
    -16-
    an offer to National Grid to purchase its generation output.                If
    the parties fail to reach an agreement within ninety days, and
    Allco believes that National Grid has acted unreasonably, then it
    may file a petition with the MDPU under 220 Mass. Code Regs.
    § 8.03(1)(c).    Allco could then challenge any resulting adverse
    MDPU decision in state court.              
    Mass. Gen. Laws ch. 25, § 5
    .
    Moreover, if Allco comes to believe that the MDPU's new rule
    violates PURPA, it will be able to petition FERC to bring an
    implementation    challenge.         See   16   U.S.C.   §   824a-3(h)(2)(B).
    Should FERC decline that invitation, Allco could itself bring an
    implementation challenge.      Id.     If Allco believes that the MDPU's
    regulations violate PURPA as applied to its dealings with National
    Grid, it will be able to bring an as-applied challenge in state
    court.1   Id. at § 824a-3(g).
    In other words, the "no man's land" in which Allco
    purports to find itself is illusory.            And again, even were it not,
    that   would   still   fall   well    short     of   showing   that   Congress
    unequivocally conferred upon QFs a private right of action against
    utilities to enforce PURPA's must-buy provision.
    1  Additionally, to the extent that Allco accuses the MDPU of
    sitting on its hands or otherwise not acting with sufficient
    diligence in promulgating the regulations in question, the proper
    remedy would still not be to sue National Grid.
    -17-
    Allco's last set of arguments all involve the FPA.             In
    brief, Allco maintains that it enjoys a private right of action
    both under section 210(h)(1) of PURPA -- which, it says, makes the
    must-buy obligation privately enforceable as a rule under the FPA
    -- and independently under sections 205-06 of the FPA, 16 U.S.C.
    §§ 824d, 824e.
    Section 210(h)(1) of PURPA provides that:
    For purposes of enforcement of any rule prescribed by
    the Commission under subsection (a) of this section
    with respect to any operations of an electric utility
    [or a QF] which are subject to the jurisdiction of
    the Commission under part II of the Federal Power Act,
    such rule shall be treated as a rule under the Federal
    Power Act. Nothing in subsection (g) of this section
    shall apply to so much of the operations of an
    electric utility, a qualifying cogeneration facility
    or a qualifying small power production facility as
    are subject to the jurisdiction of the Commission
    under part II of the Federal Power Act.
    16 U.S.C. § 824a-3(h)(1) (citations omitted).          Subsection (h)(1)
    therefore accomplishes two things.            First, it channels FERC's
    enforcement of a certain subset of rules that it has promulgated
    pursuant   to    PURPA   --   specifically,    those   pertaining   to    QF
    operations subject to FERC's jurisdiction under part II of the
    Federal Power Act -- into the FPA's enforcement scheme.                  See
    Portland Gen., 854 F.3d at 699.        Second, subsection (h)(1) also
    prevents QFs from bringing as-applied challenges involving FERC
    rules of that sort.
    -18-
    Part II of the FPA pertains only to "the transmission of
    electric energy in interstate commerce and to the sale of electric
    energy     at    wholesale   in   interstate     commerce."       
    16 U.S.C. § 824
    (b)(1); see also Portland Gen., 854 F.3d at 697.            Even if we
    assume that FERC's rules regarding the must-buy obligation are
    rules regarding the operations of QFs subject to part II of the
    FPA, that would only make those rules enforceable as rules under
    the FPA.        The question would then become whether the FPA gives
    Allco a private right of action to enforce those rules against
    National Grid.      Accordingly, this argument collapses into Allco's
    separate contention that the FPA independently gives it a right to
    enforce PURPA's must-buy obligation against National Grid.               We
    thus need not reach Allco's argument that its potential sales to
    National Grid would be subject to regulatory overlap with the FPA
    because, even assuming that were correct, its contention that the
    FPA would provide it with a private right of action against
    National Grid fails.
    Turning to that argument that the FPA allows Allco to
    sue National Grid, we first note that the FPA's text does not
    explicitly confer a private right of action.                  See 16 U.S.C.
    §§ 824d,    824e.      Furthermore,   we   see   nothing   in    that   text
    indicating that Congress meant to confer such a right, much less
    unambiguously.       We also note that Allco does not cite any cases
    -19-
    holding that the FPA contains a private right against a utility.
    The same is true of the FPA's sister statute, the Natural Gas Act
    (NGA), 
    15 U.S.C. § 717
     et seq., which courts interpret in parallel
    to the FPA,   Ark. La. Gas Co. v. Hall, 
    453 U.S. 571
    , 577 n.7 (1981)
    (noting that because the FPA and the NGA "are in all material
    respects substantially identical," the Supreme Court has developed
    an   "established   practice   of   citing   interchangeably   decisions
    interpreting the pertinent sections of the two statutes" (quoting
    FPC v. Sierra Pac. Power Co., 
    350 U.S. 348
    , 353 (1956))).
    Moreover, a number of courts have concluded that the NGA
    does not contain such a right.        See Great Lakes Gas Transmission
    Ltd. P'ship v. Essar Steel Minn. LLC, 
    843 F.3d 325
    , 329-30 (8th
    Cir. 2016); Columbia Gas Transmission, LLC v. Singh, 
    707 F.3d 583
    ,
    587 (6th Cir. 2013); Clark v. Gulf Oil Corp., 
    570 F.2d 1138
    , 1150
    (3d Cir. 1977).     We agree with them, and thus conclude that the
    FPA does not provide a private right either.         We are especially
    comfortable with this conclusion given the elaborate framework for
    FERC enforcement that section 206 of the FPA does expressly set
    out.    See 16 U.S.C. §§ 824m-p.           Therefore, because the FPA
    resoundingly does not confer a private right, it is of no help to
    Allco in its search for a private right to enforce PURPA's must-
    buy obligation against National Grid.
    -20-
    To   wrap    up,   none    of   Allco's   arguments    about    PURPA
    overcome two fundamental truths about that statute: (1) its text
    does not expressly provide for private enforcement of that sort;
    and   (2)    its    text    does   expressly      provide    for    an   intricate
    enforcement framework, involving both FERC and private litigants,
    in state and federal court.             Allco's assertion that the FPA gives
    it a private right against National Grid is similarly unavailing.
    The district court therefore correctly granted National Grid's
    motion to dismiss because PURPA does not give Allco a private right
    of action against National Grid.
    III.      ALLCO'S EFFORTS TO OBTAIN ADDITIONAL RELIEF AGAINST THE
    STATE DEFENDANTS
    We now consider Allco's contention that the district
    court should have gone beyond simply invalidating the MDPU's
    regulations,       and     calculated     National      Grid's   avoided     costs.
    "Judgment calls, including the lower court's choice of equitable
    remedies, are afforded substantial deference and will be disturbed
    only if the court has made a significantly mistaken judgment."
    Watchtower Bible & Tract Soc'y of N.Y., Inc. v. Municipality of
    San Juan, 
    773 F.3d 1
    , 7 (1st Cir. 2014) (citing Rosario-Torres v.
    Hernández-Colón, 
    889 F.2d 314
    , 323 (1st Cir. 1989) (en banc)).
    The state defendants argue that we lack jurisdiction to
    decide this issue because Allco seeks to challenge a judgment that
    was in its favorable.            However, Allco is not merely trying to
    -21-
    procure appellate review of statements or findings contained in a
    judgment in its favor, as was true in the case on which the state
    defendants rely.   See Elkin v. Metro. Prop. & Cas. Ins. Co. (In
    re Shkolnikov), 
    470 F.3d 22
    , 24 (1st Cir. 2006).      Rather, Allco
    seeks review of what it alleges was an adverse judgment with
    respect to the relief granted, and it specifically appeals not
    only from the final judgment below, but also from the district
    court's order denying further relief.
    Allco argues that the district court, in addition to
    invalidating the MDPU's regulations, should have itself undertaken
    calculating National Grid's avoided cost rate.    It highlights that
    PURPA authorizes district courts hearing implementation challenges
    to "issue such injunctive or other relief as may be appropriate."
    16 U.S.C. § 824a-3(h)(2)(B).   Arriving at that calculation, Allco
    contends, is no different than calculating damages that require
    forecasts, something courts regularly do.   Were the district court
    nonetheless reluctant to do so itself, says Allco, it should have
    appointed a special master for the task, or passed the question to
    FERC pursuant to primary jurisdiction doctrine.
    The district court, in declining to "engage in fact-
    finding to determine the proper avoided cost rate," observed that
    "[n]othing in the statutory scheme provides this Court with rate-
    making authority, and it lacks the expertise to do so."       Allco
    -22-
    Renewable Energy Ltd., 208 F. Supp. 3d at 401 (D. Mass. 2016).
    "Rather," it added, "the MDPU has the statutory authority to
    revisit its implementation of FERC's rules, either through a new
    rulemaking,       a    case-by-case   adjudication,     or   other    reasonable
    method."     Id.       The district court is correct.         Because section
    210 of PURPA generally contemplates state agencies implementing
    FERC's     rules      for   determining   avoided   cost     rates,    16 U.S.C.
    § 824a-3(b), (f), the district court certainly did not abuse its
    discretion in leaving that calculation to the MDPU.
    Nor does the primary jurisdiction doctrine provide any
    indication that the district court abused its discretion.                     "The
    doctrine     of       primary   jurisdiction   is   a   prudential     doctrine
    developed by the federal courts to promote accurate decisionmaking
    and regulatory consistency in areas of agency expertise."                 Ass'n
    of Int'l Auto. Mfrs., Inc. v. Mass. Dep't of Envtl. Prot., 
    196 F.3d 302
    , 304 (1st Cir. 1999).            Under that doctrine, if a court
    determines that an issue falls within the primary jurisdiction of
    an agency, the court may refer the issue to that agency and defer
    any decision until the agency has come to a conclusion.                 
    Id.
        We
    have also remarked that when it would otherwise be appropriate to
    stay proceedings and submit a question to an agency, requesting an
    amicus brief from that agency may represent a "more efficient and
    -23-
    expeditious alternative."        Distrigas of Mass. Corp. v. Bos. Gas
    Co., 
    693 F.2d 1113
    , 1119 (1st Cir. 1982).
    Here,    given   that   state   agencies,     not   FERC,      are
    responsible     for   implementing     FERC's     rules   with   respect     to
    determining specific avoided cost rates, it is far from clear that
    this question falls within FERC's "primary jurisdiction" to begin
    with.     Even setting that aside, it is significant that the district
    court solicited an amicus brief from FERC, and that in that amicus
    brief, FERC declined to provide a specific contract rate.                  This
    further cements our conclusion that the district court did not
    abuse its discretion in limiting itself to invalidating the MDPU
    regulations at issue.
    IV.    CONCLUSION
    Allco fails to show that the district court erred in
    dismissing its claims against National Grid, because it lacks a
    private right against National Grid.            So too does Allco fail to
    show that the district court abused its discretion in limiting the
    relief it granted against the state defendants.             Accordingly, we
    affirm.
    Affirmed.
    -24-