Commerical v. Gilbane ( 1993 )


Menu:
  • USCA1 Opinion












    United States Court of Appeals
    United States Court of Appeals
    For the First Circuit
    For the First Circuit
    ____________________

    No. 92-1904

    COMMERCIAL UNION INSURANCE COMPANY,

    Plaintiff, Appellant,

    v.

    GILBANE BUILDING COMPANY,

    Defendant, Appellee.

    ____________________

    APPEAL FROM THE UNITED STATES DISTRICT COURT

    FOR THE DISTRICT OF MASSACHUSETTS

    [Judge Edward F. Harrington, U.S. District Judge]

    ____________________

    Before

    Torruella, Circuit Judge,
    _____________
    Bownes, Senior Circuit Judge,
    ____________________
    and Stahl, Circuit Judge.
    _____________

    ____________________

    Michael P. Duffy, with whom Bert J. Capone, John J. O'Connor, and
    ________________ ______________ ________________
    Peabody & Arnold, were on brief for appellant.
    ________________
    Peter B. Krupp, with whom Thomas R. Murtagh, Joseph P. Crawford-
    ______________ _________________ ____________________
    Kelly, and Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C., were
    _____ _____________________________________________________
    on brief for appellee.


    ____________________

    May 11, 1993
    ___________________





















    STAHL, Circuit Judge. In this appeal, plaintiff-
    ______________

    appellant Commercial Union Insurance Company ("CU")

    challenges the district court's summary denial of its motion

    to stay defendant-appellee Gilbane Building Company's

    ("Gilbane") counterclaim pending arbitration. Finding error

    in the district court's decision, we reverse.

    I.
    I.
    __

    Factual Background
    Factual Background
    __________________

    During the latter half of the 1980's, Gilbane, a

    general contractor, entered into thirteen subcontracts with

    Thames Valley Steel Corporation ("TVS"), a structural steel

    subcontractor, under which TVS agreed to perform structural

    steel work for Gilbane on thirteen separate construction

    projects in Massachusetts and Rhode Island. On each project,

    CU acted as surety for TVS, issuing various performance,

    labor, and material bonds guarantying TVS's proper completion

    of its obligations. As such, each of the thirteen

    construction projects was governed by at least three

    contracts: (1) the prime contract between Gilbane and the

    individual owner; (2) the subcontract between Gilbane and

    TVS; and (3) CU's performance bond.

    In 1990, TVS ceased doing business and, as a

    result, defaulted on its obligations under each of the

    thirteen subcontracts. Disputes then arose between CU and

    Gilbane concerning CU's obligations as the guarantor of TVS'



    -2-
    2















    performance on these projects. On August 16, 1991, CU

    commenced this diversity action against Gilbane alleging that

    Gilbane wrongfully withheld contract balances owed CU in

    connection with the completion of the first twelve

    construction projects. In its answer, Gilbane denied CU's

    allegations and also brought a two-count counterclaim. In

    Count I of its counterclaim, Gilbane alleged that, in

    relation to the thirteenth construction project, TVS breached

    the terms of its subcontract by failing to perform in a good

    and workmanlike manner, and that CU breached the terms of its

    performance bond by failing to correct TVS' work. In Count

    II, Gilbane charged that CU committed unfair and deceptive

    trade practices in violation of Mass. Gen. Laws Ann. ch. 93A,

    2 and 11 (West 1984 and Supp. 1992) (hereinafter referred

    to simply as "ch. 93A"), and unfair claim settlement

    practices in violation of Mass. Gen. Laws Ann. ch. 176D,

    3(9) (West 1987 and Supp. 1992), by failing "to effectuate a

    prompt, fair and equitable settlement of Gilbane's claims . .

    . ."

    In response to Gilbane's counterclaim, CU filed a

    reply denying any liability in connection with the thirteenth

    project and amended its complaint to add a count alleging

    that Gilbane committed unfair and deceptive trade practices

    in violation of ch. 93A by withholding an undisputed amount

    "solely in order to gain leverage with respect to a dispute



    -3-
    3















    arising in connection with a different project." At that

    time, CU also filed a third-party complaint against L.

    Antonelli Iron Works and The Thompson and Lichter Company,

    Inc., both of whom had entered into subcontracts with TVS to

    perform certain services in connection with the thirteenth

    construction project. In that complaint, CU alleged that the

    third-party defendants were liable to CU for any amounts

    Gilbane might recover against CU on Count I of its

    counterclaim.

    On November 6, 1991, CU filed the instant motion to

    stay Gilbane's counterclaim pending arbitration, arguing that

    the counterclaim was subject to an express arbitration

    agreement.1 Gilbane opposed the motion to stay, contending

    that the counterclaim was not subject to an arbitration

    agreement, and in the alternative, that CU had waived its

    right to arbitrate by filing the instant lawsuit. On May 18,

    1992, the district court entered a margin order denying CU's

    motion to stay. CU appeals from that decision.

    II.
    II.
    ___



    ____________________

    1. We think it important to emphasize that Count I of the
    counterclaim concerns only the thirteenth construction
    project. The other twelve projects, which are the basis for
    the complaint by CU against Gilbane, are not implicated in
    the counterclaim. The counterclaim, therefore, can be viewed
    as separate and distinct from the complaint brought by CU
    against Gilbane. Neither party has suggested that the
    dispute as to the twelve other construction projects, which
    form the basis for CU's complaint, be submitted to
    arbitration.

    -4-
    4















    Discussion
    Discussion
    __________

    Although not raised by the parties, we first

    explain the basis of our appellate jurisdiction. Section 3

    of the Federal Arbitration Act ("FAA") contains a procedure

    by which parties to an arbitration agreement may file a

    motion to stay the trial of arbitrable claims pending

    arbitration. See 9 U.S.C.A. 3 (West 1970). Pursuant to
    ___

    that section of the statute, a district court must grant the

    stay "upon being satisfied that the issue involved . . . is

    referable to arbitration under such an agreement . . . ."

    The FAA further provides that "[a]n appeal may be taken from

    . . . an order . . . refusing a stay under section 3 of this

    title . . . ." 9 U.S.C.A. 16(a)(1)(A) (West Supp. 1992).

    As CU is appealing from a denial of a motion to stay under

    section 3 of the FAA, we therefore have appellate

    jurisdiction.

    A. Arbitrability
    A. Arbitrability
    _________________

    The arbitrability of this dispute turns on the

    interpretation of contractual terms, a question of law which

    we can determine in the first instance. See, e.g., Fashion
    ___ ____ _______

    House, Inc. v. K Mart Corp., 892 F.2d 1076, 1083 (1st Cir.
    ___________ ____________

    1989).

    1. Relevant Contract Language
    1. Relevant Contract Language
    ______________________________

    Gilbane's counterclaim is based upon CU's alleged

    breach of its performance bond on the thirteenth project



    -5-
    5















    ("the Performance Bond"). Thus, the arbitrability of this

    counterclaim depends upon whether there is language in that

    contract subjecting disputes between Gilbane and CU to

    arbitration.

    Although the Performance Bond has no language

    dealing with arbitration, it does contain a clause

    incorporating the subcontract between Gilbane and TVS ("the

    Subcontract"), which, in turn, has a clause incorporating the

    prime contract between Gilbane and the owner of the

    thirteenth project ("the Prime Contract"). It is the Prime

    Contract that contains the arbitration clause. That clause

    reads as follows:

    All claims, disputes and other
    matters in question arising out of, or
    relating to this Agreement or the breach
    thereof, . . . shall be decided by
    arbitration in accordance with the
    Construction Industry Arbitration Rules
    of the American Arbitration Association
    then obtaining unless the parties
    mutually agree otherwise. This agreement
    to arbitrate shall be specifically
    enforceable under the prevailing
    arbitration law by a three-member panel.

    The Subcontract, which was drafted by Gilbane,

    contains a clause incorporating certain provisions of the

    Prime Contract:

    [Gilbane] shall be bound to [TVS] by
    the terms of this agre[e]ment, to the
    extent that the provisions of the
    contract documents between the owner and
    [Gilbane] apply to the work of [TVS] as
    defined in this agreement[.] [Gilbane]
    shall assume toward [TVS] all the


    -6-
    6















    obligations and responsibilities that the
    owner, by those documents, assumes toward
    [Gilbane]. [Gilbane] shall have the
    benefit of all rights, remedies, and
    redress against [TVS] which the owner, by
    those documents, has against [Gilbane]. .
    . .2

    Finally, the Performance Bond has a clause

    incorporating the Subcontract by reference: "Whereas, [TVS]

    has by written agreement . . . entered into a [S]ubcontract

    with [Gilbane] . . . which [S]ubcontract is by reference made

    a part hereof . . . ."

    2. Relevant Law
    2. Relevant Law
    ________________

    In deciding whether a chain of incorporation

    rendering Gilbane's counterclaim arbitrable exists within

    these three contracts, we are mindful of the strong federal

    policy favoring arbitration agreements, a policy which

    requires us to resolve "any doubts" concerning arbitrability

    in favor of arbitration. See Moses H. Cone Memorial Hosp. v.
    ___ ____________________________

    Mercury Constr. Corp., 460 U.S. 1, 24-25 (1983). See also J
    _____________________ ___ ____ _

    & S Constr. Co., Inc. v. Travelers Indem. Co., 520 F.2d 809,
    ______________________ ____________________

    810 (1st Cir. 1975) (construing incorporation language in a

    subcontract broadly in light of "the policy favoring

    arbitration"). This policy applies "whether the problem at

    hand is the construction of the contract language itself or


    ____________________

    2. The subcontract defines "contract documents" to include
    "the agreement between the owner and [Gilbane], the
    conditions of the agreement between the owner and [Gilbane],
    general conditions, supplementary, special and other
    conditions . . . ."

    -7-
    7















    an allegation of waiver, delay, or a like defense to

    arbitrability." Moses H. Cone, 460 U.S. at 25.
    _____________

    In a remarkably similar case, the Sixth Circuit

    held that a chain of incorporation running through a prime

    contract, a subcontract, and a performance bond rendered

    disputes under the performance bond subject to the prime

    contract's arbitration clause. Exchange Mut. Ins. Co. v.
    _______________________

    Haskell Co., 742 F.2d 274, 275-76 (6th Cir. 1984). Like the
    ___________

    Performance Bond at issue here, the bond in that case did not

    itself contain an arbitration clause. Rather, the bond in

    Haskell incorporated the subcontract by reference, (employing
    _______

    incorporation language almost identical to that involved

    here), which, in turn, incorporated the prime contract by

    reference. Id. The incorporation clause in that subcontract
    ___

    read as follows: "Subcontractor hereby assumes the same

    obligations and responsibilities with respect to his

    performance under this Subcontract, that Contractor assumes

    towards Owner with respect to his performance on the [prime]

    [c]ontract." Id. at 275. The prime contract in Haskell
    ___ _______

    contained an arbitration provision almost identical to that

    in the Prime Contract at issue here. Id.
    ___

    Without reference to the federal policy requiring

    it to construe any doubts in favor of arbitrability, the

    Sixth Circuit nevertheless reasoned that the incorporation





    -8-
    8















    language in the performance bond and subcontract was broad

    enough to include the prime contract's arbitration agreement:

    Here, the performance bond
    specifically referred to and incorporated
    the subcontract. The subcontract
    provides that the same obligations and
    responsibilities apply in the subcontract
    as apply in the [prime] contract. And,
    finally, the [prime] contract provides
    that there is a duty to arbitrate. Thus,
    the performance bond incorporates by
    reference the subcontract, the
    subcontract incorporates by reference the
    [prime] contract[,] and hence[,] the duty
    to arbitrate.

    Id. at 276 (relying on J & S Constr., 520 F.2d at 810).
    ___ _____________

    If anything, the language in the Subcontract

    incorporating the terms of the Prime Contract is even broader

    than that in the Haskell subcontract. The Subcontract
    _______

    provides that, to the extent the Prime Contract (with all its

    attendant conditions) applies to the work of TVS, Gilbane

    "shall assume toward [TVS] all the obligations and
    ___

    responsibilities" that the owner assumed toward Gilbane under

    the Prime Contract. (Emphasis added). The Subcontract

    further states that "[Gilbane] shall have the benefit of all

    rights, remedies, and redress against [TVS] which the owner,

    by [the contract documents], has against [Gilbane]." The

    parties do not dispute that one of the obligations which

    Gilbane assumed toward the owner under the Prime Contract was

    to submit all disputes arising out of the contract to

    arbitration. Nor do they dispute that the bundle of "rights,



    -9-
    9















    remedies, and redress" given the owner under the Prime

    Contract included the right to submit all claims relating to

    that contract to arbitration. Accordingly, we find that the

    Subcontract bound Gilbane to arbitrate disputes relating to

    the work of TVS.3 Because the Performance Bond explicitly

    incorporated by reference the terms of the Subcontract, we

    further find that Gilbane and CU similarly bound themselves

    to submit disputes arising under the Performance Bond to









    ____________________

    3. In support of its contention that the language in the
    Subcontract should be read narrowly, Gilbane points to the
    clause in that contract expressly granting Gilbane "the
    benefits of all rights, remedies, and redress against [TVS]
    which the owner, by [the Prime Contract], has against
    [Gilbane]." Because the Subcontract does not contain a
    parallel clause expressly granting TVS "the benefit of all
    rights, remedies, and redress" under the Prime Contract,
    Gilbane contends that the parties did not intend for TVS to
    have the same right to subject disputes under this contract
    to arbitration. We do not agree.
    First, this argument ignores the immediately preceding
    clause which states that Gilbane "shall assume toward [TVS]
    all the obligations and responsibilities that the owner, by
    [the Prime Contract], has against [Gilbane]." As explained
    above, we interpret this clause to impose upon Gilbane the
    duty to arbitrate "all disputes relating to [the Prime
    Contract]," an obligation assumed by the owner under the
    Prime Contract. Second, adopting Gilbane's cramped reading
    of this language would run counter to the clearly enunciated
    federal policy of interpreting "any doubts" in contractual
    language in favor of arbitration. Moses H. Cone, 460 U.S. at
    _____________
    24-25. Finally, because Gilbane drafted the subcontract, we
    construe any ambiguities in that contract against it. See,
    ___
    e.g., LFC Lessors, Inc. v. Pacific Sewer Maintenance Corp.,
    ____ __________________ ________________________________
    739 F.2d 4, 7 (1st Cir. 1984).

    -10-
    10















    arbitration. To the extent that the district court held

    otherwise, we reverse.4



    B. Waiver
    B. Waiver
    __________

    Gilbane alternatively contends that, even if the

    counterclaim is arbitrable, CU waived its right to arbitrate

    that claim based upon its pretrial participation in this

    lawsuit. This contention we find meritless.

    In deciding this issue, we first discuss the

    appropriate standard of review. As the district court

    decided the arbitrability question by margin order, we have

    no predicate factual findings to review. In fact, it is

    possible that the district court did not reach the question

    of waiver but decided against CU solely on the basis of its



    ____________________

    4. To support its position that the district court's refusal
    to grant the stay was correct, Gilbane relies upon a series
    of cases which, it asserts, stand for the proposition that
    prime contract provisions unrelated to the work of the
    subcontractor are not incorporated by reference into a
    subcontract. See Washington Metro. Area Transit Auth. v.
    ___ ______________________________________
    Norair Eng'g Corp., 553 F.2d 233, 235-36 (D.C. Cir. 1977);
    ___________________
    John W. Johnson, Inc. v. Basic Constr. Co., Inc., 429 F.2d
    ______________________ _______________________
    764, 774-75 (D.C. Cir. 1970); United States v. Fryd Constr.
    _____________ ____________
    Corp., 423 F.2d 980, 983-84 (5th Cir.), cert. denied, 400
    _____ _____ ______
    U.S. 820 (1970); United States Steel Corp. v. Turner Constr.
    _________________________ ______________
    Co., 560 F. Supp. 871, 873-74 (S.D.N.Y. 1983). None of these
    ___
    cases, however, involved the incorporation of an arbitration
    clause. Indeed, in one of the cases relied upon by Gilbane,
    the court explicitly distinguished cases involving
    arbitration clauses as invoking the "congressional policies
    favoring arbitration . . . ." See Washington Metro., 553
    ___ __________________
    F.2d at 236. In light of Haskell, a case on all fours with
    _______
    this one, we find Gilbane's reliance upon this line of cases
    unpersuasive.

    -11-
    11















    interpretation of the contractual language. In any event,

    the facts concerning CU's pretrial participation in the

    lawsuit are undisputed. As a result, the question of waiver

    is one of law, and we review it de novo. See Page v.
    __ ____ ___ ____

    Moseley, Hallgarten, Estabrook & Weeden, Inc., 806 F.2d 291,
    ______________________________________________

    294 n.2 (1st Cir. 1986), overruled on other grounds sub nom.
    _________ __ _____ _______ ___ ____

    Shearson/American Express, Inc. v. McMahon, 482 U.S. 220
    ________________________________ _______

    (1987).

    In deference to the policies favoring arbitration,

    "courts have stated that ``waiver is not to be lightly

    inferred, and mere delay in seeking arbitration without some

    resultant prejudice to a party cannot carry the day.'" See
    ___

    id. at 293 (quoting Rush v. Oppenheimer & Co., 779 F.2d 885,
    ___ ____ _________________

    887 (2d Cir. 1985)). See also Sevinor v. Merrill Lynch,
    ___ ____ _______ ______________

    Pierce, Fenner & Smith, Inc., 807 F.2d 16, 19 (1st Cir. 1986)
    ____________________________

    ("In order for plaintiffs to prevail on their claim of

    waiver, they must show prejudice."); J & S Constr., 520 F.2d
    _____________

    at 809-10 (upholding district court's finding of no waiver

    where there had been "no showing of prejudice").

    Although Gilbane made no claim below that it would

    be prejudiced by a stay of its counterclaim, it asserts on

    appeal that it would suffer prejudice on two bases: (1) that

    it could not properly "defend" Count I (the contract claim

    for amounts allegedly owed CU on twelve of the thirteen

    construction projects) and Count II (CU's ch. 93A claim)



    -12-
    12















    without its counterclaim; and (2) that it would be forced

    into duplicative litigation. We discuss these contentions in

    turn.

    Gilbane first argues that it would suffer prejudice

    from having to defend against Count I of CU's complaint

    without its counterclaim. Accepting this contention would

    require, in essence, a finding that the thirteen construction

    projects are factually inseparable. This is simply not the

    case. Suppose, for instance, that the counterclaim proceeds

    to arbitration and is decided in Gilbane's favor. Assume

    further that the underlying lawsuit results in an award to

    CU. Under that scenario, the arbitration award could act as

    a stipulated setoff from the amount awarded CU in district

    court.5 We are unable to imagine a scenario in which

    Gilbane would suffer prejudice from having to defend Count I

    of CU's complaint in the underlying lawsuit without its

    counterclaim. Nor has Gilbane outlined such a scenario.6


    ____________________

    5. We note that Gilbane's attorney conceded as much during
    oral argument.

    6. Gilbane also argues that, because it pleaded the
    substance of its counterclaim as an affirmative defense in
    its answer to the complaint, it should be permitted to
    litigate the substance of that claim in the underlying
    action. Whether we characterize the substance of Gilbane's
    claim as a "counterclaim" or a "setoff defense," however,
    makes no difference for the purposes of determining whether
    Gilbane will theoretically be prejudiced by severing it from
    __________
    the underlying lawsuit. Second, and more important, Gilbane
    is, in our opinion, relying upon creative pleading to make an
    end run around an arbitration agreement. We have previously
    rejected a party's reliance upon procedural gamesmanship to

    -13-
    13















    We therefore find unpersuasive its belated contention that

    one might exist.

    Gilbane also asserts that it would suffer prejudice

    by having to defend against Count II of CU's complaint

    without its counterclaim. Again, Gilbane has failed to

    provide an example of how it might be prejudiced. It appears
    ___

    to be arguing, instead, that it would be judicially

    inefficient to litigate CU's ch. 93A claim in one forum and

    Gilbane's ch. 93A claim in another.7 While Gilbane may be

    correct, we fail to see how any resulting judicial

    inefficiency would prejudice Gilbane.8 Cf. Page, 806 F.2d
    ___ ____


    ____________________

    avoid the dictates of an arbitration agreement. Cf. Hilti,
    ___ ______
    Inc. v. Oldach, 392 F.2d 368, 373 n.2 (1st Cir. 1968) ("If
    ____ ______
    arbitration defenses could be foreclosed [by creative use of
    the joinder rules], the utility of such agreements would be
    seriously compromised."). We do so again today.

    7. At one point in its brief, Gilbane states that it would
    "be at risk of inconsistent verdicts . . . ." Gilbane has
    not, however, offered either an explanation of this
    perfunctory assertion or an example of a scenario in which it
    could occur. As such, we do not address it further. See
    ___
    United States v. St. Cyr, 977 F.2d 698, 701 (1st Cir. 1992)
    _____________ _______
    (reiterating well settled rule in this circuit that arguments
    adverted to on appeal in "a perfunctory manner, unaccompanied
    by some developed argumentation," are deemed waived) (quoting
    Ryan v. Royal Ins. Co. of America, 916 F.2d 731, 734 (1st
    ____ __________________________
    Cir. 1990)).

    8. In any event, considerations of judicial efficiency are
    not a sufficient basis on which to affirm the district
    court's denial of the motion to stay. See, e.g., Seguros
    ___ ____ _______
    Banvenez, S.A. v. S/S Oliver Drescher, 761 F.2d 855, 862 (2d
    ______________ ____________________
    Cir. 1985) (holding that a court "may not refuse to grant a
    stay [of a claim pending arbitration] based on considerations
    of judicial economy"); Surman v. Merrill Lynch, Pierce,
    ______ ________________________
    Fenner & Smith, 733 F.2d 59, 63 (8th Cir. 1984) (similar);
    _______________
    Dickinson v. Heinold Sec., Inc., 661 F.2d 638, 644-45 (7th
    _________ ___________________

    -14-
    14















    at 294-95 (finding no prejudice despite plaintiffs' claim

    that compelled arbitration would force them to "restart the

    entire [pretrial preparation] process before a new tribunal"

    almost two years after complaint was filed).

    Gilbane also argues that it would suffer prejudice

    by having to litigate the same facts in two separate

    proceedings, and having "to incur increased costs as a result

    of having to proceed in two arenas." This argument rests on

    the faulty premise that litigation of the counterclaim and

    CU's underlying claims would require the adjudication of

    "identical factual and legal issues." See supra pp. 11-12.
    ___ _____

    Moreover, any added costs that Gilbane would incur to

    arbitrate its counterclaim were bargained for by Gilbane. As

    such, Gilbane's final attempt to persuade us that it will

    suffer undue prejudice falls well short of the mark.

    III.
    III.
    ____

    Conclusion
    Conclusion
    __________

    In sum, we find that Gilbane's counterclaim was

    subject to an express agreement to arbitrate, and that CU did

    not waive its right to arbitrate that claim. Accordingly, we

    reverse the district court's denial of CU's motion to stay

    Gilbane's counterclaim pending arbitration and remand for

    proceedings consistent with this opinion.

    Reversed and remanded. No costs.
    Reversed and remanded. No costs.
    _________________________________


    ____________________

    Cir. 1981) (similar).

    -15-
    15