Labor Relations v. IBT, Local 379 ( 1994 )


Menu:
  • USCA1 Opinion













    UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT
    ____________________

    No. 93-2122

    LABOR RELATIONS DIVISION OF CONSTRUCTION
    INDUSTRIES OF MASSACHUSETTS, INC., ET AL.,

    Plaintiffs-Appellees,

    v.

    INTERNATIONAL BROTHERHOOD OF TEAMSTERS, CHAUFFERS,
    WAREHOUSEMEN AND HELPERS OF AMERICA, LOCAL #379,

    Defendant-Appellant.

    ____________________

    APPEAL FROM THE UNITED STATES DISTRICT COURT

    FOR THE DISTRICT OF MASSACHUSETTS

    [Hon. A. David Mazzone, U.S. District Judge]
    ___________________

    ____________________

    Before

    Breyer,* Chief Judge,
    ___________
    Coffin, Senior Circuit Judge,
    ____________________
    and Torruella, Circuit Judge.
    _____________

    _____________________

    Paul F. Kelly, with whom Anne R. Sills and Segal, Roitman &
    _____________ _____________ ________________
    Coleman were on brief for appellant.
    _______
    John D. O'Reilly III, with whom O'Reilly & Grosso was on
    _____________________ __________________
    brief for appellees.
    ____________________

    July 19, 1994
    ____________________

    ____________________

    * Chief Judge Stephen Breyer heard oral argument in this matter
    but did not participate in the drafting or the issuance of the
    panel's opinion. The remaining two panelists therefore issue
    this opinion pursuant to 28 U.S.C. 46(d).














    TORRUELLA, Circuit Judge. The circumscribed role of
    ______________

    federal courts reviewing arbitration awards in labor contract

    disputes is now well established. As the Supreme Court found in

    United Paperworkers Int'l Union v. Misco, Inc., 484 U.S. 29, 36-
    ________________________________ ___________

    45 (1987), courts must resist the temptation to substitute their

    own judgment about the most reasonable meaning of a labor

    contract for that of the arbitrator and avoid the tendency to

    strike down even an arbitrator's erroneous interpretation of such

    contracts. Instead, courts must confine themselves to

    determining whether the arbitrator's construction of the contract

    was in any way plausible.

    The issue in this case is whether any plausible reading

    of a collective bargaining agreement supports an arbitrator's

    ruling in a dispute over fringe benefit contributions.

    Plaintiffs-appellees, J.M. Cashman, Inc. and R. Zoppo Co., Inc.

    (the "plaintiffs" or "Cashman and Zoppo"), challenged the

    arbitration order, which favored the defendant-appellant,

    International Brotherhood of Teamsters, Chauffeurs, Warehousemen

    and Helpers of American, Local 379 (the "Union"), in the district

    court. The district court vacated the arbitration award and

    remanded the dispute to the arbitrator for a new resolution of

    the case. Because we find that the district court stepped

    outside of its highly circumscribed role of assessing the

    plausibility of the arbitrator's interpretation of the agreement

    between the parties, we reverse the court's holding.

    Nevertheless, we agree with the district court that the case


    -2-














    should be remanded to the arbitrator for resolution of a related

    issue of federal law.

    I. BACKGROUND
    I. BACKGROUND

    This case arises out of the arbitration of a dispute

    between the Union and a group of contractor-employers, including

    plaintiffs Cashman and Zoppo, involved in the construction of

    waste water treatment facilities in Boston Harbor (the "Boston

    Harbor Project"). On March 2, 1992, the Union filed grievances

    against Cashman, Zoppo, and six other project employers, claiming

    that truck drivers on the Boston Harbor Project who owned and

    drove their own trucks, so called "owner-operators," should

    receive certain fringe benefit contributions that the employers

    were already paying on behalf of other Boston Harbor Project

    employees. The grievances asserted that the Boston Harbor

    Project Labor Agreement ("Project Agreement"), signed by the

    Union and the employers, required that the same "health and

    welfare contributions and all pension contributions" made on

    behalf of other employees must also be made on behalf of the

    owner-operators.

    The employers claimed that they did not have to pay

    fringe benefits on behalf of owner-operators because the contract

    did not require it and, more importantly, because the Union and

    many of the employers had a long-standing practice of not paying

    such owner-operator benefits going back at least twenty-six

    years. According to the employers, this practice was established

    after the Union and certain employer-contractors on a number of


    -3-














    state construction projects (not including Cashman and Zoppo

    themselves) agreed that, to the extent a nucleus of owner-

    operator truck drivers would be present on any individual

    construction project, the employers would not be required to pay

    fringe benefits for the owner-operators. The employers working

    on the Boston Harbor Project, who were required to sign the

    Project Agreement in order to bid initially on the work, see
    ___

    Building & Constr. Trades Council v. Associated Builders &
    _____________________________________ _______________________

    Contractors, Inc., 113 S. Ct. 1190 (1993), rev'g, 935 F.2d 345
    __________________ _____

    (1st Cir. 1991) (en banc), maintained that they expected this

    established practice to continue as in previous projects.

    Cashman and Zoppo, however, had never entered into a contractual

    relationship with the Union before the Boston Harbor Project.

    Consequently, no past practices had been established between the

    Union and the plaintiffs themselves.

    Pursuant to the Project Agreement, the dispute over the

    fringe benefits was brought before an arbitrator for resolution.

    On January 20, 1993, the arbitrator found in favor of the Union

    and ordered the plaintiffs and the other employers to pay,

    retroactively, post-grievance benefits and to pay future fringe

    benefit contributions on behalf of the owner-operator truck

    drivers. In his accompanying opinion, the arbitrator explained

    that certain provisions of the Massachusetts Teamsters' Heavy

    Construction Agreement ("Teamsters Agreement"), which was

    incorporated into the Project Agreement, in conjunction with the

    Project Agreement itself, explicitly obligated employers to make


    -4-














    health insurance and pension contributions on behalf of the

    owner-operators in question.

    At issue in this appeal is the arbitrator's finding

    that the past practice of not paying the fringe benefits for

    owner-operators did not bind the parties in this case because the

    Project Agreement "wiped the slate clean" of such past practices.

    The arbitrator relied on the following language in the preamble

    of the Project Agreement to support his finding:

    No practice, understanding or agreement
    between a Contractor and a Union party
    which is not explicitly set forth in this
    Agreement shall be binding on any other
    party unless endorsed in writing by the
    Project Contractor.

    By interpreting this language as negating all past practices and

    understandings not explicitly set forth within the Project

    Agreement, the arbitrator disregarded the voluminous evidence

    presented by the employers of the established practice of

    excluding owner-operators from fringe benefit contributions. As

    a result, the language of the Project Agreement granting such

    benefits was found to be controlling.

    Also at issue on appeal is the related question of

    whether the owner-operator truck drivers are independent

    contractors or employees. If they are independent contractors,

    Section 302 of the Labor Management Relations Act ("LMRA"), 29

    U.S.C. 186, would prohibit fringe benefit payments on their

    behalf. The arbitrator acknowledged that the employers had

    argued that fringe benefit payments for the owner-operators would

    be illegal under Section 302, but he made no explicit legal or

    -5-














    factual findings on the issue in his opinion. While a rejection

    of the employers' contention was implicit in the arbitrator's

    award favoring the Union, nothing indicates that the arbitrator

    actually determined whether the owner-operators were employees or

    independent contractors for purposes of the LMRA.

    Following the entry of the arbitrator's award, Cashman

    and Zoppo filed a complaint in the district court on February 19,

    1993, requesting that the court vacate the award. On summary

    judgment, the district court held that the arbitrator had

    impermissibly exceeded his authority by misapplying the plain and

    unambiguous language of the Project Agreement preamble concerning

    past practices, thereby failing to duly consider the evidence

    that the parties had a practice of not paying fringe benefits for

    owner-operators. The district court found that the past

    practices provision of the preamble -- particularly the words,

    "no practice . . . shall be binding on any other party" (emphasis
    _______________

    added) -- clearly and unambiguously meant that established

    practices between parties A and B are not meant to bind outside

    party C. The court found that the phrase could not reasonably be

    interpreted to mean that all established practices, even those

    between parties A and B, are completely wiped out by the Project

    Agreement. Consequently, the court held that the Union could

    still be bound by the past practice of not requiring fringe

    benefit contributions for owner-operators. The district court

    vacated the arbitrator's award and remanded the case to the

    arbitrator to determine the merits, giving proper consideration


    -6-














    to the evidence of past practices.

    The court also left for the arbitrator the issue of

    whether, in light of the court's holding that past practices

    could be considered, the owner-operators are independent

    contractors, thus rendering the payment of benefits on their

    behalf illegal.

    II. ANALYSIS
    II. ANALYSIS

    A. Standard Of Review
    A. Standard Of Review
    __________________

    It is well established that federal court review of

    labor arbitral decisions, particularly on matters of contract

    interpretation, is extremely narrow and "extraordinarily

    deferential." Dorado Beach Hotel Corp. v. Uni n de Trabajadores
    ________________________ ______________________

    de la Industria Gastron mica Local 610, 959 F.2d 2, 3-4 (1st Cir.
    ______________________________________

    1992); see, e.g., Misco, 484 U.S. at 36-45 (1987); Berklee
    ___ ____ _____ _______

    College of Music v. Berklee Chapter of Mass. Fed. of Teachers,
    _________________ ____________________________________________

    Local 4412, 858 F.2d 31, 32 (1st Cir. 1988), cert. denied, 493
    __________ ____ ______

    U.S. 810 (1989). The court may not supplant the arbitrator's

    determination of the merits of a contract dispute, even if it

    finds that determination to be erroneous. Rather, the court's

    task is limited to determining if the arbitrator's interpretation

    of the contract is in any way plausible. Misco, 484 U.S. at 36-
    _____

    38; United Steelworkers of America v. Enterprise Wheel & Car
    _______________________________ ________________________

    Corp., 363 U.S. 593, 599 (1960) ("[S]o far as the arbitrator's
    _____

    decision concerns construction of the contract, the courts have

    no business overruling him because their interpretation of the

    contract is different from his."); El Dorado Technical Servs.,
    ____________________________


    -7-














    Inc. v. Uni n General de Trabajadores de Puerto Rico, 961 F.2d
    ____ ______________________________________________

    317, 319 (1st Cir. 1992) ("[A] court should uphold an award that

    depends on an arbitrator's interpretation of a collective

    bargaining agreement if it can find, within the four corners of

    the agreement, any plausible basis for that interpretation.");

    Dorado Beach, 959 F.2d at 4; Bacard Corp. v. Congreso de Uniones
    ____________ _____________ ___________________

    Industriales de Puerto Rico, 692 F.2d 210, 211 (1st Cir. 1982).
    ___________________________

    "[A]s long as the arbitrator is even arguably construing or

    applying the contract and acting within the scope of his

    authority, that a court is convinced he committed serious error

    does not suffice to overturn his decision." Misco, 484 U.S. at
    _____

    38.

    Only in a few, exceptional circumstances are courts

    able to vacate an arbitration award. When an arbitrator has

    exceeded his authority by ignoring the clear and unambiguous

    mandates or plain language of the contract or by construing the

    contract in a way that cannot possibly be described as plausible

    or rational, a court can overturn the arbitrator's judgment.

    Misco, 484 U.S. at 38 (an arbitrator's award "must draw its
    _____

    essence from the contract and cannot simply reflect the

    arbitrator's own notions of industrial justice"); Dorado Beach,
    _____________

    959 F.2d at 4; Air Line Pilots Ass'n Int'l v. Aviation Assocs.
    ____________________________ ________________

    Inc., 955 F.2d 90, 93 (1st Cir.), cert. denied, 112 S. Ct. 3036
    ____ ____ ______

    (1992); Strathmore Paper Co. v. United Paperworkers Int'l Union,
    ____________________ _______________________________

    900 F.2d 423, 426 (1st Cir. 1990); Georgia-Pacific Corp. v. Local
    _____________________ _____

    27, United Paperworkers Int'l Union, 864 F.2d 940, 944 (1st Cir.
    ____________________________________


    -8-














    1988).

    We reject plaintiffs' contention that our review of the

    district court's vacation of an arbitration award, based on an

    alleged impermissible interpretation of a contract, is made under

    the clearly erroneous standard. In this case, all deference is

    due to the arbitrator's interpretation of the contract, not to

    the interpretation of the district court. The district court

    ruled that the arbitrator exceeded his authority as a matter of

    law by ignoring plain and unambiguous language in the contract.

    We review this finding de novo and make our own determination,

    according to the standards described above, of whether the

    arbitrator's application of the contract was plausible. See,
    ___

    e.g., Upshur Coals Corp. v. United Mine Workers, Dist. 31, 933
    ____ __________________ ______________________________

    F.2d 225, 228 (4th Cir. 1991); Delta Queen Steamboat Co. v.
    ___________________________

    District 2 Marine Engs. Beneficial Ass'n, 889 F.2d 599, 602 (5th
    _________________________________________

    Cir. 1989), cert. denied, 498 U.S. 853 (1990); see also Berklee,
    ____ ______ ________ _______

    858 F.2d at 32-34 (vacating district court's reversal of

    arbitrator's interpretation of labor contract without affording

    deference to the district court's findings); Bacard , 692 F.2d at
    _______

    211-14 (implicitly applying de novo review in vacating district

    court's finding that arbitrator erroneously interpreted

    collective bargaining agreement).

    B. The Past Practices Clause
    B. The Past Practices Clause
    _________________________

    With this circumscribed standard for reviewing

    arbitration awards in mind, there is little question that the

    arbitrator's interpretation of the Project Agreement -- at least


    -9-














    to the extent that he found that the past practices clause bars

    consideration of the plaintiffs' evidence of prior fringe benefit
    __________

    arrangements -- must be upheld as a plausible reading of the

    contract. This result is compelled because the arbitrator's

    holding comports with the district court's own interpretation of

    the past practices clause when properly applied to the facts of

    this case. Thus, even if the arbitrator exceeded his authority

    in finding that the past practices clause wiped the slate clean

    of all established practices between all parties, an issue we do

    not decide, he certainly did not exceed his authority by wiping

    the slate clean between the Union and the plaintiffs in this

    particular case.

    The district court apparently failed to consider the

    possibility that plaintiffs in this case are "other parties" and

    therefore not privy to the past practice of excluding owner-

    operators from the payment of fringe benefits. According to the

    district court, the plain language of the past practices

    provision in the preamble provides merely that past practices

    established between parties A and B shall not be binding on party

    C, although they will continue to be binding on A and B

    themselves. Applying this interpretation to the present case

    reveals that fringe benefit practices between the Union and other

    employer-contractors (parties "A" and "B" respectively) are not

    binding on the plaintiffs (both party "C's"), who did not have an

    established past practice with the Union and are thus "any other

    parties" under the past practices clause. As a result, the


    -10-














    contract could be read to require the arbitrator to ignore

    evidence of past practices between the Union and other parties

    when applying the provisions of the Project Agreement to disputes

    between the Union and the plaintiffs. Because such an

    interpretation is a plausible one, we must reverse the district

    court's vacation of the arbitration ruling with respect to the

    arbitrator's construction of the Project Agreement.

    The plaintiffs take issue with such an application of

    the past practices clause to the facts of this case. They argue

    that because the Union itself was privy to the practice of not

    requiring fringe benefit payments for owner-operators, the Union

    can still be held to that practice, regardless of the fact that

    plaintiffs cannot in any way be bound by such a practice.

    Plaintiffs point to the language of the clause, which states that

    "[n]o practice . . . between a Contractor and a Union party . . .

    shall be binding on any other party," to argue that the clause

    itself concerns only the effects of past practices on new parties

    to the project agreement but in no way limits the effect of past

    practices on the Union itself.

    The plaintiffs' interpretation is certainly reasonable,

    but, for our purposes, it is also irrelevant. Our task is to

    determine whether the arbitrator exceeded his authority by

    failing to apply the contract in a plausible manner, not to seek

    out the most reasonable meaning of the contract. Interpreting

    the past practices clause to bar consideration of plaintiffs'

    evidence of past practice in this case is clearly plausible. The


    -11-














    clause can be read to preclude application of all established

    past practices to "any other party," even if that practice is in

    the "other party's" favor. Such a reading stems from one of

    several plausible constructions of the language in the clause:

    (1) no practice between parties A and B shall be binding between

    parties A and C; (2) practices not binding on party C are

    likewise unavailable to C for use against parties A or B (i.e., C

    is not entitled to rely on or benefit from a practice which is

    not binding on itself); and (3) no practice shall be binding

    unlessalreadyestablished betweenaUnion andaparticular contractor.

    In this case, the arbitrator could plausibly find that

    the practice of excluding fringe benefits for owner-operators,

    established between the Union and other contractors, is not

    binding between the Union and the plaintiffs. Alternatively, the

    arbitrator could find that plaintiffs cannot benefit from the

    past fringe benefit practice because each plaintiff is an "any

    other party" and thus could not be bound by the practice were it

    beneficial to the Union instead of to the employer.

    Plaintiffs protest that we cannot now employ such

    reasoning to retroactively salvage an otherwise unsustainable

    arbitration award. They point out that even if the Union's

    interpretation of the past practices clause is plausible, the

    arbitrator did not arrive at that interpretation himself, but

    instead, arrived at an interpretation that ignored the plain

    language of the contract. The arbitrator found that the past

    practices clause wiped the slate clean of all practices between


    -12-














    all parties, not just practices between parties A and C as

    discussed above. The arbitration award cannot be upheld,

    plaintiffs argue, on the basis of an interpretation of the

    contract that the arbitrator did not even make, because, in this

    case at least, the arbitrator might have come to a different

    conclusion as to whether past practice evidence could be

    considered if he adopted the district court's interpretation of

    the past practices clause at the time of his decision.

    We see no problem with upholding the arbitrator's

    decision on grounds or reasoning not employed by the arbitrator

    himself. To begin with, an arbitrator has no obligation to give

    his or her reasons for an award. Raytheon Co. v. Automated
    ____________ _________

    Business Sys., 882 F.2d 6, 8 (1st Cir. 1989). Once an arbitrator
    _____________

    chooses to provide such reasons, courts should upset the award,

    or remand for clarification, only when "the reasons that are
    ___

    given strongly imply that the arbitrator may have exceeded his or

    her authority." Randall v. Lodge No. 1076, 648 F.2d 462, 468
    _______ ______________

    (7th Cir. 1981); see also Cannelton Indus. v. District 17, UNWA,
    ________ _____________________________________

    951 F.2d 591, 594 (4th Cir. 1991) (remanding portion of

    arbitration award because it may have been based on a grant of

    punitive, as opposed to compensatory, damages, in which case the

    award did not draw its essence from the contract). Absent a

    strong implication that an arbitrator exceeded his or her

    authority, the arbitrator is presumed to have based his or her

    award on proper grounds. Saturday Evening Post Co. v. Rumbleseat
    _________________________ __________

    Press, Inc., 816 F.2d 1191, 1197 (7th Cir. 1987); see also
    ____________ _________


    -13-














    Chicago Newspaper Publishers' Ass'n v. Chicago WEB Printing
    ______________________________________ ______________________

    Pressman's Union, 821 F.2d 390, 394-95 (7th Cir. 1987) ("'[i]t is
    ________________

    only when the arbitrator must have based his award on some body
    ____

    of thought, or feeling, or policy, or law that is outside the

    contract . . . that the award can be said not to 'draw its

    essence from the collective bargaining agreement.''") (quoting

    Ethyl Corp. v. United Steelworkers, 768 F.2d 180, 185 (7th Cir.
    ___________ ____________________

    1985)) (emphasis in original).

    In this case, despite the arbitrator's allegedly

    erroneous reasoning, there is nothing to indicate the arbitrator

    exceeded his authority by not "arguably construing or applying

    the contract." Misco, 484 U.S. at 38; see General Teamsters,
    _____ ___ ___________________

    Auto Truck Drivers & Helpers, Local 162 v. Mitchell Bros. Truck
    ________________________________________ _____________________

    Lines, 682 F.2d 763 (9th Cir. 1982) (upholding arbitrator for
    _____

    "doing the right thing for the wrong reason"). The arbitrator's

    interpretation of the past practices clause in the preamble as

    precluding the use of past practice evidence in determining

    plaintiffs' obligations under the Project Agreement is a

    plausible interpretation of the contract and as such, must be
    ____

    upheld. El Dorado, 961 F.2d at 319. The fact that the
    __________

    arbitrator's "wipe-the-slate-clean" construction of the past

    practices clause might indicate that the arbitrator exceeded his

    authority if he had applied that construction to other parties

    not present in this litigation does not mean that he might have

    exceeded his authority in this particular case. Rather, we know

    the arbitrator did not exceed his authority because his


    -14-














    application of the past practice clause to the plaintiffs' claims

    drew its essence from the collective bargaining agreement.

    Therefore, we need not speculate how the arbitrator might have

    resolved this case had he considered the district court's

    construction of the contract language at issue.

    C. Section 302 of the LMRA
    C. Section 302 of the LMRA
    _______________________

    Unlike the dispute over the Project Agreement, the

    issue of whether fringe benefit contributions on behalf of the

    owner-operators is illegal under federal law does not involve the

    same type of circumscribed judicial review that we afford

    arbitration decisions grounded in interpretations of a contract.

    Although the arbitrator's factual findings regarding the status

    of the owner-operators under Section 302 of the LMRA, 29 U.S.C.

    186, may deserve a certain amount of deference, the issue of

    illegality is ultimately one for federal court review. Misco,
    _____

    484 U.S. at 42-43. Given that a determination under 302 could

    have criminal consequences, the plaintiffs deserve a thorough

    judicial review of an arbitrator's decision as to this issue.

    Neither party disputes that the plaintiffs' payment of

    fringe benefits on behalf of the owner-operators is illegal under

    302 if the owner-operators are independent contractors rather

    than employees. The parties do disagree, however, on whether the

    issue was properly decided by the arbitrator and, if not, how the

    issue should now be resolved. The plaintiffs argue that the

    arbitrator did not properly decide the issue and that we, or the

    district court, should find that the owner-operators are


    -15-














    independent contractors, effectively nullifying the arbitration

    award. The Union argues that the arbitrator correctly found that

    the owner-operators were employees and that we should uphold this

    finding.

    The arbitrator did, at the very least, implicitly

    decide the 302 issue by granting an award in favor of the

    Union. However, we are not satisfied that the arbitrator

    conducted the appropriate statutory analysis for making the

    required factual determination of the owner-operator's status.

    Distinguishing between employees and independent contractors for

    purposes of the LMRA is governed by general principles of agency

    law. National Labor Relations Bd. v. Amber Delivery Serv., Inc.,
    ____________________________ __________________________

    651 F.2d 57, 60 (1st Cir. 1981). Courts have spelled out a

    number of factors to be considered in making the determination of

    a party's status, including various indicia of the employer's

    "right to control" certain aspects of that party's work. Amber,
    _____

    651 F.2d at 61; Construction, Bldg. Material, etc., Local No. 221
    _________________________________________________

    v. National Labor Relations Bd., 899 F.2d 1238, 1240 (D.C. Cir.
    _____________________________

    1990); North Am. Van Lines, Inc. v. N.L.R.B., 869 F.2d 596, 599-
    _________________________ ________

    600 (D.C. Cir. 1989); H. Prang Trucking Co. v. Local Union No.
    ______________________ ________________

    469, 114 L.R.R.M. 3617 (D.N.J. 1983). Although the intent of the
    ___

    parties when they entered into a contractual relationship may be

    relevant to determining an employer's "right to control" or to

    other aspects of the agency test, no one factor is decisive.

    Todd v. Benal Concrete Constr. Co, 710 F.2d 581, 584 (9th Cir.
    ____ __________________________

    1983), cert. denied, 465 U.S. 1022 (1984); Amber, 651 F.2d at 61
    ____ ______ _____


    -16-














    (citing N.L.R.B. v. United Ins. Co, 390 U.S. 254, 258 (1968)).
    ________ _______________

    Rather, all of the incidents of the relationship between the

    employer and the alleged employee must be assessed. Amber, 651
    _____

    F.2d at 61.

    Given the arbitrator's exclusive focus on the past

    practices issue and on provisions of the contract dealing with

    fringe benefit contributions, we have serious doubts that the

    arbitrator actually conducted a proper 302 agency test analysis

    in this case. There is no reason to believe, as the Union seems

    to suggest, that the arbitrator's decision regarding the past

    practices clause, which we uphold in this opinion, is dispositive

    not only of the underlying contractual dispute, but of the 302

    issue as well. Past practices are only one facet of the complete

    agency test under 302. Consequently, the arbitrator's

    discussion of the Project Agreement and the import of past

    practices concerning the owner-operators, while relevant to the

    parties' intended working relationship and thus to the status of

    the owner-operators in this case, is not itself sufficient to

    convince us that a complete 302 agency test analysis was

    undertaken. We cannot, therefore, defer to the arbitrator's

    implicit factual finding on the owner-operators' status to uphold

    the arbitration award until a more complete 302 analysis is

    conducted.

    We are not prepared, however, to conduct that analysis

    ourselves without first giving the arbitrator the opportunity to

    reexamine the factual circumstances of this case. Plaintiffs


    -17-














    asserted in their action before the district court that the

    arbitration award is unenforceable because it violates federal

    law. The district court declined to review this claim because

    the court vacated the arbitration award on the issue of past

    practices. Because we now reverse the district court's ruling,

    we are left with plaintiffs' 302 allegations, which have yet to

    be properly adjudicated. In turn, we are not disposed toward

    making factual findings in the first instance, given the absence

    of explicit factual findings from the district court or the

    arbitrator, that are required for a proper determination of the

    owner-operators' status. Although a largely uncontradicted

    record exists in this case that would allow us to resolve the

    302 issue if we needed to, we consider ourselves too far removed

    from the dispute to properly weigh the various factors involved

    in this fact-intensive determination. In other words, we refuse

    to uphold the arbitrator's finding because plaintiffs have raised

    a claim meriting federal judicial review yet we, as a federal

    appeals court, are not in a suitable position to conduct that

    review.

    Unfortunately, the district court is in the same

    position that we are in with respect to determining the status of

    owner-operators. Consequently, we decline to remand the case

    directly to the district court for a resolution of the 302

    issue. The district court itself chose to remand the proceedings

    instead of deciding the merits of the case and we think it is the

    court's prerogative to do so. Although federal courts have a


    -18-














    duty to scrutinize such federal issues with potential criminal

    consequences, the arbitrator can play an important role in

    providing first-hand factual findings for the benefit of the

    reviewing court. Therefore, we remand this case to the

    arbitrator for a separate determination of the status of the

    owner-operators under 302.

    The plaintiffs do not dispute our authority to remand

    actions to the arbitrator; however, they claim it is

    inappropriate to do so when the issue on remand is one of federal

    law. We disagree with their contention that it is inappropriate

    for an arbitrator to apply federal statutes. On the contrary, it

    is well established that certain statutory claims may be decided

    through arbitration. See Gilmer v. Interstate/Johnson Lane
    ___ ______ ________________________

    Corp., 500 U.S. 20, 26 (1991); Page v. Moseley, Hallgarten,
    _____ ____ _____________________

    Estabrook & Weeden, Inc., 806 F.2d 291, 295 (1st Cir. 1986). We
    ________________________

    see no reason why the arbitrator cannot make the factual findings

    necessary to resolve the 302 issue in this case. Determining

    the status of owner-operators is particularly within the

    arbitrator's domain since it involves analyzing various aspects

    of the working relationship between the parties. Such a

    determination involves consideration of precisely the type of

    issues that the parties originally agreed to refer to the

    arbitrator under the arbitration clause of the Project Agreement.

    We do, nevertheless, retain jurisdiction so that the district

    court can review the final determination of the arbitrator, if

    requested to do so by one of the parties.


    -19-














    On remand, we expect the arbitrator will conduct the

    appropriate agency test analysis as described in the relevant

    caselaw. See, e.g., Amber, 651 F.2d at 60-61; Local No. 221,
    ___ ____ _____ _____________

    899 F.2d at 1240; North Am. Van Lines, 869 F.2d at 599-600;
    _____________________

    Prang, 114 L.R.R.M. at 3617-19; see also Restatement (Second) of
    _____ ________

    Agency 220 (1957). We leave it to the arbitrator to decide

    what effect, if any, the past practices clause of the Project

    Agreement and the evidence of past practice regarding the

    treatment of owner-operators has on his determination of the

    owner-operators' status under 302. Although we upheld the

    arbitrator's interpretation of the contract as barring

    consideration of past practices in resolving contractual

    disputes, we express no opinion on how the past practices clause

    in the contract and the evidence of past practices figure into

    the various factors enumerated under the agency test used to

    ascertain a party's status under 302.

    Accordingly, we reverse the district court's judgment
    _______________________________________________________

    vacating the arbitration award and remand this case to the
    _________________________________________________________________

    district court with instructions to remand the case to the
    _________________________________________________________________

    arbitrator for further proceedings consistent with this opinion.
    _______________________________________________________________














    -20-







Document Info

Docket Number: 93-2122

Filed Date: 7/19/1994

Precedential Status: Precedential

Modified Date: 9/21/2015

Authorities (21)

Associated Builders and Contractors of Massachusetts/rhode ... , 935 F.2d 345 ( 1991 )

dorado-beach-hotel-corporation-v-union-de-trabajadores-de-la-industria , 959 F.2d 2 ( 1992 )

Bacardi Corporation v. Congreso De Uniones Industriales De ... , 692 F.2d 210 ( 1982 )

National Labor Relations Board v. Amber Delivery Service, ... , 651 F.2d 57 ( 1981 )

Frederick J. Page, Jr. And Kristin D. Page v. Moseley, ... , 806 F.2d 291 ( 1986 )

Raytheon Company v. Automated Business Systems, Inc. , 882 F.2d 6 ( 1989 )

Chicago Newspaper Publishers' Association, Cross-Appellee v.... , 821 F.2d 390 ( 1987 )

Burkart Randall, a Division of Textron, Inc. v. Lodge No. ... , 648 F.2d 462 ( 1981 )

The Delta Queen Steamboat Company v. District 2 Marine ... , 889 F.2d 599 ( 1989 )

general-teamsters-auto-truck-drivers-and-helpers-local-162-v-mitchell , 682 F.2d 763 ( 1982 )

Frank L. Todd, Etc., Plaintiffs-Appellants/cross-Appellees ... , 710 F.2d 581 ( 1983 )

The Saturday Evening Post Company and the Curtis Publishing ... , 816 F.2d 1191 ( 1987 )

Strathmore Paper Company v. United Paperworkers ... , 900 F.2d 423 ( 1990 )

Ethyl Corporation v. United Steelworkers of America, Afl-... , 768 F.2d 180 ( 1985 )

North American Van Lines, Inc. v. National Labor Relations ... , 869 F.2d 596 ( 1989 )

construction-building-material-ice-coal-drivers-helpers-and-inside , 899 F.2d 1238 ( 1990 )

United Steelworkers v. Enterprise Wheel & Car Corp. , 80 S. Ct. 1358 ( 1960 )

National Labor Relations Board v. United Insurance Co. of ... , 88 S. Ct. 988 ( 1968 )

United Paperworkers International Union v. Misco, Inc. , 108 S. Ct. 364 ( 1987 )

Gilmer v. Interstate/Johnson Lane Corp. , 111 S. Ct. 1647 ( 1991 )

View All Authorities »