Atlantech Incorporated v. American Panel Corporation ( 2014 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    Nos. 13-1437
    13-1513
    13-1514
    ATLANTECH INCORPORATED,
    Plaintiff, Appellant/Cross-Appellee,
    v.
    AMERICAN PANEL CORPORATION, APC AQUISITION CORPORATION
    INCORPORATED, and UNIVERSAL AVIONICS SYSTEMS CORPORATION,
    Defendants, Appellees/Cross-Appellants.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Douglas P. Woodlock, District Judge]
    Before
    Selya, Stahl, and Lipez,
    Circuit Judges.
    Irwin B. Schwartz, with whom Nicholas R. Cassie and BLA
    Schwartz, PC were on brief, for Atlantech, Inc.
    Michael J. King, with whom John F. Farraher, Jr. and Greenberg
    Taurig, LLP were on brief, for American Panel Corporation and
    Universal Avionics Systems Corporation.
    John A. Christy, with whom Michelle Roback Kraynak, Schreeder,
    Wheeler & Flint, LLP, Justin P. O'Brien, and Collora LLP were on
    brief, for APC Acquisition Corporation, Inc.
    February 20, 2014
    STAHL, Circuit Judge.      Plaintiff Atlantech Incorporated
    ("Atlantech")    filed    a   seven-count     amended   complaint     against
    Defendants American Panel Corporation ("APC"), APC Acquisition
    Corporation, Inc. ("APC Acquisition"), and Universal Avionics
    Systems   Corporation     ("Universal")      (collectively,   "Defendants")
    asserting    claims    related   to    the   alleged    breach   of   various
    agreements involving the sale of aviation equipment.             After a jury
    trial, the parties filed post-trial motions, which the district
    court resolved partially in favor of Atlantech and partially in
    favor of Defendants.          Atlantech appeals and Defendants cross-
    appeal.   We affirm.
    I. FACTUAL BACKGROUND
    Atlantech was a dealer of aircraft LCD displays and APC
    was its primary product supplier.             Pursuant to an August 2002
    agreement,    Atlantech    was   the    exclusive   vendor    to    Ulyanovsk
    Instrument Manufacturing Design Bureau ("UIMDB"), which integrated
    the displays into its own product for use in aircraft instrument
    panels.     On December 2, 2003, APC, operating at the time as a
    division of Universal, entered into a Memorandum of Agreement with
    Atlantech for the sale of 103 1040-100 AMLCD displays ("1040 MOA").
    At the same time, APC and Atlantech reached a Non-Circumvention
    Agreement ("NCA") preventing APC from          conducting direct business
    with UIMDB for two years after the last completed transaction
    between APC and Atlantech.
    -2-
    The 1040 MOA required APC to "support" the product
    through   December    31,   2012    ("Support    Agreement");     the    parties
    dispute the meaning of the word "support" in the context of this
    provision.    The Support Agreement further required APC to maintain
    "Data Warehouse Documents" recording the intellectual property
    necessary for the production and repair of the displays.                 In the
    event that APC discontinued the product, the Support Agreement
    obligated APC to provide those documents to Atlantech.                  The 1040
    MOA also exempted Defendants from liability for "consequential,
    incidental, indirect, special or punitive damages," including "lost
    profits" and "cost of replacement goods."
    APC stopped producing 1040-100 displays in 2004.                 To
    obtain "form, fit, and function replacements" for the discontinued
    model,    Atlantech   purchased     two     hundred   1040-725    displays    in
    February 2006 ("2006 Purchase Order").            APC did not deliver any
    displays under the 2006 Purchase Order.          Under a separate purchase
    agreement, APC eventually did deliver fifteen 1040-725 displays.
    According to subsequent communications between Atlantech and APC,
    these displays did not function properly.
    In   April     2006,     Atlantech,       invoking     diversity
    jurisdiction, see 28 U.S.C. § 1332(a), filed an action in the
    District Court of Massachusetts against APC for breach of contract
    and negligent misrepresentation.          Later that year, it voluntarily
    dismissed the complaint.      In January 2007, APC sold its assets to
    -3-
    APC Acquisition.       At the same time, APC, APC Acquisition, and
    Universal agreed among themselves not to sell any further product
    to Atlantech without obtaining either a release from Atlantech of
    all liability or the written consent of the three parties to the
    agreement.     Over the course of 2008 and 2009, APC Acquisition, in
    violation of the 1040 MOA, sold sixteen display units to a third-
    party vendor, knowing that it intended to develop business with
    UIMDB.
    II. PROCEDURAL HISTORY
    This case has followed a convoluted course, and in order
    to place the parties' arguments in context it is necessary to trace
    its    procedural   path   in    some   detail.     On   February    21,   2007,
    Atlantech filed a complaint against Defendants alleging breach of
    warranty, breach of the 1040 MOA, breach of the 2006 Purchase
    Order, and negligent misrepresentation.             After two amendments to
    the    complaint,    the   parties      filed   cross-motions   for    summary
    judgment. Judge Tauro, in an order dated March 24, 2008 ("March
    2008    Order"),    granted     partial   summary   judgment    in    favor   of
    Atlantech.     While that order decided a number of issues, it left
    others unresolved. Among the issues it addressed, Judge Tauro held
    that APC was "in breach of its obligations under the Data Warehouse
    Documents provision" and granted injunctive relief to Atlantech
    requiring that APC provide it with the 1040-100 Data Warehouse
    Documents.
    -4-
    Despite the presence of unresolved issues, Judge Tauro
    entered judgment in favor of Atlantech, effectively closing the
    case.        A    series   of   motions   to     reopen   and   appeals   followed,
    culminating in this court's order dated May 19, 2010 ("May 2010
    Order"), which left in place the injunctive relief related to the
    Data Warehouse Documents and otherwise vacated the March 2008
    Order.
    On remand, the case was reassigned to Judge Woodlock.
    Two further amendments to the complaint followed.                  Atlantech filed
    the final version, the Fourth Amended Complaint, on June 1, 2011,
    alleging seven counts: Breach of Contract — Warranty (1040 MOA,
    1040-72X MOA, and 890 MOA)1 (Count I); Breach of Contract — Support
    and Product Availability (1040 MOA, 1040-72X MOA, 890 MOA, and
    Purchase Order #40323) (Count II); Breach of Contract — Data
    Warehouse Documents (1040 MOA, 1040-72X MOA, and 890 MOA) (Count
    III);       Breach   of    Contract   —   2006    Purchase      Order   (Count   IV);
    Negligent Misrepresentation (Count V); Intentional Interference
    with Contractual Relations (Count VI); and Breach of Contract — NCA
    (Count VII).          Thereafter, the district court resolved pending
    cross-motions for summary judgment and ruled in favor of Defendants
    on Counts III, V, and VI.
    An eight-day jury trial began June 13, 2011.                On the
    1
    The 1040-72X MOA and 890 MOA are not directly at issue on
    appeal.
    -5-
    seventh   trial   day,   the   court   determined   that   it   would   be
    expeditious for the jury to resolve a set of preliminary questions
    while the court heard arguments regarding directed verdict motions.
    The judge conferred extensively with trial counsel at that point to
    fashion three questions for an "interim verdict slip."            On the
    morning of the eighth day the court instructed the jury on those
    preliminary questions and sent them to deliberate while the court
    dealt with the directed verdict motions.
    Eventually, the judge indicated that he would grant a
    directed verdict in favor of Defendants on Counts I, V, and VI, and
    portions of Count II involving a purchase order that is not at
    issue on this appeal. He also explained that he was "keeping alive
    the Count III to resolve on the papers and the evidence that is
    presented here."2    The judge also engaged trial counsel in an
    extensive discussion of what additional questions remained for the
    jury to decide.
    Thereafter the jury was given a second verdict slip with
    questions regarding damages under Count IV, breach of the 2006
    Purchase Order, and Count VII, breach of the NCA. On these counts,
    the jury awarded Atlantech $1,112,476 in damages.
    2
    According to the record, Judge Woodlock had already
    resolved Counts III, V, and VI on summary judgment prior to
    trial. His reason for revisiting those counts after trial is not
    readily apparent in the transcript. None of those counts is
    presently before us on appeal, however, so the timing of their
    resolution need not concern us.
    -6-
    After dismissing the jury, the court instructed the
    parties to file a joint status report delineating the issues that
    remained to be resolved post-trial. The parties filed their report
    on July 8, 2011, and Atlantech subsequently filed a motion for
    judgment as a matter of law on Defendants' alleged breach of the
    1040 MOA Support Agreement (an unresolved issue remaining under
    Count II). The court denied that motion and ordered the parties to
    "frame this case for final resolution by means of summary judgment
    motions in the wake of trial and the record as it existed as of
    trial."
    On May 23, 2012, Atlantech filed a motion for summary
    judgment seeking damages for breach of the Support Agreement,
    prejudgment    interest    on   all        claims,   and   attorney's    fees.
    Defendants    filed   motions   for    a    directed   verdict   or,    in   the
    alternative, for judgment notwithstanding the verdict, asking the
    court to construe the Support Agreement in their favor and seeking
    a reduction in the jury's award of damages for breach of the 2006
    Purchase Agreement.       On March 6, 2013, the court found that
    Defendants were not liable for breach of the Support Agreement,
    denied prejudgment interest, awarded Atlantech $26,761.58 in fees
    and expenses, and upheld the jury's award of damages for breach of
    the 2006 Purchase Agreement ("March 2013 Order").                The parties
    appeal from the district court's March 2013 Order.
    -7-
    III. ANALYSIS
    Before us on appeal are three broad issues: (1) whether
    Defendants are liable to Atlantech for damages under the terms of
    the 1040 MOA Support Agreement; (2) whether Atlantech is entitled
    to prejudgment interest; and (3) whether the district court erred
    in upholding the jury award of damages for breach of the 2006
    Purchase Agreement.3
    A.        1040 MOA Support Agreement
    In   section   11.2    of    the    Support   Agreement,   entitled
    "Length of Product Availability," APC agreed "to support original
    product through December 31, 2012.           At that point the product may
    be discontinued."    The district court held that this provision was
    an enforceable agreement obligating Defendants "to hold open the
    opportunity    for   Atlantech    to    buy     form,   fit,   and   function
    replacements" for the 1040-100 displays for a period of ten years.
    Nevertheless, the district court entered judgment in
    favor of Defendants on this claim.            Proceeding under a theory of
    anticipatory repudiation, Atlantech argued that Defendants breached
    the Support Agreement by agreeing in January 2007 to discontinue
    sales to Atlantech, unless Atlantech provided them with a release
    from liability or they all consented.            A claim for anticipatory
    repudiation requires an absolute and unqualified refusal to perform
    3
    The parties initially disputed the award of fees and
    expenses, but settled that issue after oral argument.
    -8-
    a contract.   Textile Rubber & Chem. Co., v. Thermo-Flex Techs.,
    Inc., 
    687 S.E.2d 919
    , 922 (Ga. Ct. App. 2009).4   The district court
    found that "there [was] nothing absolute or unqualified about" the
    Defendants' refusal to perform under the contract, because they
    could have all consented to continue sales.   Accordingly, it found
    no breach of the agreement as a matter of law.    The district court
    also found that Atlantech could not prove the damages it sought,
    which were based on lost profits as a measure of direct damages.
    The court held that "[t]here is nothing inherent in the bargain
    . . . sufficient to provide reliable numbers, and this precludes
    Atlantech from recovering lost profits."
    On appeal, the parties dispute numerous issues with
    respect to the alleged breach of the Support Agreement: whether the
    mandate rule requires judgment in favor of Atlantech, whether the
    Support Agreement is an enforceable contract, the nature and scope
    of Defendants' obligations under the Support Agreement, whether
    Defendants repudiated or otherwise breached the Support Agreement,
    and whether Atlantech can prove direct damages related to the
    alleged repudiation. We can quickly dispense with Atlantech's
    argument for the application of the mandate rule. Of the remaining
    4
    "Both sides premise their arguments on Georgia law, which
    the parties reasonably understand to govern their relationship in
    this regard." Atlantech Inc. v. Am. Panel Corp., No. 07-cv-
    10342, 
    2013 WL 870227
    , at *8 (D. Mass. Mar. 6, 2013). Like the
    district court, we accept the parties' reasonable understanding
    and look to Georgia law for the substantive rules of decision.
    See Shay v. Walters, 
    702 F.3d 76
    , 79–80 (1st Cir. 2012).
    -9-
    arguments, only one requires our attention at this stage. We agree
    with the district court that Atlantech did not prove direct damages
    resulting from the alleged repudiation, and that the plain terms of
    the   contract   preclude   recovery   for   other   types   of   damages.
    Therefore the claim fails as a matter of law.        Because this issue
    is dispositive, we need not resolve the other disputes related to
    the Support Agreement.
    1.         Mandate Rule
    "[A]n appellate court's mandate controls all issues that
    were actually considered and decided by the appellate court, or as
    were necessarily inferred from the disposition on appeal." Kashner
    Davidson Sec. Corp. v. Mscisz, 
    601 F.3d 19
    , 23-24 (1st Cir. 2010)
    (quoting NLRB v. Goodless Bros. Elec. Co., 
    285 F.3d 102
    , 107 (1st
    Cir. 2002)) (internal quotation marks omitted).          "[I]ssues that
    were not decided by the appellate court . . . are not affected by
    the mandate." 
    Id. (quoting de
    Jesús–Mangual v. Rodríguez, 
    383 F.3d 1
    , 6 (1st Cir. 2004)) (alteration in original).
    Atlantech argues that Judge Tauro's March 2008 Order held
    that APC breached the Support Agreement, and that this court
    subsequently affirmed that holding.          But this court's May 2010
    Order expressly vacated the March 2008 Order in part, leaving in
    place only the injunction related to the Data Warehouse Documents.
    All that can be "necessarily inferred" from the May 2010 Order is
    that Defendants breached the provision of the Support Agreement
    -10-
    requiring them to turn over the Data Warehouse Documents.             The May
    2010 Order did not decide the question currently before us; whether
    Defendants    breached    section     11.2   of    the   Support   Agreement.
    Therefore, the mandate rule does not apply.
    2.          Damages
    In a breach of contract case, "the burden is on the
    plaintiff to show both the breach and the damage."            Adamson Co. v.
    Owens-Ill. Dev. Corp., 
    309 S.E.2d 913
    , 916 (Ga. Ct. App. 1983).
    Atlantech does not dispute that it contractually waived the right
    to seek consequential damages, including lost profits.             It argues,
    however, that lost profits can serve as a measure of direct
    damages.   It also offers two alternate measures of damages.
    At trial, Atlantech attempted to prove lost profits by
    showing past sales to UIMDB as well as evidence of UIMDB's intent
    to buy certain quantities in the future.            It relied on the prices
    at which it bought and sold the displays at the time the parties
    entered into the 1040 MOA. But as the district court observed, the
    Support Agreement itself does not prescribe any particular price or
    quantity for future sales, other than providing that prices must be
    "in line" with those from past sales.             Under these circumstances
    the district court found the evidence offered by Atlantech too
    speculative, because "[t]here is nothing inherent in the bargain
    when the parties entered into the 1040 MOA in 2003 sufficient to
    provide reliable numbers."         We agree with the district court.
    -11-
    Under Georgia law, the term "lost profits" refers to two
    distinct concepts:
    Consequential damages, which may include 'profits which
    might accrue collaterally as a result of the contract's
    performance,' are a separate concept from direct damages,
    which may include 'profits necessarily inherent in the
    contract.' Thus there are two types of lost profits: (1)
    lost profits which are direct damages and represent the
    benefit of the bargain (such as a general contractor
    suing for the remainder of the contract price less his
    saved expenses), and (2) lost profits which are indirect
    or consequential damages such as what the user of the MRI
    would lose if the machine were not working and he was
    unable to perform diagnostic services for several
    patients.
    Imaging Sys. Int'l, Inc. v. Magnetic Resonance Plus, Inc., 
    490 S.E.2d 124
    , 127 (Ga. Ct. App. 1997) (internal citation omitted).
    Another court observed that profits "necessarily inherent in the
    contract . . . are always provable." Franklin v. Demico, Inc., 
    347 S.E.2d 718
    , 721 (Ga. Ct. App. 1986).
    The question here is whether the damages Atlantech seeks
    to prove are "necessarily inherent in the contract."    We find that
    they are not, because they depend on contingencies beyond the terms
    of the contract itself. The brief examples offered by the court in
    Imaging Systems are instructive.      When a general contractor sues
    for its remaining contract price less saved expenses, the damages
    do not depend on the future action of any third party; they are
    determined by the terms of the contract and the circumstances of
    the breach.   Thus, they are "always provable" in the sense that
    they do not require evidence of what some other party might have
    -12-
    done. The damages suffered by the doctor with a malfunctioning MRI
    machine depend on how many patients one might have seen if the
    machine were working.       The doctor very well might be able to
    recover such damages by showing evidence of how many patients were
    normally seen in the past, but they would remain consequential
    damages.
    Other circuits have reached a similar understanding of
    the distinction between the two types of lost profits:
    Direct damages refer to those which the party lost from
    the contract itself—in other words, the benefit of the
    bargain—while consequential damages refer to economic
    harm beyond the immediate scope of the contract. Lost
    profits, under appropriate circumstances, can be
    recoverable as a component of either (and both) direct
    and consequential damages. Thus, for example, if a
    services contract is breached and the plaintiff
    anticipated a profit under the contract, those profits
    would be recoverable as a component of direct, benefit of
    the bargain damages. If that same breach had the knock-on
    effect of causing the plaintiff to close its doors,
    precluding it from performing other work for which it had
    contracted and from which it expected to make a profit,
    those lost profits might be recovered as "consequential"
    to the breach.
    Atl. City Assocs., LLC, v. Carter & Burgess Consultants, Inc., 
    453 F. App'x 174
    , 179-80 (3d Cir. 2011) (quoting Penncro Assocs., Inc.
    v. Sprint Spectrum, L.P., 
    499 F.3d 1151
    , 1156 (10th Cir. 2007)).
    The evidence that Atlantech offered at trial is relevant
    to lost profits as consequential, not direct, damages.     Atlantech
    is seeking to show how much it would have earned selling displays
    to UIMDB if APC had performed its obligations under the Support
    Agreement.     Because those damages rely on future deals with a
    -13-
    business that is not a party to the Support Agreement, and are
    contingent on anticipated prices and demand that are not determined
    by the contract itself, the damages are not "necessarily inherent
    in the contract."   Thus, they are consequential damages, for which
    Defendants are not liable under the terms of the 1040 MOA.
    Atlantech fares no better with its other theories of
    damages.   It argues that "under Georgia law, Atlantech may recover
    direct damages in an amount equal to the difference between the
    market price at the time the buyer learned of the breach and the
    contract price, less expenses saved at as a result of the breach."
    The obvious problem with the use of this method of measuring
    damages here is that there is no contract price in section 11.2 of
    the Support Agreement. Presumably, if APC had continued to sell
    displays to Atlantech under the terms of the Support Agreement, the
    parties would have negotiated a price for each sale.          Without a
    fixed contract price, Atlantech cannot use this method to prove
    damages.
    Finally, Atlantech argues that it "is entitled to recover
    its attempted mitigation expenses associated with Defendants'
    repudiation of their support obligations."      Atlantech defines its
    "mitigation   expenses"   as   its   "failed   efforts   to   develop   a
    substitute for the 1040-100 Display."      But the terms of the 1040
    MOA clearly exempt Defendants from liability for the "cost of
    replacement goods." Therefore, Atlantech is barred from recovering
    -14-
    damages under this theory as well.
    In sum, the district court correctly concluded that
    Atlantech had failed to prove damages for breach of the Support
    Agreement and thus finding for Defendants on that claim.
    B.             Prejudgment Interest
    In its post-trial motion, Atlantech asked the district
    court to award prejudgment interest.                  Georgia law provides for a
    discretionary award of prejudgment interest on unliquidated claims,
    Ga. Code Ann. § 13-6-13,5 but it is the role of the jury, not the
    court, to exercise that discretion. See Alphamed, Inc. v. B. Braun
    Med., Inc., 
    367 F.3d 1280
    , 1287 (11th Cir. 2004) (applying Georgia
    law); Am. Family Life Assurance Co. of Columbus, Ga. v. U.S. Fire
    Co., 
    885 F.2d 826
    , 835–36 (11th Cir. 1989).
    Atlantech    did    not   submit       a    request   for   prejudgment
    interest to the jury at trial. Therefore the court found the issue
    to be waived and denied the request.                  On appeal, Atlantech argues
    that it did not knowingly waive the request, because "the district
    court bifurcated the case in the middle of trial and allowed only
    certain issues to go to the jury."                According to Atlantech, when
    the district court bifurcated the case, it represented that it
    would       impanel   a   second    jury   at     a       later   time   to   determine
    outstanding factual issues.
    5
    "[T]he parties agree that the request is one for interest
    on unliquidated damages. . . . " Atlantech, 
    2013 WL 870227
    , at
    *8.
    -15-
    The record belies Atlantech's argument.    The court only
    "bifurcated" the trial in the sense that it sent three preliminary
    questions to the jury while the court heard arguments about issues
    pertaining to the directed verdict requests.        While the jury
    deliberated the questions submitted to it, the court repeatedly
    asked counsel to articulate which issues remained for the jury and
    which could be decided as a matter of law.   ("My touchstone is what
    else am I going to do with this jury at this time, . . . I am
    trying to figure out what else I am going to ask them."); ("I am
    searching through to identify those factual disputes that can be
    resolved in a way that I am comfortable with by this jury."); ("But
    let me just see if I can get through all of this to see what else
    is potentially left that requires jury determination . . . .");
    ("So, I would like you to be thinking about, again, what else we
    would want from this particular jury.")
    Thus, prior to submitting a second (and final) verdict
    form to the jury, the court expressly gave the parties multiple
    opportunities to identify any issues they believed the jury needed
    to decide.   Under these circumstances, there is no legitimate
    reason for Atlantech's failure even to mention the issue of
    prejudgment interest at that time, and thus the district court did
    not err in its holding that Atlantech had waived the issue.
    -16-
    C.               2006 Purchase Agreement
    Under the 2006 Purchase Agreement, Atlantech ordered 2006
    1040-725 displays from APC for $1,335,750 in order to fulfill an
    agreement it reached with UIMDB in December 2005.                     APC guaranteed
    that       the   1040-725      model    would    be    "form,   fit   and   function"
    compatible with the displays Atlantech purchased previously.                       APC
    was to deliver twenty-five units by April 15, 2006, and place the
    "[r]emaining 175 unit materials on hold until confirmation of
    compatibility."           As discussed above, APC did not deliver any
    displays under the 2006 Purchase Agreement, but did deliver fifteen
    displays under a separate agreement.                      Those fifteen displays
    apparently did not function properly, and Atlantech never gave APC
    a confirmation of compatibility.
    At   trial,   the     jury    awarded   Atlantech    $1,070,456    in
    damages on Count IV, based on the value of the UIMDB contract minus
    the cost of the 2006 Purchase Agreement, the cost of sale, and the
    amount Atlantech received for separately delivering the fifteen
    displays it received from APC.                       In their post-trial motion,
    Defendants asked the district court to reduce the damages to
    $57,862.67, which would represent the lost profits on the twenty-
    five displays that APC was supposed to deliver by April 15, 2006,
    minus the profits Atlantech received on the fifteen that APC
    6
    There is a discrepancy in the order, which appears to be
    for 201 displays but only requires delivery of 200. At trial,
    Atlantech sought damages based on the 200 units to be delivered.
    -17-
    delivered separately.      According to Defendants, they were only
    obligated to deliver twenty-five displays until Atlantech gave them
    a confirmation of compatibility; the fact that Atlantech never
    confirmed compatibility absolved them of the obligation to deliver
    the remaining 175 units.
    The district court rejected Defendants' reading of the
    contract. It read the confirmation provision as a protection for
    Defendants "against a situation in which they produced the full
    number of displays (thus bearing the cost of production for a full
    200 displays), and then also faced liability for breach if all
    those displays turned out to be incompatible with 1040-100 units."
    It concluded that "nothing indicates that a failure to provide a
    confirmation of compatibility relieved APC of its obligation to
    deliver" the full order of 200 displays, particularly in light of
    Defendants'   "fail[ure]   to   deliver   even   the   initial   round   of
    compatible displays."
    The district court's reading of the contract is correct.
    Defendants have not offered any arguments on appeal that persuade
    us otherwise.   They ask us to read the confirmation provision as a
    condition precedent to full delivery, but that is not the ordinary
    meaning of the contractual language. The phrase "on hold," which
    commonly indicates a temporary delay,7 implies the expectation of
    7
    See Random House Dictionary of the English Language 911
    (2d. ed. 1987) (defining "on hold" as "in or into a temporary
    state of interruption or suspension").
    -18-
    eventual completion. In that respect it is different from the type
    of   language   that   would    more   commonly   indicate   a   condition
    precedent, such as "subject to" or "if and only if."             The 2006
    Purchase Agreement was for 200 displays. The fact that the parties
    had the foresight to test the compatibility of a few displays prior
    to delivery of the entire order does not evince an intention to
    truncate Defendants' obligation under the contract.          Accordingly,
    we hold that the district court did not err in upholding the jury's
    award of damages.
    IV. CONCLUSION
    For the reasons explained above, we AFFIRM the district
    court's orders.   All parties shall bear their own costs.
    -19-