United States v. Charter Inter. Oil ( 1996 )


Menu:
  • United States Court of Appeals
    For the First Circuit
    No. 95-1961
    No. 95-1984
    No. 95-2019
    UNITED STATES OF AMERICA,
    Plaintiff, Appellee,
    v.
    CHARTER INTERNATIONAL OIL COMPANY,
    Defendant, Appellant.
    ACUSHNET COMPANY, ET AL.,
    Proposed Intervenors-Appellees.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Robert E. Keeton, U.S. District Judge]
    Before
    Cyr, Boudin, and Lynch, Circuit Judges.
    David B. Broughel,  with whom Jeffrey B.  Renton, and Day, Berry &
    Howard  were  on  brief,  for  appellant,  Charter  International  Oil
    Company.
    David  M. Jones, with  whom Roger  C. Zehntner,  Irene C. Freidel,
    Phoebe  S. Gallagher  and Kirkpatrick  & Lockhart  were on  brief, for
    proposed intervenors-appellees, Acushnet et al.
    Evelyn S.  Ying, Attorney,  United States  Department of  Justice,
    with  whom Lois  J.  Schiffer, Assistant  Attorney General,  Daniel C.
    Beckhard  and David C. Shilton, Attorneys, United States Department of
    Justice, were on brief, for the United States as appellee.
    May 9, 1996
    LYNCH, Circuit  Judge.   The clean-up of  a Superfund
    LYNCH, Circuit  Judge.
    hazardous waste site in New Bedford, Massachusetts is largely
    being   accomplished  and   funded  through   agreements  the
    government  has reached  with private  parties who  bear some
    legal  responsibility for  the  wastes at  the  site.   Those
    agreements, by  law, must be  approved by  the United  States
    Courts  as being  fair, reasonable,  and consistent  with the
    purposes of CERCLA, the Comprehensive Environmental Response,
    Compensation  and Liability  Act.   Multiples of  millions of
    dollars are involved in these settlements  and the stakes are
    high, both for the public and  for the parties involved.  The
    allocation of responsibility for payment of those millions --
    as  between the  public treasury and  the private  sector and
    amongst the private  players themselves -- has  given rise to
    complicated  settlement  dynamics.    Those  settlements  are
    subject  to  both the  court  approval  mechanism enacted  by
    Congress and to specific statutory clauses providing for (and
    protecting against) contribution  by some of  the potentially
    responsible parties  ("PRPs") to the settlement  sums paid by
    other such parties.
    The question  presented here is whether  the district
    court  abused its  discretion in  approving a  CERCLA consent
    decree  between the government  and Charter International Oil
    Company arising  out of the Sullivan's  Ledge Superfund Site.
    What is unusual  is that the government and Charter disagreed
    -2-
    2
    in a very fundamental sense on  interpretation of the consent
    decree.    This, in turn,  raises the issue of  the extent to
    which  the scope  of "matters  addressed" in  the decree,  an
    issue  usually resolved in separate contribution actions, was
    required  to  be determined  by  the  district court  in  its
    approval of the consent decree.
    Under the rubric  of approval of the decree, two sets
    of  private parties here  attempt to battle  out the ultimate
    allocation of contribution liability in a clean-up with costs
    estimated to be in  the order of $50 million.   Charter urges
    that    the   district   court   erred   in   rejecting   its
    interpretation,   which   would    give   Charter    complete
    contribution   protection  against  prior  settlors  for  its
    payment  of  $215,000 plus  interest.    The Acushnet  Group,
    comprised of prior settling  parties who have instituted such
    a  contribution  action  against  Charter,  urges   that  the
    district  court  erred  in  not  resolving  all  contribution
    questions in the course of approving the decree.
    We affirm the district court's order.
    The Sullivan's Ledge Superfund Site
    An  old granite quarry in  New Bedford was  used as a
    waste  disposal  area by  the city  from  1935 to  the 1970s.
    Local   industries  disposed   of  their   wastes,  including
    hazardous substances, into four  pits, extending as deep into
    the  bedrock as 150 feet.   The contaminants  from the wastes
    -3-
    3
    spread to  adjacent areas,  including some wetlands  known as
    Middle Marsh.
    In  1984,  the EPA  placed  the  area, known  as  the
    Sullivan's Ledge Site, on the National Priorities List.   See
    40  C.F.R.  Pt.  300,   App.  B.    It  began   its  Remedial
    Investigation  and Feasibility  Study  of  the two  "operable
    units" on the Site: the entire Site save for the Middle Marsh
    ("first unit") and the Middle Marsh ("second unit").  The EPA
    found  significant hazardous  substances in  the groundwater,
    soils, and sediments of both units.
    In  June 1989 EPA issued its Record of Decision ("ROD
    I")  as  to  the  first   unit,  calling  for  excavation  of
    contaminated   soils  and   sediments,  construction   of  an
    impermeable cap over the disposal area, groundwater treatment
    and wetlands remediation.   The government sued fourteen PRPs
    with  respect to  the first  unit (the  Acushnet  Group), who
    settled.  See  United States  v. Acushnet Co.,  Civ. No.  91-
    10706-K  (D. Mass.).   The  district court entered  a consent
    decree  approving and  finalizing the  settlement  (the "1991
    Decree").
    Under  the terms  of  the 1991  Decree, the  Acushnet
    Group paid $620,000 to the government for past costs incurred
    in  connection with ROD I.   The Group also agreed to perform
    the  ROD  I  remedy,  including  the  first  thirty years  of
    operation and  maintenance,  and  to pay  all  of  the  EPA's
    -4-
    4
    oversight  costs for  the first  five years  and half  of its
    oversight costs through the thirtieth year.
    On September 27, 1991,  after completing its study of
    the contamination in the Middle Marsh wetlands area, the  EPA
    issued its remedy for the second  unit ("ROD II").  On  April
    26,  1993,  the  district  court  entered  a  consent  decree
    approving the  settlement between the government  and fifteen
    PRPs  (the  Acushnet  Group  and the  City  of  New Bedford).
    United States  v. AVX Corp.,  Civ. No. 93-10104-K  (D. Mass.)
    (the "1993 Decree").  The 1993 settlors agreed to perform the
    remedy  set forth  in ROD  II and  to pay  half of  the EPA's
    oversight costs with respect to the second unit.
    Charter was offered the opportunity to participate in
    the  1991 Decree but declined  it, saying that  the price tag
    was too high  for what it believed its liability  to be.  The
    parties to both the 1991 and 1993 Decrees understood that the
    government had a larger total claim relating to the Site than
    the recovery  it had obtained  from the initial  settlors and
    that  the government  planned to  seek further  recovery from
    parties  who had not  yet settled.  That  is exactly what the
    government did,  bringing a  series of lawsuits  against non-
    settling PRPs,1 including suit against Charter.
    1.  The  government  brought a  cost  recovery  suit for  its
    shortfall on the first unit against two non-settlors.  United
    States v.  Cornell-Dubilier Electronics,  Inc., Civ.  No. 92-
    11865-K (D.  Mass.).  The  initial Cornell-Dubilier complaint
    sought approximately $2.8 million  and a declaratory judgment
    -5-
    5
    Proceedings Against Charter
    The government  pursued  Charter under  a  theory  of
    successor  liability for  a company,  Pacific Oil,  which had
    dumped  soot  from  oil  burners into  the  Sullivan's  Ledge
    landfill.2      In   June  1992   the   government  initiated
    independent  settlement   negotiations  with  Charter.     On
    December  2, 1993, the proposed  consent decree was lodged in
    the  district court and  notice was published  in the Federal
    Register.3   
    58 Fed. Reg. 65,397
      (Dec.  14,  1993).    In
    that the  defendants were liable for  the government's future
    response costs not covered  by the 1991 Decree.   After entry
    of  the  1993 Decree,  the  government  amended its  Cornell-
    Dubilier complaint, adding  three new defendants  and seeking
    an additional  $1 million  for costs  relating to  the second
    unit.    The City  of New  Bedford,  a defendant  in Cornell-
    Dubilier,  has agreed  to a  proposed decree  for unrecovered
    costs  from the  first  unit in  satisfaction  of the  claims
    asserted against it in the Cornell-Dubilier suit.
    Similarly, seeking  to recover its claims  against parties
    not settling in the initial rounds, the Acushnet  Group filed
    suit against twelve parties, excluding Charter.  See Acushnet
    Co. v. Coaters, Inc., Civ. No. 93-11219-K (D. Mass.).
    2.  Charter disputes  the contention that the  soot contained
    high concentration levels of hazardous substances.   Further,
    there were  two companies that  used the name  "Pacific Oil":
    Durfee Fuels,  a Massachusetts  corporation  and Pacific  Oil
    Company, a Rhode Island corporation.   Charter claims that it
    was Durfee Fuels  (to which it was  not a successor)  and not
    the Pacific Oil  Company (to  which it was)  that dumped  the
    soot.
    3.  Section 122(d)(2) of CERCLA requires the Attorney General
    to  provide persons who are not parties to a proposed consent
    decree  an opportunity  to  comment on  the proposed  consent
    decree "before its entry  by the court as a  final judgment."
    42 U.S.C.   9622(d)(2)(B).  Further, the Attorney  General is
    obligated  to "consider, and file with the court, any written
    comments,  views, or  allegations  relating  to the  proposed
    -6-
    6
    response,  the  Acushnet  Group  filed comments  voicing  its
    concern  that  the  decree  might be  interpreted  to  afford
    Charter  contribution   protection  against  the   claims  of
    settlors  in the 1991 and 1993 Decrees.  Charter responded in
    turn, asserting  that the prior settlors' contribution claims
    against it were  indeed impaired  by the decree.   In  August
    1994, the  government  made  it clear  to  Charter  that  its
    position was that the decree  did not grant Charter  complete
    contribution protection against the claims of  prior settlors
    and that it would  press this interpretation with  the court.
    Given  their  differing interpretations  of  the decree,  the
    government  offered to  let  Charter  withdraw,  but  Charter
    declined.
    On February  2, 1995, the government  moved for entry
    of  the Charter consent decree.  It presented to the district
    court its position  that the decree  did not provide  Charter
    with complete contribution protection against prior settlors.
    The district court consolidated the consent decree action and
    the contribution  action filed by the  Acushnet Group against
    Charter  for the limited  purpose of conducting  a hearing to
    determine the impact of  the contribution protection issue on
    entry  of the  decree.   The Acushnet  Group objected  in the
    government's case to  entry of  the decree, but  only if  the
    judgment."  
    Id.
    -7-
    7
    decree  were  interpreted to  provide  Charter  with complete
    contribution protection.4
    At   the  consolidated   hearing,  the   court  heard
    arguments  on the  proper interpretation of  the decree.   It
    gave Charter another opportunity to withdraw from the decree,
    but  Charter again declined.  The  district court entered the
    decree,  rejecting  Charter's   assertion  that  the   decree
    afforded  it complete  contribution protection  against prior
    settlors.   The Acushnet  Group's contribution action against
    Charter is currently pending before the  district court.  See
    Acushnet  Co. v. Charter Int'l Oil, Civ. No. 94-10989-REK (D.
    Mass.).
    The Consent Decree on Appeal
    Two questions are  raised by this appeal.   The first
    is  whether  the  district  court abused  its  discretion  in
    approving  the  consent  decree.5     See  United  States  v.
    DiBiase, 
    45 F.3d 541
    , 544 (1st  Cir. 1995).   The second  is
    whether  its  interpretation of  the  decree  was correct,  a
    question  which,  to the  extent it  involves issues  of law,
    4.  Charter's answer  to  the Acushnet  Group's complaint  in
    contribution asserted that the claims were barred because the
    proposed  decree between  Charter  and the  government  would
    provide full contribution protection to Charter under Section
    113(f)(2) of CERCLA, 42 U.S.C.   9613(f)(2).
    5.      Although  jurisdictional  issues  over  the  Acushnet
    Group's proposed  "intervention" in  this appeal lurk  in the
    background,  we  need  not  resolve them  since  the  Group's
    challenge fails on the  merits.  See Menorah Ins.  Co. v. INX
    Reins. Corp., 
    72 F.3d 218
    , 223 n.9 (1st Cir. 1995).
    -8-
    8
    calls  for fuller appellate review.  See AMF, Inc. v. Jewett,
    
    711 F.2d 1096
    , 1100-01 (1st Cir. 1983).  On the facts of this
    case,  the   first  question  cannot   be  answered   without
    addressing the second.
    In  approving a  consent decree,  the  district court
    must determine three things:   that the decree is  fair, that
    it is reasonable,  and that  it is faithful  to the  purposes
    that  CERCLA is intended to serve.   DiBiase, 
    45 F.3d at 543
    ;
    United  States v. Cannons Eng'g  Corp., 
    899 F.2d 79
    , 85 (1st
    Cir. 1990).  This  assessment entails, in part,  an appraisal
    of what the government is being  given by the PRP relative to
    what the PRP is receiving.  What is being given by the PRP is
    clear:  $215,000 plus interest.  It is what is being received
    which implicates  the district court's interpretation  of the
    decree and the issue of contribution protection.
    We turn  to the  statutory scheme.   In enacting  the
    1986  amendments  to  CERCLA  known as  SARA  (the  Superfund
    Amendments  and   Reauthorization  Act  of   1986),  Congress
    provided settling  parties with  certain immunity from  later
    contribution actions arising from  "matters addressed" in the
    consent  decree.    Cannons, 
    899 F.2d at 91
    ;  42 U.S.C.
    9613(f)(2).   As  to such  matters, "only  the amount  of the
    settlement  -- not  the pro  rata share  attributable to  the
    settling  party -- [is] subtracted from  the liability of the
    non settlors."  Cannons, 
    899 F.2d at 91
    .
    -9-
    9
    Thus,  because  approval of  a  consent  decree under
    CERCLA results  in  contribution protection  to the  settling
    party, it also affects the rights of PRPs who are not parties
    to the decree.   The contribution issue, in turn,  depends on
    the scope of "matters addressed" in the settlement, for:
    A person  who has  resolved its  liability to
    the   United  States . . . in   a  judicially
    approved settlement shall  not be liable  for
    claims  for  contribution  regarding  matters
    addressed in the settlement.  Such settlement
    does   not   discharge  any   of   the  other
    potentially liable persons  unless its  terms
    so  provide,  but  it  reduces  the potential
    liability of the others  by the amount of the
    settlement.
    42 U.S.C.   9613(f)(2) (emphasis added).
    This  statutory framework contemplates  that PRPs who
    do not join in a first-round settlement will be left with the
    risk  of  bearing  a  disproportionate  share  of  liability.
    "Disproportionate liability, a technique which promotes early
    settlements and  deters litigation for litigation's  sake, is
    an integral part of  the statutory plan."  Cannons,  
    899 F.2d at 92
    .
    Further,  the legislative history  of SARA shows that
    Congress contemplated that there would be partial settlements
    which  would leave  settling parties  liable for  matters not
    addressed in the agreement:
    This protection attaches only to matters that
    the  settling  party  has resolved  with  the
    [government].    Thus,  in  cases  of partial
    settlements where, for  example, a party  has
    settled with  the [government] for  a surface
    -10-
    10
    clean  up,  the settling  party shall  not be
    subject  to any  contribution  claim for  the
    surface clean  up by any party.   The settlor
    may, however, remain liable in such instances
    for  other  clean  up  action  or  costs  not
    addressed by the settlement  such as, in this
    example, a subsurface clean up.
    Statement of Senator  Stafford (sponsor of S.  51, the Senate
    bill for  the 1986 SARA  Amendments), 131  Cong. Rec.  24,450
    (1985).
    Here,  two groups  are  settlors and  each seeks,  on
    opposite  sides of  the coin,  the value of  the contribution
    proviso.   The Acushnet  Group, which settled  earlier, wants
    its  contribution  rights against  Charter  arising from  the
    Sullivan's Ledge  Site clean-up maximized.   Charter, a later
    settlor, wants to cut off all contribution claims against it.
    For  purposes  of  establishing  the  scope  of  contribution
    protection afforded to Charter by the decree under  42 U.S.C.
    9613(f)(2), it would be necessary to determine the scope of
    "matters addressed" by the decree.
    This  case, however,  involves approval of  a consent
    decree  and is  not a  suit for  contribution.   The district
    court believed, as  do we,  that it was  required to  resolve
    only certain aspects of  the dispute over "matters addressed"
    in order  to fulfill  its responsibilities in  evaluating the
    consent  decree.   Not every  aspect of  interpretation of  a
    consent  decree (or  even  the precise  contours of  "matters
    addressed") need be resolved in the course of approval of the
    -11-
    11
    decree.6    Rather, the  court must  address  so much  of the
    interpretation of the consent decree as needed to rule on the
    decree's  fairness,   reasonableness  and  fidelity   to  the
    statute.7   See  United  States v.  Charles George  Trucking,
    Inc., 
    34 F.3d 1081
    , 1088-89 (1st Cir.  1994).  There  may be
    prudential reasons, as this case demonstrates, not to resolve
    more  as  to "matters  addressed"  than is  necessary.   Such
    reasons, for example, may be related to uncertainty as to the
    specific fact  situations  in which  contribution claims  may
    arise or to  the absence  of parties whose  interests may  be
    affected.8   As  Aristotle noted,  wisdom  does not  seek for
    6.  For example, in order to achieve an agreement the parties
    may,  on  relatively  minor  matters,  engage  in  purposeful
    ambiguity, leaving to  another day a  battle which may  never
    need to be fought.  If  that ambiguity is not material to the
    tripartite test for approving a  consent decree, it would not
    be necessary to resolve  it.  Perforce, it may  be preferable
    to leave it unresolved.
    7.  Although the option  was open to  it, the district  court
    chose not to  consolidate the approval of  the consent decree
    and  the contribution  action,  for all  purposes.   District
    courts  may find such a consolidation useful, if the cases so
    warrant, to expedite and  clarify matters.  But they  are not
    required to  do so.   See Fed.  R. Civ. P.  42(a); 9  Moore's
    Federal Practice   42.02.
    8.  The arguments of the Acushnet Group and Charter, that the
    district court  was required  to determine  in the course  of
    approving  the consent  decree  all aspects  of all  possible
    contribution claims, prove too much.  The    district   court
    noted that  "[t]o the extent that there  is uncertainty about
    the precise implication"  that the  settlement agreement  may
    have, "it may be  necessary in later proceedings for  this or
    another  court   to  interpret  both  the   statute  and  the
    agreement."   It would have  been premature for  the district
    court  to issue a broad order without specific facts on which
    to base its  ruling.  Cf. Charles George Trucking, 34 F.3d at
    -12-
    12
    greater  precision than  the  nature of  the subject  admits.
    Aristotle, Nicomachean Ethics I.3, 1094b23-28 (Martin Ostwald
    ed. & trans., 1962).
    Interpretation of the Decree
    We dispose first of an  initial argument.  The United
    States  urges that,  by  consenting to  entry of  the decree,
    Charter  has  waived  its  right to  challenge  the  district
    court's interpretation of the decree.  We disagree.  "[I]t is
    possible  for  a party  to consent  to  a judgment  and still
    preserve his right to appeal," so long as he "reserve[s] that
    right unequivocally."   Coughlin v. Regan, 
    768 F.2d 468
    , 470
    (1st Cir. 1985).   Charter's Notice of  Objection makes clear
    that  it objected to, and  intended to preserve  its right to
    appeal,  any interpretation  of the  decree that  afforded it
    less than full protection against contribution claims arising
    out of the Sullivan's Ledge Site.  That suffices.
    Charter says  the decree must be  interpreted so that
    the "matters  addressed" by it  encompass all aspects  of the
    clean-up  and  remediation  of  the  Sullivan's  Ledge  Site,
    including  all  "matters  addressed"  in the  1991  and  1993
    Decrees.   Charter  argues, consequently,  that it  cannot be
    reached for contribution  at all.   The government says  that
    1088.   The district  court was also  appropriately concerned
    that  not all  potentially affected  parties were  before it.
    The  district court did what was necessary in order to decide
    the issues on approval of the decree and it was certainly not
    error to go no further.
    -13-
    13
    the "matters addressed" in the Charter  decree do not include
    the  clean-up work  that  the prior  settlors are  performing
    under their consent decrees.   Therefore, it asserts that the
    Charter decree  does not cut off  completely the contribution
    rights  of  prior  settling  parties  against  Charter  under
    Section 113(f) of  CERCLA   for costs of  remediation of  the
    Site.    The  government   further  says  that  the  "matters
    addressed"  in  the   consent  decree   encompass  only   the
    government's  "remainder"  case   against  Charter  for  that
    portion of the overall site liability  that was not addressed
    in the  prior settlements,  i.e., the government's  claim for
    the past and  future response costs that  were not reimbursed
    or covered by the prior settlements and for implementation of
    those aspects  of RODs I and II that are not performed by the
    prior settlors.
    The district  court did  rule on  this dispute as  to
    "matters  addressed," and  ruled  against Charter.   It  left
    other  aspects to  be resolved  in the  parallel contribution
    action brought by the Acushnet Group against Charter.
    In  reviewing  the  district court's  ruling  on  the
    "matters addressed"  by the  decree we  look to  the decree's
    "four corners."  See United States  v. Armour & Co., 
    402 U.S. 673
    , 681-82 (1971).   In   United States  v. ITT  Continental
    Baking Co., 
    420 U.S. 223
     (1975), the Court expounded  on the
    "four corners" rule of Armour:
    -14-
    14
    Since  a consent  decree  or order  is to  be
    construed for  enforcement purposes basically
    as a contract, reliance upon certain  aids to
    construction is proper, as with any contract.
    Such    aids   include    the   circumstances
    surrounding  the  formation  of  the  consent
    order, any technical  meaning words used  may
    have  had  to  the  parties,  and  any  other
    documents   expressly  incorporated   in  the
    decree.
    
    Id. at 238
    .
    The district  court held that it  would not interpret
    the   decree  as   Charter   contended  and   that  such   an
    interpretation  "would be  extreme in  its consequence  as to
    what   the    government   gave   up   compared    with   the
    disproportionately small cash sum the  government received in
    return."  It further stated that such an interpretation would
    be "disapproved as contrary to the public interest."
    The  determination of interpretation of the decree is
    iterative  and proceeds  incrementally, as  in most  areas of
    law,  with  priorities  for   reaching  different  levels  of
    analysis.   Cf. Lomas Mortgage, Inc., v.  Louis, No. 95-1956,
    F.3d   ,   , slip  op. at 9-10 (1st Cir.  1996) (statutory
    interpretation starts with the  plain meaning of the statute,
    but where  the statute is ambiguous,  legislative history may
    be considered); Massachusetts v. Blackstone Valley Elec. Co.,
    
    67 F.3d 981
    , 987 (1st Cir. 1995) (same).  As in most contract
    interpretation questions, we start  here with the text.   See
    Fashion House, Inc. v. K Mart Corp., 
    892 F.2d 1076
    , 1083 (1st
    Cir. 1989).
    -15-
    15
    Unfortunately, apparently due  to EPA  policy at  the
    time,9  there is  no explicit  "matters addressed"  clause in
    the  agreement.    Charter  argues  that,  nonetheless,   the
    district  court should  have interpreted  "matters addressed"
    broadly in light of  the contribution protection and covenant
    not to sue  clauses of  the agreement, as  well as  extrinsic
    evidence, particularly of the parties' negotiating history.
    In  the  absence of  explicit  language,  the parties
    agree, citing to contribution  cases from other circuits, one
    must first  look elsewhere to  determine "matters addressed."
    Different circuits have taken somewhat  different approaches.
    In Akzo Coatings, Inc. v. Aigner Corp., 
    30 F.3d 761
     (7th Cir.
    1994), the  Seventh Circuit  started with the  decree itself,
    and, in the absence of  an express "matters addressed" clause
    looked to various factors including "the particular location,
    time frame, hazardous substances, and clean-up  costs covered
    by the agreement."  
    Id. at 766
    .   That court recognized, over
    a dissent, that its "flexible, fact-based approach" would not
    offer  the "settling parties the same degree of repose as one
    9.  The  absence  of  specific  language  concerning "matters
    addressed" might be thought  to be of concern to the  EPA and
    the  public.    Having   the  scope  of  "matters  addressed"
    specifically agreed upon should lead to greater certainty and
    finality.     That  certainty  and  finality  are  attractive
    inducements  to  settle.    The  uncertainty  and  continuing
    litigation which  this case  exemplifies could reasonably  be
    thought  to be  a  deterrent to  others  to settle  with  the
    government.   Charter  advises  us  that the  EPA,  in  1995,
    changed  its policy  to require  that "matters  addressed" be
    specified.
    -16-
    16
    based solely  on the facial  breadth of the decree."   
    Id. at 767-68
    .   The dissent preferred a  broader reading, reasoning
    that more comprehensive contribution protection would lead to
    more  settlements.     See  
    id. at 773
      (Easterbrook,  J.,
    dissenting).  The Tenth Circuit  in United States v. Colorado
    & Eastern R.R. Co., 
    50 F.3d 1530
    , 1538 (10th Cir. 1995), took
    a related  "fact-specific approach,"  laying the  earlier and
    the      later      "consent      decrees     [and      their
    attachments] . . . . side by  side and comparing  the matters
    covered in  relation to the  remediation completed . . . . at
    the date of the [second] consent decree."
    We  reject  any  argument  that  Section  113(f)(2)
    itself warrants a broad  understanding of "matters addressed"
    by the decree,  just as Colorado & Eastern, 50  F.3d at 1537-
    38,  and Akzo, 
    30 F.3d at 765, 770
    ,  rejected this argument.
    The  statute  does  not  dictate any  particular  method  for
    assessing the scope of the decree.  See Akzo, 
    30 F.3d at 765
    .
    Thus,  the district  court  appropriately rejected  Charter's
    argument based on paragraph 16 of  the proposed decree, which
    provides:
    With  regard  to   claims  for   contribution
    against  [Charter]  for matters  addressed in
    this  Consent Decree the parties hereto agree
    that [Charter] is entitled to such protection
    from contribution  actions  or claims  as  is
    provided  by  CERCLA  Section  113(f)(2),  42
    U.S.C.   9613(f)(2).
    -17-
    17
    This  language  simply  repeats  the  statutory  contribution
    language  of  Section  113(f)(2),  without  defining "matters
    addressed."   Charter says that  this language in  the decree
    would  be meaningless  unless its interpretation  is adopted.
    That  is  not so.   The  language  may provide  protection to
    Charter  should  the  government  later  recover  from  other
    parties a part of its claim.
    We  confine ourselves to  the text of  the decree and
    find  the answer there, thus  not reaching the  issue of what
    other  interpretive guides,  if  any, are  permissible  under
    CERCLA.   We are  unpersuaded by Charter's  argument that the
    text of the decree supports its reading.  We believe that the
    text  of the  decree  as  to: (i)  the  scope of  the  claims
    purported to be  brought and settled; (ii)  the definition of
    the response  costs being  reimbursed by the  settlement; and
    (iii)   the  explicit  references   to  the   prior  decrees,
    forecloses Charter's interpretation.
    Charter relies heavily  on the decree's  covenant not
    to  sue  clause, which  prevents  the  government from  suing
    Charter  "pursuant to Sections  106 and 107(a)  of CERCLA and
    Section  7003 of  RCRA relating  to the  Site, including  for
    reimbursement of Response costs  or for implementation of ROD
    I or  ROD II."  But  that the government has  promised not to
    sue Charter  says nothing about  the intention as  to whether
    other, prior settling  parties were to  have their rights  of
    -18-
    18
    contribution  against Charter extinguished by this agreement.
    The one does not necessarily follow from the other.
    Untoward and  congressionally unintended consequences
    would flow from  Charter's reading.   As the Seventh  Circuit
    observed in Akzo:
    If the covenant not to sue alone were held to
    be determinative of the scope of contribution
    protection,  the United  States would  not be
    free to release settling parties from further
    litigation  with  the United  States, without
    unavoidably  cutting  off  all private  party
    claims for response costs.
    
    30 F.3d at 766
     (quoting  brief of United  States as amicus).
    We agree.   The  government may have  reasons to give  such a
    covenant unrelated  to an intent to  grant broad contribution
    protection against prior settlors.
    We find  dispositive instead  the text of  the decree
    establishing  that  Charter  was  sued  on  the  government's
    remainder case, that the government sought and Charter agreed
    to reimburse the government for its response costs as to that
    remainder  case,  and that  the  remainder  case was  defined
    against the backdrop of the prior settlements.
    The text  describing the scope  of the  claims to  be
    brought   and   settled    undermines   Charter's    proposed
    interpretation:
    The  United  States  in its  complaint  seeks
    reimbursement of response costs  incurred and
    to be  incurred by EPA and  the Department of
    Justice  for  response actions  in connection
    with the  release  or threatened  release  of
    hazardous substances at the  Sullivan's Ledge
    Superfund  Site  in   New  Bedford,   Bristol
    -19-
    19
    County, Massachusetts . . . and a declaration
    of  the  defendants'  liability  for  further
    response costs.
    Neither the complaint nor the  decree asserts a claim against
    Charter for  the remediation work being done  by the Acushnet
    Group.  A  reading of a decree  which far exceeds  the relief
    sought  by  plaintiffs'  complaint   would  be  strained  and
    doubtful.   See  Navarro-Ayala v.  Hernandez-Colon, 
    951 F.2d 1325
    , 1341 (1st Cir. 1991).  Even crediting the argument that
    some settlements  may exceed the boundaries of claims made in
    the complaint,10 there is  nothing in this decree to  lead to
    that result.11
    10.  Cf.  Charles  George Trucking, 
    34 F.3d at 1090
     (consent
    decree   may   resolve   claims  for   damages   not  pleaded
    specifically, if the parties so intend, so long as the claims
    are within the general scope of the pleadings).
    11.  We  note the  potential  problem of  the government  not
    honoring its  agreement with  prior  settlors by  collusively
    agreeing  with  subsequent  settlors  on  language  in  their
    agreement broader than the claims the government made against
    those  subsequent  settlors.    Cf.  Akzo,  
    30 F.3d at 774
    (Easterbrook,  J.,  dissenting)  (making  an  analogous point
    about the government inducing PRPs to enter large settlements
    with promises of broad contribution protection and then later
    urging the  district court  to arrive  at a  narrow reading).
    That is not this case.  The district court here expressed its
    skepticism   that  the   earlier  settlement   empowered  the
    government  to  do whatever  it  wished  about impairing  the
    contribution rights that were  retained by the prior settling
    parties.   The  government has  expressly disavowed  any such
    intention.
    In  addition, the government has a serious disincentive
    to collude with later settlors to cut off the rights of prior
    settlors just to extract  a higher second-round settlement in
    a single clean-up proceeding.   It is the government  that is
    the repeat player in  the world of CERCLA clean-ups.   Should
    the  government  develop  a  reputation  for  cheating  early
    settlors,  that would  deter settlements  in later  clean-ups
    -20-
    20
    The definition  of response costs in  the decree also
    does  not  support  Charter's  interpretation.    The  decree
    defines Charter's $215,000 payment as being "in reimbursement
    of  Response Costs,"  which are  defined as  the government's
    response  costs.   The  decree says  "the  United States  has
    incurred, and  will continue  to incur, response  costs which
    have  not been recovered under the 1991 Consent Decree or the
    1993 Consent Decree."   The decree estimates the government's
    shortfall to exceed $4  million in such response costs.   The
    decree  also  indicates  that  the  government  evaluated the
    $215,000  to be paid by Charter in terms of these unrecovered
    costs  of  at  least  $4  million  and  the  risk  that  some
    remediation work may not be completed by other settlors.  The
    amount was not evaluated against  the total costs of clean-up
    at the Sullivan's Ledge Site.
    Further,  as the government  points out,  the Charter
    decree explicitly  refers  to the  earlier decrees.   In  the
    prior settlements  the Acushnet  Group did  not  give up  the
    right  to seek contribution from  those who were  not part of
    those  settlements.   The  prior  settlements are  explicitly
    referenced and described  in the Charter decree.   Under such
    circumstances  we  may consider  these  prior  settlements in
    interpreting the  decree.    Cf. ITT Continental  Baking, 420
    (and reduce  the amounts early-round settlors  are willing to
    pay)  and  hence, in  the  long  run,  hurt the  government's
    interests.
    -21-
    21
    U.S. at 238.  In light of these considerations,  we hold that
    the   text   of   the   decree   supports  the   government's
    interpretation and  not Charter's and so  affirm the district
    court's ruling on this point.
    Charter argues that the  decree is ambiguous and that
    extrinsic evidence of the  negotiating history of the parties
    demonstrates that  Charter was intended to  be protected from
    all contribution claims. Cf. Thomas Hobbes, Leviathan Ch. XI,
    at  84   (Michael  Oakeshott  ed.  1962)   (1651)  (men  call
    indeterminate that  which they  wish to contest  because they
    have  interests  at  stake).     While  in  routine  contract
    interpretation extrinsic  evidence may be considered when the
    disputed  terms  are ambiguous,  we  do not  find  the decree
    ambiguous,  and  such  evidence  may  not  be  considered  to
    contradict  the written terms of the  agreement.  See Brennan
    v. Carvel Corp., 
    929 F.2d 801
    , 808 (1st Cir. 1991).
    Even so,  we  doubt, but  do not  decide, whether  in
    interpreting a CERCLA consent  decree it would be appropriate
    to rely on the  type of extrinsic evidence  Charter proffers.
    This court has at times considered certain types of extrinsic
    evidence in interpreting decrees  in public institution civil
    rights  actions.  See Navarro-Ayola,  
    951 F.2d at 1343
    .  But
    CERCLA settlements, unlike ordinary contract  formation, take
    place  in  a  unique  statutory framework.    That  framework
    requires that before a decree is entered by the court, notice
    -22-
    22
    of  the  decree be  published,  there be  an  opportunity for
    public comment, and that the Attorney General take account of
    the  commentary and  reserve  the right  to withhold  consent
    should the  commentary show  the decree to  be inappropriate.
    42 U.S.C.   9622(d)(2).  That  public comment is part of  the
    record  before  the  district  court.    
    Id.
       The  statutory
    structure  thus assumes that the  public will be given access
    to the relevant documentary information  on the decree.   The
    evidence  of the negotiating  history which Charter proffered
    was not within the information the public had available.12
    It is  worth  asking why  the  court should  enter  a
    consent decree when there was  a fundamental dispute over the
    effect of the decree.  There are two responses.  The first is
    that  Charter  expressed its  intent  to  live with  whatever
    interpretation the court ultimately gave the decree. There is
    no unfairness to  Charter.  When Charter said that it had not
    understood the government's position to be that Charter would
    not  be   afforded  complete  contribution   protection,  the
    government  offered to  allow  Charter to  withdraw from  the
    agreement.   Charter declined.   Charter knew  the government
    would  present  a  contrary interpretation  to  the  district
    12.  Even were we to  adopt Charter's method of analysis,  we
    see nothing in the  negotiating materials that indicates that
    the  government intended to  undercut its earlier settlements
    with the Acushnet Group or that it ever agreed with Charter's
    view  on the scope of contribution protection afforded by the
    decree.
    -23-
    23
    court.   Charter also knew  that courts are  required to give
    some deference to  the judgment of the Attorney  General that
    the settlement  is appropriate.13   Charles George  Trucking,
    
    34 F.3d at 1085
    .   In  addition,  the district  court  gave
    Charter the  opportunity to  withdraw from the  settlement in
    the face  of a contrary  government position and  the court's
    statement that  it would  most likely rule  against Charter's
    interpretation.  Charter again declined.  Counsel for Charter
    informed the court that, win or lose in its interpretation of
    the decree, Charter preferred  to have an agreement  with the
    government.  Such  an agreement, Charter  acknowledged, would
    both provide it with some  contribution protection and get it
    out  of costly  litigation with the  government.   Indeed, on
    appeal, Charter does not ask us to vacate the decree.  Rather
    its position is that the decree should be upheld and that its
    interpretation should be substituted for that of the district
    court.
    Second,  while  a  different  case might  lead  to  a
    different result,  we think  that the policies  behind CERCLA
    are better served here by holding Charter to the consequences
    of its  roll  of  the dice.    Perhaps mindful  of  the  huge
    13.  We   reject  the  Acushnet  Group's  argument  that  the
    district court is required to defer to the Attorney General's
    judgment to the extent  of exercising no independent judgment
    of  its own.  See Charles  George Trucking,  
    34 F.3d at 1085
    (although in entering a decree a district court must defer to
    the  EPA's judgment and to  the parties' agreement,  it has a
    responsibility to exercise its independent judgment).
    -24-
    24
    resources  going  into  the  transactions   costs  of  CERCLA
    litigation,  rather   than   to  remediating   the   sites,14
    Congress sought  in SARA to encourage  earlier resolutions by
    agreement.   See United States  v. SCA Servs.  of Ind., Inc.,
    
    827 F. Supp. 526
    , 530-31  (N.D. Ind. 1993).  If a  party were
    permitted to use the consent decree process to delay, whether
    in  good faith  or by design,  and then  to undo  a decree by
    saying  its understanding  of the  base terms  was different,
    then  the  congressional purposes  would  be  undercut.   Cf.
    Menorah,  
    72 F.3d at 223
    .   Given that  Charter voluntarily
    chose  to consent to the decree, despite the significant risk
    of an  interpretation contrary to  its interests, it  was not
    unreasonable  for  the district  court  to  have entered  the
    decree.
    Approval of the Consent Decree
    There  was no  abuse  of discretion  by the  district
    court in approving the decree,  as based on the  government's
    14.  See  Jan Paul  Acton  & Lloyd  S.  Dixon, Superfund  and
    Transaction Costs:  The Experience of Insurers and Very Large
    Industrial   Firms   32   (1992)(estimating   that   of   the
    approximately  $470  million paid  in  1989  by insurers  for
    hazardous waste clean-ups, 88% went to legal costs); see also
    Lloyd  S.   Dixon,  The  Transactions   Costs  Generated   by
    Superfund's  Liability Approach 183,  in Analyzing Superfund:
    Economics, Science  and Law, (Richard L. Revesz  & Richard B.
    Stewart eds.,  1995)(noting that  for 1991 alone  the private
    sector  incurred over  $4  billion  in  transactions  costs);
    William  N. Hedeman  et al.,  Superfund Transaction  Costs: A
    Critical Perspective  on the  Superfund Liability  Scheme, 
    21 Envtl. L. Rep. 10413
    , 10423 (1991) (30-60% of hazardous waste
    clean-up funds go to lawyers).
    -25-
    25
    interpretation.   We  note  that Charter  does not  seriously
    challenge  on  this  point,  preferring  to  argue  that  its
    interpretation is mandated and that its interpretation  meets
    the tripartite  test.  The district court,  before entering a
    consent  decree, is  obliged to  determine that  it is  fair,
    reasonable and consistent with the goals of CERCLA.  DiBiase,
    
    45 F.3d at 543
    ;  Cannons,  
    899 F.2d at 85
    .    In turn,  "an
    appellate court  may overturn a district  court's decision to
    approve or reject the  entry of a CERCLA consent  decree only
    for manifest abuse of  discretion."  Charles George Trucking,
    
    34 F.3d at 1085
    .
    Under the terms  of the decree Charter  agreed to pay
    $215,000  plus interest,  in settlement  of the  government's
    claims of  approximately $4  million in  unrecovered response
    costs  for the  first  and second  units.   In  exchange  the
    government  covenanted  not  to  sue  or take  administrative
    action against  Charter "pursuant to Sections  106 and 107(a)
    of  CERCLA  or Section  7003 of  RCRA  relating to  the Site,
    including    for   reimbursement   of   Response   Costs   or
    implementation   of  ROD  I  or  ROD  II."15    Charter  also
    15.  The  government's  covenant not  to  sue  is subject  to
    certain  reservations, including:  (a) that  with respect  to
    future  liability, the covenant not to sue does not come into
    effect until  certification by  the EPA that  remedial action
    for  the site under  ROD I and  Rod II is  completed; and (b)
    reopener  provisions  which  allow  the  government  to  seek
    further   relief   if   previously  unknown   conditions   or
    information reveal that the remedial actions for the site are
    not protective of human health or the environment.
    -26-
    26
    receives  protection against  contribution  claims  of  other
    parties  from whom the  government might subsequently recover
    all or part of its multi-million dollar remainder claim.
    Fairness & Reasonableness
    Fairness  has a procedural  component (involving the
    negotiation  process, see Cannons, 
    899 F.2d at 85
    ), which is
    not at  issue here,  and a  substantive component, which  is.
    
    Id. at 86
    .    "Substantive  fairness  introduces  into  the
    equation concepts  of corrective justice  and accountability:
    a  party should  bear the cost  of the  harm for  which it is
    legally responsible . . . .   The logic behind these concepts
    dictates  that  settlement  terms  must be  based  upon,  and
    roughly   correlated   with,  some   acceptable   measure  of
    comparative fault, apportioning liability among  the settling
    parties  according  to  rational (if  necessarily  imprecise)
    estimates of how  much harm each PRP has done."  Cannons, 
    899 F.2d at 87
     (citations  omitted);  see  also Charles  George
    Trucking,  
    34 F.3d at 1089
      (so  long as  the  basis  for a
    sensible   "approximation   `roughly  correlated   with  some
    acceptable   measure   of    comparative   fault'"    exists,
    "difficulties   in   achieving   precise    measurements   of
    comparative  fault  will  not  preclude a  trial  court  from
    entering  a consent  decree"  (quoting Cannons,  
    899 F.2d at 87
    )).
    -27-
    27
    A  district court's reasonableness inquiry, like that
    of  fairness,  is  a  pragmatic one,  not  requiring  precise
    calculations.   See Charles George  Trucking 
    34 F.3d at 1085
    (depth  of inquiry  depends  on the  context and  information
    available  to the court).  The question is whether the decree
    provides for an efficient clean-up and adequately compensates
    the public for its  costs, in light of the  foreseeable risks
    of loss.  See Cannons, 
    899 F.2d at 89-90
    .  Because the first-
    round  settlors  have  already  contracted  to implement  the
    clean-up,  we  review only  the  adequacy  and efficiency  of
    implementing the cash settlement  reached here.  This amounts
    to asking  whether the  terms of  the settlement  are roughly
    proportional  to  Charter's responsibility  and  whether they
    serve the public interest.
    Approval of Charter's cash-out settlement of $215,000
    plus  interest  in  exchange  for  both limited  contribution
    protection  and  a  limited  covenant  not  to sue  from  the
    government cannot be said  to constitute a manifest abuse  of
    discretion.  Although $215,000 is small  in absolute terms as
    compared to the government's total unrecovered response costs
    of  $4  million,  it  must  be  evaluated  in  context.    In
    particular, Charter's liability  in this case was  uncertain.
    It was not clear  whether Pacific Oil, the company  which had
    contributed  to  the  wastes   at  the  Site,  was  Charter's
    predecessor.  The degree to which the predecessor's wastes --
    -28-
    28
    soot  from oil  fuel --  contained hazardous  substances that
    would have  contributed to the Site's  contamination was also
    at issue.  Given  the potentially high costs of  litigating a
    difficult case  against Charter and the benefit  of a certain
    cash  settlement (and  the limited  contribution protection),
    the $215,000 plus interest payment passes muster.  This court
    explained in Cannons:
    In  a  nutshell,  the  reasonableness   of  a
    proposed  settlement  must take  into account
    foreseeable  risks of  loss. . . .   The same
    variable,   we   suggest,   has   a   further
    dimension: even if  the government's case  is
    sturdy, it may take time and money to collect
    damages  or  to  implement  private  remedial
    measures  through litigatory success.  To the
    extent  that  time  is  of  essence  or  that
    transaction  costs  loom large,  a settlement
    which nets less than  full recovery of clean-
    up  costs  is  nonetheless  reasonable. . . .
    The  reality   is   that,  all   too   often,
    litigation is  a cost-ineffective alternative
    which can squander valuable resources, public
    as well as private.
    
    899 F.2d at 90
      (citations omitted).  In addition,  there are
    other non-first-round settlors against whom the government is
    currently seeking to recover the  remainder of its $4 million
    claim.
    The  question arises  as  to whether  the decree,  as
    entered, unfairly hurts the interests of third  parties.  See
    Charles George Trucking, 
    34 F.3d 1085
    -89 (addressing  third-
    party  challenge  to entry  of CERCLA  consent decree).   For
    purposes of  our review,  the district  court's determination
    that  the  decree  does  not  represent  a  complete  bar  to
    -29-
    29
    contribution  claims  that first-round  settlors  expected to
    have against those  that did  not settle along  with them  is
    adequate to  pass the abuse  of discretion threshold.16   Cf.
    Charles  George Trucking,  at 1088 (in  entering a  decree it
    might be better to  leave technical disputes between settling
    parties in a class to the discourse between them).  As to the
    extinguished  contribution  claims of  non-settlors  or later
    round  settlors,  protection  against  those   claims  was  a
    reasonable benefit Charter acquired in exchange  for settling
    before those others.
    Fidelity to the Statute
    As we noted in Cannons, the two major policy concerns
    underlying  CERCLA are  ensuring  that  prompt and  effective
    clean-ups  are put into place  and making sure  that the PRPs
    responsible for the  hazards created  bear their  approximate
    share of the responsibility.   
    899 F.2d at 89-91
    ;  cf. United
    States v. Rohm  & Haas  Co., 
    721 F.Supp. 666
    ,  680 (D.  N.J.
    1989) (noting Congress' goal of expediting effective remedial
    16.  In the separate contribution action between the Acushnet
    Group  and Charter,  Charter  had asserted  that the  consent
    decree provided  it with  an affirmative defense  against the
    Acushnet Group's contribution claims.  The Acushnet Group, in
    turn,  moved for summary judgment on the issue of whether the
    decree afforded Charter such a  defense.  The district  court
    denied  the motion  without  ruling on  its  merits.   It  is
    basically  that motion  that the  parties want us  to decide.
    However, absent  unusual circumstances,  denial of a  summary
    judgment motion  is not  independently appealable as  a final
    order.  See Pedraza v. Shell Oil Co., 
    942 F.2d 48
    , 54-55 (1st
    Cir.  1991), cert.  denied, 
    502 U.S. 1082
      (1992).   No such
    circumstances exist here.
    -30-
    30
    action and minimizing litigation).  Both  these goals and the
    honoring of the settlement  dynamics Congress created in SARA
    are effectuated here.
    CERCLA, through Section 113(f)(2),  provides settling
    parties with broad contribution protection so as to encourage
    them to settle early.   See Browning-Ferris, 33 F.3d  at 102-
    03.   However, CERCLA also  aims to induce  those parties who
    settle  earlier to do so  for higher amounts  than they might
    otherwise  by assuring  them the  right to  seek contribution
    protection from those  who have  not as yet  settled.17   See
    42  U.S.C. 9613(3)(B); see also  S. Rep. No.  11, 99th Cong.,
    1st Sess. 44 (1985); cf. Colorado & Eastern, 50  F.3d at 1535
    (Section  113(f)(1) was  intended to  enable those  bearing a
    disproportionate  share of  the  liability in  a clean-up  to
    recover from others).   Hence, a  decree that is read  not to
    provide  second-round  settlors  with  complete  contribution
    protection against prior settlors is consistent with the goal
    of enabling  the government  to enter  into  early and  large
    17.  An early cash-out  settlement may sometimes require  the
    settling  party to pay a premium for the risks the government
    bears out of the uncertainty of the total cost of the remedy.
    As more is known about the site and as the government decides
    on  the  precise  remedy,  that uncertainty,  and  hence  the
    premium, is reduced, but not eliminated.  Here, there were no
    settlements  until the  RODs were issued  and the  remedy was
    outlined.  Nonetheless,  early settlors,  even post-ROD,  may
    pay some premium.  Settlors  who actually perform the remedy,
    such  as the Acushnet Group,  assume the risks  of the actual
    costs of performance.  Congress may well have thought it fair
    to  require later settlors to bear a share of those risks and
    premiums.
    -31-
    31
    settlements.   Cf. Akzo,  
    30 F.3d 767
      (interpreting "matters
    addressed" clause  of decree not to  bar the claims  of a PRP
    that  had undertaken  remedial  work prior  to  entry of  the
    decree); United  States v.  Alcan  Aluminum, Inc.,   
    25 F.3d 1174
    , 1186  n.17 (3d  Cir. 1994)  (in light  of  the goal  of
    promoting  early  large  settlements,   the  assertion  of  a
    contribution  defense by  a  second-round  settlor against  a
    first-round  settlor  is   far  more  problematic  than   its
    assertion against a non-settlor).
    Conclusion
    The  district  court's  order  entering  the  consent
    decree is affirmed.
    -32-
    32
    

Document Info

Docket Number: 95-1961

Filed Date: 5/9/1996

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (17)

Roberto Navarro-Ayala v. Rafael Hernandez-Colon , 951 F.2d 1325 ( 1991 )

United States of America v. Charles George Trucking, Inc. , 34 F.3d 1081 ( 1994 )

Amf Incorporated v. Raymond L. Jewett , 711 F.2d 1096 ( 1983 )

United States v. Ugo Dibiase, Etc. , 45 F.3d 541 ( 1995 )

Menorah Insurance v. INX Reinsurance Corp. , 72 F.3d 218 ( 1995 )

Fashion House, Inc. v. K Mart Corporation, Fashion House, ... , 892 F.2d 1076 ( 1989 )

Akzo Coatings, Incorporated, and the O'Brien Corporation v. ... , 30 F.3d 761 ( 1994 )

Richard Coughlin v. Donald Regan, Secretary of the Treasury , 768 F.2d 468 ( 1985 )

Commonwealth of Massachusetts v. Blackstone Valley Electric ... , 67 F.3d 981 ( 1995 )

robert-brennan-and-joanne-brennan-v-carvel-corporation-and-raymond , 929 F.2d 801 ( 1991 )

united-states-of-america-v-cannons-engineering-corp-appeal-of-olin-hunt , 899 F.2d 79 ( 1990 )

cruz-pedraza-alejandrina-pedraza-roberto-pedraza-and-mary-ellen-pedraza , 942 F.2d 48 ( 1991 )

united-states-v-alcan-aluminum-inc-champion-auto-generator-service-inc , 25 F.3d 1174 ( 1994 )

United States v. SCA Services of Indiana, Inc. , 827 F. Supp. 526 ( 1993 )

United States v. ITT Continental Baking Co. , 95 S. Ct. 926 ( 1975 )

United States v. Armour & Co. , 91 S. Ct. 1752 ( 1971 )

United States v. Rohm & Haas Co. , 721 F. Supp. 666 ( 1989 )

View All Authorities »