Labor Relations Division of Construction Industries of Massachusetts, Inc. v. International Brotherhood of Teamsters, Local 379 , 29 F.3d 742 ( 1994 )


Menu:
  •                   UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT
    No. 93-2122
    LABOR RELATIONS DIVISION OF CONSTRUCTION
    INDUSTRIES OF MASSACHUSETTS, INC., ET AL.,
    Plaintiffs-Appellees,
    v.
    INTERNATIONAL BROTHERHOOD OF TEAMSTERS, CHAUFFERS,
    WAREHOUSEMEN AND HELPERS OF AMERICA, LOCAL #379,
    Defendant-Appellant.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. A. David Mazzone, U.S. District Judge]
    Before
    Breyer,* Chief Judge,
    Coffin, Senior Circuit Judge,
    and Torruella, Circuit Judge.
    Paul F. Kelly,  with whom Anne R. Sills and Segal, Roitman &
    Coleman were on brief for appellant.
    John D. O'Reilly  III, with  whom O'Reilly &  Grosso was  on
    brief for appellees.
    July 19, 1994
    *   Chief Judge Stephen Breyer heard oral argument in this matter
    but did not  participate in the drafting  or the issuance  of the
    panel's  opinion.   The remaining  two panelists  therefore issue
    this opinion pursuant to 28 U.S.C.   46(d).
    TORRUELLA, Circuit  Judge.   The circumscribed  role of
    federal  courts reviewing  arbitration awards  in labor  contract
    disputes is now well established.  As the  Supreme Court found in
    United  Paperworkers Int'l Union v. Misco, Inc., 
    484 U.S. 29
    , 36-
    45 (1987), courts must resist the temptation  to substitute their
    own  judgment about  the  most  reasonable  meaning  of  a  labor
    contract for that  of the  arbitrator and avoid  the tendency  to
    strike down even an arbitrator's erroneous interpretation of such
    contracts.     Instead,   courts  must   confine  themselves   to
    determining whether the arbitrator's construction of the contract
    was in any way plausible.
    The issue in this case is whether any plausible reading
    of a  collective bargaining  agreement  supports an  arbitrator's
    ruling   in  a   dispute  over   fringe   benefit  contributions.
    Plaintiffs-appellees, J.M.  Cashman, Inc. and R.  Zoppo Co., Inc.
    (the  "plaintiffs"  or  "Cashman   and  Zoppo"),  challenged  the
    arbitration   order,   which  favored   the  defendant-appellant,
    International Brotherhood of Teamsters,  Chauffeurs, Warehousemen
    and Helpers of American, Local 379 (the "Union"), in the district
    court.   The  district court  vacated the  arbitration award  and
    remanded  the dispute to the  arbitrator for a  new resolution of
    the  case.   Because  we find  that  the district  court  stepped
    outside  of  its  highly  circumscribed  role  of  assessing  the
    plausibility of the arbitrator's interpretation  of the agreement
    between   the   parties,   we   reverse   the  court's   holding.
    Nevertheless,  we agree  with the  district  court that  the case
    -2-
    should  be remanded to the arbitrator for resolution of a related
    issue of federal law.
    I.  BACKGROUND
    This case arises  out of the  arbitration of a  dispute
    between the Union and  a group of contractor-employers, including
    plaintiffs  Cashman and  Zoppo, involved  in the  construction of
    waste water  treatment facilities  in Boston Harbor  (the "Boston
    Harbor Project").  On  March 2, 1992, the Union  filed grievances
    against Cashman, Zoppo, and six other project employers, claiming
    that truck drivers  on the  Boston Harbor Project  who owned  and
    drove  their  own  trucks,  so  called "owner-operators,"  should
    receive certain  fringe benefit contributions  that the employers
    were  already paying  on behalf  of other  Boston  Harbor Project
    employees.    The  grievances  asserted that  the  Boston  Harbor
    Project  Labor Agreement  ("Project  Agreement"),  signed by  the
    Union  and  the employers,  required  that the  same  "health and
    welfare  contributions  and all  pension  contributions"  made on
    behalf of  other employees  must also  be made on  behalf of  the
    owner-operators.
    The employers  claimed that  they did  not have  to pay
    fringe benefits on behalf of owner-operators because the contract
    did not require it  and, more importantly, because the  Union and
    many  of the employers had a long-standing practice of not paying
    such  owner-operator  benefits  going  back at  least  twenty-six
    years.  According to the employers, this practice was established
    after the Union  and certain employer-contractors on a  number of
    -3-
    state  construction projects  (not  including  Cashman and  Zoppo
    themselves)  agreed  that, to  the  extent  a nucleus  of  owner-
    operator  truck  drivers  would  be  present  on  any  individual
    construction project, the  employers would not be required to pay
    fringe benefits  for the owner-operators.   The employers working
    on  the  Boston Harbor  Project, who  were  required to  sign the
    Project  Agreement in  order to  bid initially  on the  work, see
    Building  &  Constr.  Trades  Council v.  Associated  Builders  &
    Contractors,  Inc., 
    113 S. Ct. 1190
     (1993), rev'g,  
    935 F.2d 345
    (1st  Cir. 1991)  (en banc), maintained  that they  expected this
    established  practice  to  continue  as  in   previous  projects.
    Cashman and Zoppo, however, had never entered into  a contractual
    relationship  with the  Union before  the Boston  Harbor Project.
    Consequently, no past practices  had been established between the
    Union and the plaintiffs themselves.
    Pursuant to the Project Agreement, the dispute over the
    fringe benefits was brought  before an arbitrator for resolution.
    On January 20, 1993, the  arbitrator found in favor of  the Union
    and  ordered the  plaintiffs  and  the  other employers  to  pay,
    retroactively, post-grievance benefits  and to pay  future fringe
    benefit  contributions on  behalf  of  the  owner-operator  truck
    drivers.   In his accompanying opinion,  the arbitrator explained
    that  certain provisions  of the  Massachusetts Teamsters'  Heavy
    Construction   Agreement   ("Teamsters  Agreement"),   which  was
    incorporated into the Project  Agreement, in conjunction with the
    Project Agreement itself, explicitly obligated employers to  make
    -4-
    health  insurance  and pension  contributions  on  behalf of  the
    owner-operators in question.
    At  issue in  this appeal  is the  arbitrator's finding
    that  the past  practice of  not paying  the fringe  benefits for
    owner-operators did not bind the parties in this case because the
    Project Agreement "wiped the slate clean" of such past practices.
    The arbitrator relied on  the following language in  the preamble
    of the Project Agreement to support his finding:
    No  practice, understanding  or agreement
    between  a Contractor  and a  Union party
    which is not explicitly set forth in this
    Agreement shall  be binding on  any other
    party  unless endorsed in  writing by the
    Project Contractor.
    By  interpreting this language as negating all past practices and
    understandings  not  explicitly  set  forth  within  the  Project
    Agreement,  the  arbitrator disregarded  the  voluminous evidence
    presented  by  the  employers  of  the  established  practice  of
    excluding  owner-operators from fringe benefit contributions.  As
    a result,  the language  of the  Project Agreement granting  such
    benefits was found to be controlling.
    Also at  issue on  appeal is  the  related question  of
    whether   the  owner-operator   truck  drivers   are  independent
    contractors or  employees.  If they  are independent contractors,
    Section 302  of the Labor  Management Relations Act  ("LMRA"), 29
    U.S.C.    186,  would prohibit fringe  benefit payments  on their
    behalf.    The arbitrator  acknowledged  that  the employers  had
    argued that fringe benefit payments for the owner-operators would
    be illegal under  Section 302, but he  made no explicit  legal or
    -5-
    factual findings on the issue in his opinion.  While a  rejection
    of  the employers'  contention was  implicit in  the arbitrator's
    award favoring  the Union, nothing indicates  that the arbitrator
    actually determined whether the owner-operators were employees or
    independent contractors for purposes of the LMRA.
    Following  the entry of the arbitrator's award, Cashman
    and Zoppo filed a complaint in the district court on February 19,
    1993, requesting that  the court  vacate the award.   On  summary
    judgment,  the  district  court  held  that  the  arbitrator  had
    impermissibly exceeded his authority by misapplying the plain and
    unambiguous language of the Project Agreement preamble concerning
    past  practices, thereby  failing to  duly consider  the evidence
    that the parties had a practice of not paying fringe benefits for
    owner-operators.    The  district   court  found  that  the  past
    practices provision  of the  preamble -- particularly  the words,
    "no practice . . . shall be binding on any other party" (emphasis
    added)  --  clearly  and  unambiguously  meant  that  established
    practices between parties A and  B are not meant to  bind outside
    party C.  The court found that the phrase could not reasonably be
    interpreted to  mean that  all established practices,  even those
    between parties A  and B, are completely wiped out by the Project
    Agreement.   Consequently, the  court held  that the Union  could
    still  be  bound by  the past  practice  of not  requiring fringe
    benefit contributions for  owner-operators.   The district  court
    vacated  the  arbitrator's award  and  remanded the  case  to the
    arbitrator to  determine the merits,  giving proper consideration
    -6-
    to the evidence of past practices.
    The court  also left  for the  arbitrator the  issue of
    whether,  in light  of  the court's  holding that  past practices
    could   be  considered,   the  owner-operators   are  independent
    contractors,  thus rendering  the  payment of  benefits on  their
    behalf illegal.
    II.  ANALYSIS
    A.  Standard Of Review
    It  is well  established that  federal court  review of
    labor  arbitral  decisions, particularly  on matters  of contract
    interpretation,   is   extremely   narrow  and   "extraordinarily
    deferential."  Dorado Beach Hotel Corp. v. Uni n  de Trabajadores
    de la Industria Gastron mica Local 610, 
    959 F.2d 2
    , 3-4 (1st Cir.
    1992);  see,  e.g.,  Misco,  
    484 U.S. at 36-45
      (1987); Berklee
    College  of Music v. Berklee  Chapter of Mass.  Fed. of Teachers,
    Local 4412,  
    858 F.2d 31
    , 32  (1st Cir. 1988), cert.  denied, 
    493 U.S. 810
     (1989).   The  court may not  supplant the  arbitrator's
    determination of the  merits of  a contract dispute,  even if  it
    finds that determination  to be erroneous.   Rather, the  court's
    task is limited to determining if the arbitrator's interpretation
    of the contract is in any way plausible.   Misco, 
    484 U.S. at
    36-
    38;  United Steelworkers  of America  v. Enterprise  Wheel  & Car
    Corp.,  
    363 U.S. 593
    , 599  (1960) ("[S]o far  as the arbitrator's
    decision concerns  construction of the contract,  the courts have
    no business  overruling him  because their interpretation  of the
    contract is  different from  his."); El Dorado  Technical Servs.,
    -7-
    Inc.  v. Uni n General de  Trabajadores de Puerto  Rico, 
    961 F.2d 317
    , 319 (1st Cir.  1992) ("[A] court should uphold an award that
    depends  on  an  arbitrator's  interpretation   of  a  collective
    bargaining agreement if it  can find, within the four  corners of
    the agreement,  any plausible basis  for that  interpretation.");
    Dorado Beach, 
    959 F.2d at 4
    ; Bacard  Corp. v. Congreso de Uniones
    Industriales de Puerto Rico,  
    692 F.2d 210
    , 211 (1st  Cir. 1982).
    "[A]s long  as  the arbitrator  is  even arguably  construing  or
    applying  the  contract  and  acting  within  the  scope  of  his
    authority, that  a court is convinced he  committed serious error
    does not suffice to  overturn his decision."  Misco, 
    484 U.S. at 38
    .
    Only in  a few,  exceptional  circumstances are  courts
    able  to vacate  an arbitration  award.   When an  arbitrator has
    exceeded  his authority  by  ignoring the  clear and  unambiguous
    mandates or plain language  of the contract or by  construing the
    contract  in a way that cannot possibly be described as plausible
    or  rational, a  court  can overturn  the arbitrator's  judgment.
    Misco,  
    484 U.S. at 38
     (an  arbitrator's  award "must  draw its
    essence  from   the  contract  and  cannot   simply  reflect  the
    arbitrator's own notions of  industrial justice"); Dorado  Beach,
    
    959 F.2d at 4
    ;  Air Line  Pilots Ass'n Int'l v. Aviation Assocs.
    Inc., 
    955 F.2d 90
    , 93  (1st Cir.), cert. denied, 
    112 S. Ct. 3036
    (1992); Strathmore Paper Co.  v. United Paperworkers Int'l Union,
    
    900 F.2d 423
    , 426 (1st Cir. 1990); Georgia-Pacific Corp. v. Local
    27,  United Paperworkers Int'l Union, 
    864 F.2d 940
    , 944 (1st Cir.
    -8-
    1988).
    We reject plaintiffs' contention that our review of the
    district court's  vacation of an  arbitration award, based  on an
    alleged impermissible interpretation of a contract, is made under
    the clearly erroneous standard.   In this case, all  deference is
    due to  the arbitrator's interpretation  of the contract,  not to
    the interpretation of  the district  court.   The district  court
    ruled that the arbitrator  exceeded his authority as a  matter of
    law by ignoring  plain and unambiguous language  in the contract.
    We  review this finding de  novo and make  our own determination,
    according  to  the  standards  described above,  of  whether  the
    arbitrator's  application of  the contract  was plausible.   See,
    e.g.,  Upshur Coals Corp. v.  United Mine Workers,  Dist. 31, 
    933 F.2d 225
    ,  228 (4th  Cir. 1991);  Delta  Queen Steamboat  Co. v.
    District  2 Marine Engs. Beneficial Ass'n, 
    889 F.2d 599
    , 602 (5th
    Cir.  1989), cert. denied, 
    498 U.S. 853
     (1990); see also Berklee,
    858  F.2d  at  32-34   (vacating  district  court's  reversal  of
    arbitrator's interpretation  of labor contract  without affording
    deference to the district court's findings); Bacard , 
    692 F.2d at 211-14
     (implicitly  applying de novo review  in vacating district
    court's   finding   that   arbitrator   erroneously   interpreted
    collective bargaining agreement).
    B.  The Past Practices Clause
    With   this   circumscribed   standard  for   reviewing
    arbitration awards in  mind, there  is little  question that  the
    arbitrator's interpretation of the  Project Agreement -- at least
    -9-
    to the extent  that he found that the  past practices clause bars
    consideration of the plaintiffs' evidence of prior fringe benefit
    arrangements  -- must  be upheld  as a  plausible reading  of the
    contract.   This  result  is compelled  because the  arbitrator's
    holding comports with the  district court's own interpretation of
    the past practices clause  when properly applied to the  facts of
    this case.  Thus,  even if the arbitrator exceeded  his authority
    in finding that the  past practices clause wiped the  slate clean
    of  all established practices between all parties, an issue we do
    not decide, he certainly  did not exceed his authority  by wiping
    the  slate clean  between the  Union and  the plaintiffs  in this
    particular case.
    The  district court  apparently failed to  consider the
    possibility that plaintiffs in this case are  "other parties" and
    therefore not  privy to  the past  practice  of excluding  owner-
    operators  from the payment of fringe benefits.  According to the
    district  court,  the  plain   language  of  the  past  practices
    provision  in the  preamble provides  merely that  past practices
    established between parties A and B shall not be binding on party
    C,  although  they  will  continue  to  be  binding  on  A and  B
    themselves.   Applying  this interpretation  to the  present case
    reveals that fringe benefit practices between the Union and other
    employer-contractors (parties  "A" and "B" respectively)  are not
    binding on the plaintiffs (both party "C's"), who did not have an
    established  past practice with the Union and are thus "any other
    parties"  under  the past  practices clause.    As a  result, the
    -10-
    contract  could be  read  to  require  the arbitrator  to  ignore
    evidence of  past practices between  the Union and  other parties
    when applying the provisions of the Project Agreement to disputes
    between   the  Union  and  the   plaintiffs.    Because  such  an
    interpretation is a plausible one,  we must reverse the  district
    court's vacation  of the arbitration  ruling with respect  to the
    arbitrator's construction of the Project Agreement.
    The plaintiffs  take issue with such  an application of
    the past practices clause to the  facts of this case.  They argue
    that because the  Union itself was privy  to the practice  of not
    requiring fringe benefit payments for owner-operators,  the Union
    can still be  held to that practice, regardless  of the fact that
    plaintiffs  cannot  in  any way  be  bound  by  such a  practice.
    Plaintiffs point to the language of the clause, which states that
    "[n]o practice . . . between a Contractor and a Union party . . .
    shall be  binding on any other  party," to argue that  the clause
    itself concerns only the effects of past practices on new parties
    to the project agreement but in  no way limits the effect of past
    practices on the Union itself.
    The plaintiffs' interpretation is certainly reasonable,
    but, for  our purposes, it  is also irrelevant.   Our task  is to
    determine  whether  the  arbitrator  exceeded  his  authority  by
    failing to apply the contract in a plausible manner, not to  seek
    out the  most reasonable meaning  of the contract.   Interpreting
    the  past practices  clause to  bar consideration  of plaintiffs'
    evidence of past practice in this case is clearly plausible.  The
    -11-
    clause  can be  read to preclude  application of  all established
    past practices to "any  other party," even if that practice is in
    the  "other party's" favor.   Such  a reading  stems from  one of
    several plausible  constructions of  the language in  the clause:
    (1) no practice between parties A  and B shall be binding between
    parties  A and  C;  (2) practices  not  binding  on party  C  are
    likewise unavailable to C for use against parties A or B (i.e., C
    is not  entitled to rely on  or benefit from a  practice which is
    not  binding on  itself); and  (3) no  practice shall  be binding
    unlessalreadyestablished betweenaUnion andaparticular contractor.
    In this case, the  arbitrator could plausibly find that
    the practice  of excluding fringe  benefits for  owner-operators,
    established  between  the Union  and  other  contractors, is  not
    binding between the Union and the plaintiffs.  Alternatively, the
    arbitrator  could find  that plaintiffs  cannot benefit  from the
    past fringe benefit  practice because each  plaintiff is an  "any
    other party"  and thus could not be bound by the practice were it
    beneficial to the Union instead of to the employer.
    Plaintiffs  protest  that  we  cannot  now  employ such
    reasoning to  retroactively  salvage an  otherwise  unsustainable
    arbitration  award.   They  point out  that  even if  the Union's
    interpretation  of the  past practices  clause is  plausible, the
    arbitrator  did not  arrive at  that interpretation  himself, but
    instead,  arrived at  an  interpretation that  ignored the  plain
    language of the  contract.   The arbitrator found  that the  past
    practices clause wiped  the slate clean of all  practices between
    -12-
    all  parties, not  just  practices between  parties  A and  C  as
    discussed  above.    The  arbitration  award  cannot  be  upheld,
    plaintiffs argue,  on  the  basis  of an  interpretation  of  the
    contract  that the arbitrator did not even make, because, in this
    case  at least,  the arbitrator  might have  come to  a different
    conclusion  as  to  whether   past  practice  evidence  could  be
    considered if  he adopted the district  court's interpretation of
    the past practices clause at the time of his decision.
    We  see  no  problem with  upholding  the  arbitrator's
    decision on  grounds or reasoning not employed  by the arbitrator
    himself.  To begin with, an arbitrator  has no obligation to give
    his  or her  reasons for  an  award.   Raytheon Co.  v. Automated
    Business Sys., 
    882 F.2d 6
    , 8 (1st Cir. 1989).  Once an arbitrator
    chooses to provide such reasons,  courts should upset the  award,
    or remand  for clarification,  only when  "the  reasons that  are
    given strongly imply that the arbitrator may have exceeded his or
    her authority."   Randall v.  Lodge No. 1076,  
    648 F.2d 462
    , 468
    (7th  Cir. 1981); see also Cannelton Indus. v. District 17, UNWA,
    
    951 F.2d 591
    ,  594  (4th  Cir.  1991)  (remanding  portion   of
    arbitration award because  it may have  been based on a  grant of
    punitive, as opposed to compensatory, damages, in which  case the
    award did not  draw its  essence from  the contract).   Absent  a
    strong  implication  that  an  arbitrator  exceeded  his  or  her
    authority,  the arbitrator is presumed  to have based  his or her
    award on proper grounds.  Saturday Evening Post Co. v. Rumbleseat
    Press,  Inc., 
    816 F.2d 1191
    , 1197  (7th  Cir. 1987);  see  also
    -13-
    Chicago  Newspaper  Publishers'  Ass'n v.  Chicago  WEB  Printing
    Pressman's Union, 
    821 F.2d 390
    , 394-95 (7th Cir. 1987) ("'[i]t is
    only when the arbitrator must  have based his award on some  body
    of thought,  or feeling, or  policy, or law  that is outside  the
    contract  . .  . that  the award  can be  said not  to  'draw its
    essence  from the  collective bargaining  agreement.''") (quoting
    Ethyl Corp. v. United  Steelworkers, 
    768 F.2d 180
    , 185  (7th Cir.
    1985)) (emphasis in original).
    In  this  case,   despite  the  arbitrator's  allegedly
    erroneous reasoning, there is  nothing to indicate the arbitrator
    exceeded his  authority by  not "arguably construing  or applying
    the contract."   Misco, 
    484 U.S. at 38
    ;  see General  Teamsters,
    Auto Truck Drivers &  Helpers, Local 162 v. Mitchell  Bros. Truck
    Lines,  
    682 F.2d 763
      (9th Cir.  1982) (upholding  arbitrator for
    "doing  the right thing for the wrong reason").  The arbitrator's
    interpretation of the  past practices clause  in the preamble  as
    precluding  the  use of  past  practice  evidence in  determining
    plaintiffs'   obligations  under  the   Project  Agreement  is  a
    plausible  interpretation of  the contract and  as such,  must be
    upheld.    El  Dorado,  
    961 F.2d at 319
    .    The  fact  that the
    arbitrator's  "wipe-the-slate-clean"  construction  of  the  past
    practices clause might indicate  that the arbitrator exceeded his
    authority  if he had  applied that construction  to other parties
    not  present in this litigation does not  mean that he might have
    exceeded  his authority in this particular case.  Rather, we know
    the  arbitrator   did  not  exceed  his   authority  because  his
    -14-
    application of the past practice clause to the plaintiffs' claims
    drew  its  essence  from  the  collective  bargaining  agreement.
    Therefore, we  need not speculate  how the arbitrator  might have
    resolved  this  case  had  he  considered  the  district  court's
    construction of the contract language at issue.
    C.  Section 302 of the LMRA
    Unlike  the  dispute  over the  Project  Agreement, the
    issue  of whether fringe  benefit contributions on  behalf of the
    owner-operators is illegal under federal law does not involve the
    same  type  of  circumscribed  judicial  review  that  we  afford
    arbitration decisions grounded in interpretations of  a contract.
    Although the  arbitrator's factual findings  regarding the status
    of the owner-operators under Section 302 of the LMRA, 29 U.S.C.
    186,  may deserve  a certain  amount of  deference, the  issue of
    illegality is  ultimately one for  federal court review.   Misco,
    
    484 U.S. at 42-43
    .  Given that a determination under    302 could
    have  criminal  consequences, the  plaintiffs deserve  a thorough
    judicial review of an arbitrator's decision as to this issue.
    Neither party disputes that the plaintiffs' payment  of
    fringe benefits on behalf of the owner-operators is illegal under
    302  if the owner-operators are  independent contractors rather
    than employees.  The parties do disagree, however, on whether the
    issue was properly decided by the arbitrator and, if not, how the
    issue  should now  be resolved.   The  plaintiffs argue  that the
    arbitrator did not properly decide the issue and  that we, or the
    district  court,   should  find  that   the  owner-operators  are
    -15-
    independent contractors, effectively  nullifying the  arbitration
    award.  The Union argues that the arbitrator correctly found that
    the owner-operators were employees and that we should uphold this
    finding.
    The  arbitrator  did,  at  the  very  least, implicitly
    decide  the    302 issue  by granting  an award  in favor  of the
    Union.    However,  we  are  not satisfied  that  the  arbitrator
    conducted  the  appropriate  statutory analysis  for  making  the
    required  factual determination  of the  owner-operator's status.
    Distinguishing  between employees and independent contractors for
    purposes  of the LMRA is governed by general principles of agency
    law.  National Labor Relations Bd. v. Amber Delivery Serv., Inc.,
    
    651 F.2d 57
    ,  60 (1st  Cir. 1981).   Courts  have spelled  out a
    number of factors to be considered in making the determination of
    a  party's status,  including various  indicia of  the employer's
    "right  to control" certain aspects of that party's work.  Amber,
    
    651 F.2d at 61
    ; Construction, Bldg. Material, etc., Local No. 221
    v. National Labor Relations  Bd., 
    899 F.2d 1238
    , 1240  (D.C. Cir.
    1990); North Am. Van Lines, Inc.  v. N.L.R.B., 
    869 F.2d 596
    , 599-
    600 (D.C. Cir.  1989); H. Prang  Trucking Co. v. Local  Union No.
    469, 
    114 L.R.R.M. 3617
     (D.N.J. 1983).  Although the intent of the
    parties when they  entered into a contractual relationship may be
    relevant  to determining an  employer's "right to  control" or to
    other  aspects of  the agency  test, no  one factor  is decisive.
    Todd  v. Benal Concrete  Constr. Co, 
    710 F.2d 581
    , 584 (9th Cir.
    1983),  cert. denied, 
    465 U.S. 1022
     (1984); Amber, 
    651 F.2d at
    61
    -16-
    (citing  N.L.R.B. v. United Ins.  Co, 
    390 U.S. 254
    , 258 (1968)).
    Rather,  all of  the incidents  of the  relationship between  the
    employer and the alleged  employee must be assessed.   Amber, 
    651 F.2d at 61
    .
    Given  the arbitrator's  exclusive  focus on  the  past
    practices issue  and on provisions  of the contract  dealing with
    fringe  benefit contributions,  we have  serious doubts  that the
    arbitrator actually conducted a proper   302 agency test analysis
    in this case.  There is no  reason to believe, as the Union seems
    to  suggest, that  the arbitrator's  decision regarding  the past
    practices clause, which we uphold in this opinion, is dispositive
    not only of the underlying contractual dispute, but of the    302
    issue as well.  Past practices are only one facet of the complete
    agency  test  under      302.    Consequently,  the  arbitrator's
    discussion  of  the  Project Agreement  and  the  import  of past
    practices concerning  the owner-operators, while relevant  to the
    parties'  intended working relationship and thus to the status of
    the owner-operators  in this  case, is  not itself  sufficient to
    convince  us that  a  complete    302  agency test  analysis  was
    undertaken.   We  cannot,  therefore, defer  to the  arbitrator's
    implicit factual finding on the owner-operators' status to uphold
    the arbitration award  until a  more complete    302 analysis  is
    conducted.
    We are not prepared,  however, to conduct that analysis
    ourselves without first giving  the arbitrator the opportunity to
    reexamine  the factual  circumstances of  this case.   Plaintiffs
    -17-
    asserted  in  their action  before  the district  court  that the
    arbitration award  is unenforceable  because it  violates federal
    law.   The district court  declined to review  this claim because
    the  court vacated  the arbitration  award on  the issue  of past
    practices.  Because we now  reverse the district court's  ruling,
    we are left with plaintiffs'   302 allegations, which have yet to
    be properly adjudicated.   In  turn, we are  not disposed  toward
    making  factual findings in the first instance, given the absence
    of  explicit factual  findings  from the  district  court or  the
    arbitrator, that  are required for a proper  determination of the
    owner-operators'  status.    Although  a  largely  uncontradicted
    record exists in  this case that would allow us  to resolve the
    302 issue if we  needed to, we consider ourselves too far removed
    from the dispute to properly  weigh the various factors  involved
    in this  fact-intensive determination.  In other words, we refuse
    to uphold the arbitrator's finding because plaintiffs have raised
    a claim meriting  federal judicial  review yet we,  as a  federal
    appeals court, are  not in  a suitable position  to conduct  that
    review.
    Unfortunately,  the  district  court  is  in  the  same
    position that we are in with respect to determining the status of
    owner-operators.   Consequently,  we decline  to remand  the case
    directly to  the district  court for a  resolution of  the    302
    issue.  The district court itself chose to remand the proceedings
    instead of deciding the merits of the case and we think it is the
    court's prerogative to  do so.   Although federal  courts have  a
    -18-
    duty to  scrutinize such  federal issues with  potential criminal
    consequences,  the  arbitrator  can  play an  important  role  in
    providing  first-hand factual  findings  for the  benefit of  the
    reviewing  court.     Therefore,  we  remand  this  case  to  the
    arbitrator for  a  separate determination  of the  status of  the
    owner-operators under   302.
    The plaintiffs  do not dispute our  authority to remand
    actions   to  the   arbitrator;   however,  they   claim  it   is
    inappropriate to do so when the issue on remand is one of federal
    law.   We disagree with their contention that it is inappropriate
    for an arbitrator to apply federal statutes.  On the contrary, it
    is well established that certain statutory claims may  be decided
    through arbitration.    See  Gilmer  v.  Interstate/Johnson  Lane
    Corp., 
    500 U.S. 20
    , 26  (1991);  Page v.  Moseley,  Hallgarten,
    Estabrook & Weeden, Inc., 
    806 F.2d 291
    , 295 (1st Cir. 1986).  We
    see no reason why the arbitrator cannot make the factual findings
    necessary  to resolve the   302  issue in this case.  Determining
    the   status  of  owner-operators   is  particularly  within  the
    arbitrator's domain  since it involves  analyzing various aspects
    of  the  working  relationship  between  the  parties.    Such  a
    determination  involves consideration  of precisely  the  type of
    issues  that  the parties  originally  agreed  to  refer  to  the
    arbitrator under the arbitration clause of the Project Agreement.
    We  do, nevertheless,  retain jurisdiction  so that  the district
    court can review  the final determination  of the arbitrator,  if
    requested to do so by one of the parties.
    -19-
    On remand,  we expect  the arbitrator will  conduct the
    appropriate  agency test  analysis as  described in  the relevant
    caselaw.   See, e.g.,  Amber,  
    651 F.2d at 60-61
    ;  Local No. 221,
    
    899 F.2d at 1240
    ;  North Am.  Van  Lines, 
    869 F.2d at 599-600
    ;
    Prang, 114 L.R.R.M. at 3617-19; see also  Restatement (Second) of
    Agency    220 (1957).   We leave it  to the arbitrator  to decide
    what effect, if  any, the  past practices clause  of the  Project
    Agreement  and  the  evidence  of  past  practice  regarding  the
    treatment  of owner-operators  has  on his  determination of  the
    owner-operators' status  under    302.   Although  we upheld  the
    arbitrator's   interpretation   of   the   contract   as  barring
    consideration   of  past   practices  in   resolving  contractual
    disputes,  we express no opinion on how the past practices clause
    in  the contract and the  evidence of past  practices figure into
    the various  factors enumerated  under the  agency  test used  to
    ascertain a party's status under   302.
    Accordingly,  we reverse the  district court's judgment
    vacating  the  arbitration award  and  remand  this case  to  the
    district  court with  instructions  to  remand  the case  to  the
    arbitrator for further proceedings consistent with this opinion.
    -20-
    

Document Info

Docket Number: 93-2122

Citation Numbers: 29 F.3d 742

Judges: Breyer, Coffin, Torruella

Filed Date: 7/19/1994

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (20)

Bacardi Corporation v. Congreso De Uniones Industriales De ... , 692 F.2d 210 ( 1982 )

Building & Construction Trades Council of the Metropolitan ... , 113 S. Ct. 1190 ( 1993 )

Burkart Randall, a Division of Textron, Inc. v. Lodge No. ... , 648 F.2d 462 ( 1981 )

Frank L. Todd, Etc., Plaintiffs-Appellants/cross-Appellees ... , 710 F.2d 581 ( 1983 )

United Steelworkers v. Enterprise Wheel & Car Corp. , 80 S. Ct. 1358 ( 1960 )

National Labor Relations Board v. United Insurance Co. of ... , 88 S. Ct. 988 ( 1968 )

Chicago Newspaper Publishers' Association, Cross-Appellee v.... , 821 F.2d 390 ( 1987 )

dorado-beach-hotel-corporation-v-union-de-trabajadores-de-la-industria , 959 F.2d 2 ( 1992 )

The Delta Queen Steamboat Company v. District 2 Marine ... , 889 F.2d 599 ( 1989 )

North American Van Lines, Inc. v. National Labor Relations ... , 869 F.2d 596 ( 1989 )

National Labor Relations Board v. Amber Delivery Service, ... , 651 F.2d 57 ( 1981 )

Frederick J. Page, Jr. And Kristin D. Page v. Moseley, ... , 806 F.2d 291 ( 1986 )

Ethyl Corporation v. United Steelworkers of America, Afl-... , 768 F.2d 180 ( 1985 )

construction-building-material-ice-coal-drivers-helpers-and-inside , 899 F.2d 1238 ( 1990 )

El Dorado Technical Services, Inc. v. Union General De ... , 961 F.2d 317 ( 1992 )

general-teamsters-auto-truck-drivers-and-helpers-local-162-v-mitchell , 682 F.2d 763 ( 1982 )

Raytheon Company v. Automated Business Systems, Inc. , 882 F.2d 6 ( 1989 )

Strathmore Paper Company v. United Paperworkers ... , 900 F.2d 423 ( 1990 )

upshur-coals-corporation-v-united-mine-workers-of-america-district-31 , 933 F.2d 225 ( 1991 )

United Paperworkers International Union v. Misco, Inc. , 108 S. Ct. 364 ( 1987 )

View All Authorities »