United States v. DiBiase ( 1995 )


Menu:
  • yFebruary 15, 1995UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT
    No. 94-1841
    UNITED STATES OF AMERICA,
    Plaintiff, Appellee,
    v.
    UGO DIBIASE, ETC., ET AL.,
    Defendants, Appellants.
    ERRATA SHEET
    ERRATA SHEET
    The  opinion of  the Court  issued on  January 25,  1995, is
    corrected as follows:
    On cover sheet, line 6, change "Louis" to "Lois"
    UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT
    No. 94-1841
    UNITED STATES OF AMERICA,
    Plaintiff, Appellee,
    v.
    UGO DIBIASE, ETC., ET AL.,
    Defendants, Appellants.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. A. David Mazzone, U.S. District Judge]
    Before
    Selya, Circuit Judge,
    Bownes, Senior Circuit Judge,
    and Stahl, Circuit Judge.
    Stephen M.  Leonard, with  whom Mintz, Levin,  Cohn, Ferris,
    Glovsky & Popeo was on brief, for appellants.
    John E.  Darling, with  whom Joseph  C.  Correnti, Ellen  M.
    Winkler, and  Serafini, Serafini and  Darling were on  brief, for
    defendant-appellee South Essex Sewerage Dist.
    Joan  M.  Pepin,  with  whom  Lois  J.  Schiffer,  Assistant
    Attorney General,  David C.  Shilton, Catherine Adams  Fiske, and
    Andrea Nervi Ward Attorneys, U.S. Dept. of Justice, Environment &
    Natural Resources Div.,  and John T. McNeil,  Sr. Asst't Regional
    Counsel, U.S. Environmental Protection Agency, were on brief, for
    the United States.
    January 25, 1995
    SELYA, Circuit  Judge.  The United  States negotiated a
    SELYA, Circuit  Judge.
    settlement with a potentially  responsible party, the South Essex
    Sewerage  District  (SESD),   fixing  SESD's  share  of   certain
    emergency removal costs incurred by the government in the cleanup
    of a Superfund site.1   The district court placed  its imprimatur
    on the settlement by entering a consent decree (the SESD decree).
    Appellant, Ugo DiBiase, a  non-settling responsible party left to
    hold  the bag for the  remainder of the  emergency removal costs,
    prosecuted this appeal in hopes of convincing us that the consent
    decree is unfair.  We are not persuaded.
    I.  BACKGROUND
    I.  BACKGROUND
    The Salem  Acres Superfund Site (the  Site) consists of
    five  acres of undeveloped land  containing wetlands and a brook,
    located  in Salem, Massachusetts.   From  1946 until  1969, James
    Grasso  owned it.  During that interval, Grasso permitted SESD to
    dump  at the Site.   SESD deposited sewerage  wastes into unlined
    "sludge  pits" which were surrounded by earthen berms and fences.
    SESD  maintained  the  Site,  including the  berms  and  interior
    fencing,  during  the period  that  Grasso permitted  it  to dump
    there.
    In  December of 1969, Grasso sold a large tract of land
    that encompassed  the Site  to Salem  Acres, Inc., a  corporation
    1At that point in time, the emergency removal costs totalled
    $2,258,893.    They comprised  sums already  spent by  the United
    States for  containment and capping  work at  the Site,  together
    with interest and costs  of enforcement.  See 42  U.S.C.    9604,
    9607.
    3
    owned  jointly by two brothers,  Ugo and Elio  DiBiase.2  Unaware
    that the property had changed  hands, SESD transported a shipment
    of solid wastes to the sludge pits early in 1970.  When appellant
    learned  of this occurrence, he  informed SESD that  he would not
    tolerate disposal at the Site in the future.  SESD refrained from
    further dumping.
    During  the  1970s,  appellant received  correspondence
    from various  municipal agencies,  including the Board  of Health
    and the Fire Department, expressing concern over the unrestricted
    access to the  Site and the random dumping that was taking place.
    Appellant responded  by erecting  gates at  the entrances  to the
    property, but he did not thereafter maintain them.  Consequently,
    intermittent dumping by unknown parties continued.
    Appellant claims that he had no direct knowledge of the
    sludge pits until  1980, when  a state agency  notified him  that
    legal action would be taken unless he rectified conditions at the
    Site.  Even when confronted with this threat, appellant failed to
    take meaningful  action.  He agreed to install new gates, but, in
    the end, neglected to do so.  And although the  earthen berms and
    interior fencing  around the sludge pits  had completely decayed,
    2In 1982,  Elio DiBiase  divested himself of  any beneficial
    interest in  the property, and the  corporation transferred title
    to  the Site  to  DiBiase Salem  Realty  Trust, an  entity  under
    appellant's  sole   control.    Hence,  the   defendants  in  the
    underlying  action  include  DiBiase  Salem   Realty  Trust;  Ugo
    DiBiase,   in  his   capacity  as   trustee;  and   Ugo  DiBiase,
    individually.    For ease  in  reference, we  ignore  both Elio's
    passing  involvement  and  the  inclusion  of  the  trust   as  a
    defendant, and treat Ugo  DiBiase as the property owner  and sole
    appellant.
    4
    appellant made no discernible effort to investigate the situation
    or  ameliorate the  obvious  hazards (or  so  the district  court
    supportably found).
    In  1987, an  easily foreseeable  contretemps occurred.
    Heavy  rains  caused  the  sludge pits  to  overflow  and release
    deleterious  substances into  the nearby wetlands  (including the
    brook).  The United  States Environmental Protection Agency (EPA)
    reacted  to the release  by conducting the  two emergency removal
    actions that underlie  this appeal.  After  completing that work,
    the  government  sued appellant  and  SESD, seeking  not  only to
    recover  EPA's  emergency removal  costs  but  also to  secure  a
    declaration  of  the  defendants'  liability  for  future cleanup
    costs.
    In  due   season,  the   district  court  granted   the
    government's   motion  for   partial  summary   judgment  against
    appellant, finding him liable for past  and future response costs
    at  the  Site  under  the Comprehensive  Environmental  Response,
    Compensation, &  Liability Act (CERCLA), 42  U.S.C.    9601-9675.
    The government  lodged a  similar  motion against  SESD, but  the
    district court  never ruled on it.   Thus, at the  time it signed
    the consent decree, SESD remained a potentially responsible party
    (PRP) rather than a demonstrably responsible party (like DiBiase)
    whose liability had been judicially established.
    Throughout the proceedings,  the government  endeavored
    to arrange a global  settlement.  Though EPA's  negotiations with
    appellant  came to naught, its negotiations with SESD bore fruit.
    5
    After  notice, opportunity  for public  comment, and  an in-court
    hearing, the district court, over appellant's vigorous objection,
    entered the SESD decree on April 5, 1994.  Under it, SESD agreed,
    inter  alia, to reimburse the  United States for  85% of the past
    removal costs  calculated  as of  the  settlement date.    SESD's
    payment amounted to $1,822,775.
    On May 6,  1994, the   district court entered  judgment
    against  appellant for  $494,207, representing  the unremunerated
    portion of the government's  historic removal costs calculated as
    of  that  date.3   After the  court  denied DiBiase's  motion for
    reconsideration, this appeal ensued.
    II.  STANDARD OF REVIEW
    II.  STANDARD OF REVIEW
    The legislative history of the Superfund Amendments and
    Reauthorization Act of 1986  (SARA), P.L. 99-499,   101  et seq.,
    clearly indicates that, when  reviewing a proposed consent decree
    in the CERCLA context, a trial court does not write on a pristine
    page.   Instead, its function  is circumscribed:   it must ponder
    the proposal only to  the extent needed to "``satisfy  itself that
    the  settlement  is reasonable,  fair,  and  consistent with  the
    purposes  that CERCLA is intended  to serve.'"   United States v.
    Cannons Eng'g Corp.,  
    899 F.2d 79
    , 85 (1st  Cir. 1991)  (quoting
    House Report).
    This  circumscription  has important  ramifications for
    appellate  oversight.    We  elucidated the  standard  of  review
    3The   amount  also   includes   incremental  interest   and
    enforcement  costs  arising  after  the  effective  date  of  the
    settlement between SESD and the United States.  See supra note 1.
    6
    governing  the entry  of CERCLA consent  decrees in  Cannons, and
    reaffirmed  that  standard in  United  States  v. Charles  George
    Trucking, Inc., 
    34 F.3d 1081
     (1st  Cir. 1994).  We noted that, by
    the time CERCLA consent decrees reach this court,
    they  are  "encased  in  a  double  layer  of
    swaddling."   In  the  first  place, a  trial
    court, without  abdicating its responsibility
    to exercise independent judgment,  must defer
    heavily  to  the parties'  agreement  and the
    EPA's  expertise . . .  .    The second basis
    for deference is equally compelling.  Because
    an  appellate court ordinarily cannot rival a
    district  court's  mastery  of   a  factually
    complex case . . . the district court's views
    must be accorded considerable respect.
    Largely in consequence  of these  layers
    of   protective   swaddling,   an   appellate
    tribunal  may  overturn  a  district  court's
    decision to approve or  reject the entry of a
    CERCLA consent decree only for manifest abuse
    of  discretion.     [In  other   words],  the
    decision  below  stands unless  the objectors
    can  show that, in  buying into [the decree],
    the lower  court made a serious  error of law
    or suffered a meaningful lapse of judgment.
    
    Id. at 1085
      (quoting and citing Cannons, 899 F.2d at 84).  It is
    this yardstick   which must be used to  measure the lower court's
    acceptance of the SESD decree.
    III.  DISCUSSION
    III.  DISCUSSION
    On appeal, DiBiase does not attack the district court's
    liability determination.   Rather,  he fires a  rifle shot  aimed
    strictly  and  solely  at  the  appropriateness  of  the  court's
    allocation of the emergency  removal costs.  The shot  misses the
    mark.
    In actuality, appellant draws a bead on an  even tinier
    target.  He virtually concedes that two of the three criteria for
    7
    the  approval  of  an  environmental  consent  decree  have  been
    satisfied, and snipes only  at the fairness vel  non of the  SESD
    decree.     Moreover,  while   fairness  in  respect   to  CERCLA
    settlements  has both a procedural  and a substantive aspect, see
    Cannons, 899 F.2d  at 86, appellant does not train  his sights on
    any  alleged procedural  unfairness.   Since our inquiry  must be
    limited accordingly, the issue  before us reduces to  whether the
    SESD decree, as approved below, is substantively fair.
    Substantive  fairness   has  a  protean   quality  and,
    therefore, is often discussed  in general terms.  In  Cannons, we
    wrote:
    Substantive  fairness   introduces  into  the
    equation concepts of  corrective justice  and
    accountability:  a party should bear the cost
    of  the  harm   for  which   it  is   legally
    responsible.  The logic behind these concepts
    dictates  that settlement terms must be based
    upon,  and  roughly  correlated   with,  some
    acceptable  measure   of  comparative  fault,
    apportioning liability among settling parties
    according   to   rational   (if   necessarily
    imprecise)  estimates of  how much  harm each
    PRP has done . . . .
    Whatever   formula   or   scheme   EPA
    advances for measuring comparative  fault and
    allocating liability should be upheld so long
    as   the   agency   supplies    a   plausible
    explanation for it,  welding some  reasonable
    linkage  between the  factors it  includes in
    its  formula or scheme  and the proportionate
    shares of settling PRPs.
    Id. at 87  (citations omitted).  Viewing the  SESD decree in this
    deferential perspective, we find EPA's rationale for the proposed
    allocation to be  plausible, and also  find the district  court's
    endorsement of that rationale to be well within the parameters of
    8
    fundamental fairness.
    In the  first instance,  the allocation  reflects EPA's
    determination that both SESD  and DiBiase are legally responsible
    to reimburse the public fisc for the emergency removal costs.  It
    is impossible to quarrel with  this determination.  SESD,  though
    not adjudged liable, no  longer contests its liability.   By like
    token,  DiBiase  has  not   appealed  the  district  court  order
    adjudging him liable for the damages; and, legally, the liability
    of responsible parties in a CERCLA case is joint and several, see
    O'Neil  v. Picillo, 
    883 F.2d 176
    , 178-79 (1st  Cir. 1989), cert.
    denied, 
    493 U.S. 1071
     (1990).
    Next,  the allocation  fashioned  by EPA  reflects  the
    agency's assessment  that SESD, as the  generator and transporter
    of most  of the toxic waste dumped in the sludge pits, is chiefly
    responsible  for the  offending conditions.   The  consent decree
    recognizes this  primary responsibility  by assigning  the lion's
    share of the removal  costs to SESD.   The flip side of  the same
    coin is that the consent decree implicitly recognizes appellant's
    lesser  involvement by  leaving a relatively  small share  of the
    removal costs (15%) to be collected from him.
    The district court concluded that this apportionment is
    fair.  The court  cited its earlier judgment on  liability, noted
    appellant's  utter   failure  to   take  any  action   either  to
    investigate conditions or to  ameliorate danger during almost two
    decades  of  involvement in  Site ownership  and more  than seven
    years of actual knowledge about the sludge pits, and specifically
    9
    rejected  appellant's claim  that he "did  no wrong."   Appellant
    importunes us to set  aside the district court's order.   Despite
    having  been  adjudged liable,  appellant  stubbornly  refuses to
    recognize  his own culpability and maintains that it is unfair to
    expect him  to bear any  of the  removal costs.   His importuning
    fails for no fewer than five reasons.
    In  the first place, appellant  does not cite    and we
    have  been  unable  to  locate    any  CERCLA  case  in  which  a
    demonstrably liable party has been  held entitled to safe passage
    in  a  global settlement.   We  think  it is  counterintuitive to
    suppose that any such entitlement exists.
    Second, and  relatedly, we regard  appellant's argument
    as a surreptitious attempt to relitigate his "innocent landowner"
    defense,  see  42  U.S.C.     9607(b)(3)  (exonerating  PRPs  who
    "exercised due  care" and  can demonstrate,  inter  alia, that  a
    release  was caused "solely" by a third party's act or omission);
    see  also Westwood  Pharmaceuticals,  Inc. v.  National Fuel  Gas
    Distrib'n Corp.,  
    964 F.2d 85
    ,  89-91 (2d Cir.  1992) (discussing
    operation  of  innocent  landowner  defense),4  rejected  by  the
    4For  purposes  of  this   statutory  provision,  a  PRP  is
    responsible  for the acts and omissions of his employees, agents,
    or other persons  who have a "contractual relationship" with him.
    42  U.S.C.    9607(b)(3).   The  term "contractual  relationship"
    includes relationships involving "land contracts, deeds, or other
    instruments transferring title," 42 U.S.C.   9601(35), subject to
    certain  exceptions.     One  such  exception   is  for  innocent
    landowners,  that is,  acquirers of  land who,  having made  "all
    appropriate inquiry" into  the condition of  the property at  the
    time  of acquisition,  id.    9601(35)(B),  nevertheless "had  no
    reason to know" that any environmental problem might exist, id.
    9601(35)(A).
    10
    district  court  when  it  granted the  government's  motion  for
    partial  summary judgment.   We  have no  warrant to  entertain a
    collateral attack on that judgment.  It follows  that, as a party
    jointly and  severally liable  for payment  of all the  emergency
    removal costs, appellant cannot  reasonably expect others to foot
    the entire bill.
    In the third place, the allocation  proposed by EPA and
    ratified  by  Judge   Mazzone  does  not  strike  us   as  either
    substantially disproportionate or manifestly unfair.  To be sure,
    SESD played a leading role in  the contamination of the Site  and
    appellant, who  came on  the scene  later, played  an appreciably
    less prominent role.   But, an actor cast in a bit part is not to
    be confused with a  mere spectator, whose only involvement  is to
    lounge  in  the  audience  and watch  events  unfold.   Appellant
    contributed to the 1987  incident in a variety of  ways.  Despite
    being warned  of a  potentially dangerous condition,  he twiddled
    his thumbs:   he failed  to safeguard the  Site, thus  permitting
    third parties to dump  at will and exacerbate an  already parlous
    situation;  fiddled while  the  earthen berms  deteriorated;  and
    turned a blind eye to evolving public health and safety concerns.
    Allocating 15% of the historic removal costs as appellant's share
    seems commensurate  with these shortcomings and  with the quantum
    of comparative fault fairly ascribable to him.
    Fourth, appellant's  concept    which seems to  be that
    liable  parties  should go  scot free  in environmental  cases if
    other parties  are considerably  more culpable    runs at  cross-
    11
    purposes  with  CERCLA's  policy of  encouraging  settlements  as
    opposed to endless court  battles.  See H.R.  Rep. No. 253,  99th
    Cong.,  1st  Sess., pt.  5, at  58-59  (1985), reprinted  in 1986
    U.S.C.C.A.N. 3124, 3181-82; see also United Technologies Corp. v.
    Browning-Ferris Indus., Inc., 
    33 F.3d 96
    , 102-03  (1st Cir. 1994)
    (explaining  the  interface  between settlement  and  liability).
    Such  settlements  reduce   excessive  litigation  expenses   and
    transaction  costs,  thereby  preserving  scarce   resources  for
    CERCLA's real goal:   the expeditious cleanup  of hazardous waste
    sites.
    In  most  instances,  settlement  requires  compromise.
    Thus, it  makes sense for  the government,  when negotiating,  to
    give a PRP a  discount on its maximum  potential liability as  an
    incentive to  settle.  Indeed, the  statutory scheme contemplates
    that  those who  are slow  to settle  ought to  bear the  risk of
    paying more if they are eventually found liable.  See 42 U.S.C.
    9613(f)(2) - (3); see also Cannons, 899 F.2d at  91-92.  Congress
    apparently thought that paradigm fair, and so do we.
    This case  illustrates the point.   The government gave
    SESD  a 15%  discount on  its maximum  potential exposure.   This
    proved  to be  a  sufficient incentive  to achieve  a settlement,
    despite  the  fact   that  SESD's  liability  had  not  yet  been
    adjudicated.   Appellant    who,  unlike SESD,  already had  been
    found  liable    received ample  opportunities to buy  peace, but
    took no advantage of them.   Against this unsympathetic backdrop,
    appellant cannot rewardingly complain that he must now shoulder a
    12
    larger share of the overall expense than might have been the case
    if he had moved faster or if SESD had proven intransigent.
    Fifth, and  last, fairness  rarely can be  described in
    absolute terms.   There  is  no litmus  test for  it  and no  one
    allocation  that will, in a  CERCLA case, comprise  the only fair
    allocation.    Rather,  fairness  is  a  mutable  construct  that
    "tak[es]  on  different forms  and  shapes  in different  factual
    settings."  Cannons, 899 F.2d at  85.  Absent a mistake of  law
    and  we see  none here    this reality,  coupled with  the twice-
    insulated deference afforded CERCLA consent  decrees, see Charles
    George Trucking, 
    34 F.3d at 1085
    ; Cannons, 899 F.2d at 84, places
    a  heavy burden  on  an  objector  who  strives  to  convince  an
    appellate  court  that  error inheres  in  the  entry  of such  a
    decree.5  In this case,  the burden has not been carried.   Judge
    Mazzone's finding  that the  SESD decree  falls  within the  wide
    universe of fair solutions is abundantly supported.
    IV.  CONCLUSION
    IV.  CONCLUSION
    We need go no further.6   Because appellant has neither
    5This burden is particularly weighty when the district judge
    is  called  upon to  assess  the comparative  fault  of different
    classes of PRPs.  So it is here.  The court below had to contrast
    the fault ascribable  to a generator and transporter  (SESD) with
    the  fault  ascribable   to  a  landowner  (DiBiase).    In  such
    circumstances, the  trial judge  is in  effect forced  to compare
    apples with oranges.  Accordingly, his prolonged  exposure to the
    litigation  and his  firsthand  knowledge of  the case's  nuances
    become extremely important, heightening the need for deference.
    6This appeal presents no issues anent cleanup costs over and
    above  the emergency removal costs.   The parties  informed us at
    oral argument that all  issues of that nature have  been resolved
    amicably.
    13
    offered any compelling reason to brand the consent decree  unfair
    nor persuaded us  that the district court  blundered in approving
    it, his appeal falters.
    Affirmed.
    Affirmed.
    14