    No. 96-1465
    TABER PARTNERS I,
    A NEW YORK GENERAL PARTNERSHIP,
    Plaintiff, Appellant,
    v.
    MERIT BUILDERS, INC., A PUERTO RICO CORPORATION, ET AL.,
    Defendants, Appellees.
    No. 96-1466
    TABER PARTNERS I,
    A NEW YORK GENERAL PARTNERSHIP,
    Plaintiff, Appellant,
    v.
    MERIT BUILDERS, INC., A PUERTO RICO CORPORATION, ET AL.,
    Defendants, Appellees.
    No. 96-1467
    TABER PARTNERS I,
    A NEW YORK GENERAL PARTNERSHIP,
    Plaintiff, Appellee,
    v.
    MERIT BUILDERS, INC., A PUERTO RICO CORPORATION, ET AL.,
    Defendants, Appellees,
    DESARROLLOS METROPOLITANOS, S.E.,
    Third Party Defendant, Appellant.
    APPEALS FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF PUERTO RICO
    [Hon. Jaime Pieras, Jr., U.S. District Judge]
    Before
    Selya, Circuit Judge,
    Coffin and Bownes, Senior Circuit Judges.
    Arch Y.
    Stokes with whom Stokes
    & Murphy, Ruben
    T. Nigaglioni and
    McConnell & Valdes
    were on brief for plaintiff, appellant Taber Partners
    I.
    Eric
    A.
    Tulla with whom  Rivera,
    Tulla
    &
    Ferrer,  Woods
    &
    Woods,
    Raffle F. Ojeda-Colon
    were on brief for defendants, appellees and cross-
    appellants, Merit Builders, Inc., and Merit Builders, S.E.,  Harold
    D.
    Vincente, with whom   Vincente
    &
    Cuebas, was on brief for appellee
    Insurance Company of North America.
    Humberto
    Guzman-Rodriguez with whom Fiddler,
    Gonzalez
    &
    Rodriguez
    were on brief for third-party defendant, appellant Desarrollos
    Metropolitanos, S.E.
    JULY 31, 1997
    BOWNES, Senior
    Circuit
    Judge. This breach of
    contract case is a product of the renovation and expansion of
    the Ambassador Plaza Hotel and Casino (formerly a Howard
    Johnson Hotel) in San Juan, Puerto Rico. Plaintiff-appellant
    Taber Partners I is the owner of the hotel. Its two partners
    are A. Eugene Romano and his daughter, Linda Romano.
    Defendant-appellee and cross-appellant Merit Builders, Inc. was
    the general contractor. John Schlump, one of the two owners of
    Merit, directed the construction and reconstruction work on the
    hotel.
    On January 18, 1989, Taber entered into a "cost-plus"
    construction contract with Merit whereby Merit became the
    general contractor for the renovation and expansion of the
    hotel. Prior to this, Schlump had been retained as a
    consultant by Eugene Romano to advise him how to proceed with
    the proposed reconstruction and expansion. The "cost-plus"
    contract was followed by a fixed price contract; both contracts
    were collectively called the Tower contract. A third contract
    was entered into by the parties for finish work on the casino,
    two restaurants, and the hotel lobby.
    On February 20, 1991, Taber filed a complaint in the
    federal district court of Puerto Rico alleging breach of
    contract by reason of delay, defective performance, and
    negligent workmanship. There was also a claim for fraud and
    deceit. The complaint was amended twice; the causes of action
    -3-
    3
    remained essentially the same. At some point, it is not clear
    from the record just when, Taber sued the Insurance Company of
    North America under the performance bond INA issued for the
    Tower contract.
    Merit brought a counterclaim against Taber alleging
    multiple breaches of contract, a claim based on Taber's alleged
    delays and changes in the scope and nature of the work
    contracted for, and fraud. Merit also brought a third-party
    action against Desarrollos Metropolitanos, S.E., the concrete
    subcontractor. It brought another third-party complaint
    against Victor Torres and Associates, the inspectors of the
    work, alleging breach of duty and tortious interference with
    the performance of the contracts between Taber and Merit.
    After a fourteen-week trial, the jury returned a
    verdict finding that Merit was not liable to Taber. It further
    found that Taber owed Merit $1,597,414.00 for breach of
    contract. We consider Taber's appeal first.
    At the close of the evidence, the district court
    dismissed Merit's claim against Victor Torres and Associates.
    TABER'S APPEAL
    Taber forwards two issues on appeal: The ruling of
    the district court excluding evidence of the loss of value of
    the hotel due to defective construction work; and improper jury
    instructions.
    -4-
    4
    The Exclusionary Ruling
    We start with the exclusionary ruling. In a pre-
    trial order the court ruled that it would not allow evidence as
    to the loss of value of the hotel. Taber had two expert
    witnesses who would have testified that the reconstruction and
    renovation work by Merit was done so incompetently and
    defectively that the hotel's value was considerably less than
    what it would have been had it been done properly.
    At the start of its specific instructions the court
    told the jury:
    Taber Partners I claims that Merit
    Builders, Inc. breached all contracts
    entered into for the renovation and
    expansion of the Ambassador Plaza Hotel
    and Casino by failing to properly
    construct the building and by failing to
    complete the project in time. As a
    result, plaintiff claims that it suffered
    damages suffered [sic] due to alleged
    construction defects and time delays for
    which it seeks to recover the total sum of
    $3,730,995 from Merit.
    This was an accurate statement of Taber's claims.
    The jury answered the following questions on Merit's
    liability:
    PART A: Taber's claim against Merit for
    breach of contract
    Question 1A.
    Do you find that under the Lump Sum
    Tower Contract Merit failed to perform its
    duties and obligations or in any other way
    breached its contract with Taber by
    failing to comply with the plans and
    specifications?
    -5-
    5
    . . .
    Question 3A.
    Do you find that under the Specialty
    Contract Merit failed to perform its
    duties or in any other way breached its
    contract with Taber by failing to comply
    with the plans and specifications?
    . . .
    Question 5A.
    Do you find that under the Cost Plus
    Contract Merit failed to perform its
    duties or in any other way breached its
    contract with Taber by failing to follow
    the plans and specifications?
    These jury findings establish beyond peradventure
    that Merit was not liable to Taber for breach of contract,
    which was the basis of Taber's claims against Merit.
    We have read the transcript testimony of all
    witnesses who testified on behalf of Taber. The record shows
    that there was a plethora of evidence from which the jury could
    have found liability, if it believed any of the witnesses. But
    it chose not to do so. If any principle is embedded firmly in
    our law it is that the jury is the final arbiter of the facts
    and credibility decisions are exclusively within its domain.
    Another firmly established legal rule is that a
    finding of liability must precede any finding of damages.
    -6-
    6
    Taber seeks to avoid this rule by arguing that "the Judge
    erroneously forced Taber to argue liability without being
    permitted to prove damages; it is the rare jury that will find
    liability when it cannot appreciate that the plaintiff has
    suffered damage." Taber's Brief at 20. This argument is
    belied by the record. The court allowed in evidence all
    damages claimed by Taber except that of the value of the hotel
    and those that were duplicative.
    Randall Redman, an expert witness called by Taber,
    testified that, after inspecting the project, he told Eugene
    Romano that the only way to achieve a quality building that
    would last would be to tear the building down and start all
    over.
    During the testimony of Eugene Romano it was
    stipulated as follows:
    If the jury finds that there was a
    delay by Merit in the performance of any
    of the contracts, the parties agree that
    there is a $2,000 liquidated damages
    provision per day, per contract, which
    includes the specialty contract. That is
    to say, the work for the casino,
    restaurant and lobby, plus and also the
    tower contract.
    The cost-plus contract is
    specifically not made a part of this
    stipulation as it had no time limit in
    which it was supposed to be complete.
    Eldon Gayle Tipping, another of Taber's experts,
    testified that the cost to repair this project would be in
    excess of the original contract price. He testified
    -7-
    7
    specifically that the damages due to defective concrete work
    were $1,353,703.00.
    Victor Torres, a civil engineer, was retained to
    settle disputes between the parties and issue certificates of
    payment. He testified extensively about change orders and
    "deductive" change orders. A "deductive" change order results
    in a decrease of the amount due for a specific contract change.
    Torres testified that he allowed $856,944.90 in deductive
    change orders out of $3,938,228.64 claimed by Taber.
    The most extensive testimony on damages came from
    Linda Romano, a partner, with her father, in Taber. She
    started her testimony by stating:
    The Witness: We sued Merit Builders
    because we paid Merit in excess of $12
    million to build us a quality hotel within
    a specified time and they didn't do it.
    And we sued the Insurance Company of North
    America because they promised the
    performance, they secured the performance
    of Merit under the performance bond.
    By Mr. Stokes:
    Q    Ms. Romano, what are you seeking by
    this lawsuit?
    A    I am asking the jury to find that the
    Insurance Company of North America and
    Merit Builders should pay us in excess of
    three and a half million dollars.
    In addition to that, I am asking the
    jury to find that we have paid Merit in
    full. I am seeking to be made whole,
    although I don't believe I can be.
    -8-
    8
    Linda Romano testified for four days on direct
    examination. She explained the defects in construction. This
    part of her testimony was amplified by numerous photographs,
    which were admitted in evidence. Ms. Romano took over 2,000
    photos of the work in progress. Romano gave specific costs of
    change orders and deductive change orders. She concluded her
    testimony by summarizing the amount due Taber for defective
    work and time delays -- $3,730,995.00. This was the figure
    given by the court in its instructions to the jury as to the
    amount Taber claimed in damages.
    Despite the argumentative rhetoric in Taber's brief,
    the record makes it abundantly clear that the jury was fully
    informed as to the construction defects alleged by Taber and
    its claim for the costs of correcting them. The district court
    allowed 98% of the evidence offered by Taber to be presented to
    the jury. This is not a case of a trial judge being technical
    and limiting in his evidentiary rulings. Taber received an
    eminently fair trial. It cannot now seize upon one adverse
    ruling on the preclusion of certain evidence on damages to
    overturn the jury's findings that Merit was not liable to Taber
    for breach of contract. Such findings preclude, as a matter of
    law, any contention on damages.
    The Jury Instructions
    We state this issue as it is worded in Taber's brief
    -9-
    9
    at page 3:
    The District Court, in this case
    arising from faulty hotel construction,
    reversibly erred by improperly instructing
    the jury to presume as factually
    legitimate the certificates for payment
    issued by the inspecting engineer/
    architect, Victor Torres, in direct
    contravention of the contract language,
    yet failing to instruct the jury to assume
    as similarly legitimate the deductive
    change orders and substantial completion
    decisions certified by the same
    individual.
    This plaint founders on the same barrier reef as did
    Taber's argument excluding one of its claims for damages -- the
    jury findings of no liability.
    We also point out that in this circuit objections to
    jury instructions cannot be properly preserved unless a party
    objects after the charge and before the jury has retired to
    consider the case. The mandate of Fed. R. Civ. P. 51 is stated
    as follows:
    No party may assign as error the giving or
    the failure to give an instruction unless
    that party objects thereto before the jury
    retires to consider its verdict,  stating
    distinctly the matter objected to and the
    grounds
    of
    the
    objection. Opportunity
    shall be given to make the objection out
    of the hearing of the jury. (Emphasis
    added).
    We have construed this to mean what it says. Objections to
    jury instructions must be stated fully after the charge and
    before the jury retires regardless of any pre-charge
    objections. See
    Senra v. Cunningham
    , 
    9 F.3d 168
    , 171 (1st Cir.
    -10-
    10
    1993); Elgabri v. Lekas, 
    964 F.2d 1255
    , 1259 (1st Cir. 1992);
    Transnational
    Corp.
    v.
    Rodio
    &
    Ursillo,
    Ltd., 
    920 F.2d 1066
    ,
    1069 (1st Cir. 1990). Failure to follow our regime results in
    a plain error analysis.
    After the charge the court invited counsel to the
    bench. All counsel except Taber's made detailed objections on
    the record. The only thing counsel for Taber said was: "Same
    comments as yesterday, Your Honor." This was not sufficient
    under Fed. R. Civ. P. 51 and our case law.
    We have read the jury instructions carefully and find
    no plain error. In fact, we think the jury instructions
    explained this difficult, complex, and lengthy case clearly and
    fairly to the jury.
    MERIT'S COUNTERCLAIM
    Fraud
    Merit objects to the pre-trial dismissal of its fraud
    claim against Taber. The record discloses the following pre-
    trial order:
    Finally, during the Pretrial
    Conference, the parties discussed with the
    Court the fraud claims presented by Taber
    and Merit in the Second Amended Complaint
    and the Counterclaim. Both parties agreed
    that
    these
    fraud
    allegations
    lack
    the
    requisite
    specificity
    detailed
    under
    Rule 9(b)
    of
    the
    Federal
    Rules
    of
    Civil
    Procedure. However, neither party brought
    this issue to the Court's attention before
    the Pretrial Conference. In light of the
    parties' admissions during the Conference,
    and after close examination of the
    complaint and the counterclaim, the Court
    -11-
    11
    will not allow evidence or allegations of
    fraud to be made during Trial by either
    party. (Emphasis added).
    In light of Merit's agreement that its fraud allegations lacked
    the specificity required under Fed. R. Civ. P. 9(b), Merit is
    foreclosed from objecting to the exclusion of its fraud claim.
    Moreover, we have read the entire counterclaim carefully and it
    is obvious that Merit did not rely on any of the fraudulent
    acts alleged. Reliance was not alleged in the fraud claim.
    This was a breach of contract case. Merit's answer and
    counterclaim make it evident that its defense to the breach of
    contract claim was that it met its contract obligations and was
    owed money by Taber (which the jury found to be true).
    Dismissal of Merit's Contract Claims
    Merit objects to two other pre-trial rulings:
    (1) the preclusion of damages compensable in the "construction
    context" of this case; (2) the preclusion of damages from
    Taber's delays and changes in the nature and scope of the work
    contracted.
    As we understand it from Merit's brief at page 48,
    Merit claims that in addition to the amount awarded it by the
    jury for unpaid change orders and other specified claims, it
    has a claim for "disruptions and resulting damages" in the
    amount of two million dollars.  
    Id.
    The answer to this claim comes from the record.
    During the trial, Merit attempted through a blow-up to
    -12-
    12
    introduce evidence of damages for general overhead, general
    field conditions, acceleration costs, and delay damages. The
    court excluded the claim for three reasons. We need go no
    further than the first:
    First, for the pretrial conference on
    February 28, 1995, the Court ordered the
    parties to submit an itemization of all
    damages to be claimed at trial. Merit
    submitted its itemized list of damages by
    motion dated February 28, 1995. During
    said conference Merit discussed with the
    Court all of the claims it wanted to
    present at trial and never mentioned the
    claims brought to the Court's attention
    yesterday.
    Merit waived its claim to the additional damages
    sought by its failure to submit them in accord with the pre-
    trial order of the court.
    The jury's findings that Merit was not liable to
    Taber nullified the two third-party claims brought by Merit.
    The judgment of the district court is     Affirmed.
    Costs on appeal are against Taber.