Walsh v. Zurich American Insurance Comp ( 2017 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 15-2245
    JAMES WALSH,
    Plaintiff, Appellee,
    v.
    ZURICH AMERICAN INSURANCE COMPANY, d/b/a ZURICH DIRECT MARKETS,
    d/b/a ZURICH NORTH AMERICA COMMERCIAL,
    d/b/a ZURICH NORTH AMERICA, et al.,
    Defendants, Appellants.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF NEW HAMPSHIRE
    [Hon. Steven J. McAuliffe, U.S. District Judge]
    Before
    Howard, Chief Judge,
    Selya and Lipez, Circuit Judges.
    Charles P. Roberts, III, with whom Donald S. Prophete and
    Constangy, Brooks, Smith & Prophete LLP were on brief, for
    appellants.
    Jamie N. Hage, with whom Douglas J. Miller, Kathleen A.
    Davidson, and Hage Hodes, P.A. were on brief, for appellee.
    February 22 2017
    LIPEZ, Circuit Judge. A jury found that appellant Zurich
    American      Insurance       Company     ("Zurich")        breached       employment
    agreements with appellee James Walsh when it substantially reduced
    his incentive pay for a lucrative deal -- the largest of its type
    in the company's history -- and did not pay incentive on another
    deal.1      Walsh was awarded double damages and attorney's fees,
    totaling     nearly    $2.4    million,    based      on   findings    that    Zurich
    willfully and without good cause withheld the compensation owed.
    On    appeal,      Zurich   asserts   that     the    evidence      failed    to   show
    contractual breaches, let alone willful ones.                 Hence, the company
    argues, the district court erred in denying its motion for judgment
    as a matter of law on Walsh's contract and wage claims.                        Zurich
    alternatively argues that the district court committed legal error
    by instructing the jury to disregard contract provisions that gave
    the company discretion to limit incentive pay.
    Having     carefully     reviewed       the   record    and     pertinent
    caselaw, we reject Zurich's contention that it was entitled to
    judgment as a matter of law on the breach-of-contract and wage
    claims.     We also uphold the jury's breach and willfulness findings
    stemming from Zurich's withholding of incentive compensation for
    a    deal   made    with    Great   American    Insurance     Company        ("GAIC").
    However, we agree that the district court erroneously concluded
    1
    We note that defendants are a group of related corporate
    entities whom we refer to collectively as "Zurich."
    - 2 -
    that,   if    Walsh    had    an     enforceable        incentive   plan    when    the
    unprecedented deal was struck with Automobile Protection Corp.
    ("APCO"), Zurich lacked discretion as a matter of law to change
    Walsh's incentive formula for that deal.                  Rather than telling the
    jury to disregard the contractual discretion provisions applicable
    to   that    deal,    the    court    should     have    instructed   the    jury   to
    determine whether Zurich's exercise of discretion satisfied the
    implied contractual obligation of good faith and fair dealing.
    We   therefore        vacate    the   district     court's     judgment
    insofar as it incorporates the jury's verdict on the APCO deal,
    affirm the judgment with respect to the GAIC deal, and remand for
    further proceedings.
    I.
    A. Factual Background
    Walsh's dispute with Zurich centers on two compensation
    plans that awarded him incentive pay based on certain types of new
    business brought into the company.                 We sketch the facts as the
    jury could have found them, drawing all reasonable inferences in
    the plaintiff's favor. See, e.g., Butynski v. Springfield Terminal
    Ry. Co., 
    592 F.3d 272
    , 274 (1st Cir. 2010).
    Walsh was hired by Zurich in 1996 as a finance and
    insurance ("F&I") regional administrator responsible for sales in
    Maine and New Hampshire, and he was promoted in 1999 to regional
    sales manager.       Walsh focused on selling various types of coverage
    - 3 -
    to   car   dealers,    including       vehicle    service    contracts,      credit
    insurance, and tire and wheel coverage.                In early 2007, Walsh
    approached his superiors, Bill Stoothoff and Dennis Kane, seeking
    increased   responsibility       and    the    potential     for   salary    growth
    within the company.         Told that nothing was currently available,
    Walsh looked elsewhere.         He received an offer from GMAC in Chicago
    that included a guaranteed salary of $350,000 over eighteen months,
    a $20,000 signing bonus, and a relocation package.
    Within an hour after giving Zurich notice of his decision
    to leave the company, Walsh received a phone call from Kane,
    Zurich's vice president of direct markets, who asked him to
    consider    staying    in   a   new,    soon-to-be-created         position.     In
    subsequent discussions, Stoothoff, Zurich's vice president of F&I,
    offered Walsh the opportunity to manage a new market for Zurich,
    the "alternative distribution channel" -- ADC -- in which the
    company, instead of selling service contracts and other auto-
    related insurance only through car dealers, would sell their
    products more broadly, e.g., selling service contracts through
    telemarketing    and    credit     unions,       equipment    coverage      to   the
    original manufacturers, and contractual liability policies to
    third party administrators of service contracts.
    Walsh advised Stoothoff of his three requirements for
    staying at Zurich: (1) a job description that would allow him to
    grow, with unlimited potential, (2) an annual salary of $250,000
    - 4 -
    for the next eighteen months, and (3) "an incentive plan that
    allows me to make money and grow and do what I need to do."   Zurich
    agreed to meet those terms.   In October 2007, Walsh, Stoothoff and
    Kane signed a "Supplemental Pay Agreement" providing Walsh with a
    monthly supplement of $13,246.63, payable through March 2009, in
    addition to his $91,000 base salary -- a total of roughly $250,000
    annually.    The supplemental payments, which were "in lieu of any
    incentives earned," were designed to meet Walsh's salary demand
    until the new business he was expected to generate would produce
    incentive pay sufficient to support a comparable, or higher,
    salary.
    The October 2007 agreement did not specify the incentive
    arrangement that would go into effect in April 2009, and the
    company began discussing the details of Walsh's incentive plan the
    following summer.    By mid-August 2008, Walsh, Stoothoff and Kane
    had settled on a target of $8 million for the new ADC business in
    2009, and they discussed an incentive formula that would result in
    a total 2009 salary of about $250,000 at the midpoint, with a low
    of $183,000 and a high of $292,000.2     By that time, Walsh's base
    salary had increased to $135,000, and his supplemental payments
    2 The written model prepared by the company's compensation
    specialists showed Walsh's projected incentive pay for the
    multiple types of business for which he was responsible ranging
    from a low-end total of about $48,000 to a maximum of about
    $157,000. The targeted mid-point amount was $115,000, of which
    $60,000 was attributed to the ADC.
    - 5 -
    had decreased ($9,583.35 monthly), with his total annual salary
    still set to be roughly $250,000 until the start of the incentive
    plan in April 2009.
    Through   a     series   of    meetings       and    emails,    Walsh,
    Stoothoff,    Kane,    and    Diane    Eldridge,       a   Zurich     compensation
    consultant,    reached     consensus       on   the    plan      described   above,
    including a revision requested by Walsh in the description of the
    ADC incentive.    Following a meeting on August 27, 2008, Walsh was
    "satisfied that my plan was done. . . .               As far as I'm concerned,
    my boss [Stoothoff] and his boss [Kane] told me that this is your
    plan."   Although Walsh acknowledged that he never saw anything in
    writing confirming that the plan was "final," and the August 2008
    plan was never entered into Zurich's finance system, Walsh viewed
    the "backroom HR or accounting" procedures as irrelevant to the
    plan's completion.         Stoothoff, who had been asked to complete
    Walsh's incentive plan before he left Zurich at the end of August
    2008, also believed that he had accomplished that task.
    The plan on its face covered the entire 2009 calendar
    year, but it was superseded through March by the Supplemental Pay
    Agreement that had been executed in October 2007.                    Hence, Walsh
    would first be eligible to receive incentive payments under the
    August 2008 Plan for premiums received by Zurich after April 1,
    2009.    In addition to a chart that specified variable percentages
    for Walsh's ADC incentive "based on year to date performance
    - 6 -
    against prorated production and profitability goals,"3 the August
    2008 Plan contained the following "CONDITIONS":
    1.   The PLAN is effective January 1, 2009.
    INCENTIVE under the PLAN shall be solely
    within the discretion of the Executive Vice
    President of the COMPANY and is subject to
    interpretation by him / her.     The PLAN is
    subject to cancellation by the Executive Vice
    President at any time.
    . . . .
    7.   Management of the COMPANY reserves the
    right   to    limit  INCENTIVE  in   unique
    situations.4
    Walsh       testified    that   these   provisions   giving   Zurich   --   and
    specifically, Kane, the executive vice president -- the discretion
    to cancel or limit his incentive pay, "didn't mean anything to
    [him]," because such provisions had "never been enforced."
    In September 2008, Walsh contacted representatives of
    APCO to discuss selling Zurich's new alternative distribution
    3
    The Plan stated that ADC incentive would be paid on "NET
    DEALER REMIT (net of chargebacks) for reinsurance and retro
    accounts sold through ALTERNATE DISTRIBUTION CHANNELS." The chart
    was in the form of a nine-box matrix with different percentages
    listed at each intersection of profitability and production goals.
    4
    A third reference to discretion appeared under the heading
    "PURPOSE OF THE PLAN":
    The purpose of the INCENTIVE PLAN is to
    establish a formula whereby certain employees
    . . . may, at the sole discretion of the
    President, be paid an INCENTIVE PAYMENT for
    the PLAN YEAR as a reward to encourage them to
    help make the business of the COMPANY a
    success.
    - 7 -
    products.    The discussions proved fruitful and, in December 2008,
    Walsh closed a deal with APCO likely to produce an amount of
    premiums in 2009 that far surpassed even the high-end projection
    in   the    compensation   models   Zurich    had   prepared   for   Walsh.
    Immediately after the contract signing in a Georgia hotel, as they
    rode an elevator together, Kane told Walsh that he would make a
    lot of money on the deal.      Under the 2008 Plan, Walsh would have
    been entitled to ADC incentive pay of nearly $870,000 in 2009.
    That plan, however, was not implemented.        Rather, in January 2009,
    Kane informed Walsh that he would not allow this amount of ADC
    incentive, and that a new incentive arrangement needed to be
    developed.
    Walsh initially protested any change, telling Kane that
    he was shocked by the refusal to adhere to the incentive program
    they had worked out in August 2008.          Within a few days, however,
    concluding that he had no choice but to accept a change or leave
    the company, Walsh acquiesced to Kane's request that he recommend
    an alternative plan that Walsh would consider fair.                  Walsh's
    subsequent proposal provided for a base salary of $250,000 for the
    duration of the APCO relationship, plus incentives, but Kane
    responded by email that the salary amount "won't work" because "no
    one is on a 250k salary" other than the company's top executive.
    They scheduled a phone conference for later in the week.
    - 8 -
    Walsh testified that he started that call, on January
    30, by again expressing his dissatisfaction with the change in his
    compensation package, but Kane nonetheless "immediately rolled
    into, this is how we're going to pay you going forward."             Kane
    then told Walsh that his compensation for 2009 would consist of a
    continued guarantee of $250,000 in annual income (as Walsh had
    been promised in October 2007), accomplished through base salary
    and an extension of the supplemental pay agreement that was due to
    expire in April 2009.     In addition, the new incentive plan -- the
    "February 2009 Plan" -- would entitle Walsh to $1,000 for each $1
    million of ADC premium paid monthly.        On February 19, Eldridge
    reported to Walsh that Kane had formally approved that plan, with
    minor revisions as Walsh and Eldridge had discussed, and that she
    would be uploading it into Zurich's compensation database.
    Pursuant   to    the   February   2009   Plan,   Walsh's    ADC
    incentive in 2009 for the APCO deal -- $77,000 -- was less than
    one-tenth of the incentive he would have earned under the August
    2008 Plan.   Nonetheless, his total compensation for 2009 reached
    $398,000, which consisted of base salary, supplemental payments,
    and incentives.
    Although the February 2009 Plan technically covered only
    calendar year 2009, no new plan was put into effect for 2010, and
    Walsh continued to operate under the February 2009 Plan.         In the
    late summer and early fall of 2010, another dispute about incentive
    - 9 -
    pay arose when Zurich refused to pay Walsh $101,000 based on new
    business with GAIC.      Although the GAIC transaction was booked by
    Zurich's accounting department as ADC income -- for which Walsh
    would be entitled to incentive pay -- the company maintained that
    the deal was unique and did not in fact fit within the ADC category.
    Accordingly, in mid-October 2010, Zurich executives moved to amend
    Walsh's    still-operative   February        2009   Plan    to   eliminate    his
    entitlement to the $101,000 incentive.
    By that time, the relationship between Walsh and Zurich
    had deteriorated even further. Kane had left Zurich in early 2010,
    and Walsh's new boss, Tina Mallie, told him in June 2010 that his
    future travel to meet with customers was being restricted.                     In
    conversations with Mallie in September, and with another new boss,
    Kathi Ingham, in October, Walsh learned that he would no longer be
    responsible     for   reinsurance    business,      which    had   provided     a
    substantial portion of his incentive pay.            On October 29, he sent
    Ingham an email advising that he would be leaving Zurich in thirty
    days.     He was terminated later that day.
    B. Procedural Background
    In January 2012, Walsh filed a complaint against Zurich
    in New Hampshire state court.         Seeking more than $14 million in
    damages, he alleged breach of contract, breach of the implied
    covenant of good faith and fair dealing, wrongful discharge, and
    willful violation of New Hampshire's wage and hour law. He claimed
    - 10 -
    that Zurich owed him additional APCO incentive, as promised in the
    August 2008 Plan, and GAIC incentive as provided by the February
    2009 Plan.      The case was removed to federal court based on
    diversity jurisdiction, and a trial took place before a jury.
    During the trial, the court granted Zurich's motion for
    judgment as a matter of law on the wrongful discharge claim,5 but
    it otherwise denied the company's motions for judgment as a matter
    of law both at the close of plaintiff's case and at the close of
    all evidence.    The court rejected Zurich's contention that Walsh
    did not produce sufficient evidence to establish that the August
    2008 Plan was a binding agreement or that he was entitled to
    incentive on the GAIC deal. The court also decided not to instruct
    the jury on the implied covenant claim, concluding that the
    contractual good faith issue was subsumed within the breach claim.
    Specifically with respect to the APCO deal, the court ruled that,
    if the jury found that the August 2008 Plan was not an enforceable
    contract, there would be no basis for a claim that the company had
    breached an implied contractual covenant.    Conversely, the court
    held, if the jury found that the August 2008 Plan was a binding
    agreement, Zurich could not have had a good faith belief that the
    5 Walsh has not appealed the court's ruling on the wrongful
    discharge claim, and we do not further address it.
    - 11 -
    Plan's discretion provisions permitted it to retroactively modify
    Walsh's compensation for the APCO deal via the February 2009 Plan.
    The jury found in favor of Walsh on the claims for breach
    of contract and willful violation of New Hampshire wage law, the
    latter finding providing the basis for doubling the contractual
    damages.      See N.H. Rev. Stat. Ann. § 275:44(IV).6         The court
    subsequently denied Zurich's post-trial motion for judgment as a
    matter of law on those claims, and it granted Walsh's motion for
    attorney's    fees   and   expenses.   The   monetary   awards,   before
    doubling, were $791,353 on the APCO deal and $101,000 on the GAIC
    6 Section 275:44 is titled "Employees Separated From Payroll
    Before Pay Days," and it generally provides for the prompt payment
    of wages owed. At issue here is subsection (IV), which states, in
    pertinent part:
    If an employer willfully and without good
    cause fails to pay an employee wages as
    required under . . . this section, such
    employer shall be additionally liable to the
    employee for liquidated damages in the amount
    of 10 percent of the unpaid wages for each day
    except Sunday and legal holidays upon which
    such failure continues after the day upon
    which payment is required or in an amount
    equal to the unpaid wages, whichever is
    smaller . . . .
    N.H. Rev. Stat. Ann. § 275:44(IV). The New Hampshire Supreme Court
    deems an employer's failure to pay owed compensation "willful and
    without good cause" when the nonpayment is done "voluntarily, with
    knowledge that the wages are owed and despite financial ability to
    pay them."   Ives v. Manchester Subaru, Inc., 
    498 A.2d 297
    , 302
    (N.H. 1985) (Souter, J.).
    - 12 -
    deal. The parties stipulated to an award of $595,000 in attorney's
    fees and $9,171.52 in other legal expenses.
    This appeal followed.
    II.
    On    appeal,    Zurich    argues       that   the   district   court
    incorrectly    concluded   that     sufficient      evidence    supported    the
    jury's breach-of-contract and willfulness findings on the APCO and
    GAIC deals and, hence, the court erred by denying its motions for
    judgment as a matter of law on every claim submitted to the jury.
    On the question of breach, Zurich argues that Walsh failed to prove
    two facts necessary to find the company liable for the disputed
    incentive amounts: (1) the August 2008 Plan was an enforceable
    contract covering the APCO deal, and (2) the GAIC deal involved
    ADC business covered by the February 2009 incentive plan.                    In
    addition, Zurich maintains that the court made a legal error in
    handling the APCO breach claim when it refused to instruct on the
    covenant of good faith and fair dealing or "to submit any issue
    regarding Zurich's right under the August 2008 Plan to modify the
    plan and/or limit incentive before the plan became effective on
    April 1, 2009."
    Zurich    further   claims       that    the   evidence   failed    to
    establish that the company acted willfully and without good cause
    when it paid Walsh incentive for the APCO deal under the February
    2009 Plan, rather than the August 2008 Plan, and in refusing to
    - 13 -
    pay incentive on the GAIC deal.    As may be appropriate based on
    the outcome of its claims on the merits, the company also seeks
    reversal of the attorney's fee award or remand for reconsideration
    of the fee amount.
    We review de novo the district court's denial of Zurich's
    motions for judgment as a matter of law, "viewing the evidence in
    the light most favorable to the nonmoving party."     T G Plastics
    Trading Co. v. Toray Plastics (Am.), Inc., 
    775 F.3d 31
    , 37 (1st
    Cir. 2014) (quoting Monteagudo v. Asociación de Empleados del
    Estado Libre Asociado de P.R., 
    554 F.3d 164
    , 170 (1st Cir. 2009)).
    We also apply de novo review to the asserted instructional error.
    See Burke v. McDonald, 
    572 F.3d 51
    , 57 (1st Cir. 2009) ("Where, as
    here, a claim of instructional error challenges the very basis for
    instructing or refusing to instruct on a particular subject, we
    review that claim of error de novo.").
    A. The August 2008 Plan
    1. Sufficiency of the Evidence
    In the circumstances of this case, whether the August
    2008 Plan was an enforceable contract is a question of fact, see,
    e.g., Durgin v. Pillsbury Lake Water Dist., 
    903 A.2d 1003
    , 1006
    (N.H. 2006), and we may overturn the jury's finding that it was a
    finalized agreement only if we can say that no reasonable jury
    could have reached that conclusion, see, e.g., T G Plastics Trading
    - 14 -
    
    Co., 775 F.3d at 38
    .      Zurich is unable to satisfy this "stringent
    standard."    
    Id. Three witnesses
      testified   that   they   understood   the
    contract was effectively a done deal by the time Stoothoff left
    Zurich at the end of August.       Walsh reported that the discussions
    among him, Stoothoff, Kane, and Eldridge through the summer of
    2008 culminated with a meeting in Eldridge's office on August 27
    for the purpose of "finaliz[ing] this plan." Walsh testified that,
    during that meeting, Stoothoff "called in . . . and gave his
    blessing," and Walsh left Eldridge's office "satisfied that my
    plan was done."       Stoothoff similarly testified that he believed
    "all of the essential terms [had] been agreed to," and he therefore
    "thought we were done" and "assumed [the plan] was final" when he
    left Zurich.     He agreed that a reasonable person in Walsh's shoes
    would "have reasonably believed that he would be paid on that
    incentive plan for 2009."        Stoothoff also testified that Kane had
    approved the plan as it stood on August 27.
    To be sure, other evidence suggested that the August
    2008 Plan was never finalized, at least in the way incentive plans
    ordinarily were implemented at Zurich.         Eldridge testified that
    she never received a formal sign-off from Kane on the August 2008
    Plan, noting that "[t]he only approval I received from him was in
    February of '09."     Hence, she never submitted the August 2008 Plan
    for inclusion in Zurich's compensation database.               Even Walsh
    - 15 -
    testified that he did not know what steps needed to be taken to
    implement his plan once it had been agreed upon.          He acknowledged
    that "finalized to me and finalized to the managers above me may
    mean two different things," and he recognized that Stoothoff "may
    have [had] other things to do to get it through and get through
    the system."    Indeed, Stoothoff testified that he did not remember
    Kane saying the plan was final, but he "assumed it was [based] on
    the way the interactions were going."
    The record thus presents mixed messages about the status
    of the August 2008 Plan, and that conflict was for the jurors to
    resolve.   It is not our role to second-guess their determination
    that a meeting of the minds -- and, hence, a binding agreement --
    was reached when the discussion of terms ended on August 27, with
    everyone's apparent approval. See Chisholm v. Ultima Nashua Indus.
    Corp., 
    834 A.2d 221
    , 225 (N.H. 2003) ("A meeting of the minds is
    present when the parties assent to the same terms."); see also
    
    Durgin, 903 A.2d at 1006
    ("A valid, enforceable contract requires
    offer, acceptance, consideration, and a meeting of the minds.").
    The   missing   formal   steps   --   including   entry    into   Zurich's
    compensation database -- could be attributed to the fact that
    implementation of the Plan was more than seven months away rather
    than to its non-final status.7
    7Zurich also highlights the absence of any written protest
    by Walsh about the subsequent change in incentive as an indication
    - 16 -
    Accordingly, we reject Zurich's contention that the
    record does not support the jury's finding that the August 2008
    Plan was an enforceable contract.
    2.   Breach of Contract Instructions
    a. Background
    Throughout the trial, Zurich's counsel argued that, even
    if the August 2008 Plan was a binding agreement, the company was
    free to reduce Walsh's incentive for the APCO deal pursuant to the
    language giving management discretion on whether to pay incentive
    and, specifically, to "limit INCENTIVE in unique situations."   The
    district court ultimately decided that New Hampshire law barred
    Zurich from relying on the Plan's discretion provisions, and, over
    Zurich's objection, it instructed the jury on that point as
    follows:
    Now, you have heard some evidence in this case
    suggesting that the August 2008 incentive plan
    contained language reserving discretion to
    Zurich to change the incentive rates with
    respect to the APCO deal as it deemed
    appropriate. That reservation of rights does
    not permit Zurich to change incentive pay
    rates for the APCO deal after it was closed.
    If you find that the August 2008 incentive
    plan is a binding contract, Zurich is
    that he understood the August 2008 Plan was not final under "the
    established procedure at Zurich for approving and finalizing pay
    plans." That inference is countered, however, by Walsh's testimony
    that he felt compelled either to accept the new plan "or walk out
    the door and try to find another job" -- with the latter choice
    not feasible at that time.
    - 17 -
    obligated to pay plaintiff in accordance with
    its terms with respect to the APCO deal.
    In   rejecting   Zurich's   reliance   on   the   discretion
    provisions, the district court took the view that Walsh's incentive
    pay from the APCO deal, though not labeled as such, was akin to a
    commission that, under New Hampshire case law, necessarily vested
    in December 2008 and could not be withheld absent extenuating
    circumstances, such as a financial disaster for the company.8     See,
    e.g., New Eng. Homes, Inc. v. R.J. Guarnaccia Irrevocable Tr., 
    846 A.2d 502
    , 504 (N.H. 2004) (stating the general rule that "a person
    employed on a commission basis to solicit sales orders is entitled
    to his commission when the order is accepted by his employer"
    8 In its oral ruling on Zurich's renewed motion for judgment
    as a matter of law following the presentation of all evidence, the
    court stated, inter alia, the following:
    So New Hampshire common law is pretty
    clear,    it   seems   to    me.     You   cannot
    retroactively divest an employee of a deferred
    compensation amount that he's already earned
    under an agreement that was extant. And if
    that weren't enough, New Hampshire statutory
    law and regulatory law is pretty clear.
    . . . Certainly Zurich could change the terms
    of employment with respect to incentive pay,
    but only prospectively, not retroactively.
    . . .
    So to the extent that language purports
    to    vest     Zurich    with    discretion    to
    retroactively     change    a   vested   deferred
    compensation entitlement, it's contrary to
    statutory law, and therefore is ultra vires
    and    against   public    policy   and   totally
    unenforceable.
    - 18 -
    (quoting Galloway v. Chicago-Soft, Ltd., 
    713 A.2d 982
    , 984 (N.H.
    1998))); see also Gilman v. Cheshire Cty., 
    493 A.2d 485
    , 488 (N.H.
    1985) (holding that an employer may not "impair its obligation to
    pay [certain] benefits by changing its . . . policy after the
    compensation was earned").        The court also construed regulatory
    and statutory provisions to allow "only prospective[]" changes to
    Walsh's incentive pay.       See N.H. Code Admin. R. Lab. 803.03(c)
    (requiring employers to provide written notice of a change in an
    employee's rate of pay or salary "prior to the effective date of
    such   change");   see    also   N.H.   Rev.   Stat.   Ann.    §   275:49(II)
    (requiring notice of changes in rates of pay "prior to the time of
    such changes").
    In addition, the court observed that Zurich's promise to
    pay Walsh at a specific rate was designed to incentivize him to
    sell ADC products.       Once he did so, the court ruled, the company
    had no discretion to change the incentive formula solely to "[m]ake
    Zurich richer [and] [m]ake the plaintiff poorer."             The court thus
    held that any exercise of discretion to retroactively deny Walsh
    "a vested deferred compensation entitlement" was "against public
    policy and totally unenforceable." See supra note 8. Accordingly,
    it refused to instruct the jury on the covenant of good faith and
    fair dealing "because I'm not going to allow the defense of we
    have discretion to not pay him."
    - 19 -
    On appeal, Zurich reiterates its contention that the
    August 2008 Plan and New Hampshire law allowed the company to
    change Walsh's incentive formula, limited only by the obligation
    to do so reasonably and in good faith.         The company asserts that
    the record unequivocally demonstrates that it complied with this
    obligation, and, hence, it is entitled to judgment as a matter of
    law on the breach of contract claim.          At a minimum, the company
    argues, the jurors should have been instructed on the implied
    covenant of good faith and told that, if they found the August
    2008 Plan to be a binding agreement, they must go on to determine
    whether Zurich's substitution of a new plan in February 2009 was
    a reasonable and good-faith exercise of the discretion explicitly
    given to company management by the Plan.           As we explain below, we
    agree that Zurich was entitled to such an instruction.
    b. Interpreting the Plan
    The district court reached its conclusion that Walsh's
    incentive for the APCO deal vested in December 2008, barring its
    retroactive reduction, by "reading [the August 2008 Plan] in
    context and properly construing it."          The court's focus on the
    terms of the agreement is consistent with both employment law
    generally and New Hampshire's approach to employment contract
    disputes.    See Restatement of Employment Law § 3.02(b) ("Whether
    incentive   compensation     has   been   earned   is   determined   by   the
    agreement   on   incentive   compensation    between     the   employer   and
    - 20 -
    employee   or   any     binding    employer   promise   or    binding    policy
    statement.");9 New Eng. 
    Homes, 846 A.2d at 508
    (finding that
    ambiguity in a Letter of Understanding setting forth commission
    structure created "a legitimate dispute as to whether the plaintiff
    owed wages to the employees"); 
    Galloway, 713 A.2d at 985
    (examining
    employment    agreement     to    determine   whether   contract   specified
    departure from general rule that "employees paid on a commission
    basis earn commissions when their employer accepts an order"); see
    also Pachter v. Bernard Hodes Grp., Inc., 
    891 N.E.2d 279
    , 285 (N.Y.
    2008) ("[W]hen a commission is 'earned' and becomes a 'wage' for
    purposes of [the New York wage-payment statute] is regulated by
    the parties' express or implied agreement . . . .").
    However,    the   district   court   did   not   identify    which
    specific terms of the August 2008 Plan it relied on, and our own
    9 Section 301 of the Restatement of Employment Law, titled
    "Right to Earned Compensation," includes the following comment:
    Earned    compensation.     The    employer's
    obligation to pay compensation depends on
    whether the employee has earned it. In the
    case of a salary or wage, the employee is
    typically paid for a period of service, and
    the compensation is earned when that period
    ends . . . . In the case of commissions, the
    employee is paid for sales made or other unit
    of   output   produced,   and   whether   the
    compensation is earned depends on whether the
    sales have been made or other unit of output
    has been produced in accordance with the
    parties' agreement.
    
    Id. § 3.01,
    cmt. d.
    - 21 -
    review of the Plan's language leads us to a contrary view.       See
    Clukey v. Town of Camden, 
    797 F.3d 97
    , 101 (1st Cir. 2015) (stating
    that a trial court's contract interpretation is reviewed de novo);
    Birch Broad., Inc. v. Capitol Broad. Corp., 
    13 A.3d 224
    , 228 (N.H.
    2010) (same).   Before detailing our reasoning, we note that we
    agree with the underlying premise of the district court's ruling
    -- i.e., if the August 2008 Plan gave Walsh "a vested deferred
    compensation entitlement," equivalent to an ordinary commission,
    for his work on the APCO deal, Zurich could not reduce that
    entitlement retroactively.    Hence, the first inquiry is whether,
    under the August 2008 Plan, the incentive promised to Walsh for
    the APCO business vested when he closed the deal in December 2008.
    In interpreting the Plan, we "give the language used by
    the parties its reasonable meaning, considering the circumstances
    and the context in which the agreement was negotiated, and reading
    the document as a whole."    Birch 
    Broad., 13 A.3d at 228
    .   When we
    conduct that examination, we find multiple indicators that Walsh
    did not "earn" incentive when the APCO deal closed in December
    2008; rather, his entitlement to incentive pay vested when Zurich
    received ADC premiums and could apply the variables specified in
    the August 2008 Plan to determine the amount of incentive due.
    First, as the district court recognized, the August 2008
    Plan does not set forth a classic commission arrangement, whereby
    the employee is entitled to a certain percentage of the amount of
    - 22 -
    a sale of goods or real estate.10   See, e.g., New Eng. 
    Homes, 846 A.2d at 504
    (specifying three and one-half percent "commission"
    for modular home sales); 
    Galloway, 713 A.2d at 984-85
    (specifying
    "commission rate[s]" "to be paid on sales closed").       Although
    commission in the insurance industry would more likely be based on
    premiums received than on "products" (i.e., policies) sold, and
    the Plan establishes a premium-based measure, the agreement does
    not say that Walsh "earns" a specified percentage of the premiums
    resulting from the sale of ADC insurance products.    Rather, the
    Plan's self-proclaimed purpose is to set up a "formula whereby
    certain employees . . . may, at the sole discretion of the
    President, be paid an INCENTIVE PAYMENT for the PLAN YEAR as a
    reward to encourage them to help make the business of the COMPANY
    a success."   The "Purpose" paragraph goes on to say that "[t]he
    amount of INCENTIVE to each PARTICIPANT is related to VEHICLE
    SERVICE CONTRACT new business & service."   (Emphasis added.)
    Specifically with respect to ADC incentive, the Plan
    states:
    ALTERNATIVE DISTRIBUTION CHANNEL incentive
    shall be paid on Net Dealer, Third Party
    Administrator, Agency Business and Original
    Equipment    Manufacture  Remit   (net   of
    10 Early in the trial, the court observed that the promised
    incentive "looks like commission, but neither side is claiming
    it's a commission," and it noted at another point that Walsh
    "didn't have a deal per commission when he made the sale." The
    court properly looked beyond the terminology in attempting to
    discern the nature of the incentive.
    - 23 -
    chargebacks)    sold   through    ALTERNATIVE
    DISTRIBUTION CHANNELS. . . . Quarterly
    INCENTIVE shall be calculated on year to date
    performance against prorated production and
    profitability goals . . . [and] when
    calculation results in a negative amount, no
    INCENTIVE shall be paid in that quarter.
    The amount of incentive pay, which is described generally as
    "related   to"   new   ADC   business,   thus   depends     specifically   on
    developments occurring after the deal -- "year to date" factors
    that, as Walsh explained at trial, include the "loss ratio" for
    the new products.      Indeed, the Plan contemplates the possibility
    that no incentive will be paid in some fiscal quarters.
    In other words, the incentive arrangement in the August
    2008 Plan is framed as a computation based on the company's net
    income from certain new business, not as a calculable entitlement
    triggered by sales consummated by Walsh.          In fact, in its ruling
    on Zurich's post-trial motion for judgment as a matter of law on
    the GAIC deal, the district court noted the parties' concession
    "that Walsh did not have to personally sell anything in order to
    receive incentive pay on this, or any other, deal producing
    Alternative Distribution Channel revenue; he was compensated based
    on premiums realized through the ADC."            Order at 24 n.1.         The
    acknowledged     reliance    on   premiums      collected     to   determine
    incentive, rather than on Walsh's own efforts, underscores the
    distinction between the Plan and a typical commission arrangement.
    That is, the incentive promise here was premised on the receipt of
    - 24 -
    premiums, starting in April 2009, and not on the acquisition of
    the new business that would produce those premiums.
    Second, the Plan by its terms went into effect on January
    1, 2009, and Walsh's incentive payments were not scheduled to begin
    until April.       There is no dispute that, at least until the first
    of   the   year,    the    only   operative   agreement   governing   Walsh's
    compensation       above    his   base   salary   was     the   October   2007
    Supplemental Pay Agreement.           Thus, when the August 2008 Plan was
    adopted (according to the jury), it provided a promise of future
    payment, not an immediate entitlement.            The district court noted
    this prospective effect, observing that, as of December 2008, the
    pertinent "employment period hasn't commenced."            Walsh's testimony
    reinforces the future focus of the August 2008 Plan. In describing
    how the ADC incentive program was set up, Walsh noted that he and
    his superiors expected premiums to come in on a monthly basis,
    "[s]o at the end of my supplemental pay on April 1st of 2009, I
    would need to have premiums coming in the door in order for me to
    earn income."       (Emphasis added.)     At another point, he similarly
    stated that his incentive was based on "the actual premium that
    came in the door."
    Third, the Plan states that departing employees are
    entitled to "INCENTIVE earned prior to termination," and specifies
    that the incentive due "shall be calculated based on production
    and profitability at the time of termination and paid at the next
    - 25 -
    regular   INCENTIVE    pay    date."       Once   again,   the   focus    is    on
    performance factors that can only be established when premiums
    start to be paid.      Under this provision, if Walsh had left Zurich
    in February or March of 2009, he would not be entitled to an
    incentive   payment     because      his   compensation    package   did       not
    incorporate the incentive formula until April 2009.               Hence, this
    provision seems at odds with a determination that he had "earned"
    incentive as soon as he closed the deal.
    Taken together, the Plan's express language and its
    context -- notably, that it did not govern Walsh's compensation
    until April 2009 -- persuade us that the legally correct reading
    of the August 2008 Plan does not give Walsh vested incentive pay
    at the time he closes a deal.          Rather, when the Plan took effect
    on January 1, Walsh acquired a contractual right to receive ADC
    incentive pursuant to the Plan's formula -- a right that, as
    explained below, constrained Zurich's discretion to alter the
    formula -- but he had not yet earned any incentive.                      Walsh's
    testimony is compatible with this reading, and the interpretation
    gains further strength from the Plan's multiple references to the
    company's discretion to withhold or change the incentive pay
    specified   therein.         Walsh   was   told   in   express   terms     that,
    notwithstanding the formula in the Plan, the incentive pay he will
    receive in the future may be limited by management in "unique
    situations."   In other words, he was warned that his incentive pay
    - 26 -
    may differ from the Plan's terms.   He accepted the Plan with that
    warning.   See Olbres v. Hampton Coop. Bank, 
    698 A.2d 1239
    , 1243
    (N.H. 1997) ("[P]arties generally are bound by the terms of an
    agreement freely and openly entered into, and courts cannot make
    better agreements than the parties themselves have entered into or
    rewrite contracts merely because they might operate harshly or
    inequitably."   (quoting Mills v. Nashua Fed. Sav. & Loan Assoc.,
    
    433 A.2d 1312
    , 1315 (N.H. 1981) (alteration in original)).
    Of course, as we explain in the next section, this
    interpretation of the Plan does not mean that Zurich possessed
    unbridled authority to revise the incentive formula for 2009 to
    Walsh's detriment.   Rather, it means only that the February 2009
    Plan did not effect a retroactive diminution of earned compensation
    that would be barred as a matter of law.11    The question remains
    whether the particular adjustment that Zurich made, even though
    facially permissible under the discretion provisions of the August
    2008 Plan, nonetheless constituted a breach of contract.
    11 Under this construction of the August 2008 Plan, the
    district court's reliance on New Hampshire provisions requiring
    notice of changes in compensation "prior to the time of such
    changes" was also misplaced. N.H. Rev. Stat. Ann. § 275:49(II);
    see also N.H. Code Admin. R. Lab. 803.03(c). Walsh had notice of
    the February 2009 Plan before the change in his incentive pay took
    effect in April.
    - 27 -
    c. The Obligation of Good Faith
    Under New Hampshire law, a contract giving one party
    unlimited discretion to modify the agreement is permissible, but
    subject   to    "an    implied       obligation    of    good    faith      to   observe
    reasonable limits in exercising that discretion, consistent with
    the parties' purpose or purposes in contracting." Centronics Corp.
    v. Genicom Corp., 
    562 A.2d 187
    , 193 (N.H. 1989) (Souter, J.)
    (emphasis added).        Hence, when discretionary action adverse to the
    complaining      party    is     taken,    the     question      is   whether        "the
    defendant's      exercise       of    discretion    exceeded       the      limits    of
    reasonableness."       
    Id. The answer
    to this question depends on
    identifying the common purpose or purposes of
    the contract, against which the reasonableness
    of the complaining party's expectations may be
    measured,   and   in  furtherance   of   which
    community standards of honesty, decency and
    reasonableness can be applied.
    
    Id. at 193-94;
    see also Milford-Bennington R.R. Co. v. Pan Am Rys.,
    Inc.,   
    695 F.3d 175
    ,     179-80    (1st    Cir.   2012)     (describing       New
    Hampshire law); Livingston v. 18 Mile Point Dr., Ltd., 
    972 A.2d 1001
    , 1005-06 (N.H. 2009) (stating that the function of the implied
    good-faith duty, in the context of "limitation of discretion in
    contractual performance," is "to prohibit behavior inconsistent
    with    the    parties'      agreed-upon      common     purpose      and     justified
    expectations,     as     well    as   'with   common     standards       of      decency,
    - 28 -
    fairness    and    reasonableness'"     (quoting       Richard   v.   Good   Luck
    Trailer Court, 
    943 A.2d 804
    , 808 (N.H. 2008)) (citation omitted)).
    As described above, the district court refused to allow
    the jury to consider the reasonableness of Zurich's substitution
    of the February 2009 Plan for the August 2008 Plan with respect to
    the APCO incentive.      Instead, the court resolved that issue as a
    matter     of   law,   incorrectly      ruling    that     Zurich     had    acted
    unreasonably      because,   in   its   view,    the   company   impermissibly
    withheld an amount of incentive that Walsh had already earned.
    Zurich asks us for the converse ruling: a determination
    as a matter of law that it acted reasonably and in good faith.
    The company asserts that the reduction in Walsh's incentive was
    reasonable, and thus proper, because it was driven by the enormous,
    unanticipated value of the APCO deal.            As noted above, Walsh would
    have been entitled to nearly $870,000 in APCO incentive alone in
    2009 under the August 2008 Plan -- giving him total compensation
    for the year of about $1.1 million.             That salary far exceeds the
    annual income discussed in 2007 when Walsh was persuaded to stay
    at Zurich, and it also eclipses by a large margin the high-end
    salary predicted for 2009 by the modeling for the August 2008 Plan
    ($292,000).       More pertinently, Walsh's claimed incentive amount
    dwarfs the incentive modeling for the first year of ADC business,
    which predicted a high point of $90,000.                Hence, Zurich argues,
    the roughly $400,000 income that resulted from the February 2009
    - 29 -
    incentive arrangement -- combined with the company's decision to
    extend Walsh's guaranteed monthly supplemental payments12 -- was
    patently   reasonable   and   consistent   with   the   parties'   "common
    purpose or purposes."    Centronics 
    Corp., 562 A.2d at 194
    ; see also
    
    id. ("[T]he good
    faith requirement is not a fail-safe device
    barring a defendant from the fruits of every plaintiff's bad
    bargain, or empowering courts to rewrite an agreement even when a
    defendant's discretion is consistent with the agreement's legally
    contractual character.").
    Although Zurich offers a plausible view of the evidence,
    we cannot say that it is the only permissible view.         A jury could
    have found that the amount of the reduction in Walsh's anticipated
    APCO incentive was excessive in light of the parties' intentions
    when the August 2008 Plan was developed.          Zurich knew that Walsh
    was hoping for unlimited potential in his new position, and the
    company's stated goal was to keep Walsh at Zurich.          A jury could
    thus find that, when they agreed to the August 2008 Plan, the
    parties' underlying objective was to provide Walsh, as soon as
    possible, with substantially higher income than the minimum he had
    12As noted above, the October 2007 Supplemental Pay Agreement
    ended by its terms in March 2009. The monthly payments it provided
    were specifically "in lieu of any incentives earned." When Zurich
    switched to the February 2009 Plan for Walsh's incentive pay, it
    also prepared a new Supplemental Pay Agreement that provided a
    monthly allotment of $12,777.77 from April to December 2009 "in
    addition to any incentives earned."
    - 30 -
    been guaranteed when he agreed to remain at Zurich.   Though no one
    anticipated such a lucrative deal to materialize so early in
    Zurich's acquisition of ADC business, a jury could view the switch
    to a much less favorable incentive formula for the APCO business
    as inconsistent with the wide-open compensation potential the
    parties had agreed upon.   In addition, Walsh's testimony suggested
    that he acted to his disadvantage based on the terms of the August
    2008 Plan because its incentive structure motivated him to take
    "the chance" of focusing solely on the APCO business, rather than
    pursuing multiple other deals.
    Given that the evidence presented at trial could have
    supported either of these scenarios, the district court erred by,
    in effect, directing the jury to find a breach if it found the
    August 2008 Plan to be a binding, enforceable agreement.   Instead,
    the court should have instructed the jurors that, because the Plan
    expressly gave Zurich discretion to limit incentive pay, they must
    go on to determine whether the company reasonably and in good faith
    exercised that authority -- i.e., whether the particular changes
    to Walsh's compensation package in February 2009 satisfied the
    implied contractual covenant of good faith.   See Centronics 
    Corp., 562 A.2d at 193
    .
    Put another way, Zurich's adoption of a less favorable
    formula would not in itself be a breach of the contract's explicit
    terms because the August 2008 Plan on its face allowed Zurich to
    - 31 -
    make whatever changes it wanted to Walsh's incentive pay.                 Walsh's
    APCO-related breach claim thus depended on whether, in making that
    change, Zurich breached the covenant of good faith and fair dealing
    implicit in the August 2008 Plan.              If the jury were to find no
    violation of the implied covenant, there would be no contractual
    breach. Consequently, the portion of the district court's judgment
    incorporating the finding of breach must be vacated.
    3.    Willfulness
    Our decision invalidating the finding of breach with
    respect to the APCO incentive necessarily also invalidates the
    jury's finding that Zurich "willfully and without good cause"
    failed to pay wages owed, in violation of New Hampshire law.                N.H.
    Rev. Stat. Ann. § 275:44(IV); see supra note 6.                    Zurich argues
    that it is entitled to judgment as a matter of law on the statutory
    claim, which provided for doubling the breach-of-contract damages.
    New    Hampshire    courts       have     construed    the    phrase
    "willfully and without good cause" to mean "voluntarily, with
    knowledge that the wages are owed and despite financial ability to
    pay them."    
    Chisholm, 834 A.2d at 226
    (quoting Ives v. Manchester
    Subaru,   Inc.,     
    498 A.2d 297
    ,   302    (N.H.    1985)   (Souter,   J.)).
    Although an employer cannot avoid a willfulness finding simply by
    disputing an employee's entitlement to pay, see 
    Chisholm, 834 A.2d at 225-26
    , "no liquidated damages are available when an employer's
    refusal to pay wages is based upon bona fide belief that he is not
    - 32 -
    obligated to pay them," New Eng. 
    Homes, 846 A.2d at 507-08
    (quoting
    Richmond v. Hutchinson, 
    829 A.2d 1075
    , 1077 (N.H. 2003)).                     New
    Hampshire law contemplates legitimate disputes "over the amount of
    wages," and employers are directed by statute to pay "without
    condition" and within specified time periods "all wages, or parts
    thereof, conceded by [them] to be due, leaving to the employee all
    remedies he might otherwise be entitled to . . . as to any balance
    claimed."      N.H. Rev. Stat. Ann. § 275:45(I).
    We    leave    this   willfulness    issue     for   resolution    on
    remand.   In a new trial, additional evidence may be offered on the
    parties' expectations and understandings when they agreed to the
    August 2008 Plan.         The question of willfulness should be assessed
    on the basis of any such new record.            However, we take no view as
    to whether the issue of willfulness should reach the jury.              Hence,
    as with the issue of breach, we vacate the judgment entered on the
    statutory wage claim with respect to the APCO incentive.
    B. The GAIC Incentive
    1.    Sufficiency of the Evidence
    Zurich attempted to persuade the jury that the type of
    business involved in the GAIC deal was never intended to trigger
    incentive pay for Walsh, and that the company's decision to amend
    the February 2009 Plan to exclude that payment was merely an
    attempt   to     clarify    his   compensation.      The    record,   however,
    permitted the jury to conclude otherwise.
    - 33 -
    As with the August 2008 Plan, the evidence was not one-
    sided, and Zurich offered testimony that could have supported a
    verdict in its favor.      Kathi Igham, the vice president for finance
    and insurance in the fall of 2010, testified that the disputed
    GAIC deal was "purely a financial transaction[] that didn't fall
    under [Walsh's] responsibilities of the sale and service of the
    alternative     distribution      channel."       She    elaborated     that   the
    agreement was "just a transfer of liability from Great American to
    Zurich," and, as such, it was not "appropriate" for Walsh to
    receive incentive on that deal.              In addition, she explained that
    this   type    of   transaction    was   not    "contemplated     within   th[e]
    definition" of ADC, but was placed there "from an accounting
    perspective" because it was even less suitable for placement on
    the "direct side" of the business -- i.e., "it ended up to be a
    good sort of path of least resistance to put it in the alternate
    channel."       Terry   McCafferty,      a    Zurich    senior   vice   president
    involved in the GAIC deal, likewise described that business as "a
    very unusual transaction" -- "not something we normally do" -- and
    stated that "there was really no place else to put it per se that
    made sense."
    Walsh, however, presented evidence permitting the jury
    to find that the 2009 Plan awarded him incentive on the GAIC deal.
    Indeed, an email sent on September 8, 2010 from a payroll employee
    - 34 -
    to Tina Maillie -- Ingham's predecessor as vice president --
    explicitly said as much.      In pertinent part, the email stated:
    The financial statements for August include
    $105M in premium on the GAIC reinsurance deal.
    Based on the 2009 plan, we would pay $105,000
    to Jim Walsh on this premium. How would you
    like to handle the August incentive due to the
    current review of the 2009 plan and the dollar
    amount of the incentive payment?13
    A month later, on October 13, Ingham sent an email to Eldridge
    containing the following directive: "[A]s we discussed, we should
    have an amendment that stipulates that Jim [Walsh] will not receive
    incentive related to the GAIC UPR transaction that posted in
    September for $101m."    McCafferty, despite his statement that the
    deal was "very unusual," said he could offer no guidance on whether
    it was -- or was not -- properly categorized as ADC business.
    Zurich's contention is that these communications about
    amending   Walsh's   incentive   plan    simply   reflect     the   company's
    effort to reconcile the language of the plan with the understanding
    that the GAIC deal was not, in fact, ADC business and, hence,
    should not be treated as a basis for incentive for Walsh.              Given
    the   competing   evidence,   however,    we   cannot   say    that   it   was
    13It appears that there were two separate GAIC deals that
    closed at about the same time, totaling $105 million. The parties'
    dispute concerns only $101 million in GAIC business -- hence, an
    incentive of $101,000 (at the rate of $1,000 per $1 million under
    the February 2009 Plan).
    - 35 -
    unreasonable for the jury to accept Walsh's claim that he was
    entitled to incentive pay for the $101 million GAIC deal.
    2.     Willfulness
    The evidence described above also was sufficient to
    permit the jury's finding that Zurich acted willfully in refusing
    to pay Walsh incentive on the disputed GAIC deal.                  Given the jury
    finding    that    the   February   2009    Plan      covered     that   deal,    the
    communications        above    permit      the        inference     that     Zurich
    "voluntarily, with knowledge of the obligation and despite the
    financial ability to pay it," withheld the $101,000 incentive owed
    to Walsh.     
    Ives, 498 A.2d at 302
    .
    III.
    To briefly recap our holdings, we find no error in the
    district court's denial of judgment as a matter of law to Zurich
    on the APCO breach-of-contract claim.            The evidence was sufficient
    to support the jury's finding that the August 2008 Plan was an
    enforceable       agreement.     However,     because      the    district   court
    erroneously instructed the jury that Zurich lacked discretion to
    change    Walsh's    incentive   pay,   and      it    consequently      failed    to
    instruct the jury on the implied covenant of good faith, we vacate
    the portion of its judgment incorporating the jury's breach-of-
    contract finding on the APCO incentive and the related violation
    of statutory wage law (the willfulness issue).                    Accordingly, we
    vacate the award on the APCO deal of $1,582,706 (the claimed
    - 36 -
    incentive of $791,353, doubled by statute).      On the GAIC claim, we
    affirm the judgment incorporating the jury's findings and, hence,
    uphold the award on that deal of $202,000 (the claimed incentive
    of $101,000, doubled).    Given these holdings, and the need for the
    district court to reconsider its award of attorney's fees, we
    vacate that award.
    Going forward, this case will be in a considerably
    different posture.    Neither the enforceability of the August 2008
    Plan nor the GAIC claims will be retried.        In addition, we have
    found, as a matter of law, that the August 2008 Plan does not
    entitle Walsh to incentive payments for the APCO deal pursuant to
    the formula set forth in that plan.       Hence, the focus will be on
    whether Zurich's exercise of its reserved discretion to change
    Walsh's   incentive      arrangement     "exceeded   the   limits   of
    reasonableness."     Centronics 
    Corp., 562 A.2d at 193
    .    Relatedly,
    the issue of willfulness under the New Hampshire wage statute must
    be revisited.   See N.H. Rev. Stat. Ann. § 275:44(IV).     Given this
    landscape, we believe both parties would be well advised to
    consider settlement.
    Affirmed in part, vacated in part, and remanded for
    proceedings consistent with this opinion.      Each party to bear his
    or its own costs.
    - 37 -
    

Document Info

Docket Number: 15-2245P

Judges: Howard, Lipez, Selya

Filed Date: 2/22/2017

Precedential Status: Precedential

Modified Date: 11/5/2024