Arch Insurance Company v. The Graphic Builders LLC ( 2022 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 21-1126
    ARCH INSURANCE COMPANY,
    Plaintiff, Appellee,
    v.
    THE GRAPHIC BUILDERS LLC,
    Defendant, Appellant,
    RCM MODULAR, INC.,
    Defendant.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Nathaniel M. Gorton, U.S. District Judge]
    Before
    Thompson, Lipez, and Kayatta,
    Circuit Judges.
    Richard E. Briansky, with whom Eckert Seamans Cherin &
    Mellott, LLC and Peckar & Abramson, P.C. were on brief, for
    appellant.
    Jonathan C. Burwood, with whom Watt, Tieder, Hoffar &
    Fitzgerald, LLP was on brief, for appellee.
    June 1, 2022
    LIPEZ, Circuit Judge.           In this diversity case, The
    Graphic Builders LLC ("Graphic"), a general contractor, is seeking
    to enforce a performance bond issued by Arch Insurance Co. as
    surety for a subcontractor hired to work on a major project for
    Graphic.   Arch, however, claims that Graphic breached the terms of
    the performance bond, and it seeks a judgment declaring that it
    has no liability under the bond.           The district court sided with
    Arch,   concluding   that   Graphic    was   required   to   terminate   the
    subcontractor as a condition of seeking performance from Arch but
    had not done so.     See Arch Ins. Co. v. Graphic Builders LLC, 
    519 F. Supp. 3d 54
    , 60-61 (D. Mass. 2021).            Accordingly, the court
    granted summary judgment for Arch.
    On appeal, Graphic argues that the district court erred
    in concluding that Arch's obligation to provide the warranty
    performance   it   seeks    was   conditioned    on   termination   of   the
    subcontractor.     Graphic asserts that both the bond's language and
    relevant precedent support its position. We disagree and therefore
    affirm the district court's judgment.
    I.
    When reviewing a grant of summary judgment, we consider
    the facts in the light most favorable to the nonmoving party. See,
    e.g., Modeski v. Summit Retail Sols., Inc., 
    27 F.4th 53
    , 56 (1st
    Cir. 2022).   In this case, there is no material disagreement about
    the facts, which we set forth below.         Graphic and Arch debate only
    - 2 -
    whether those facts give rise to Arch's obligations under the
    performance bond.
    In 2017, Graphic was hired for a construction project in
    Charlestown,    Massachusetts,      that    consisted   of    converting      an
    existing   commercial   building       to    loft-style      apartments       and
    constructing a four-story apartment building on the same property.
    Graphic and the property owner agreed on a modular method of
    construction for the new building, and Graphic then selected an
    experienced modular manufacturer, RCM Modular, Inc., to fabricate
    and assemble the structure at a cost of about $8.6 million.               Among
    the   obligations   included   in    the    subcontract      was   a   "Special
    Manufacturers [sic] Warranty" for the modular units' windows and
    doors.1
    A   performance   bond    issued    in   conjunction        with   the
    subcontract rendered Arch, as surety, "jointly and severally"
    responsible for RCM's obligations.          Section 3 of the bond, which
    is reproduced in Section II below, specifies the actions by Graphic
    1Graphic asserts in its brief that Arch was obliged "to issue
    a post-completion window warranty and other warranties," but it
    does not specify what "other warranties" are at issue. At oral
    argument, Graphic's counsel stated that only the window warranty
    is at issue.    Following Graphic's lead, we focus on the window
    warranty and consider waived any assertion that a different
    analysis would apply to "other warranties."
    - 3 -
    that would trigger Arch's "obligation under th[e] Bond," including
    declaring RCM in default and terminating the subcontract.2
    Shortly after RCM delivered the modular units to Graphic
    in   May   2018,    Graphic   complained     to   RCM   that    the    units   were
    defective.       Graphic reported that, among other issues, the windows
    leaked and the exteriors of the modules were misaligned.                       In a
    letter to Arch recounting the sequence of events that followed its
    initial complaints, Graphic reported that it had received "no
    meaningful response from RCM."        It therefore "engaged in remedial
    efforts     to    correct   the   defectively     delivered      and    installed
    modules."3       Issues remained, however, and Graphic and RCM met at
    the project site in September 2018 to "develop[] a remediation
    plan to correct the defective work[,] including producing the
    window     manufacturer's     warranty."      According    to    Graphic,      "RCM
    2Arch's performance bond is in a standard format commonly
    used in the construction industry and known as an American
    Institute of Architects A312 Performance Bond (2010 ed.). See,
    e.g., St. Paul Fire & Marine Ins. Co. v. VDE Corp., 
    603 F.3d 119
    ,
    124 (1st Cir. 2010) (noting that a leading commentator on
    construction law has described the A312 performance bond as "one
    of the clearest, most definitive, and widely used type of
    traditional   common   law   'performance   bonds'   in   private
    construction" (quoting Philip L. Bruner & Patrick J. O'Connor,
    Jr., 4A Bruner & O'Connor on Construction Law § 12:16 (2009))).
    3Although the record is somewhat unclear on this point, it
    appears that a substantial amount of the remedial work was done by
    third-party subcontractors hired by Graphic but that RCM itself
    was asked to address the window deficiencies.
    - 4 -
    failed to complete the remediation plan," and the manufacturer
    refused to provide a warranty.
    There followed a series of letters from Graphic to RCM
    and Arch, initially providing notice only of RCM's potential
    default and then, on April 30, 2019, notifying RCM and Arch of
    RCM's default.    The April 30 letter stated that Graphic was
    declaring RCM in default because, among other reasons, it had
    failed to deliver a window warranty and had not "undertake[n]
    remedial steps to defectively rendered Work and forc[ed] Graphic
    to do so at its own expense."    Graphic noted, however, that it was
    "not yet terminating its Subcontract with RCM," but reserved the
    right to do so.   Graphic followed up with another letter to Arch,
    dated May 3, reiterating the notice of default and advising that
    "Graphic is not yet taking the next step of terminating the
    Subcontract and making demand on the Bond in the hope that RCM
    and/or Arch" would arrange to quickly complete the unfinished work
    and "make a good faith move to reduce the large financial impacts
    Graphic has suffered."4   In a letter dated May 3, Arch acknowledged
    receipt of Graphic's April 30 and May 3 communications, noting its
    4 The May 3 letter detailed the expedited remedial work
    Graphic deemed necessary to allow building occupancy by June 1 and
    asked that "RCM and/or Arch deploy, without further delay, the
    qualified staff, materials and equipment needed to correct
    defectively rendered Work" or to complete unfinished work. Among
    the listed requests, subject to the project owner's agreement, was
    "a warranty bond as a substitute for the window warranty that RCM
    has been unable to deliver."
    - 5 -
    understanding that Graphic was "not attempting to make a claim on
    the Arch Performance Bond."
    In September 2019, Graphic sent a detailed letter to
    Arch, with a copy to RCM, stating that it was providing notice of
    RCM's default pursuant to the terms of the performance bond and
    demanding that Arch pay $3.175 million in remedial costs that
    Graphic had incurred "as a result of [RCM]'s failure to perform."
    In response, Arch denied liability on the ground that Graphic had
    not complied with multiple prerequisites specified in the bond for
    triggering Arch's surety obligations.    Arch noted, inter alia, the
    undisputed fact that Graphic had "not terminat[ed] RCM before it
    undertook to complete RCM's scope of work," a failure that,
    according to Arch, rendered the bond "null and void."
    In December 2019, Arch filed this action seeking a
    declaratory judgment that Graphic had materially breached the
    performance   bond,   thereby   discharging    Arch    from   liability.5
    Graphic   counterclaimed,   asserting   that   the    preconditions   for
    performance set forth in section 3 of the bond do not apply to
    Arch's obligations to indemnify Graphic for its costs related to
    RCM's defective work or the surety's obligation to provide a window
    5 An earlier state-court lawsuit filed by Graphic against RCM,
    later amended to include Arch, was removed to federal court by
    Arch and consolidated with this action. In its brief, Arch reports
    that, in May 2021, an arbitration panel awarded Graphic roughly
    $1.8 million against RCM. We note these other proceedings solely
    as background; they play no role in our resolution of this appeal.
    - 6 -
    warranty in RCM's stead.            Arch subsequently moved for summary
    judgment.       In   its    opposition,     Graphic     asserted,    among   other
    arguments,    that     it   could   not    satisfy    the   bond's    termination
    requirement "because RCM had 'substantially completed' its work
    under the subcontract and thus could not be terminated."                       Arch
    Insurance Co., 519 F. Supp. 3d at 61.
    In granting summary judgment for Arch, the district
    court rejected Graphic's assertion that it was unable to terminate
    the subcontract.       It found that Graphic had "indisputably failed
    to comply with a condition precedent" for Arch's liability under
    the performance bond by "unilaterally arrang[ing] for third-party
    subcontractors to remediate RCM's work" instead of terminating
    RCM.   Id.      Accordingly, the court held that Graphic materially
    breached the bond and that Arch was "discharged from any and all
    liability" under it.        See id.   This appeal followed.
    II.
    On appeal, Graphic reiterates its contention that it had
    no obligation to comply with section 3 of the bond to be entitled
    to the performance it demands from Arch, and it also again argues
    that termination was neither feasible nor legally permissible
    because   RCM    had    substantially       completed    its   work    under    the
    subcontract.     Before turning to those issues, however, we briefly
    pause to note a change in Graphic's approach.               As described above,
    Graphic asked the district court to impose two types of obligations
    - 7 -
    on Arch: indemnification for Graphic's costs in completing RCM's
    work       and    "complet[ion    of]   RCM's   Warranty   Obligations   Post
    Completion."         Graphic has abandoned its indemnification claim on
    appeal.6         Hence, as stated by Graphic's counsel at oral argument,
    "the sole and only issue . . . in this appeal is to enforce Arch's
    post-completion guarantee of its obligation to issue a window
    warranty."
    We review a district court's grant of summary judgment
    de novo.         Clark Sch. for Creative Learning, Inc. v. Phila. Indem.
    Ins. Co., 
    734 F.3d 51
    , 54 (1st Cir. 2013).            Here, as noted above,
    the material facts are undisputed. The parties' differences spring
    from the terms of the performance bond and related caselaw.
    A. The Terms of the Performance Bond
    The question at the heart of this appeal is whether
    section 3 of the bond, which sets forth a series of preconditions
    for Arch's obligation to act on behalf of RCM, applies to Graphic's
    window warranty claim.           In relevant part, section 3 states:
    §3 If there is no [Contractor][7] Default under
    the [Subcontract], the Surety's obligation
    under th[e] Bond shall arise after:
    Graphic also brought a claim under Massachusetts's unfair
    6
    business practices statute that it does not pursue on appeal. See
    Mass. Gen. Laws ch. 93A, §§ 2, 11.
    The performance bond identifies Graphic as "Owner," but
    7
    provides in section 15 that, if the bond covers an agreement
    between a contractor and subcontractor, "the term Contractor in
    this Bond shall be deemed to be Subcontractor and the term Owner
    shall be deemed to be Contractor."   Thus, we have replaced the
    term "Owner" in section 3 with "Contractor," "Construction
    - 8 -
    .1 the [Contractor] first provides notice
    to the [Subcontractor] and the Surety that the
    [Contractor] is considering declaring a
    [Subcontractor] default.    Such notice shall
    indicate    whether   the    [Contractor]   is
    requesting     a    conference    among    the
    [Contractor], [Subcontractor] and Surety to
    discuss the [Subcontractor]'s performance
    . . . .
    .2    the   [Contractor]    declares    a
    [Subcontractor]   Default,   terminates    the
    [Subcontract] and notifies the Surety; and
    .3 the [Contractor] has agreed to pay the
    Balance   of  the   [Subcontract]   Price   in
    accordance with the terms of the [Subcontract]
    to the Surety or to a contractor selected to
    perform the [Subcontract].
    Under section 5 of the bond, "[w]hen the [Contractor]
    has satisfied the conditions of Section 3," the surety must take
    one of several specified actions at its own expense. These include
    arranging for the original subcontractor to complete the job;
    taking   over   completion   of    the   work    "through        its   agents   or
    independent     contractors";     arranging     for   a    new    subcontractor
    acceptable to the contractor; or, in lieu of completing the work,
    determining "the amount for which it may be liable" and making
    that payment to the contractor.
    As described below, Graphic also invokes section 1 of
    the bond, which states in full: "The [Subcontractor] and Surety,
    Contract"    with      "Subcontract,"         and         "Contractor"      with
    "Subcontractor."
    - 9 -
    jointly and severally, bind themselves, their heirs, executors,
    administrators, successors, and assigns to the [Contractor] for
    the performance of the [Subcontract], which is incorporated herein
    by reference."
    B. Governing Law of Contract Interpretation
    Under Massachusetts law, "we construe [the] insurance
    policy de novo under the general rules of contract interpretation."
    Clark Sch. for Creative Learning, 734 F.3d at 55 (quoting Valley
    Forge Ins. Co. v. Field, 
    670 F.3d 93
    , 97 (1st Cir. 2012)).         Neither
    party   claims   that   the    language   of   the   performance   bond   is
    ambiguous; each insists that the plain language of the bond
    supports its position.        We agree that there are no ambiguities in
    the contested provisions and, hence, our task is to "interpret
    [the bond] according to its plain terms."            Farmers Ins. Exch. v.
    RNK, Inc., 
    632 F.3d 777
    , 784 (1st Cir. 2011) (quoting Den Norske
    Bank AS v. First Nat'l Bank of Bos., 
    75 F.3d 49
    , 52 (1st Cir.
    1996)); see also Nicolaci v. Anapol, 
    387 F.3d 21
    , 26 (1st Cir.
    2004) ("Ambiguity is not created merely because the litigants
    disagree about the meaning of a contract.").
    In examining the terms of the bond, we must be mindful
    that "a contract should be construed to give it effect as a
    rational business instrument and in a manner which will carry out
    the intent of the parties."         Starr v. Fordham, 
    648 N.E.2d 1261
    ,
    1270 (Mass. 1995) (quoting Shane v. Winter Hill Fed. Sav. & Loan
    - 10 -
    Ass'n, 
    492 N.E.2d 92
    , 94 (Mass. 1986)).       To ascertain "the scope
    of a party's obligations" under an agreement, we may not "isolat[e]
    words and interpret[] them as though they stood alone," id. at
    1269 (quoting Bos. Elevated Ry. Co. v. Metro. Transit Auth., 
    83 N.E.2d 445
    , 451 (Mass. 1949)), but must instead "construe the
    contract as a whole, in a reasonable and practical way, consistent
    with its language, background, and purpose," USM Corp. v. Arthur
    D. Little Sys., Inc., 
    546 N.E.2d 888
    , 893 (Mass. App. Ct. 1989)
    (cited favorably in MCI WorldCom Commc'ns, Inc. v. Dep't of
    Telecomms. & Energy, 
    810 N.E.2d 802
    , 810 (Mass. 2004)).          Surety
    agreements are similarly construed.       See St. Paul Fire & Marine
    Ins. Co. v. VDE Corp., 
    603 F.3d 119
    , 122 (1st Cir. 2010) ("As a
    general matter, 'surety contracts are subject to the same rules of
    construction as other contracts.     The terms of surety obligations,
    therefore, "should be interpreted as a whole, and not out of the
    context of all the other terms."'" (quoting In re Sinking of M/V
    Ukola, 
    806 F.2d 1
    , 4 (1st Cir. 1986))); Gordon & Dilworth v.
    Abbott, 
    154 N.E. 523
    , 524 (Mass. 1926) ("The liability of a surety
    or guarantor is to be ascertained from the terms of the written
    instrument   by   which   his   obligation   is   expressed,   construed
    according to the usual rules of interpretation in the light of the
    subject-matter, the well-understood usages of the business, and
    the relations of the parties to the transaction.").
    - 11 -
    C. Does the Bond Oblige Arch to Provide the Window Warranty?
    It is undisputed that Graphic fulfilled the requirements
    of section 3.1 of the performance bond with respect to its warranty
    claim.     As described above, Graphic sent multiple letters to Arch
    stating that it was considering declaring a default, including on
    the warranty issue, and it sought a conference among the parties
    (which occurred in April 2019). It also is undisputed that Graphic
    did not fulfill the requirements of sections 3.2 and 3.3. Although
    Graphic declared RCM in default, it did not terminate RCM and it
    never agreed to pay Arch any portion of the contract price.
    Graphic, however, maintains that its demand that Arch provide a
    window warranty does not require compliance with section 3's
    conditions.
    Graphic's   argument      depends     on    distinguishing       the
    provision of the window warranty from the physical work that RCM
    was obligated to perform under the subcontract.                Its principal
    contention is that a "post-completion" warranty obligation is not
    reasonably     subject   to   section     3's    termination        requirement.
    Graphic, however, is not making a post-completion warranty claim
    in   the     sense   that     such    a   claim        ordinarily     would   be
    understood -- i.e., a demand under an operative warranty for
    remediation     of   construction      work     that    is   revealed,    post-
    completion, to be defective.          See, e.g., Sweetwater Apartments,
    PA, LLC v. Ware Constr. Servs., Inc., No. 11-CV-155, 2012 WL
    - 12 -
    3155564, at *5 (M.D. Ala. Aug. 3, 2012) (concluding that the surety
    was liable for repairs under a one-year warranty issued by its
    principal) (citing cases).8         Rather, Graphic asserts that RCM
    failed to produce a promised warranty.
    The   caselaw   Graphic    cites   provides   no   support   for
    excluding that sort of warranty claim from section 3's scope.
    Together, sections 3 and 5 of the A312 bond protect the surety by
    clearly signaling when the surety must take over for a defaulting
    principal and by giving the surety the choice on how to remediate
    the default.    See generally St. Paul Fire & Marine Ins. Co. v.
    City of Green River, 
    93 F. Supp. 2d 1170
    , 1178 (D. Wyo. 2000),
    aff'd, 6 Fed. App'x 828 (10th Cir. 2001) (noting the importance of
    preserving the surety's "ability to protect itself pursuant to
    performance options granted under a performance bond"); Enter.
    Cap., Inc. v. San-Gra Corp., 
    284 F. Supp. 2d 166
    , 177 (D. Mass.
    2003) (same).   Graphic appears to be arguing that this protection
    is inapplicable to its warranty claim for two primary reasons: (1)
    it is not asking Arch to remedy or complete RCM's physical window
    work, and (2) the warranty does not come into play until after the
    physical work is done.    Neither reason stands up to scrutiny.
    8We cite to the unpublished decision in Sweetwater Apartments
    because Graphic relies on that case, and on a half-dozen other
    cases cited in Sweetwater, both published and unpublished, to
    support its argument.
    - 13 -
    The   obligation   to    provide   a   manufacturer's   window
    warranty is a distinct element of the Graphic-RCM subcontract.
    The mere fact that the warranty obligation does not involve hands-
    on construction does not reveal why it would be excluded from the
    conditions in the bond that apply to other performance elements of
    the subcontract.    Nor does timing provide the explanation.        While
    the benefits of a warranty ordinarily may be realized after a
    construction project is completed (or substantially completed),
    see, e.g., Stonington Water St. Assocs., LLC v. Hodess Bldg. Co.,
    
    792 F. Supp. 2d 253
    , 260 (D. Conn. 2011) (describing "the punch
    list" as the "list of warranty work"), procuring the warranty from
    the window manufacturer was an          obligation that needed to be
    fulfilled before RCM's performance under the contract would be
    complete.   Indeed, Graphic has valued RCM's warranty obligation at
    $2 million, a significant proportion of the subcontract's total
    price tag of roughly $8.6 million.9
    We see nothing in the language of the bond that would
    exclude RCM's default in fulfilling the warranty obligation from
    section 3's requirements.      The performance options available to
    Arch under section 5 of the bond are no less suitable for the
    9  In its Opposition to Plaintiff's Motion for Summary
    Judgment, Graphic stated that it was "forced . . . to sign an
    independent guaranty in the amount of $2 million providing the
    [project] Owner the same rights as under the contractual warranty,"
    and it listed "a warranty liability in the amount of $2 million"
    among its damages related to RCM's work.
    - 14 -
    warranty obligation than for the physical work of fixing the
    windows. Arch might have attempted to secure the warranty by using
    its   own   agents    or   a   new    subcontractor   to   remedy     the   window
    problems, as contemplated by section 5. Or it might have attempted
    to    secure    the   warranty      through   negotiations   with     the   window
    manufacturer based on the remedial work that RCM had already
    performed.
    Importantly, as these possible scenarios for Arch's
    actions under section 5 reveal, the warranty "performance" that
    Graphic seeks is inextricably linked to the window installation
    itself.     The warranty was withheld based on the manufacturer's
    assessment that the installation remained problematic even after
    RCM's remedial efforts.10           In effect, then, Graphic's version of a
    warranty claim is an attempt to shift to Arch the risk Graphic
    assumed when, instead of terminating RCM and placing the burden of
    remediating the window installation in Arch's hands, it persisted
    in demanding action from RCM.
    To separate the subcontract's window installation and
    warranty       obligations     in    the   way   Graphic   proposes    would    be
    inconsistent with the "language, background, and purpose" of the
    performance bond, USM Corp., 
    546 N.E.2d at 893
    , as it would clearly
    In a March 2019 email to Graphic, the window manufacturer
    10
    referred to ongoing "installation deficiencies at this project
    [that] are incompatible with issuance of a warranty."
    - 15 -
    frustrate the bond's design to allow the surety to manage the
    response to a default for which it would be responsible.             With
    respect to securing the warranty, Graphic's decision to eschew
    termination   and   continue   working   with   RCM   despite   Graphic's
    ongoing dissatisfaction with RCM's performance was no different,
    under the terms of the bond, from a unilateral decision to replace
    RCM with a third-party subcontractor.     Both decisions sidestep the
    requirements of section 3 and "extinguish[] the options available
    to [the surety] under [section 5] of the performance bond."        Solai
    & Cameron, Inc. v. Plainfield Cmty. Consol. Sch. Dist. No. 202,
    
    871 N.E.2d 944
    , 956 (Ill. App. Ct. 2007); see also, e.g., Seaboard
    Sur. Co. v. Town of Greenfield, 
    370 F.3d 215
    , 220 (1st Cir. 2004)
    (noting that "[c]ourts have consistently held that an obligee's
    action that deprives a surety of its ability to protect itself
    pursuant to performance options granted under a performance bond
    constitutes a material breach, which renders the bond null and
    void" (quoting St. Paul Fire & Marine, 
    93 F. Supp. 2d at 1178
    ));
    Dragon Constr., Inc. v. Parkway Bank & Tr., 
    678 N.E.2d 55
    , 58 (Ill.
    App. Ct. 1997) ("Surely, [the insurer] would not have issued the
    surety bonds if it did not have the authority to protect itself
    through the selection of a successor contractor.").
    Arguably, then, to obtain Arch's performance of RCM's
    promise to provide the manufacturer's window warranty, Graphic
    should have terminated RCM and asked Arch to take over the task of
    - 16 -
    properly     completing        the     window        installation          work      to    the
    satisfaction of the manufacturer. At a minimum, however, the terms
    of   the    bond     required     Graphic       to     comply       with      section     3's
    prerequisites to trigger Arch's specific obligation to furnish the
    window     warranty.        Put   simply,     Graphic      is       claiming      that    RCM
    defaulted     in    performing       the    warranty      portion        of    its    window
    obligations,        but   it   has    not   satisfied         the    bond's       condition
    precedent for Arch to assume responsibility for that default.
    In resisting this construction of the bond, Graphic has
    insisted that, pursuant to the subcontract and general principles
    of contract law, it properly gave RCM the opportunity to cure the
    window defects.11         See generally 4A Philip L. Bruner & Patrick J.
    O'Connor, Jr., 4A Bruner & O'Connor on Construction Law § 12:42
    (August     2021)    (hereafter       "Bruner      &    O'Connor")         (stating       that
    "[t]ermination for default clauses commonly require the obligee to
    give the contractor and the surety 'notice of default' prior to
    termination        for    default"    for    the       purpose      of     "giv[ing]       the
    contractor    an     opportunity       to   'cure'      the    default        and    thereby
    preclude termination").              Moreover, Graphic says, it would have
    11In its September 2019 letter to RCM and Arch, Graphic said
    that it had "expressly negotiated the right to cure RCM's defects
    without terminating the Subcontract and collect these costs from
    both RCM and the Surety."       Although section 16.3.1 of the
    subcontract states that Graphic is authorized to correct RCM's
    defective work and charge RCM for "any damage, loss, cost or
    expense suffered or incurred," the provision makes no reference to
    the surety.
    - 17 -
    faced "the potential risk of a claim for wrongful termination" if
    it had terminated RCM and invoked the performance bond instead of
    working with RCM to resolve the window issues.
    We acknowledge the difficulty contractors may face in
    navigating    between    the     risk    of    premature     termination    of    a
    subcontractor    and    the    risk     of    failing   to    comply     with    the
    requirements of section 3 of the A312 performance bond.                    See 4A
    Bruner & O'Connor, supra, at § 12:38 (noting that "[a] wrong
    decision to terminate is a material breach of contract and results
    in the obligee's completion of the contract without recourse
    against the contractor or surety" and that "[t]he wrong decision
    not to terminate may result in unsatisfactory completion . . . ,
    with recourse limited to the contractor and not the surety").                   Yet
    that is the framework under which Graphic agreed to operate
    pursuant to the performance bond, and it was obliged to adhere to
    the bond's terms to invoke the bond's coverage. Under those terms,
    it   was   Graphic's    burden   to     determine   if,    and   when,    RCM   had
    defaulted and to terminate RCM if it sought recourse for the
    default from Arch. See generally Salois v. Dime Sav. Bank of N.Y.,
    FSB, 
    128 F.3d 20
    , 26 n.10 (1st Cir. 1997) ("[U]nder Massachusetts
    law, 'one who signs a writing that is designed to serve as a legal
    document . . . is presumed to know its contents.'" (quoting Hull
    v. Attleboro Sav. Bank, 
    596 N.E.2d 358
    , 362 (Mass. App. Ct. 1992))
    (omission in original)).
    - 18 -
    In any event, the record unequivocally belies Graphic's
    suggestion that a delicate balance between premature and required
    termination existed here.         Graphic first sought remediation from
    RCM in May 2018, and it complained repeatedly about defective
    window installation -- along with making demands for the warranty
    -- through the spring of 2019.          In the first of two letters sent
    to RCM in October 2018, Graphic demanded "a full-scale remediation
    effort" that would "ensure complete and permanent correction of
    every window."       In the same letter, Graphic directed RCM "to
    immediately      provide    the      missing    warranty,"     along     with
    "confirmation that the final installation currently in progress
    complies with the manufacturer's requirements."
    More than two months later, in its January 2019 letter
    notifying RCM and Arch of RCM's potential default, Graphic stated
    that    RCM   was   in   "material    breach   of   the   Subcontract"   and
    identified, among the breaches, the "[f]ailure to install properly
    all windows in accordance with the manufacturer's requirements."
    In March 2019, as noted above, the window manufacturer communicated
    its concern about continuing installation deficiencies.            Then, in
    April and May 2019, Graphic notified Arch of RCM's default,
    including the failure to provide the warranty, while expressly
    declining to terminate the subcontract.12           Hence, even if Graphic
    In May 2019, Graphic proposed three "undertakings" to RCM
    12
    and Arch "to avoid termination and to mitigate the cascading
    - 19 -
    justifiably and properly allowed RCM to attempt to cure the window
    problems and obtain the manufacturer's warranty into the fall of
    2018,        that    rationale   for    refraining   from     termination   cannot
    insulate Graphic's decision not to do so when those initial
    curative efforts failed -- or at least by the following spring,
    when it deemed RCM in default.13
    We likewise find untenable Graphic's contention that
    section 1 of the bond, which broadly asserts RCM's and Arch's joint
    and several responsibility for performing the contract, supports
    its warranty claim against Arch.               Graphic makes the astonishing
    assertion that "[n]owhere in [section] 1 of the Arch Performance
    Bond     or    the    Subcontract      . . . are   any   of   [Graphic]'s   rights
    negative       consequential impacts associated with such a decision."
    As noted        above, these included a demand that "RCM and/or Arch
    secure a        warranty bond as a substitute for the window warranty
    that RCM       has been unable to deliver."
    We note that, in deposition testimony, Graphic's
    13
    representative, Marvin Lahoud, stated that Graphic's interactions
    with Arch and RCM in 2018 and 2019 were aimed at eliciting
    cooperation in resolving the construction problems without the
    need to terminate RCM.      Lahoud explained that RCM's "specific
    manufacturing techniques and abilities" precluded terminating the
    subcontract   because    no    other  subcontractor   could   have
    satisfactorily completed the modular construction work in RCM's
    stead, at least without extraordinary expense and a lengthy delay.
    We do not minimize the difficulties Graphic faced in completing
    the project in a timely way. However, the view that only RCM could
    appropriately perform the remedial work is inconsistent with
    Graphic's acceptance of a bond under which Arch's obligation to
    perform includes the right to choose the path forward in the event
    of a default, including the option to select alternative
    contractors.
    - 20 -
    contingent upon termination of RCM."            While that statement is
    accurate, basic contract principles -- and Massachusetts law --
    make clear that section 1 of the bond is only reasonably understood
    as qualified by the provisions and conditions that follow.                See
    McAdams v. Mass. Mut. Life Ins. Co., 
    391 F.3d 287
    , 299 (1st Cir.
    2004) ("Contracts must . . . be read as a whole."); Bos. Elevated
    Ry. Co., 83 N.E.2d at 451 (rejecting a construction of a contract
    derived from "isolating words and interpreting them as though they
    stood alone").    The surety is not a party to the subcontract, and
    it necessarily plays a different role in the relationship among
    the parties.     That role is defined by the bond, which, for the
    specific warranty claim at issue here, requires Graphic to fulfill
    the prerequisites of section 3 before Arch's "obligation under
    th[e] Bond shall arise."      See Elm Haven Constr. Ltd. P'ship v.
    Neri Constr. LLC, 
    376 F.3d 96
    , 100 (2d Cir. 2004) (noting that one
    of the "standard principles of contract interpretation" applicable
    to surety bonds "is that, before a surety's obligations under a
    bond can mature, the obligee must comply with any conditions
    precedent" (quoting U.S. Fid. & Guar. Co. v. Braspetro Oil Servs.
    Co., 
    369 F.3d 34
    , 51 (2d Cir. 2004))).
    Hence,   pursuant   to    the     unambiguous   language   of   the
    performance bond, any obligation of Arch to provide the window
    warranty was conditioned on Graphic's termination of RCM, an action
    Graphic chose not to take.
    - 21 -
    D.     Was Termination of RCM Foreclosed as a Matter of Law?
    As a backup argument, Graphic asserts that applicable
    judicial precedent prevented it from terminating the subcontract
    after RCM had delivered and installed the modules -- i.e., after
    the "physical" work covered by the subcontract, albeit defective,
    was completed.        Graphic's contention that it was not permitted to
    terminate     RCM     despite   the     bond's     requirement      rests    on   the
    proposition that a contractor may not lawfully be terminated once
    its work under a contract is "substantially complete."                      But even
    if this proposition is generally correct, see 4A Bruner & O'Connor,
    supra, at § 12:45,14 it does not help Graphic on the record before
    us.
    Section 10.1.3 of the Graphic-RCM subcontract defines
    "substantial completion" as "the time when construction Work is
    sufficiently        complete    in    accordance     with     the   Drawings      and
    Specifications so the Owner can occupy or utilize the Work or a
    designated portion thereof for the use to which it was intended."
    That     definition    tracks     the     widely   accepted    understanding       of
    "substantial        completion"      in     the    construction      industry      in
    Massachusetts and elsewhere.               See Kettle Brook Lofts, LLC v.
    Specht, 
    177 N.E.3d 176
    , 186 (Mass. App. Ct. 2021) ("[T]he term
    Section 12:45 of the Bruner & O'Connor treatise states that
    14
    an "obligee may not terminate for default a construction contract
    that has been substantially performed."
    - 22 -
    ['substantially complete'] is well understood in the context of
    construction of real property to refer to a state in which the
    property is ready to be used for its intended purpose, in this
    case, residential occupancy."); Kinetic Builder's Inc. v. Peters,
    
    226 F.3d 1307
    ,   1315   (Fed.   Cir.    2000)    ("A   project   should     be
    considered substantially completed when it is capable of being
    used for its intended purpose."); 3 Bruner & O'Connor, supra, at
    § 8:27 ("As a general rule, substantial completion is defined as
    that point in the construction where the work is sufficiently
    complete that the owner may occupy or utilize the work for the use
    for which it was intended.").            Substantial completion does not
    necessarily mean that the work is free of all defects, but only
    that there is "such an approximation to complete performance that
    the   owner    obtains   substantially       what    was    called   for   by   the
    contract."      Handy v. Bliss, 
    90 N.E. 864
    , 864 (Mass. 1910); see
    also id. at 864-65 (noting that "there might be a substantial
    performance of the contract" even if "omissions and imperfections"
    remain).
    Graphic's position appears to be that these principles
    of    construction    law    supersede      the   bond's     pre-condition      for
    termination (as we have construed the bond) for their warranty
    claim.     Specifically, it argues that it could not terminate RCM
    after RCM had installed the modules because the subcontract work
    was at that point substantially completed -- notwithstanding the
    - 23 -
    defects.     However,    this      assertion   of   substantial    completion
    directly conflicts with Graphic's representations to RCM and Arch
    throughout the nine months, from July 2018 through April 2019, in
    which Graphic was demanding remediation of the work performed by
    RCM before ultimately declaring RCM in default.              In its September
    2019 letter to RCM and Arch, Graphic recounted that, when the first
    modules were delivered and installed, the defects -- including
    leaking windows -- "were so prolific and systemic that it precluded
    [Graphic]   and   any   of   its    subcontractors    from    completing   the
    remaining work on the Project."          In its April 30, 2019 letter to
    RCM and Arch providing notice of default, Graphic listed among
    RCM's material breaches of the subcontract RCM's "[f]ailure to
    deploy the labor and materials needed to achieve Substantial
    Completion of the Work by May 31, 2019."              Indeed, several days
    later -- in its letter of May 3 -- Graphic demanded that RCM and
    Arch expedite the remedial work so that the building would be ready
    for occupancy by June 1.        In that letter, Graphic accused RCM of
    "fail[ing] to perform under the terms of the Subcontract, or for
    that matter, to perform by any measure."
    Graphic, in other words, told RCM and Arch that RCM had
    not yet achieved "Substantial Completion" of its work as of May
    2019 and that the building was not yet in a condition to be occupied
    at that time.      Graphic's argument that it could not lawfully
    terminate RCM once the modular units had been installed -- or even
    - 24 -
    after RCM's unsuccessful attempts to fix the windows -- thus lacks
    both legal and factual support.     We note, moreover, that Graphic
    took the position that the option to terminate remained as late as
    May 2019, when it advised RCM and Arch that it was "not yet taking
    the next step of terminating the Subcontract and making demand on
    the Bond."15
    In   sum,   the   performance   bond   required   Graphic   to
    terminate RCM to trigger Arch's obligation to provide a window
    warranty, and the undisputed facts in the record show that Graphic
    had ample knowledge of RCM's alleged failures at a time when
    termination remained a viable option under the relevant principles
    of law.   The district court therefore properly granted summary
    judgment for Arch.
    Affirmed.
    15 In its reply brief, Graphic asserts that Arch may not rely
    on deposition testimony to defend the district court's grant of
    summary judgment by "attempt[ing] to establish that substantial
    completion was never reached and that [Graphic] consciously chose
    not to terminate Arch," stating that the testimony "at most, raises
    a question of fact as to whether termination was permissible when
    the warranty issue arose."     Although we recount some of that
    testimony above, see supra note 13, our conclusion regarding
    substantial completion is based solely on the legal principles
    cited above as applied to the undisputed facts in the record,
    including Graphic's clear, express representations in the
    correspondence it sent to RCM and Arch.
    - 25 -
    

Document Info

Docket Number: 21-1126P

Filed Date: 6/1/2022

Precedential Status: Precedential

Modified Date: 6/1/2022

Authorities (19)

Dragon Construction, Inc. v. Parkway Bank & Trust , 287 Ill. App. 3d 29 ( 1997 )

Hull v. Attleboro Savings Bank , 33 Mass. App. Ct. 18 ( 1992 )

St. Paul Fire & Marine Insurance v. VDE Corp. , 603 F.3d 119 ( 2010 )

Solai & Cameron, Inc v. Plainfield Community Consolidated ... , 374 Ill. App. 3d 825 ( 2007 )

St. Paul Fire & Marine Insurance v. City of Green River , 93 F. Supp. 2d 1170 ( 2000 )

Enterprise Capital, Inc. v. San-Gra Corp. , 284 F. Supp. 2d 166 ( 2003 )

USM Corp. v. Arthur D. Little Systems, Inc. , 28 Mass. App. Ct. 108 ( 1989 )

Stonington Water Street Assoc., LLC v. Hodess Building Co. , 792 F. Supp. 2d 253 ( 2011 )

Farmers Insurance Exchange v. RNK, Inc. , 632 F.3d 777 ( 2011 )

in-re-the-sinking-of-the-mv-ukola-crew-cases-the-oceanus-mutual , 806 F.2d 1 ( 1986 )

Nicolaci v. Anapol , 387 F.3d 21 ( 2004 )

elm-haven-construction-limited-partnership , 376 F.3d 96 ( 2004 )

united-states-fidelity-and-guaranty-company-and-american-home-assurance , 369 F.3d 34 ( 2004 )

Salois v. Dime Savings Bank , 128 F.3d 20 ( 1997 )

Kinetic Builder's, Inc.,appellant v. F. Whitten Peters, ... , 226 F.3d 1307 ( 2000 )

Seaboard Surety Co. v. Town of Greenfield Ex Rel. ... , 370 F.3d 215 ( 2004 )

McAdams v. Massachusetts Mutual Life Insurance , 391 F.3d 287 ( 2004 )

Den Norske Bank As v. First Nat'L of Bost , 75 F.3d 49 ( 1996 )

Valley Forge Insurance v. Field , 670 F.3d 93 ( 2012 )

View All Authorities »