APB Realty, Inc. v. Georgia-Pacific LLC ( 2020 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 19-1311
    APB REALTY, INC.,
    Plaintiff, Appellant,
    v.
    GEORGIA–PACIFIC LLC,
    Defendant, Appellee,
    LIQUIDITY SERVICES, INC.; BEASLEY FOREST PRODUCTS, INC.,
    Defendants.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Leo T. Sorokin, U.S. District Judge]
    Before
    Howard, Chief Judge,
    Lynch and Kayatta, Circuit Judges.
    Howard B. D'Amico and Howard B. D'Amico, P.C. on brief for
    appellant.
    Nicholas D. Stellakis, Timothy J. Fazio, Shauna R. Twohig,
    and Hunton Andrews Kurth LLP on brief for appellee.
    January 17, 2020
    KAYATTA, Circuit Judge.            Before our court for the second
    time, this case now illustrates one important difference between
    facts sufficient to make a claim plausible for pleading purposes
    and facts sufficient to render a judgment against the claimant
    clearly erroneous.      For the following reasons, we affirm as not
    clearly erroneous the district court's judgment entered after a
    bench trial finding no binding contract between the parties.
    I.
    APB    brought   this        breach-of-contract    claim   against
    Georgia–Pacific after a putative deal for the sale of rail cars
    fell through.    In round one of this case, we considered whether
    the facts alleged in APB's complaint stated a cause of action
    sufficient to survive a motion to dismiss under Federal Rule of
    Civil Procedure 12(b)(6).           See APB Realty, Inc. v. Ga.–Pac. LLC,
    
    889 F.3d 26
    , 27–29 (1st Cir. 2018).           For the reader's convenience,
    we repeat those alleged facts more or less verbatim as follows:
    *       *       *
    In    April   2015,       Georgia-Pacific    let   APB   know   that
    Georgia-Pacific had eighty-eight rail cars to sell "where is, as
    is."   APB was interested, and extended an offer to Georgia-
    Pacific's broker as follows:
    Total for all 88 x Log Stake Railcars
    $1,636,000 (Including 16% Buyer's Premium).
    - 2 -
    APB   spoke   further     with   Georgia-Pacific's   broker,
    apparently to obtain schematics on the cars.      On July 23, Georgia-
    Pacific's broker sent another email, stating as follows:
    Per our discussion yesterday, here are the
    schematics for the cars, that include the
    manufacturer information.
    Our team has presented your offer to [Georgia-
    Pacific] for final approval, and should have
    an answer by close of business tomorrow.
    I'll let you know when the approval comes, and
    please don't hesitate to call if you should
    have any additional questions.
    One of [our] team members along with [Georgia-
    Pacific] will coordinate transfers of all of
    the cars upon completion of the sale.
    On July 24, Georgia-Pacific's broker emailed APB once more, as
    follows:
    Here are the two options that [Georgia-
    Pacific] has brought back for us to close the
    deal on.
    Option 1, basically states that for $61K, you
    buy insurance that will replace as many
    Southern Wheels as needed to eliminate that
    problem.   [Georgia-Pacific] will manage and
    take care of that issue. So after any real
    costs, you are paying a small percentage as
    insurance against the number being larger than
    51 wheel sets.
    Option 2 is the deal with you taking
    responsibility for any Southern Wheels.
    Let me know which deal is best for you, and
    I'll get this closed out as early as possible
    next week.
    The email then proceeded to summarize the options thusly:
    Option 1   . . . As is, where is.      Georgia-
    Pacific   assumes    responsibility   for   the
    replacement of all southern wheels if found.
    Customer     retains     responsibility     for
    - 3 -
    transportation to final destination. Proposed
    Offer: $1,697,000. . . .
    Option 2:   . . . As is where is.    Customer
    assumes responsibility for the replacement of
    all southern wheels if found.        Customer
    retains responsibility for transportation to
    final    destination.       Proposed   Offer:
    1,636,000.
    The complaint does not tell us what "Southern Wheels"
    are.   But the parties' communications as alleged do make clear
    that Georgia-Pacific regarded them as being a problem with some of
    the cars that would take on the order of $61,000 ($1,697,000 minus
    $1,636,000) to eliminate.
    Three days later, APB responded that it was "leaning
    towards option 1, should know this afternoon," and confirmed with
    Georgia-Pacific's   broker   one    detail   that   apparently   arose   in
    conversation (45 cars would "come with the free move").            Before
    APB confirmed its selection, however, Georgia-Pacific's broker
    emailed once again, this time with the news that Georgia-Pacific
    accepted an offer to sell all 88 railcars,
    which was substantially higher than yours.
    This offer has been processed, and we expect
    to close on it shortly. If this high offer
    does not close we will come back to you and
    see if you have a further offer for these cars.
    Adding insult to injury, APB shortly thereafter learned that the
    interloping purchaser was the same company with which APB, a
    broker, had been negotiating to resell the cars.           In short, the
    seller and the ultimate buyer cut out APB, the middle person.
    *      *        *
    - 4 -
    In our prior decision, we held that those alleged facts
    allowed us to "plausibly infer the making and breaking of a
    contract."       
    Id. at 30
    .   We therefore vacated the dismissal of the
    complaint and remanded so that the case might proceed beyond the
    pleadings.       
    Id.
    On remand, both parties moved for summary judgment.           In
    so doing, neither party offered any new material evidence,1 and
    both agreed to the facts as alleged.             In other words, they agreed
    that the alleged communications took place as stated, but neither
    party offered any further evidence as to how to construe those
    communications in light of industry convention or as a result of
    other       transactions   between   the    parties.    The   district    court
    proposed to convert the motions into a bench trial on the paper
    record, and the parties agreed.              The district court thereafter
    issued a decision construing Georgia–Pacific's communications as
    conveying      an   expectation   that     any   agreement   should   expressly
    address the Southern Wheels problem, and so no contract existed
    1
    Georgia–Pacific submitted an email from APB dated July 27,
    2015 (three days after the critical July 24 email that either did
    or did not constitute an acceptance). In the July 27 email, APB
    referred to the July 24 email as a "counter" (i.e., counteroffer),
    which Georgia–Pacific argued showed that APB did not consider the
    deal final at that time. APB also filed an affidavit from one of
    its employees, Kirk Bryant, indicating his belief that the parties
    formed a contract by July 24 and explaining that the "counter"
    term did not actually indicate a contrary belief.      Because the
    district court as factfinder assigned no weight adverse to APB
    based on its July 27 email, neither do we.
    - 5 -
    because APB never timely conveyed its willingness to provide such
    an express term.   See Situation Mgmt. Sys., Inc. v. Malouf, Inc.,
    
    724 N.E.2d 699
    , 703 (Mass. 2000) ("[T]o create an enforceable
    contract, there must be agreement between the parties on the
    material terms of that contract . . . .").     The court thus entered
    judgment in favor of Georgia–Pacific.     APB timely appealed.
    II.
    Courts ordinarily treat the existence of a contract as
    a question of fact, see McGurn v. Bell Microprods., Inc., 
    284 F.3d 86
    , 93 (1st Cir. 2002), which we review for clear error on appeal
    from a bench trial, see Sawyer Bros., Inc. v. Island Transporter,
    LLC, 
    887 F.3d 23
    , 29 (1st Cir. 2018).
    APB   has   provided   no   persuasive   argument   that   the
    district court committed clear error.       The district court found
    that, "as of the July 24 email proposing the[] two options,
    Georgia–Pacific had decided it wanted responsibility for Southern
    Wheels to be an express term of any agreement and that it was
    unwilling to rest on an 'as is' provision."           "[F]or Georgia–
    Pacific," the court said, "APB's acknowledgement of the existence
    of Southern Wheels was a material term."       As such, the district
    court found that the July 24 email did not constitute an acceptance
    because the parties did not reach a mutual agreement over the
    material terms, and so they did not form a contract.
    - 6 -
    This reading of the parties' written communications
    seems to us entirely reasonable.        As APB claims, one could fairly
    read APB's first communication as offering to buy the cars "as is,
    where is."    Georgia–Pacific's reply, though, did not say that it
    considered the offer acceptable.        Rather, it offered two options,
    each of which included an express statement as to which party
    assumed responsibility for the Southern Wheels.           Discovery might
    plausibly have shown that the express statement manifested merely
    a redundant, immaterial reiteration of "as is." On the other hand,
    in the absence of such evidence, one could reasonably read Georgia–
    Pacific's options as each requiring something APB had not yet
    offered:    an express acknowledgment of the Southern Wheels problem
    and of which party would take on responsibility for this problem.
    In short, the record allowed a ruling in favor of either party.
    APB argues that the district court failed to appreciate
    that our prior appellate decision "shifted the burden" to Georgia–
    Pacific to prove that no contract existed.           In particular, APB
    points to our observation that "Georgia–Pacific may well have
    arguments    that   the   context     surrounding   the   communications,
    evidence not yet before the court, or relevant convention and usage
    lead ultimately to a conclusion that no contract was formed here."
    APB Realty, 889 F.3d at 29.         Thus, APB argues in effect that the
    district court violated the "law of the case" doctrine by ruling
    in favor of Georgia–Pacific without Georgia–Pacific's having put
    - 7 -
    forward any substantial new evidence.         See, e.g., United States v.
    Vigneau, 
    337 F.3d 62
    , 67 (1st Cir. 2003); Kapche v. City of San
    Antonio, 
    304 F.3d 493
    , 496 (5th Cir. 2002).
    This    argument   ignores   the   fact   that   the    procedural
    posture of the case has shifted.              In our first decision, we
    reviewed a grant of a motion to dismiss for failure to state a
    claim.   Under the standard of review we apply in assessing a
    challenge to such rulings, we said that we could "plausibly infer"
    that the parties had formed a contract.          APB Realty, 889 F.3d at
    30; see also Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009); Bell
    Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 570 (2007).              We similarly
    said that "[o]ne could reasonably interpret Georgia–Pacific's
    [July 24] email" as an acceptance of a contract offer. APB Realty,
    889 F.3d at 29 (emphasis added).              Nothing in that statement
    suggests that we would not also consider a contrary interpretation
    reasonable, even without any new evidence from Georgia–Pacific.
    Just because a complaint states a plausible claim for relief does
    not mean that the claimant has conclusively proven that claim.              A
    well-pleaded complaint need only "raise a reasonable expectation
    that   discovery    will   reveal   evidence"    supporting       the   claim.
    Twombly, 
    550 U.S. at 556
    ; see also Cardigan Mountain Sch. v. N.H.
    Ins. Co., 
    787 F.3d 82
    , 88 (1st Cir. 2015).              APB's subsequent
    failure to produce new evidence dashed that expectation, thereby
    reducing, rather than strengthening, its case.
    - 8 -
    By reading too much into our prior ruling, APB also
    misapprehends the manner in which the burden of proof rested once
    the district court tried the case to a decision.     As plaintiff
    alleging a breach of contract, APB assumed the burden of proving
    a contract and a breach.   See Martin v. Vector Co., 
    498 F.2d 16
    ,
    25 (1st Cir. 1974); see also 2 McCormick on Evidence § 337 (8th
    ed.) (explaining the difference between burden of pleading, burden
    of production, and burden of persuasion).
    III.
    For the foregoing reasons, we affirm.
    - 9 -