Beyond Nuclear v. U.S. Nuclear Regulatory Commission ( 2013 )


Menu:
  •              United States Court of Appeals
    For the First Circuit
    No. 12-1561
    BEYOND NUCLEAR, Paul Gunter, Director of Reactor Oversight
    Project; NEW HAMPSHIRE SIERRA CLUB, Kurt Ehrenberg, Field
    Organizer; SEACOAST ANTI-POLLUTION LEAGUE, Doug Bogen,
    Executive Director,
    Petitioners,
    v.
    U.S. NUCLEAR REGULATORY COMMISSION,
    Respondent,
    NEXTERA ENERGY SEABROOK, LLC; TAUNTON MUNICIPAL LIGHTING PLANT;
    MA MUNICIPAL WHOLESALE ELECTRIC COMPANY;
    HUDSON LIGHT & POWER DEPARTMENT,
    Interested Parties, Intervenors.
    PETITION FOR REVIEW FROM THE
    UNITED STATES NUCLEAR REGULATORY COMMISSION
    Before
    Lynch, Chief Judge,
    Boudin,* Circuit Judge,
    and Woodlock,** District Judge.
    *
    Judge Boudin heard oral argument in this matter, and
    participated in the semble, but he did not participate in the
    issuance of the panel's opinion in this case. The remaining two
    panelists therefore issued the opinion pursuant to 
    28 U.S.C. § 46
    (d).
    **
    of the District of Massachusetts, sitting by designation.
    Terry J. Lodge, for petitioners.
    Jeremy M. Suttenberg, Attorney, Office of the General Counsel,
    U.S. Nuclear Regulatory Commission, with whom Ignacia S. Moreno,
    Assistant Attorney General, J. David Gunter II, Attorney, Appellate
    Section, Environmental and Natural Resource Division, U.S.
    Department of Justice, Marian L. Zobler, Acting General Counsel,
    and John F. Cordes, Jr., Solicitor, were on brief, for respondent.
    David R. Lewis, with whom Robert B. Ross, Pillsbury Winthrop
    Shaw Pittman LLP, Mitchell S. Ross, and Steven C. Hamrick were on
    brief, for intervenor NextEra Energy Seabrook, LLC.
    Nicholas J. Scobbo, Jr., and Ferriter Scobbo & Rodophele, PC,
    on brief, for intervenors MA Municipal Wholesale Electric Company,
    Taunton Municipal Lighting Plant, and Hudson Light & Power
    Department.
    January 4, 2013
    -2-
    LYNCH,    Chief     Judge.     NextEra   Energy   Seabrook,     LLC,
    operates the Seabrook, New Hampshire, Unit 1 nuclear power plant,
    which provides a significant portion of the baseload electric power
    used in New England.       NextEra applied on May 25, 2010, to renew the
    Seabrook operating license, which will otherwise expire on March
    15, 2030.    See 
    42 U.S.C. § 2133
     (permitting renewal of operating
    licenses).   Renewal is allowed up to twenty years in advance.               See
    
    10 C.F.R. § 54.31
    (b).          With its application, NextEra submitted an
    environmental report, as required by 
    10 C.F.R. § 51.53
    (c).                 That
    report discussed the feasibility of alternative sources of electric
    energy.
    As part of that licensing process, the Nuclear Regulatory
    Commission ("NRC"), on March 8, 2012, issued a decision denying the
    admission of a contention by Beyond Nuclear, the New Hampshire
    Sierra Club, and the Seacoast Anti-Pollution League (collectively
    "BN"), which questioned and sought a hearing on the conclusion in
    the environmental report by NextEra that offshore wind electric
    generation   was     not   a   reasonable      alternative   to   the   extended
    licensing of Seabrook.          In doing so, the NRC reversed the Atomic
    Safety and Licensing Board's ("ASLB") admission of that contention.
    The NRC's denial of admission of a contention here means that it
    ruled petitioners were not entitled to have a hearing on the merits
    about their contention that generation of electricity from offshore
    -3-
    wind was a reasonable alternative source of baseload energy to the
    relicensing of Seabrook.
    On   petition   for   review,   BN   advances   two    primary
    challenges to the NRC's decision.           First, it argues that in
    formulating      its   contention-admissibility     standard      the   NRC
    misapplied case law interpreting the National Environmental Policy
    Act ("NEPA"), 
    42 U.S.C. § 4321
     et seq.      Second, it argues that when
    the NRC applied its contention-admissibility standard to the facts,
    its conclusion that the contention was inadmissible was arbitrary,
    capricious, an abuse of discretion, or not otherwise in accordance
    with the law.     Neither argument is persuasive, and for the reasons
    set forth below, we deny BN's petition for review.
    I.
    We give a brief description of the regulatory scheme
    governing the process for renewal of nuclear power plant operating
    licenses.   The NRC must comply with obligations under two separate
    statutes, the Atomic Energy Act ("AEA"), 
    42 U.S.C. § 2011
     et seq.,
    and NEPA.     Accordingly, it has two distinct sets of regulations
    containing requirements for license applicants.        Massachusetts v.
    United States, 
    522 F.3d 115
    , 119 (1st Cir. 2008).                 The AEA
    addresses protection of public health and safety and provides the
    statutory basis for renewing licenses, designating the NRC to make
    the decision and to issue applicable rules and regulations.             
    42 U.S.C. §§ 2133
    , 2134(b); see Massachusetts, 
    522 F.3d at 119
    .
    -4-
    Initial licenses are valid for up to forty years and may be
    renewed.     
    Id.
     § 2133(c).     Under NRC regulations, a licensee may
    apply for a license renewal up to twenty years before expiration
    and the renewed license may be issued for a fixed time of no more
    than twenty years in excess of the current operating license.                
    10 C.F.R. § 54.31
    .
    To fulfill the agency's obligations under NEPA, the NRC
    has promulgated a different set of regulations, codified at 10
    C.F.R. Part 51.      See 
    10 C.F.R. § 51.10
    .      NEPA requires agencies to
    study and document the environmental impacts and alternatives to
    proposed "major Federal actions significantly affecting the quality
    of the human environment."      
    42 U.S.C. § 4332
    (C).1         The requirement
    serves   two    purposes.     First,    "it   places   upon   an   agency   the
    obligation      to   consider   every        significant   aspect     of    the
    environmental impact of a proposed action."            Balt. Gas & Elec. Co.
    v. Natural Res. Def. Council, Inc., 
    462 U.S. 87
    , 97 (1983) (quoting
    Vt. Yankee Nuclear Power Corp. v. Natural Res. Def. Council, Inc.,
    
    435 U.S. 519
    , 553 (1978)) (internal quotation marks omitted).
    "Second, it ensures that the agency will inform the public that it
    has indeed considered environmental concerns in its decisionmaking
    process."      
    Id.
     (citing Weinberger v. Catholic Action of Haw. Peace
    1
    The NRC considers a license renewal to be a major federal
    action significantly affecting the quality of the human environment
    and so requires its staff to prepare an environmental impact
    statement for such an action.       
    10 C.F.R. § 51.20
    (b)(2); 
    id.
    § 51.95(c).
    -5-
    Educ. Project, 
    454 U.S. 139
    , 143 (1981)).                 The NRC requires
    applicants     for   relicensing,    here,     NextEra,     to    submit   an
    environmental report to assist it.        
    10 C.F.R. § 51.53
    (c)(1).         The
    NRC must take a "hard look" at the environmental impacts of major
    actions.   Massachusetts, 
    522 F.3d at 127
    .
    The environmental report must include consideration of
    alternative sources of energy generation to the relicensing, 
    10 C.F.R. § 51.45
    (b)(3), and must discuss their environmental impacts,
    
    id.
     § 51.53(c)(2).2    At issue here is only one limited portion of
    the environmental report filed with the application on May 25,
    2010, by NextEra.
    The AEA also imposes a requirement that the NRC "shall
    grant a hearing upon the request of any person whose interest may
    be affected by the proceeding," such as a license renewal.                  
    42 U.S.C. § 2239
    (a)(1)(A).   Although       NEPA    does not    provide   for
    hearings on environmental matters, Union of Concerned Scientists v.
    NRC, 
    920 F.2d 50
    , 56 (D.C. Cir. 1990), NRC regulations provide for
    hearings, including as to NEPA issues.              To obtain a hearing, a
    petitioner must make a written request under 
    10 C.F.R. § 2.309
    (a),
    2
    In their analysis of alternatives, applicants may use
    information from the NRC's Generic Environmental Impact Statement
    ("GEIS")   including   discussion   of  the   reasonableness   of
    alternatives.   Final Rule, Environmental Review for Renewal of
    Nuclear Power Plant Operating Licenses, 
    61 Fed. Reg. 28,467
    ,
    28,471-73 (June 5, 1996).    That is not directly involved here
    because alternative energy sources must be further evaluated in
    individual licensing proceedings. 
    Id. at 28,471-73
    ; see 
    10 C.F.R. § 51.53
    (c)(2).
    -6-
    which must state the contention to be raised, 
    id.
     § 2.309(f).          On
    issues arising   under   NEPA,   contentions   must   be based   on   the
    applicant's environmental report.       Id. § 2.309(f)(2).        To be
    admissible a contention must:
    (i) Provide a specific statement of the issue
    of law or fact to be raised or controverted
    . . . ;
    (ii) Provide a brief explanation of the basis
    for the contention;
    (iii) Demonstrate that the issue raised in the
    contention is within the scope of the
    proceeding;
    (iv) Demonstrate that the issue raised in the
    contention is material to the findings the NRC
    must make to support the action that is
    involved in the proceeding;
    (v) Provide a concise statement of the alleged
    facts or expert opinions which support the
    requestor's/petitioner's position on the issue
    . . . together with references to specific
    sources   and    documents   on    which   the
    requestor/petitioner intends to rely . . . ;
    (vi) Provide sufficient information to show
    that a genuine dispute exists with the
    applicant/licensee on a material issue of law
    or fact . . . .
    Id. § 2.309(f)(1).   In other words, the NRC denies hearings when
    the party's criticism of a portion of the applicant's environmental
    report does not meet the requirements of the regulations as to the
    admission of a contention.   The NRC found that BN's attack on the
    wind power analysis portion of NextEra's environmental report
    failed to meet the standards for being an admissible contention and
    so denied a hearing on this point.
    -7-
    II.
    We next address the relevant facts.       Seabrook is New
    England's largest nuclear reactor, having a capacity of 1245
    megawatts, and provides 8.2% of the actual generation of the
    Independent System Operator New England ("ISO-NE"), which the
    environmental   report   explains   "is   a   regional   network   that
    coordinates the movement of wholesale electricity in all or parts
    of Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island,
    and Vermont."
    A.   NextEra's Environmental Report
    NextEra's   environmental   report,   among   other   things,
    addressed four alternative sources of energy to renewing Seabrook's
    license that it deemed viable, reasonable alternatives: natural
    gas-fired generation; coal-fired generation; a new nuclear plant;
    and power purchases.
    The report also discussed wind power, of which NextEra is
    the leading generator in North America, but concluded it was not a
    reasonable alternative as a source of baseload electricity during
    the relevant period of time.   It is on that point that petitioners
    sought a full hearing before the Commission.
    The environmental report stated that "[f]or the purposes
    of this environmental report, alternative generating technologies
    were evaluated to identify candidate technologies that would be
    capable of replacing Seabrook Station's nominal net base-load
    -8-
    capacity of 1,245 MWe," and that it "accounted for the fact that
    Seabrook Station is a base-load generator and that any feasible
    alternative to Seabrook Station would also need to be able to
    generate base-load power."          Thus, any reasonable alternative would
    need to generate baseload power.3
    NextEra's      report    relied      on     the   NRC's     GEIS   for    the
    proposition that wind power is not suitable for baseload generation
    because of its intermittent nature. That intermittent nature meant
    that there had to be energy storage mechanisms.                       Energy storage
    mechanisms     are   too     expensive          to     resolve    the     problem     of
    intermittency and the technology for the generation of offshore
    wind energy is "not sufficiently demonstrated at this time."
    The NRC published a notice in the Federal Register
    providing    an   opportunity       for    all       interested   parties      to    file
    contentions.      See   Notice      of    Acceptance for Docketing              of   the
    Application and Notice of Opportunity for Hearing Regarding Renewal
    of Facility Operating License No. NPF-86 for an Additional 20-Year
    3
    Baseload power means that energy is produced at near full
    capacity, with high availability. Envtl. Law & Policy Ctr. v. NRC,
    
    470 F.3d 676
    , 679 (7th Cir. 2006). Baseload generating sources,
    such as nuclear plants, have a 90-97% capacity factor, which is the
    ratio of electrical energy produced by a generating unit for a
    period of time to the electrical energy that could have been
    produced at continuous, full power operations during the same time.
    Alliance to Protect Nantucket Sound, Inc. v. Dep't of Pub. Utils.,
    
    959 N.E.2d 413
    , 426 n.25 (Mass. 2011).           According to the
    environmental report, wind power has a capacity factor of 20-40%,
    an assertion not challenged by petitioners.
    -9-
    Period; NextEra Energy Seabrook, LLC; Seabrook Station, Unit 1, 
    75 Fed. Reg. 42,462
     (July 21, 2010).
    BN   filed   a   hearing   petition    on     October     20,   2010,
    proposing   its   one    contention    and    focusing     on   the   potential
    production of baseload power through either storing wind-produced
    power or interconnected offshore wind farms.              BN attached twenty-
    one exhibits, including news articles, government reports, and
    academic articles, which it said supported its contention.
    We provide some useful context.              BN was not the only
    entity to file a hearing petition.              The NRC has admitted two
    contentions challenging other aspects of the environmental report
    and will hold hearings on those contentions.4
    B.   ASLB Ruling on BN's Wind Power Contention
    The NRC "appoints [ASLBs] to conduct public hearings and
    to   make   intermediate     or   final      decisions    in    administrative
    proceedings" relating to licensing decisions. Johnston v. NRC, 
    766 F.2d 1182
    , 1183 (7th Cir. 1985).               A Board consists of three
    members, one of whom is qualified in the conduct of administrative
    proceedings and two of whom have technical or other qualifications
    4
    The first admitted contention, submitted by Friends of the
    Coast and the New England Coalition ("Friends/NEC") contends that
    the severe accident mitigation analysis in the report minimizes or
    underestimates the potential amount of radioactive release in a
    severe accident. The second admitted contention, also filed by
    Friends/NEC, contends that the report's severe accident mitigation
    analysis used an improper atmospheric dispersion model that
    underestimated the area likely to be affected by a severe accident.
    -10-
    the NRC deems appropriate. 
    42 U.S.C. § 2241
    (a).        ASLBs now preside
    over most licensing hearings.      Citizens Awareness Network, Inc. v.
    United States, 
    391 F.3d 338
    , 357 n.6 (1st Cir. 2004) (Lipez, J.,
    concurring).      Here, the NRC appointed an ASLB and the ASLB heard
    arguments on BN's contention, as well as on contentions filed by
    other groups.5
    The Board determined that BN's contention was admissible,
    limiting its scope solely to offshore wind, and specifically citing
    to representations made orally by a BN representative at a hearing.
    The representations were that an exhibit, Ex. 17, University of
    Maine, "Maine Offshore Wind Plan," establishes that offshore wind
    farms would deliver baseload energy by 2015.6        That representation
    proved to be untrue.
    C.    NRC Rejection of BN's Contention
    NextEra appealed the Board's decision to the Commission,
    which unanimously reversed the admission. The NRC will reverse the
    ASLB based on an error of law or abuse of discretion.          S.C. Elec.
    & Gas Co. & S.C. Pub. Serv. Auth., 
    72 N.R.C. 197
    , 200 (2010).          The
    NRC   correctly    stated   the   standard   for   admission   --   that   a
    5
    These included three safety-related contentions concerning
    management of aging plant systems, structures, and components, and
    a six-part contention on the severe accident mitigation analysis in
    the environmental report.
    6
    BN's representative specifically stated "Well, I think that
    we have established by our exhibit from the University of Maine
    that -- I think if the Board looks at it, that they are delivering
    baseload by 2015."
    -11-
    petitioner must present "sufficient information to show that a
    genuine dispute exists with the applicant/licensee on a material
    issue of law or fact."7   See 
    10 C.F.R. § 2.309
    (f)(1)(vi).     That
    meant NextEra's environmental report only needed to consider (1)
    baseload-power alternatives, not non-baseload alternatives, and (2)
    only such alternatives "likely to exist" during the renewal period.
    The Commission explained that, because of the difficulty inherent
    in predicting the viability of technologies decades in advance, in
    most cases reasonable alternatives are those that are "currently
    commercially viable, or will become so in the relatively near
    term."
    As a result:
    [T]o submit an admissible contention on energy
    alternatives in a license renewal proceeding,
    a petitioner ordinarily must provide 'alleged
    facts or expert opinion' sufficient to raise a
    genuine dispute as to whether the best
    information available today suggests that
    commercially viable alternate technology (or
    combination of technologies) is available now,
    or will become so in the near future, to
    supply baseload power.
    Applying that standard, the Commission concluded the Board erred in
    admitting the contention for four reasons:
    7
    This NRC standard differs from the summary judgment
    standard. See Gulf States Util. Co., 
    40 N.R.C. 43
    , 51 (1994). The
    NRC imposed the requirement to make the admission of contentions
    more difficult after Congress called for changes because of delays
    caused by poorly defined and poorly supported contentions. See
    Dominion Nuclear Conn., Inc., 
    54 N.R.C. 349
    , 358 (2001).
    -12-
    - there was no challenge by BN to the fact
    that storing wind power is too costly to be
    commercially viable;
    - the data submitted by BN did not demonstrate
    that offshore wind farms would provide timely
    and feasible baseload power;
    - BN's own exhibits stated that the lack of
    "requisite technology is an obvious barrier to
    establishment of the deep-water wind industry
    in Maine or elsewhere in the near term," and
    that     essential     infrastructure      for
    installation, transmission, and maintenance
    does not yet exist; and
    - the Board had supplied a basis for BN's
    contention that BN did not itself make, that
    interconnected offshore wind farms could
    constitute a single, discrete energy source,
    but this error was deemed harmless.
    III.
    A.            NEPA and the NRC's Admissibility Standard
    A major argument advanced in BN's briefing is that the
    NRC misused or misapplied NEPA case law in its decision.            The
    argument is wrong.
    First, NEPA does not, by its own terms or its intent,
    alter   the     Commission's   hearing    procedures,   including   the
    requirement that a petitioner provide sufficient information to
    show a genuine dispute on a material issue of law or fact.           
    10 C.F.R. § 2.309
    (f)(1)(vi).      The Supreme Court has been clear that
    "the only procedural requirements imposed by NEPA are those stated
    in the plain language of the Act."       Vt. Yankee, 
    435 U.S. at 548
    .
    NEPA does not mandate particular hearing procedures, Balt. Gas &
    Elec. Co., 
    462 U.S. at 100-01
    , and does not require hearings, Union
    of Concerned Scientists, 
    920 F.2d at 56
    .      "As a result, NEPA does
    -13-
    not alter the procedures agencies may employ in conducting public
    hearings."     
    Id.
    Further, the NEPA requirements are procedural in nature
    and do not mandate particular results or specific standards.                             See
    United States v. Coal. for Buzzards Bay, 
    644 F.3d 26
    , 31 (1st Cir.
    2011).    Rather, NEPA requires an agency to take a "hard look" at
    environmental consequences.              
    Id. at 31
    .
    BN suggests that by requiring an alternative energy
    source to provide baseload power, the NRC defined the objectives of
    the proposed actions so narrowly that it engaged in "outcome-
    controlled rigging."             See Citizens Against Burlington, Inc. v.
    Busey, 
    938 F.2d 190
    , 196 (D.C. Cir. 1991) (stating agency cannot
    make   objectives          so   narrow    that        outcome    is    a    "foreordained
    formality").
    That is not the case, for reasons both of law and common
    sense.         NEPA    requires          only        consideration         of   reasonable
    alternatives.         See, e.g., Natural Res. Def. Council, Inc. v.
    Morton, 
    458 F.2d 827
    , 837 (D.C. Cir. 1972).                            That means "the
    concept   of    alternatives        must        be    bounded    by    some     notion    of
    feasibility,"        Vt.     Yankee,     
    435 U.S. at 551
    ,   which      includes
    alternatives that are "technically and economically practical or
    feasible," Theodore Roosevelt Conservation P'ship v. Salazar, 
    661 F.3d 66
    , 69 (D.C. Cir. 2011) (quoting 
    43 C.F.R. § 46.420
    (b))
    (internal quotation marks omitted).                   Moreover, an agency need only
    -14-
    consider alternatives that will "bring about the ends" of the
    proposed action, Busey, 
    938 F.2d at 195
    , and where the agency is
    not itself the project's sponsor, "consideration of alternatives
    may accord substantial weight to the preferences of the applicant,"
    City of Grapevine v. Dep't of Transp., 
    17 F.3d 1502
    , 1506 (D.C.
    Cir. 1994) (quoting Busey, 
    938 F.2d at 197-98
    ) (internal quotation
    mark omitted).
    NextEra operates a baseload power generator at Seabrook,
    and despite BN's "outcome-controlled rigging" argument, BN's own
    brief concedes it was "permissible" for the NRC to consider the
    goal of providing baseload electrical power.     Thus, BN does not
    challenge the NRC's decision, in considering the feasibility of an
    alternative energy source, to focus on whether such an alternative
    source could supply baseload power.    Cf. Envtl. Law & Policy Ctr.
    v. NRC, 
    470 F.3d 676
    , 684 (7th Cir. 2006) (upholding baseload
    generation as appropriate goal).
    BN then attempts an argument that the NRC was required to
    consider what alternatives might look like in forty years time.8
    Not so.   Here again the NRC has taken a sensible course.   The NRC
    8
    Within this line of argument, BN also takes issue with the
    NRC's citation to Town of Winthrop v. FAA, 
    535 F.3d 1
    , 11-13 (1st
    Cir. 2008), which the NRC cited for the proposition that an
    environmental impact statement is not intended to be a "research
    document."    BN argues that petitioners are not calling for
    additional research like the plaintiffs in Winthrop, but instead
    handed over information to the Commission. This argument goes more
    toward whether BN submitted sufficient information to raise a
    genuine dispute, which is dealt with below.
    -15-
    stated       that   "[a]ssessments       of     future   energy    alternatives
    necessarily are of a predictive nature," and that "the applicant --
    and the agency -- are limited by the information that is reasonably
    available      in   preparing   the    environmental     review   documents."
    Because of the inherent difficulty in predicting decades in advance
    the viability of technologies not currently operational and years
    away from large-scale development, "in most cases a 'reasonable'
    energy alternative is one that is currently commercially viable, or
    will become so in the relatively near term."
    The NRC acknowledged the need for prediction, and made a
    rational decision that in most instances the best predictor of
    viability of an alternative in the distant future is the near term
    viability of the alternative.9           It did so in compliance with the
    law.        The duty under NEPA is to "study all alternatives that
    'appear reasonable and appropriate for study at the time' of
    drafting the EIS."       Roosevelt Campobello Int'l Park Comm'n v. EPA,
    
    684 F.2d 1041
    ,        1047   (1st     Cir.    1982)   (quoting   Seacoast   Anti-
    Pollution League v. NRC, 
    598 F.2d 1221
    , 1228 (1st Cir. 1979)).10
    9
    The NRC's decision acknowledged that there may be some
    instances where there is evidence of "unusual predictive
    reliability" to establish that an energy alternative not yet
    operational and many years away from large-scale development is
    likely to exist in the relevant future time period.
    10
    Contrary to BN's argument, other language in these cited
    opinions that    states   agencies   must   consider   "significant
    alternatives," brought to their attention by the public, see, e.g.,
    Campobello, 
    684 F.2d at 1047
    , does not require the granting of a
    hearing simply because the public proposes some alternative.
    -16-
    Forecasting should be based on "existing technology and those
    developments which can be extrapolated from it." Natural Res. Def.
    Council, Inc. v. NRC, 
    547 F.2d 633
    , 639-40 (D.C. Cir. 1976), rev'd
    on other grounds, Vt. Yankee, 
    435 U.S. 519
    .11        This aspect of the
    NRC's framework does provide a "hard look" at alternatives.
    Substantial deference is required when an agency adopts
    reasonable interpretations of its own regulations, and we must
    accept the agency's position unless it is "plainly erroneous or
    inconsistent with the regulation."      Auer v. Robbins, 
    519 U.S. 452
    ,
    461 (1997) (quoting Robertson v. Methow Valley Citizens Council,
    
    490 U.S. 332
    , 359 (1989)) (internal quotation marks omitted).
    Because the NRC's elaboration of its admissibility standard was
    generally    reasonable   and   consistent    with    both   
    10 C.F.R. § 2.309
    (f)(1)(vi) and NEPA, BN's challenge to the standard fails.
    B.   The NRC's Application of its Admissibility Standard to Facts
    Our review is delimited by the Administrative Procedure
    Act ("APA"), which authorizes the court to reverse the NRC's
    decisions only if they are "arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law."             5 U.S.C.
    11
    BN asserts that the NRC's reliance on Carolina Environmental
    Study Group v. United States, 
    510 F.2d 796
     (D.C. Cir. 1975), which
    the NRC cited for the proposition that it need not consider "remote
    and speculative" alternatives, is misplaced. At its core, BN's
    argument is that it presented information showing that offshore
    wind is not remote or speculative, which is relevant to the NRC's
    application of its standard, not the correctness of the standard.
    -17-
    § 706(2)(A); Massachusetts, 
    522 F.3d at 126
    .           Indeed, "[t]he [AEA]
    is hallmarked by the amount of discretion granted the Commission in
    working to achieve the statute's ends."         Massachusetts v. NRC, 
    878 F.2d 1516
    , 1523 (1st Cir. 1989).
    "An agency's decision is not arbitrary and capricious if
    that decision was based on consideration of the relevant factors
    and if it did not commit a clear error of judgment."                  Town of
    Winthrop v. FAA, 
    535 F.3d 1
    , 8 (1st Cir. 2008).             A decision fails
    "if the agency relied on improper factors, failed to consider
    pertinent aspects of the problem, offered a rationale contradicting
    the evidence before it, or reached a conclusion so implausible that
    it   cannot    be   attributed   to   a   difference   of   opinion   or   the
    application of agency expertise."            Associated Fisheries of Me.,
    Inc. v. Daley, 
    127 F.3d 104
    , 109 (1st Cir. 1997).
    BN sounds a theme which has no record support -- that the
    NRC improperly made a determination as to the reasonableness of
    offshore wind, at the admissibility stage, on the merits.              To the
    contrary, the NRC made it clear that it was not doing that, but
    examining BN's submissions against the admissibility standard.              It
    stated that "[BN] has not provided support for its claim that
    offshore wind is technically feasible and commercially viable . . .
    and therefore has not submitted an admissible contention," and that
    "[BN's] 'offshore wind' contention is not sustainable on its face
    -18-
    because it lacks a supporting basis," a result reached "without
    improperly resolving disputed facts."
    This theme by BN is a backdoor challenge to the decision
    made by the NRC in 1989, at the prompting of Congress, to toughen
    the standards for getting a hearing on contentions.        See Rules of
    Practice for Domestic Licensing Proceedings -- Procedural Changes
    in the Hearing Process, 
    54 Fed. Reg. 33,168
    , 33,170 (Aug. 11, 1989)
    (imposing requirement that to be admissible a contention must
    provide "sufficient information . . . to show that a genuine
    dispute exists"); see also 
    10 C.F.R. § 2.309
    (f)(1)(vi). Congress
    was concerned and called for change because "[s]erious hearing
    delays -- of months or years -- occurred, as licensing boards
    admitted and then sifted through poorly defined or supported
    contentions."     Dominion Nuclear Conn., Inc., 
    54 N.R.C. 349
    , 358
    (2000). So, the NRC adopted the new rules to "raise the threshold"
    for admitting contentions.     54 Fed. Reg. at 33,168.     "[M]aterials
    cited as the basis for a contention are subject to scrutiny by the
    board   to   determine   whether   they   actually   support   the   facts
    alleged,"     Calvert Cliffs 3 Nuclear Project, LLC, 
    72 N.R.C. 720
    ,
    750 (2010); otherwise, the aims of the rules and of Congress would
    be thwarted.
    We hold that the NRC's decision to deny admissibility to
    BN's contention constituted reasoned decisionmaking and was not
    arbitrary or capricious.     See Allentown Mack Sales & Servs., Inc.
    -19-
    v. NLRB, 
    522 U.S. 359
    , 374 (1998) (requiring agency adjudications
    to be subject to requirement of reasoned decisionmaking).                 That
    decision is reasonable because BN: (1) failed to even argue that
    the baseload requirement was inappropriate; and (2) its exhibits
    did not raise a genuine dispute as to the viability and feasibility
    of offshore wind to meet baseload requirements by 2030.
    First, BN's contention did not respond to the requirement
    that a reasonable alternative must provide baseload power.               BN did
    not supply information to dispute NextEra's conclusion that energy
    storage devices are too costly and baseload power generation by
    wind power would require such devices.          The relevant exhibit only
    discussed     storage potential,   but    not   cost.      Ex.    3,   National
    Renewable Energy Laboratory, "Creating Baseload Wind Power Systems
    Using      Advanced   Compressed   Air     Energy       Storage    Concepts,"
    (Oct. 2006).     That failure by BN alone is fatal to their claim of
    error.12    We go beyond that and also discuss the NRC's other fact-
    based grounds as contained in the record.
    12
    In its reply brief, BN asserts the NRC failed to consider
    certain other exhibits. The argument is both waived and also fails
    on its merits. In its opening brief, BN either: (1) only mentioned
    these exhibits in the facts; or (2) used them in an unrelated
    portion of its argument. Thus, this argument is waived. See Waste
    Mgmt. Holdings, Inc. v. Mowbray, 
    208 F.3d 288
    , 299 (1st Cir. 2000).
    These exhibits purportedly show that by interconnecting offshore
    wind farms, one can, in theory, provide baseload power, and that
    efforts are being made to make such interconnections a reality, but
    they do not address current or near term feasibility or viability
    of such technology as required by the NRC. Moreover, as discussed
    below, BN failed to establish an admissible contention that
    offshore wind farms, themselves, are or will be feasible or viable.
    -20-
    The exhibit relied upon by BN before the ASLB to support
    their representation -- that wind power off Maine's coast would
    provide   baseload    power   by   2015   --   does   not   support   BN's
    representation.      The exhibit does not make any suggestion about
    baseload power, let alone in the 2015 time period.           The one-page
    exhibit,13 an illustrative chart, calls for the deployment of one
    3-5 megawatt prototype turbine in 2012-2014 and five turbines
    capable of producing 25 megawatts, combined, in 2014-2016, which
    cannot provide baseload power, much less power on the scale of
    Seabrook.14
    Moreover, the NRC reasonably concluded that BN's exhibits
    did not raise a genuine dispute as to the technical feasibility or
    commercial viability of offshore wind farms in the relevant time
    period.15 In fact, two of BN's own exhibits undercut its position.
    13
    BN argues that when the NRC stated that the exhibit refers
    to a plan, not a statement of expectation, it arbitrarily imposed
    a new, heightened standard. The NRC was pointing out that BN's
    representative mischaracterized what the exhibit communicates. It
    did not require a statement of expectation for the admissibility
    standard to be met.
    14
    Thus, we reject BN's argument that the NRC departed from its
    typical standard of review in reversing the ASLB. Although the NRC
    reviews ASLB decisions for abuse of discretion, this deferential
    standard of review does not prevent the NRC from reversing the
    ASLB's decision to admit a contention when the NRC reasonably
    concludes that the contention is unsupported by the record.
    15
    In its reply brief, BN raises, for the first time, the
    argument that the Commission improperly required it to address the
    commercial viability of offshore wind as a source of baseload
    power. The argument was not raised in the opening brief and is
    waived.     Mowbray, 208 F.3d at 299.         Further, NextEra's
    -21-
    A report of the Maine Energy Task Force to then-Governor Baldacci
    stated that:
    [T]echnologies that would enable the placement
    of wind turbines on floating platforms or
    other structures in greater depths needed to
    tap the world-class deep-water wind resources
    in Maine's coastal waters or in adjoining
    federal waters are under development . . . .
    Lack of the requisite technology is an obvious
    barrier to establishment of the deep-water
    wind industry in Maine or elsewhere in the
    near term.
    Ex. 14, "Final Report of the Ocean Energy Task Force to Governor
    John E. Baldacci" (Dec. 2009) 27 (emphasis added).
    Other evidence supports the NRC's conclusion.              A 2010
    predecisional   draft   report   by   the   U.S.   Department   of   Energy
    submitted by BN also stated that: "significant challenges . . .
    need to be overcome"; uncertainty exists as to potential project
    power production and turbine and array designs; the implications of
    adding large amounts of offshore wind generation to the power
    system need to be better understood to know if it can be reliably
    integrated; and the infrastructure needed to install, operate, and
    maintain offshore wind farms cost-effectively does not currently
    exist in the U.S.   Ex. 15, U.S. Department of Energy, "Creating an
    Offshore Wind Industry in the United States" (Sept. 2010) 7-10.16
    environmental report concluded that offshore              wind was not
    technically proven, which logically leads to              it not being
    commercially viable.
    16
    BN directs our attention to other portions of these exhibits
    that set a target date of 2030 for 5 gigawatts of offshore wind
    -22-
    BN argues that Exhibit 14 stated that shallow offshore
    wind power is viable today (because of its use in Europe) and
    points to Exhibit 11, European Wind Energy Association, "Oceans of
    Opportunity," (Sept. 2009), discussing the growth of offshore wind
    in Europe.      As the NRC correctly noted, another of BN's exhibits,
    Ex. 19, U.S. Department of Energy, "20% Wind Energy by 2030" (July
    2008) 57, stated that such European shallow-water technology is too
    expensive and too difficult to site in U.S. waters.                     And, both
    exhibits are silent on the critical issue of baseload generation.17
    The NRC's decision was not arbitrary or capricious and
    there is no basis in law to set it aside.
    IV.
    If new information about the technical and economic
    feasibility of offshore wind as a source of baseload power, which
    differs    materially        from    that    which   was   available    when    the
    contention      at   issue     was    filed,     becomes   available    prior    to
    Seabrook's license renewal, NRC regulations would permit the filing
    of   a    new    contention,         if     timely   submitted.        10   C.F.R.
    power off the coast of Maine and 54 gigawatts nationwide.      But
    those   same   exhibits   acknowledge    that   such   goals   are
    "extraordinary," Ex. 14 at vii, and "ambitious," Ex. 15 at 10, and
    BN ignores the contingent nature of those plans.
    17
    We need not and do not address BN's challenge to the NRC's
    finding that the ASLB improperly provided a basis for BN's
    contention that offshore wind could count as a single, discrete
    source of energy. The NRC ruled such error was harmless because
    alternatives do not need to be single, discrete sources, and it was
    not the basis of the NRC's decision.
    -23-
    § 2.309(c)(1)(i)-(iii).     NRC's counsel confirmed that at oral
    argument.     See Massachusetts, 
    522 F.3d at 130
     (NRC bound by
    admissions to court).    Of course, to be admitted, any newly filed
    contention would still need to meet the admissibility requirements
    in 
    10 C.F.R. § 2.309
    .
    The petition for review is denied.
    -24-
    

Document Info

Docket Number: 12-1561

Judges: Lynch, Boudin, Woodlock

Filed Date: 1/4/2013

Precedential Status: Precedential

Modified Date: 3/2/2024

Authorities (22)

Associated Fisheries of Maine, Inc. v. Daley ( 1997 )

Town of Winthrop v. Administration ( 2008 )

Massachusetts v. United States ( 2008 )

United States v. Coalition for Buzzards Bay ( 2011 )

Commonwealth of Massachusetts v. United States Nuclear ... ( 1989 )

Citizens Awareness Network, Inc. v. United States ( 2004 )

Theodore Roosevelt Conservation Partnership v. Salazar ( 2011 )

citizens-against-burlington-inc-v-james-b-busey-iv-administrator ( 1991 )

Natural Resources Defense Council, Inc. v. Rogers C. B. ... ( 1972 )

City of Grapevine, Texas v. Department of Transportation, ... ( 1994 )

Joseph W. Johnston v. Nuclear Regulatory Commission of the ... ( 1985 )

environmental-law-and-policy-center-blue-ridge-environmental-defense ( 2006 )

seacoast-anti-pollution-league-and-audubon-society-of-new-hampshire-v ( 1979 )

roosevelt-campobello-international-park-commission-v-united-states ( 1982 )

Carolina Environmental Study Group v. The United States of ... ( 1975 )

union-of-concerned-scientists-v-united-states-nuclear-regulatory ( 1990 )

Allentown MacK Sales & Service, Inc. v. National Labor ... ( 1998 )

Weinberger v. Catholic Action of Hawaii/Peace Education ... ( 1981 )

Vermont Yankee Nuclear Power Corp. v. Natural Resources ... ( 1978 )

Robertson v. Methow Valley Citizens Council ( 1989 )

View All Authorities »