ST Engineering Marine, Ltd. v. Thompson, MacColl & Bass, LLC, P.A. ( 2023 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 22-1844
    ST ENGINEERING MARINE, LTD.,
    Plaintiff, Appellee,
    v.
    THOMPSON, MACCOLL & BASS, LLC, P.A.,
    Defendant, Appellant.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MAINE
    [Hon. Jon D. Levy, U.S. District Judge]
    Before
    Rikelman, Selya, and Howard,
    Circuit Judges.
    James M. Bowie, with whom Thompson Bowie & Hatch LLC was on
    brief, for appellant.
    Lee H. Bals, with whom Marcus Clegg was on brief, for
    appellee.
    December 6, 2023
    SELYA, Circuit Judge.                  Following a bench trial, the
    district    court    found        that    a       law   firm,    defendant-appellant
    Thompson, MacColl & Bass, LLC, P.A. (TM&B), had breached its duty
    of care in advising its quondam client, plaintiff-appellee ST
    Engineering Marine, Ltd. (STEM), about the viability of a maritime
    lien.   The district court further found that TM&B's negligence was
    the actual and proximate cause of STEM's loss and awarded STEM
    damages in the amount of $261,839.04.                    TM&B appeals.       Affording
    due deference to the district court's findings of fact, we affirm.
    I
    We briefly rehearse the relevant facts and travel of the
    case.   In 2013, STEM owned the M/V Nova Star.                       At that time, it
    entered into a bareboat charter agreement for the vessel with Nova
    Star Cruises Ltd. (NSC).                 NSC assumed responsibility for all
    aspects of the vessel's operations and associated costs (including
    providing   and     paying    for    bunker        fuel).       It   hired   the   ship-
    management company Fleetpro Ocean Inc. (Fleetpro) to operate the
    M/V Nova Star as its agent.
    In    June       of     2015,          Fleetpro      contacted     Bunkers
    International Corporation (BIC), a firm that arranged the delivery
    of fuel for charterers, to supply fuel for the M/V Nova Star.
    Fleetpro proceeded to send BIC purchase orders for two sales. Each
    purchase order laid out the details of the particular sale, listed
    Fleetpro "AS AGENTS FOR" NSC, and listed BIC as the "Supplier."
    - 2 -
    BIC thereafter engaged Sprague Operating Resources, LLC
    (Sprague) to supply fuel to the vessel.                       Neither the vessel's
    owner,   its     master,    nor   Fleetpro       had    any    involvement      in   the
    selection of Sprague as the fuel vendor.
    Withal, Sprague supplied fuel to the M/V Nova Star on
    two separate occasions.           At the end of each delivery, the master
    and chief engineer of the vessel signed or stamped the fuel
    receipts.        Sprague sent an invoice to BIC after each delivery
    ($147,354.92 for the first delivery and $149,719.68 for the second
    delivery).       In turn, BIC sent invoices to NSC "and/or Master,
    Owners, Operators,         Charterers, Managers, Managing Agents" for
    $156,460.73 and $157,729.23.          Fleetpro paid BIC, but BIC filed for
    bankruptcy without paying Sprague.
    Months later, the M/V Nova Star was arrested at the
    instance    of    a   company     asserting      a   maritime     lien    for    unpaid
    services.    In the ensuing melee, several other entities (including
    Sprague)    purposed       to   assert    maritime       liens    on     the    vessel.
    Pertinently, Sprague alleged that it had acquired its maritime
    lien of $297,074.60 upon supplying the M/V Nova Star with fuel.
    With its vessel embroiled in numerous legal actions,
    STEM turned to TM&B for legal advice.                  STEM asked TM&B to analyze
    the flurry of lien claims and assess the validity of each claim so
    that STEM could decide which claims should be resisted (that is,
    bonded but not paid) and which claims should be settled.                        In mid-
    - 3 -
    November 2015, a TM&B attorney and STEM's president and in-house
    counsel exchanged multiple emails.     The attorney advised that
    Sprague's lien should be honored and its claim paid.       In one of
    his November 16, 2015, emails, the attorney added:
    Dear All,
    I have reviewed the lien claims and have
    requested    back-up    documents    from  the
    claimants. Once we get the back-up documents,
    I will provide my comments on the bona fide
    nature of the lien claims.
    . . . Sprague Energy is the provider of
    bunker on the order of [BIC] . . . . Sprague
    has attached to its complaint copies of the
    bunker receipts for its two deliveries, both
    signed by the Master. I understand that BIC
    is the bunker trader that filed for bankruptcy
    protection . . . .
    If BIC was acting as agent or broker for
    the ship and ordered bunkers for the ship from
    Sprague and then filed in bankruptcy, the fact
    that Fleetpro paid BIC would not help us in
    the lien claim filed by the innocent
    provide[r]    that   actually   delivered  the
    bunkers. Our recourse is to file a claim in
    the BIC bankruptcy proceeding for the amount
    paid to Sprague. [STEM] would in effect step
    into the position of Sprague claiming against
    BIC.
    Acting on TM&B's advice, STEM proceeded to settle Sprague's claim
    for $267,366.    It then filed a counterpart claim in the BIC
    bankruptcy proceeding for an equivalent sum.   But in the end, STEM
    recovered only $5,526.96 as a result of its bankruptcy claim.
    In September of 2020, STEM sued TM&B for professional
    negligence.   STEM alleged that TM&B had advised it that Sprague
    possessed a valid maritime lien on the M/V Nova Star and that the
    - 4 -
    only way to extinguish the lien was by paying Sprague for the fuel
    it had supplied.       In providing this advice, STEM alleged, TM&B
    fell below the standard of care that it owed to STEM and was
    negligent.      As STEM saw the matter, TM&B negligently failed to
    advise it that the governing law was "unsettled generally and in
    a state of transition"; that there was no controlling decision on
    the issue in the District of Maine; that further investigation
    into Sprague's claim was needed; that STEM could try to provide
    security   to    obtain     the   release     of   the   M/V    Nova    Star   while
    contesting      Sprague's    lien    claim;    and    that     there    were   legal
    arguments that could be made to defeat Sprague's claim.                    Because
    it paid Sprague "as a direct and proximate result" of TM&B's
    negligent advice, STEM averred, it was entitled to recover damages
    from TM&B.
    TM&B    denied     that    its   legal     advice     fell   below    the
    applicable standard of care but it did not deny that it had advised
    STEM that Sprague had a valid lien.                Pretrial discovery ensued,
    followed by a three-day bench trial.               The district court ruled in
    favor of STEM.      See ST Eng'g Marine, Ltd. v. Thompson, MacColl &
    Bass, LLC, 
    633 F. Supp. 3d 354
    , 365 (D. Me. 2022).                In the process,
    the court found that Sprague was a subcontractor.                 See 
    id. at 357
    .
    It then found that "STEM, Nova Star Cruises, and Fleetpro did not
    control the selection or performance of Sprague, nor did they have
    - 5 -
    other dealings with Sprague apart from the routine acceptance of
    the delivery."     
    Id. at 357-58
    .
    In its conclusions of law, the court held that TM&B
    breached the duty of care that it owed to STEM.                See 
    id. at 361
    .
    The most recent First Circuit case concerning maritime liens at
    the time TM&B advised STEM (November of 2015) was Cianbro Corp. v.
    George   H.    Dean,   Inc.,   
    596 F.3d 10
        (1st    Cir.   2010),   which
    established that "a subcontractor who was not directly ordered to
    provide necessaries can assert a lien if 'it can be shown that an
    entity authorized to bind the ship controlled the selection of the
    subcontractor and/or its performance.'"              ST Eng'g Marine, 633 F.
    Supp. 3d at 358 (quoting Cianbro, 
    596 F.3d at 17
    ).                 Nevertheless,
    TM&B predicated its advice on the older case of Tramp Oil & Marine,
    Ltd. v. M/V Mermaid I, 
    805 F.2d 42
     (1st Cir. 1986), and failed to
    "account for Cianbro's analysis of the issue."                 ST Eng'g Marine,
    633 F. Supp. 3d at 359-60.       The court further concluded that — by
    not conducting legal research beyond Tramp Oil and by not rereading
    any of the cases cited and/or relied upon in Cianbro — TM&B
    furnished advice based on an "erroneous interpretation of the
    controlling law at the time."          Id. at 361.         TM&B — the district
    court determined — thereby failed to exercise due diligence in
    investigating     Sprague's    lien    claim       and,    thus,   breached   the
    professional duty that it owed to STEM.              See id.
    - 6 -
    The district court proceeded to find that this breach of
    duty proximately caused STEM's loss:      "it is more likely than not
    that STEM would have been able to prove in the underlying arrest
    proceeding that BIC was not acting as an agent of STEM, Nova Star
    Cruises, or Fleetpro."        Id. at 365.     So, STEM proved "by a
    preponderance of the evidence that it would have prevailed in the
    arrest proceeding on Sprague's maritime lien claim but for TM&B's
    negligent advice."      Id.    The court concluded its decision by
    ordering TM&B to pay STEM $261,839.04 in damages.      See id.
    This timely appeal ensued.
    II
    When a district court conducts a bench trial, we review
    de novo its legal conclusions.     See United States v. 15 Bosworth
    St., 
    236 F.3d 50
    , 53 (1st Cir. 2001).         This review encompasses
    "determinations about the sufficiency of the evidence."       Aadland
    v. Boat Santa Rita II, Inc., 
    42 F.4th 34
    , 41 (1st Cir. 2022)
    (quoting 15 Bosworth St., 
    236 F.3d at 53
    ).       The district court's
    factual findings are, of course, reviewed for clear error.        See
    id.; see also Fed. R. Civ. P. 52(a)(6) ("Findings of fact, whether
    based on oral or other evidence, must not be set aside unless
    clearly erroneous, and the reviewing court must give due regard to
    the   trial   court's    opportunity     to   judge   the   witnesses'
    credibility."). The clear error standard is deferential and, where
    it applies, we will not overturn a factual finding unless — on the
    - 7 -
    whole of the record — we are "left with the definite and firm
    conviction that a mistake has been committed."                    United States v.
    U.S. Gypsum Co., 
    333 U.S. 364
    , 395 (1948).
    Although the parties do not raise the question, "we have
    an obligation to inquire into our subject matter jurisdiction sua
    sponte."   One & Ken Valley Hous. Grp. v. Me. St. Hous. Auth., 
    716 F.3d 218
    , 224 (1st Cir. 2013).               Here, that inquiry reduces to a
    determination    as     to    whether        we    are    sitting      in     diversity
    jurisdiction or in admiralty jurisdiction.
    STEM's cause of action sounds in legal malpractice (a
    tort arising under the common law).                    STEM is a business entity
    organized under the laws of Singapore and has its principal place
    of business there.           TM&B is a professional services company
    organized under Maine law, which maintains its principal place of
    business in Portland, Maine. The matter in controversy comfortably
    exceeds the sum of $75,000.
    Although        questions    of    maritime      law     linger      at   the
    margins,     those    questions        are    subordinate         to    the     alleged
    malpractice and the resulting injury. Put another way, the alleged
    negligent act and resulting injury, in combination, do not comprise
    the stuff needed to trigger admiralty jurisdiction.                         For a tort
    claim to come within admiralty jurisdiction, it "must satisfy
    conditions    both    of    location    and       of   connection      with    maritime
    - 8 -
    activity."       Jerome B. Grubart, Inc. v. Great Lakes Dredge & Dock
    Co., 
    513 U.S. 527
    , 534 (1995).
    Here, the location requirement has not been satisfied.
    The alleged tort (the allegedly negligent advice) occurred on land.
    And   as   we    have   recently   explained,   "[w]hen . . . the       'injury
    suffered' is on 'land,'" it must be shown "that 'a vessel on
    navigable water' caused the tort."              Rhode Island v. Shell Oil
    Prods. Co., 
    35 F.4th 44
    , 61 (1st Cir. 2022) (quoting Jerome B.
    Grubart, Inc., 
    513 U.S. at 534
    ). STEM suffered its injury on land,
    and it was an attorney's advice — not a vessel on navigable waters
    — that is alleged to have caused the tort.
    Given this collocation of facts, we hold that this
    lawsuit     arises      in   diversity   jurisdiction.      See    
    28 U.S.C. § 1332
    (a)(2).        The case simply does not present the conditions
    required to invoke admiralty jurisdiction.
    This determination, in turn, controls our choice of law.
    Because the case is in a federal court by virtue of diversity
    jurisdiction,        state   law   supplies   the    substantive   rules    of
    decision.       See Erie R.R. Co. v. Tompkins, 
    304 U.S. 64
    , 78 (1938);
    Conformis, Inc. v. Aetna, Inc., 
    58 F.4th 517
    , 528 (1st Cir. 2023).
    The parties agree that the law of Maine controls, and we accept
    that reasonable agreement.          See Borden v. Paul Revere Life Ins.
    Co., 
    935 F.2d 370
    , 375 (1st Cir. 1991).             We caution, though, that
    when we address the questions of maritime law that are embedded in
    - 9 -
    this controversy, we look to federal maritime law and precedents
    —   as   Maine    courts   would   likewise     do.        See,     e.g.,   Offshore
    Logistics, Inc. v. Tallentire, 
    477 U.S. 207
    , 223 (1986) (explaining
    that state law is constrained by what some have called the reverse-
    Erie     doctrine,   "which   requires       that   the    substantive      remedies
    afforded by the States conform to governing federal maritime
    standards").
    A
    Under Maine law, a plaintiff seeking to prove attorney
    malpractice "must show (1) a breach by the defendant of the duty
    owed to the plaintiff to conform to a certain standard of conduct;
    and (2) that the breach of that duty proximately caused an injury
    or loss to the plaintiff."          Brooks v. Lemieux, 
    157 A.3d 798
    , 802
    (Me. 2017) (quoting Pawlendzio v. Haddow, 
    148 A.3d 713
    , 715 (Me.
    2016)).     TM&B challenges the district court's determination that
    it breached the duty of care that it owed to STEM.                          It also
    challenges the district court's determination that any such breach
    was an actual and proximate cause of the injury to STEM.                          We
    address these challenges separately.
    B
    We   start    with    the   district         court's    determination
    regarding breach of duty.          In Maine, the duty of care owed by an
    attorney to his client is the use of "such skill, prudence and
    diligence as is reasonable according to the standards of ordinarily
    - 10 -
    competent    lawyers      performing   similar      services     under    like
    conditions."      Pawlendzio,    148   A.3d   at    715    (quoting    Sohn   v.
    Bernstein, 
    279 A.2d 529
    , 532 (Me. 1971)).
    TM&B argues that the district court erred in concluding
    that it breached the duty it owed to STEM.                In TM&B's view, it
    exercised    reasonable    skill,   prudence,      and    diligence    when   it
    advised STEM that Sprague had a valid lien claim.
    Notably, TM&B does not contest the district court's
    determination that its advice to STEM was predicated on Tramp Oil.
    It continues to argue that Tramp Oil was (and is) the most relevant
    precedent.   Building on this foundation, it argues that the advice
    that it provided to STEM was correct.           In the process, it takes
    issue with the district court's conclusion that Cianbro, not Tramp
    Oil, is controlling.      See ST Eng'g Marine, 633 F. Supp. 3d at 360.
    We review for clear error the district court's finding
    that TM&B breached its duty of care to STEM.              See Fairest-Knight
    v. Marine World Distribs., Inc., 
    652 F.3d 94
    , 98 (1st Cir. 2011).
    Embedded within this clear-error review is a legal determination
    as to what was in November of 2015 the most recent and relevant
    law, when viewed through the eyes of a reasonably                     skillful,
    prudent, and diligent attorney.        We review this embedded question
    of law de novo.    See Aadland, 42 F.4th at 41.
    For a start, we discern no clear error in the district
    court's determination that TM&B breached its duty of care to STEM.
    - 11 -
    The record, fairly read, supports a finding that the legal research
    that TM&B's attorney conducted in examining Sprague's lien claim
    was not carried out with sufficient care and attention as would be
    expected of a reasonably skillful, prudent, and diligent lawyer.
    So, too, the fact that the TM&B attorney did not alert STEM to the
    unsettled nature of maritime lien law in the First Circuit supports
    the district court's finding of negligence.            Had he conducted a
    more careful and attentive canvass of the case law, he would have
    identified at least three reasons why a cloud of uncertainty hung
    over the Tramp Oil dicta upon which he relied.           Given this cloud
    of   uncertainty,    a   reasonably   skillful,    prudent,   and   diligent
    attorney would have explicitly hedged his advice, apprising STEM
    of the unsettled nature of the law in this area.
    First,    a reasonably     skillful, prudent, and diligent
    attorney would have understood that the statements in Tramp Oil
    were dicta.   There, Logos Shipping APS, a charterer of a vessel,
    asked J&L Bunkers A/S (J&L) to arrange fuel for the chartered
    vessel.   See Tramp Oil, 
    805 F.2d at 44
    .          J&L then contacted Tramp
    Oil and Marine, Ltd. (Tramp), a fuel broker.              See 
    id.
         Tramp
    contracted with Exxon International (Exxon), which caused Colonial
    Oil Industries, Inc. (Colonial) to supply the fuel to the vessel.
    See 
    id.
       Once the fuel was supplied, Tramp paid Exxon in full —
    but did so without any authorization from the owner or charterer
    of the vessel.      See 
    id. at 44-45
    .   After J&L failed to repay Tramp
    - 12 -
    in full, Tramp claimed that it had acquired a maritime lien.                         See
    
    id. at 44
    . By paying Exxon, Tramp asserted it had made an "advance"
    on behalf of the vessel.            
    Id. at 45
    .      And pursuant to the rule of
    advances, it professed to have acquired the lien that Exxon had
    previously held.          See 
    id.
    We rejected Tramp's contention, explaining that Tramp
    had acted without authorization from either the vessel's owner or
    any other person with proper authority.                        See 
    id. at 45-46
    .      We
    added,    as    an    aside,    that     "[n]o    one    disputes     that   Exxon   and
    Colonial, as direct suppliers of the fuel to the [vessel], would
    be   entitled        to   a   maritime    lien.         Fuel    is   unquestionably   a
    'necessary' within the meaning of the Act, and it was furnished
    upon the order of someone with authority to do so."1                         
    Id. at 44
    .
    Later in the opinion, we wrote that "Tramp's payment was used to
    satisfy an outstanding lien claim."                 
    Id. at 45
    .        In other words,
    we implied that both Exxon and Colonial had valid and outstanding
    lien claims.
    As a reasonably skillful, prudent, and diligent attorney
    would have realized, these last two statements were plainly dicta.
    See Lake Charles Stevedores, Inc. v. Professor Vladimir Popov MV,
    1The Act discussed in Tramp Oil (and in effect at that time)
    was the Federal Maritime Lien Act, the predecessor to the
    Commercial Instruments and Maritime Liens Act (CIMLA), 
    46 U.S.C. §§ 31301-31343
    . The CIMLA was in effect at all times relevant to
    the case at hand.
    - 13 -
    
    199 F.3d 220
    , 230 (5th Cir. 1999) (reaching this conclusion).            In
    Tramp Oil, we were not asked to address the viability of these
    lien claims.      Accordingly, our statement that "[n]o one disputes
    that Exxon and Colonial . . . would be entitled to a maritime
    lien," 
    805 F.2d at 44
    , was not intended to be read as a general
    pronouncement of law.     Seen in this light, a reasonably skillful,
    prudent, and diligent attorney would have understood that it would
    not   be   safe   to   rely   on   the   Tramp   Oil   dicta   as   binding
    pronouncements.
    Second, we discern no clear error in the district court's
    finding that the TM&B attorney failed to conduct adequate legal
    research. See ST Eng'g Marine, 633 F. Supp. 3d at 361. In reaching
    this conclusion, we think that the district court               must have
    regarded the TM&B attorney's primary misstep as failing to conduct
    research with an adequate level of care and attention.          The record
    supports a conclusion that — had TM&B's attorney read the relevant
    case law with the requisite degree of care and attention — he would
    have discovered that the other courts of appeals that had addressed
    the matter all had departed from his reading of Tramp Oil's dicta
    when determining the circumstances in which a direct supplier of
    a necessary acquires a maritime lien.
    On TM&B's reading, Tramp Oil stands for the proposition
    that as long as a supplier provides a necessary to a vessel and
    does so pursuant to an order that was initially issued by a
    - 14 -
    vessel's owner or a person authorized by the owner, the supplier
    is entitled to a maritime lien.   This is true, TM&B asserts, even
    if the order is relayed through multiple layers of intermediaries,
    each of whom passes along the entire order for a traditional
    necessary that originated from the vessel.
    A reasonably skillful, prudent, and diligent attorney
    conducting adequate legal research would have realized that — by
    November of 2015 — the courts of appeals had moved away from this
    interpretation of the provision in the Commercial Instruments and
    Maritime Liens Act (CIMLA), which states that "a person providing
    necessaries to a vessel on the order of the owner or a person
    authorized by the owner . . . has a maritime lien on the vessel."
    
    46 U.S.C. § 31342
    (a).   Those courts had held — contrary to Tramp
    Oil's dicta — that, in order to be considered to have provided a
    necessary "on the order of the owner or a person authorized by the
    owner," a supplier must do more than simply deliver a necessary.
    Some additional connection with a person authorized to bind the
    vessel must be shown.
    To be sure, this essential connection can be forged in
    a variety of ways.   One way is through privity of contract with
    the owner or a person authorized by the owner.   Cf. Farwest Steel
    Corp. v. Barge Sea-Span 241, 
    828 F.2d 522
    , 525-26 (9th Cir. 1987)
    (holding that subcontractor — who lacked privity of contract with
    owner or person authorized by owner — did not have claim to lien
    - 15 -
    when general repair contractor who hired him failed to pay him for
    his services).    Another way is by showing that the supplier has
    been explicitly "nominated by the owner" of the vessel to provide
    a necessary, Marine Fuel Supply & Towing, Inc. v. M/V Ken Lucky,
    
    869 F.2d 473
    , 475 (9th Cir. 1988), and demonstrating that the
    necessary has been directly "sold to" a person with authority to
    bind the vessel, 
    id. at 477
     (emphasis in original).            A third way
    is by involvement with an owner or a person authorized by the owner
    in a manner that was "significant and ongoing during the pertinent
    transaction."    Galehead, Inc. v. M/V Anglia, 
    183 F.3d 1242
    , 1245
    (11th Cir. 1999).
    Although these three ways differ from each other, there
    is a common denominator:        all of the relevant case law teaches
    that merely being the supplier of a necessary does not suffice to
    acquire a maritime lien.            The short of it is that, among the
    decided cases, the general trend as of November of 2015 was
    pointing away from Tramp Oil's dicta.
    Third, had TM&B's attorney conducted more careful and
    attentive   research   —   as   a    reasonably   skillful,   prudent,   and
    diligent attorney would have done — he would have understood that
    our most recent case on maritime liens, Cianbro, cast Tramp Oil's
    dicta in grave doubt. In Cianbro, the Hornbeck entities contracted
    with the Cianbro Corporation (C-Corp.) to convert their two sulfur
    tankers into multi-purpose supply vessels.           See 
    596 F.3d at 12
    .
    - 16 -
    C-Corp., in turn, contracted with Hub Technologies, Inc. (Hub) to
    fabricate certain steel components that were to be used in the
    conversion work.    See 
    id.
       Hub then subcontracted with Dean Steel
    (Dean) to perform some of the initial cutting work on the steel.
    See 
    id. at 13
    .     C-Corp. shipped raw steel directly to Dean, and
    Dean returned the     cut material to     Hub, which fabricated    the
    components that C-Corp. had ordered.      See 
    id.
       After Hub failed to
    pay Dean and filed for bankruptcy, Dean claimed maritime liens on
    the vessels.   See 
    id.
       The district court rejected Dean's claim,
    holding that it failed to satisfy several of the requirements for
    a maritime lien.    See 
    id. at 14
    .
    We upheld the district court's decision.       See 
    id. at 18
    .
    Among other things, we rejected Dean's claim that it had acted "on
    the order of the owner or a person authorized by the owner," as
    required by CIMLA.    
    Id. at 16-18
    .     Dean's claim that C-Corp. had
    the authority to bind the vessels' owners, we explained, "would
    strain the language and purpose of the Maritime Lien Act."       
    Id. at 17
    . In addition, we determined, that Dean's claims fared no better
    under the Fifth Circuit's analysis of CIMLA and its so-called
    middleman line of cases.2     See 
    id.
       Dean was unable to show "that
    2 In Lake Charles Stevedores, 
    199 F.3d at 228-29
    , the Fifth
    Circuit       differentiated       between       the       general
    contractor/subcontractor line of cases and the middleman line of
    cases in assessing whether a supplier of a necessary has acted "on
    the order of the owner or a person authorized by the owner." The
    former line of cases involves instances in which an owner or agent
    - 17 -
    an   entity   authorized    to   bind   the   ship    controlled      [its]
    selection . . . and/or     its   performance."       
    Id.
       (quoting    Lake
    Charles Stevedores, 
    199 F.3d at 229
    ).
    Had TM&B's attorney given due weight to Cianbro — we
    think it reasonable to conclude, as did the district court — that
    he would have had second thoughts about the persuasive force of
    Tramp Oil's dicta.   Although our discussion of the middleman line
    of cases in Cianbro was not a model of clarity, it is apparent
    that the Cianbro court concluded that a supplier does not acquire
    a maritime lien simply by virtue of providing a necessary.             Some
    additional connection with a person authorized to bind the vessel
    must be shown.   Cianbro's narrow reading of the term "on the order
    of a vessel hires a general contractor to complete a task and the
    contractor solicits subcontractors for assistance in completing
    the work.   See 
    id. at 229
    .    A subcontractor lacking privity of
    contract with the "owner or a person authorized by the owner" can
    acquire a lien if "it can be shown that an entity authorized to
    bind the ship controlled the selection of the subcontractor and/or
    its performance." 
    Id.
    In contrast, the middleman line of cases involves instances
    in which an owner or agent of a vessel employs a broker to find a
    third party to complete a job that it needs done. See 
    id. at 229
    ("The primary distinguishing characteristic between a general
    contractor and a middle-man . . . is that a general contractor can
    be expected to supply the necessary itself, whereas a middle-man
    is not expected to do so."). In such cases, a court must assess
    "the nature of the relationship between each pair of entities that
    are involved in the transaction at issue (e.g., agent vs.
    independent contractor)" in determining whether a supplier lacking
    privity can acquire a lien. 
    Id. at 230
    . It is this test — and
    not "whether an intermediary can be expected to supply the
    necessaries itself" — that determines whether a supplier has a
    valid lien claim. 
    Id.
    - 18 -
    of the owner or a person authorized by the owner" is consistent
    with both our favorable citation to Fifth Circuit precedent and
    our steadfast adherence to the "well-established precept that the
    requirements for the allowance of a maritime lien are strictly
    construed."     Cianbro, 
    596 F.3d at 14
    .
    TM&B's   contrary     contentions         are    unconvincing.         It
    conspicuously avoids any consideration of whether Sprague would
    qualify for a maritime lien under the analysis put forth in Lake
    Charles Stevedores, 
    199 F.3d at 230
    , the most pertinent Fifth
    Circuit precedent.      When analyzing whether a middleman qualifies
    for    a   maritime   lien,    what     is   crucial     "is       not   whether    an
    intermediary can be expected to supply the necessaries itself that
    distinguishes instances in which the actual suppliers have liens,
    but it is rather the nature of the relationship between each pair
    of entities that are involved in the transaction at issue (e.g.,
    agent vs. independent contractor)."              
    Id.
    TM&B avoids this analysis for two obvious reasons.                    For
    one thing, the analysis undermines TM&B's overarching argument
    that a supplier acquires a lien merely by virtue of providing the
    necessary.      For another thing, the analysis paves the conceptual
    path for understanding why TM&B's advice that Sprague had a valid
    lien    claim   was   incorrect.         After    all,       the    nature    of   the
    relationship      between     Sprague    and      the    only      three     entities
    authorized to bind the M/V Nova Star (STEM, NSC, and Fleetpro) was
    - 19 -
    not one of agency — and the district court so found.    See ST Eng'g
    Marine, 633 F. Supp. 3d at 357.    It follows inexorably that — under
    the test articulated in Lake Charles Stevedores — Sprague did not
    have a valid lien claim.
    At oral argument, TM&B placed great emphasis on the Ninth
    Circuit's decision in Ken Lucky, 869 F.2d at 473.           But that
    decision offers scant support for TM&B's reading of the law.
    There, as in this case, an intermediary was used in ordering the
    fuel.    See id. at 476.   Even so, the role of that intermediary did
    not factor into the Ken Lucky court's analysis because the lien
    challenger admitted that the fuel was ordered by and sold to a
    person with authority to bind the vessel.     See id. at 477.   Here,
    by contrast, Sprague sold the fuel to BIC, which was not authorized
    to bind the vessel.
    Nor does TM&B's reliance on the legislative history of
    CIMLA gain it any headway.     This history, it argues, demonstrates
    that "American companies like Sprague that supply traditional
    necessaries directly to foreign vessels on an order that originated
    from the vessel were the intended beneficiaries of the Lien Act."
    Whether or not such a reading of the legislative history is correct
    — a matter on which we take no view — we do not rely on legislative
    history alone to interpret statutory text.3    See, e.g., Chamber of
    3To the extent that Tramp Oil relied on legislative history,
    at least one other court of appeals has thrown shade on its
    - 20 -
    Com. of U.S. v. Whiting, 
    563 U.S. 582
    , 599 (2011) ("Congress's
    'authoritative   statement   is     the    statutory   text,   not   the
    legislative history.'") (quoting Exxon Mobil Corp. v. Allapattah
    Servs., Inc., 
    545 U.S. 546
    , 568 (2005)).
    That ends this aspect of the matter.         We hold that, by
    November of 2015, Tramp Oil's dicta as to how a direct supplier of
    a necessary could acquire a maritime lien were on life support.
    Here, moreover, the record supports the district court's finding
    that TM&B's attorney failed to conduct adequate legal research —
    research that, when properly evaluated, would have exposed the
    frailty of Tramp Oil's dicta.      The record also supports a finding
    that TM&B's attorney did not appropriately counsel his client about
    the cloud of uncertainty that hovered over Sprague's lien claim.4
    analysis. See Triton Marine Fuels Ltd. v. M/V Pacific Chukotka,
    
    575 F.3d 409
    , 418 (4th Cir. 2009) ("Tramp Oil relies on a
    misreading of the FMLA's legislative history.").
    4 Maine's highest court has not spelled out what standard of
    care a reasonably skillful, prudent, and diligent attorney owes to
    his client when confronted with an area of law that is unsettled.
    Some jurisdictions hold that an attorney fulfills his duty of care
    by conducting adequate legal research and exercising reasonable
    judgment when dealing with an unsettled area of law. See, e.g.,
    Kempf v. Magida, 
    832 N.Y.S.2d 47
    , 49 (N.Y. App. Div. 2007). Other
    jurisdictions require an attorney to alert his client that there
    is an unsettled question of law and inform his client as to any
    adverse outcome that could arise should the law subsequently be
    decided contrary to his view.    This requirement stems from the
    attorney's obligation to afford his client "the opportunity to
    assess the risk" and make an educated decision. Williams v. Ely,
    
    668 N.E.2d 799
    , 806 (Mass. 1996). For present purposes, we need
    not make an "informed prophecy" as to which rule the Maine Supreme
    Judicial Court would adopt. Blinzler v. Marriott Int'l, Inc., 81
    - 21 -
    We thus decline to disturb the district court's conclusion that
    TM&B failed to exercise "such skill, prudence and diligence as is
    reasonable according to the standards of ordinarily competent
    lawyers     performing   similar    services    under   like   conditions."
    Pawlendzio, 148 A.3d at 715.       Thus, we hold that the district court
    did   not   clearly   err   when   it   found   that    TM&B   breached   the
    professional duty that it owed to STEM.          See ST Eng'g Marine, 633
    F. Supp. 3d at 361.
    Let us be perfectly clear.          An attorney is not an
    insurer, liable for professional negligence simply because his
    advice proves to be incorrect.          The standard of care expected of
    an ordinarily competent attorney is not omniscience.            Instead, it
    is the exercise of a reasonable level of skill, prudence, and
    diligence in conducting research and advising his or her client.
    The district court's finding that TM&B's performance undershot
    this standard was not clearly erroneous.           Cf. Cumpiano v. Banco
    Santander P.R., 
    902 F.2d 148
    , 152 (1st Cir. 1990) (explaining that
    when reviewing for clear error, "we ought not to upset findings of
    fact or conclusions drawn therefrom unless, on the whole of the
    record, we form a strong, unyielding belief that a mistake has
    been made").
    F.3d 1148, 1151 (1st Cir. 1996).        In this instance, TM&B failed to
    satisfy either standard.
    - 22 -
    C
    Our voyage is not yet finished.              What remains is for us
    to examine the district court's finding that the negligence of
    TM&B's attorney proximately caused STEM's loss.
    We    begin    with    first      principles.        "[I]n    a     legal
    malpractice case, once a plaintiff demonstrates that the defendant
    attorney    was    negligent,      the    plaintiff      must    show    that   that
    negligence actually and proximately caused his or her injury."
    Wheeler    v.    White,   
    714 A.2d 125
    ,     127   (Me.   1998).     To    prove
    causation, "a plaintiff must demonstrate that he or she would have
    achieved a more favorable result but for the defendant's alleged
    legal malpractice."        Niehoff v. Shankman & Assocs. Legal Ctr.,
    P.A., 
    763 A.2d 121
    , 124 (Me. 2000).                 "[T]he plaintiff typically
    proves that the attorney's professional negligence caused injury
    to the plaintiff by presenting evidence of what would have happened
    in the underlying action had the attorney not been negligent."
    Reppucci v. Nadeau, 
    238 A.3d 994
    , 999 (Me. 2020) (quoting Brooks,
    157 A.3d at 804).
    TM&B strives to convince us that the district court
    clearly erred in finding that it was more likely than not that
    STEM would have prevailed in contesting Sprague's lien claim but
    for TM&B's advice.        TM&B suggests that this finding was clearly
    erroneous in two ways.          First, it contends that Sprague's lien was
    valid:    the finding that Sprague was not selected or controlled by
    - 23 -
    STEM,    NSC,   or   Fleetpro   was   not,     as   TM&B   sees    it,    based   on
    sufficient evidence. Second, TM&B contends that the district court
    should    not   have   regarded   the   advice      that   TM&B    gave    to   STEM
    concerning Sprague's maritime lien claim as dispositive.
    Neither contention moves the needle.            The district court
    did not clearly err when it found the allegations that Sprague put
    forth in its complaint — including that BIC was authorized to bind
    the vessel — to be just that:           allegations made "after-the-fact"
    and "on information and belief."         ST Eng'g Marine, 633 F. Supp. 3d
    at 364.    Allegations are not evidence, and the district court was
    at liberty to find — as it did — that the revealed facts discredited
    Sprague's allegations.
    So, too, the district court did not clearly err in
    affording little weight to STEM's allegation in the BIC bankruptcy
    proceeding that BIC was paid as an intermediary.                  See id. at 364-
    65.     This allegation was riddled with factual errors and it shed
    little light on whether STEM, NSC, or Fleetpro agreed that BIC
    would operate as an agent on their behalf. Similarly, the district
    court did not commit clear error when it rejected TM&B's claim
    that the language in the Fleetpro purchase order directing BIC to
    coordinate the delivery of fuel with the vessel's master signified
    that BIC was an agent of STEM, NSC, or Fleetpro.                  See id. at 365.
    Nothing in this purchase order suffices to prove that BIC had an
    agency relationship with STEM, NSC, or Fleetpro.              In fact — and as
    - 24 -
    the district court found, see id. — this purchase order listed
    Fleetpro "AS AGENTS FOR" NSC and BIC as the "Supplier," thus
    dispelling any notion that either BIC or Sprague was acting as an
    agent for STEM, NSC, or Fleetpro, id. at 357.
    Nor did the district court clearly err when it rejected
    the claim that Sprague's fuel delivery receipts evinced the fact
    that those in charge of the vessel knew that Sprague was asserting
    a lien.        These receipts, as the district court found, "reflect
    nothing more than the vessel's acceptance of the deliveries."              Id.
    at 365.
    TM&B's contention that its advice was not the actual
    cause of STEM's loss is equally unavailing.                In support, TM&B
    claims that the conditional nature of its advice in one of its
    November 16, 2015, emails "did not . . . foreclose the possibility
    that BIC might not have been authorized to pass along an order on
    behalf    of    the   vessel."   It    also    claims   that   STEM's   conduct
    obstructed TM&B's ability to evaluate the asserted liens.
    None of these claims withstand scrutiny.            The record
    supports a conclusion that TM&B was focused only on whether the
    order that BIC placed with Sprague "originated" with the vessel;
    and whether the fuel was actually delivered. Yet those two factors
    alone were not sufficient to determine whether Sprague had a valid
    maritime lien.        See supra Part II(B).       Although TM&B hedged its
    advice regarding BIC on the assumption that BIC was acting as an
    - 25 -
    agent or a broker, this advice was faulty in the first instance.
    The conditional nature of TM&B's advice thus fails to shield it
    from liability. By like token, even if STEM assumed responsibility
    for collecting documents that would have been of relevance in
    analyzing Sprague's lien claim, that fact would not discharge TM&B
    of its responsibility for the advice that it provided.      And the
    fact that STEM, not TM&B, opted to pursue expedited settlement of
    the lien claim does not change the equation.
    We thus hold that the district court did not clearly err
    when it determined that STEM had proven by a preponderance of
    evidence that it would have prevailed in the arrest proceedings on
    Sprague's maritime lien claim but for TM&B's errant advice.
    III
    We need go no further. For the reasons elucidated above,
    the judgment of the district court is
    Affirmed.
    - 26 -
    

Document Info

Docket Number: 22-1844

Filed Date: 12/6/2023

Precedential Status: Precedential

Modified Date: 12/6/2023