Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority ( 2012 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 12-1326
    IN RE:   REDONDO CONSTRUCTION CORPORATION,
    Debtor.
    REDONDO CONSTRUCTION CORPORATION,
    Appellee,
    v.
    PUERTO RICO HIGHWAY AND TRANSPORTATION AUTHORITY,
    Appellant.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF PUERTO RICO
    [Hon. Carmen Consuelo Cerezo, U.S. District Judge]
    Before
    Torruella, Howard and Thompson,
    Circuit Judges.
    Raúl Castellanos-Malavé, with whom Development & Construction
    Law Group, LLC was on brief, for appellant.
    Freddie Pérez-González, with whom Freddie Pérez-González &
    Assoc., P.S.C. was on brief, for appellee.
    November 21, 2012
    HOWARD,     Circuit      Judge.       Chapter     11    debtor    Redondo
    Construction     Corporation        ("Redondo")         brought     an     adversary
    proceeding against the Puerto Rico Highway and Transportation
    Authority ("Authority") in the United States Bankruptcy Court for
    the   District   of    Puerto    Rico,    claiming       amounts    due     for   work
    performed on five construction projects.                   Following a lengthy
    trial, the bankruptcy court awarded Redondo a total of nearly
    $10,250,000 in damages, plus interest at 6% per annum from the
    "payment due" date for each project.                 The district court affirmed
    the judgment in all respects.            The crux of the Authority's claim
    before this court concerns the award of interest.
    I.     PROCEDURAL HISTORY
    After      filing    a    voluntary        petition     for    bankruptcy
    protection   under     Chapter      11   of    the    Bankruptcy    Code,    Redondo
    commenced an adversary proceeding against the Authority to collect
    monies that the Authority allegedly owed Redondo for work performed
    on five construction projects.1          Redondo claimed that the Authority
    failed to compensate it for additional work Redondo had to perform
    on each project due to unanticipated problems, including unforeseen
    site conditions and flawed design plans.                The complaint was tried
    before the bankruptcy court.
    1
    The five projects are: Las Cumbres Avenue, Río Grande de
    Loíza Bridge, Ponce-Adjuntas PR-10, Kennedy Avenue, and Third
    Millennium Park.    Redondo initially made a claim for a sixth
    project but voluntarily dismissed the claim before trial.
    -2-
    In its post-trial brief, Redondo argued that it was
    entitled to prejudgment interest under Article 1061 of the Puerto
    Rico Civil Code as damages for contractual delay.               See 
    P.R. Laws Ann. tit. 31, § 3025
    .   In   the   alternative,   Redondo   sought
    prejudgment interest under Rule 44.3(b) of the Puerto Rico Rules of
    Civil Procedure on the basis of the Authority's alleged obstinacy
    in the course of the litigation.            See P.R. Laws Ann. tit. 32, app.
    III, R. 44.3(b).
    The bankruptcy court entered judgment in Redondo's favor
    and awarded interest on all damages at the rate of 6% per annum
    from the "payment due" date for each project.2             In its summary of
    Redondo's claims, the court noted that Redondo sought interest for
    contractual delay pursuant to Article 1061.            In awarding interest,
    however, the court quoted the language of Rule 44.3(b) and, without
    further reasoning, concluded that Redondo was entitled to the
    "current legal interest" of 6%.
    The Authority challenged the bankruptcy court's decision
    in the district court, see 28 U.S.C. 158(a), arguing that the
    bankruptcy court erred in awarding Redondo damages on some of the
    claims and in assessing interest under Rule 44.3(b).             The district
    2
    The bankruptcy court awarded interest from August 10, 2001
    for the Las Cumbres Avenue, Río Grande de Loíza Bridge, and Ponce-
    Adjuntas PR-10 projects; from July 18, 1999 for the Kennedy Avenue
    project; and from December 3, 2000 for the Third Millennium Park
    project. In so doing, the court agreed with Redondo's expert that
    interest began to accrue thirty days after the date of final
    inspection for each project, when payment became due.
    -3-
    court affirmed the judgment in all respects, without elaborating
    its reasons for affirming the award of interest.           This timely
    appeal followed.
    II.   ANALYSIS
    The Authority presents three claims of error. First, the
    Authority argues that, to the extent that the 6% interest award
    represents postjudgment interest, the rate instead should be 0.11%
    in accordance with 
    28 U.S.C. § 1961
    .          Second, it argues that no
    prejudgment interest was owed because the court did not make a
    finding that the Authority had engaged in obstinate conduct in the
    course of the litigation, as Rule 44.3(b) of the Puerto Rico Rules
    of Civil Procedure requires.       Finally, it argues that the court
    erroneously awarded Redondo an excess amount for its patent and
    excise taxes claim for one project.
    We review the bankruptcy court's findings of fact for
    clear error and its rulings of law de novo.             In re Advanced
    Cellular Sys., Inc., 
    483 F.3d 7
    , 10 (1st Cir. 2007).       In so doing,
    we provide "no particular deference" to the district court's
    conclusions.   
    Id.
     (internal quotation marks omitted).
    A.   Postjudgment Interest
    The parties agree that 
    28 U.S.C. § 1961
     governs any
    postjudgment interest award in this case. See Cummings v. Standard
    Register Co., 
    265 F.3d 56
    , 68 (1st Cir. 2001) (federal law governs
    postjudgment interest on a federal court judgment even in an action
    -4-
    otherwise governed by state law).        Section 1961 provides that
    "[i]nterest shall be allowed on any money judgment in a civil case
    recovered in a district court" and is to be calculated "from the
    date of the entry of the judgment" at a rate fixed in the statute.
    
    28 U.S.C. § 1961
    ; Kaiser Aluminum & Chem. Corp. v. Bonjorno, 
    494 U.S. 827
    , 835 (1990).    Postjudgment interest is mandatory and the
    prevailing party is entitled to it even if the district court made
    no provision for its payment. Cordero v. De Jesus-Mendez, 
    922 F.2d 11
    , 15 (1st Cir. 1990).
    The interest awarded in this case was not intended to be
    postjudgment interest.    The judgment provides that interest at 6%
    per annum began to accrue from specified dates when the Authority
    was required to pay Redondo's claims for each project, well before
    the entry of judgment in Redondo's favor.      Although the judgment
    does not specify the end date for the accrual of interest, there is
    nothing to suggest that it would extend beyond the date of entry of
    the judgment.
    The issue of postjudgment interest nonetheless remains.
    The Authority deposited the amount of the judgment with the clerk
    of the district court on February 17, 2012, stalling the accrual of
    postjudgment interest as of that date.     See Cordero, 
    922 F.2d at 18-19
     (postjudgment interest ceases to accrue as of the date of
    deposit of funds with the court).      Because the judgment had been
    entered on September 30, 2011, Redondo is entitled to postjudgment
    -5-
    interest for the period between the entry of judgment and the date
    of deposit.       The Authority suggests that the amount that it
    deposited includes interest at a rate of 6% for that time period,
    rather than the lower statutory rate.              Accordingly, we remand for
    assessment of postjudgment interest from September 30, 2011 to
    February 17, 2012 at the rate provided in Section 1961.
    B.   Prejudgment Interest
    "When state-law claims (such as the contract claims at
    issue   here)    are   adjudicated    by     a    federal    court,   prejudgment
    interest is normally a matter of state law."                In re Redondo Constr.
    Corp., 
    678 F.3d 115
    , 125 (1st Cir. 2012).                Here, the law of Puerto
    Rico supplies the rule of decision concerning prejudgment interest.
    See 
    id.
    The bankruptcy court awarded Redondo prejudgment interest
    on all damages at the rate of 6% per annum from the payment due
    date for each project.        The parties disagree whether the interest
    was assessed as a sanction under Rule 44.3(b) of the Puerto Rico
    Rules of Civil Procedure or as damages for contractual delay under
    Article   1061   of    the   Puerto   Rico       Civil   Code.    The   Authority
    maintains that prejudgment interest was awarded pursuant to Rule
    44.3(b) but erroneously so because the court failed to make the
    requisite finding that the Authority was obstinate in litigating
    the case.   Redondo concedes that the lack of a finding of obstinacy
    precludes assessment of interest pursuant to Rule 44.3, but argues
    -6-
    that the court awarded interest pursuant to Article 1061, not
    pursuant to Rule 44.3.
    Rule 44.3(b) provides for prejudgment interest at a
    specified rate when the court determines that the losing party was
    obstinate in the course of the litigation.3             P.R. Laws Ann. tit.
    32, app. III, R. 44.3(b); Dopp v. Pritzker, 
    38 F.3d 1239
    , 1252 (1st
    Cir. 1994).        "A finding of obstinacy requires that the court
    determine    a     litigant   to   have    been    unreasonably   adamant    or
    stubbornly       litigious,   beyond      the   acceptable   demands   of   the
    litigation, thereby wasting time and causing the court and the
    other litigants unnecessary expense and delay."              Dopp, 
    38 F.3d at 1252
     (internal quotation marks omitted).               The bankruptcy court
    cited Rule 44.3(b) as the basis for the interest award.                But the
    court made no finding of obstinacy, precluding the assessment of
    interest pursuant to Rule 44.3(b).                See In re Redondo Constr.
    Corp., 
    678 F.3d at 126
     (rejecting the argument that Rule 44.3(b)
    provided the basis for prejudgment interest award in a different
    adversary proceeding between the same parties "because the court
    made no finding regarding the Authority's temerity or obstinance").
    To salvage the interest award, Redondo argues that the
    bankruptcy court did not mean what it said. Redondo maintains that
    3
    Although the rule does not apply when the defendant is the
    Commonwealth of Puerto Rico or one of its agencies, the exemption
    does not extend to public corporations like the Authority.
    Rodriguez Cancel v. P.R. Elec. Power Auth., 
    16 P.R. Offic. Trans. 542
     (1985).
    -7-
    the court in fact awarded interest for contractual delay pursuant
    to Article 1061 but instead cited to Rule 44.3(b) either in error
    or to indicate its inapplicability.4        We cannot indulge such
    speculation.     The bankruptcy court did acknowledge that one basis
    for Redondo's interest claim was Article 1061.       Nothing in the
    opinion, however, indicates that the court awarded interest on this
    basis.
    Nor can we determine from the record before us that
    Redondo is entitled to the prejudgment interest award pursuant to
    Article 1061.5     Unless parties agree otherwise, when a contract
    obliges a party to pay a sum of money, Article 1061 provides for
    payment of interest "as an [] indemnity for damages, by way of
    penalty, for default in payment." Rivera v. Crescioni, 
    77 P.R. 43
    ,
    51 (1954); accord P.R. & Am. Ins. Co. v. Superior Court of P.R., 
    84 P.R. 597
    , 599 (1962).    Default in payment occurs "as of the date in
    4
    Redondo indeed goes further and explains the court's
    apparent blunder as "the result of [the judge's] time constraints
    in the drafting of his decision[.]" The judge retired on the day
    he issued the opinion.
    5
    Captioned "Interest as indemnity for nonpayment of money,"
    Article 1061 provides:
    Should the obligation consist in the payment of a sum of
    money, and the debtor should be in default, the indemnity
    for losses and damages, should there not be a stipulation
    to the contrary, shall consist in the payment of the
    interest agreed upon, and should there be no agreement,
    in that of the legal interest. Until another rate is
    fixed by the Government, interest at the rate of six
    percent (6%) per annum shall be considered as legal.
    
    P.R. Laws Ann. tit. 31, § 3025
    .
    -8-
    which judicial or extrajudicial demand was made for [payment]."
    Widow of Vázquez v. Vázquez Cintrón, 
    85 P.R. 266
    , 268 (1962)
    (citing 31 
    P.R. Laws Ann. tit. 31, § 3017
    ).                We cannot determine
    when   such    demands   were   made    in   this   case    and   whether   they
    correspond to the dates that the bankruptcy court designated for
    the accrual of interest.
    Because uncertainty surrounds the prejudgment interest
    award, we remand the case to the district court with instructions
    to vacate that award and return the case to the bankruptcy court
    for a determination of whether an award of prejudgment interest is
    appropriate, and, if so, the basis for the award, the applicable
    rate of interest, and the period of accrual.           We take no view as to
    the outcome of this further inquiry.
    C.   Revised Amount for One Claim
    The Authority's final claim is that the court erroneously
    awarded Redondo an excess amount for its patent and excise taxes
    claim for the Ponce-Adjuntas PR-10 project.                 Specifically, the
    court awarded a sum of $1,082,654.56 for the claim despite the fact
    that Redondo revised the amount to $818,302 at trial and presented
    evidence only as to that amount.             Reducing the amount for this
    claim requires further modification of the judgment because Redondo
    was awarded 15% profit on all its successful claims.                   Redondo
    concedes the error and consents to the modification of the judgment
    -9-
    as requested by the Authority. Accordingly, we remand for entry of
    a revised partial judgment bearing such modifications.
    III.   CONCLUSION
    We vacate the district court's judgment to the extent
    necessary to allow for resolution of the aforementioned issues and
    remand the case for further proceedings consistent with this
    opinion.   The parties shall bear their own costs of this appeal.
    -10-