Devon Energy Production Company v. Line Finders ( 2022 )


Menu:
  • Appellate Case: 21-6119     Document: 010110738905      Date Filed: 09/14/2022    Page: 1
    FILED
    United States Court of Appeals
    UNITED STATES COURT OF APPEALS                        Tenth Circuit
    FOR THE TENTH CIRCUIT                      September 14, 2022
    _________________________________
    Christopher M. Wolpert
    Clerk of Court
    DEVON ENERGY PRODUCTION
    COMPANY, L.P.,
    Plaintiff - Appellee,
    v.                                                   Nos. 21-6119 & 21-6162
    (D.C. No. 5:20-CV-00636-F)
    LINE FINDERS, LLC, d/b/a Line Finders,                     (W.D. Okla.)
    f/k/a Line Finders, Inc.,
    Defendant - Appellant.
    _________________________________
    ORDER AND JUDGMENT *
    _________________________________
    Before TYMKOVICH, Chief Judge, MATHESON and EID, Circuit Judges.
    _________________________________
    Defendant-Appellant Line Finders, LLC, appeals the district court’s
    enforcement of a settlement agreement in favor of Plaintiff-Appellee Devon Energy
    Production Company, L.P. Line Finders also appeals the district court’s award of
    attorney fees to Devon. We consolidated the appeals. Exercising jurisdiction under
    
    28 U.S.C. § 1291
    , we affirm the district court’s judgment.
    *
    After examining the briefs and appellate record, this panel has determined
    unanimously that oral argument would not materially assist in the determination of
    this appeal. See Fed. R. App. P. 34(a)(2); 10th Cir. R. 34.1(G). The case is therefore
    ordered submitted without oral argument. This order and judgment is not binding
    precedent, except under the doctrines of law of the case, res judicata, and collateral
    estoppel. It may be cited, however, for its persuasive value consistent with
    Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.
    Appellate Case: 21-6119    Document: 010110738905       Date Filed: 09/14/2022     Page: 2
    I. BACKGROUND
    Line Finders provides support services for Devon’s oil and gas operations. In
    2018, two Line Finders employees, Marcus Murschel and Michael Elsasser, were
    injured in a gas-line explosion allegedly caused by a Devon employee. Mr. Murschel
    demanded compensation from Devon, prompting Devon to seek defense and
    indemnification from Line Finders under their support services contract—the “Master
    Service and Supply Agreement Onshore and Maritime” (MSSA), Aplt. App. at 22.
    Line Finders rejected Devon’s request, so Devon filed this diversity action, asserting
    claims for declaratory relief, breach of contract, and damages.
    The parties engaged in settlement negotiations. Line Finders outlined several
    material terms to resolve the dispute, and on April 7, 2021, Devon emailed Line
    Finders a counter-offer. Devon proposed, among other things, that the parties file a
    joint or unopposed motion to enter judgment in favor of Devon on its claim for
    declaratory relief. If granted, Devon would dismiss its remaining claims and Line
    Finders would not appeal. If Mr. Murschel or Mr. Elsasser advanced their claims, the
    parties would resubmit a request for defense and indemnification to Line Finders’
    insurer. If denied coverage, Line Finders would defend and indemnify Devon. Both
    parties would sign the written settlement agreement. On April 8, Line Finders agreed
    to these terms and invited Devon to prepare a draft settlement agreement for review.
    Devon prepared a draft. The parties modified it over the next several weeks.
    On May 21, 2021, Devon sent Line Finders the settlement agreement. That same
    day, Line Finders’ attorney responded, “The settlement agreement looks fine. Please
    2
    Appellate Case: 21-6119    Document: 010110738905       Date Filed: 09/14/2022    Page: 3
    send me an execution version and I will procure signature.” 
    Id. at 142
    . Devon did
    not immediately send an execution version to Line Finders, however, and on June 9,
    Devon received a demand for compensation from Mr. Elsasser, the second Line
    Finders employee injured in the explosion. Two days later, on June 11, Devon
    signed the settlement agreement, and on June 17, sent it to Line Finders for execution
    with Mr. Elsasser’s demand attached. The parties later tendered Mr. Elsasser’s
    demand to the insurer, but Line Finders never signed the settlement agreement.
    Devon moved the district court to enforce the settlement agreement and enter
    judgment on its claim for declaratory relief. Line Finders objected, arguing (1) it
    never signed the settlement agreement, which was contingent on mutual execution,
    and (2) the settlement agreement was premised on a mistake and fraud because
    Line Finders relied on the fact that Mr. Elsasser had not made a demand, which
    Devon failed to disclose immediately. Devon disputed both arguments, contending
    (1) the settlement agreement superseded all prior understandings and did not require
    signatures, and (2) there was no mistake because the settlement agreement expressly
    contemplated that both Mr. Murschel and Mr. Elsasser could advance their claims,
    nor was there fraud because the parties negotiated, and Line Finders accepted, the
    settlement agreement before Mr. Elsasser submitted his demand.
    The district court enforced the settlement agreement, ruling that Line Finders’
    counsel accepted the settlement agreement on May 21, and nothing in the settlement
    agreement required mutual execution. The court also determined there was no
    mistake of fact because Line Finders understood it was possible Mr. Elsasser could
    3
    Appellate Case: 21-6119    Document: 010110738905         Date Filed: 09/14/2022     Page: 4
    pursue his claims, which was expressly contemplated in the settlement agreement.
    Nor was there fraud, the court concluded, because Line Finders accepted the
    settlement agreement on May 21 before Devon received Mr. Elsasser’s demand on
    June 9. Thus, the district court recorded a journal entry of judgment in favor of
    Devon on its claim for declaratory relief. The district court also granted Devon’s
    motion to dismiss its remaining claims and awarded Devon attorney fees. Line
    Finders now appeals the district court’s enforcement of the settlement agreement and
    award of attorney fees.
    II. DISCUSSION
    A. Settlement Agreement
    1. Legal standards
    “A trial court has the power to summarily enforce a settlement agreement
    entered into by the litigants while the litigation is pending before it.” United States v.
    Hardage, 
    982 F.2d 1491
    , 1496 (10th Cir. 1993). State contract law governs issues of
    formation. Shoels v. Klebold, 
    375 F.3d 1054
    , 1060 (10th Cir. 2004). In Oklahoma,
    whether there has been a meeting of the minds to form a settlement agreement is a
    question of fact. Gomes v. Hameed, 
    184 P.3d 479
    , 485 (Okla. 2008). Thus, although
    we generally “review the [district] court’s approval of the settlement agreement for
    an abuse of discretion,” Hardage, 982 F.2d at 1495, we review the district court’s
    ultimate finding that the parties reached a binding settlement agreement for clear
    error, see Shoels, 
    375 F.3d at 1056
    .
    4
    Appellate Case: 21-6119    Document: 010110738905         Date Filed: 09/14/2022       Page: 5
    Under Oklahoma law, “[a] settlement agreement is an oral or written contract
    between the parties. As such, it is subject to the rules of offer and acceptance and of
    mutual assent which control any issue of contract formation.” In re De-Annexation
    of Certain Real Property from City of Seminole, 
    204 P.3d 87
    , 89 (Okla. 2009)
    (citation omitted). “[A]n acceptance will not bind the offeror unless it is
    unconditional, identical to the offer, and does not modify, delete or introduce any
    new terms into the offer.” 
    Id.
     (quotations omitted). Settlement agreements
    are generally favored and “should not be set aside absent fraud, duress, undue
    influence, or mistake.” Vela v. Hope Lumber & Supply Co., 
    966 P.2d 1196
    , 1198
    (Okla. Civ. App. 1998).
    2. Analysis
    Line Finders contends the district court erred in enforcing the settlement
    agreement because (a) it was not signed by both parties, (b) it was premised on a
    mistake of fact and fraud, and (c) the district court failed to hold an evidentiary
    hearing. We reject all of these arguments.
    a. Signatures
    Relying on Devon’s counter-offer from April 7, which proposed that any
    settlement agreement be signed by both parties, Line Finders contends that mutual
    execution was a condition precedent that was unsatisfied because Line Finders never
    signed the settlement agreement. This argument fails because the parties are not
    bound by the terms of Devon’s April 7 counter-offer. Line Finders agreed to those
    terms but invited Devon to draft a proposed settlement agreement that the parties
    5
    Appellate Case: 21-6119     Document: 010110738905        Date Filed: 09/14/2022     Page: 6
    proceeded to modify until Line Finders accepted the final version on May 21. See
    Aplt. App. at 142-46 (email exchanges discussing modifications). The modifications
    prevented the parties from being bound until Line Finders accepted the settlement
    agreement on May 21. See In re De-Annexation of Certain Real Property, 204 P.3d
    at 89. And nothing in the May 21 settlement agreement requires mutual execution.
    Line Finders insists that when its attorney accepted the settlement agreement,
    he expressly stated he would “procure [a] signature.” Aplt. App. at 142. But it was
    Line Finders’ acceptance of the settlement agreement that was binding, not counsel’s
    procurement of a signature. See E. Cent. Okla. Elec. Coop., Inc. v. Okla. Gas &
    Elec. Co., 
    505 P.2d 1324
    , 1328 (Okla. 1973) (“An agreement to make and execute a
    certain written agreement, the terms of which are mutually understood and agreed on,
    is in all respects as valid and obligatory as the written contract itself would be if
    executed.” (quotations omitted)); see also 2 Williston on Contracts § 6:44 (4th ed.
    May 2022 update) (“[A]ny written contract, though signed by only one party, will
    bind the other if he or she accepts the writing.”). Indeed, “a contract becomes
    binding where it is executed by one party, is forwarded to the other for execution or
    approval, is received and retained by the latter but never formally signed or approved
    by him, and both parties act in reliance upon it as a valid contract.” J.P.C. Petroleum
    Corp. v. Vulcan Steel Tank Corp., 
    118 F.2d 713
    , 716 (10th Cir. 1941) (applying
    Oklahoma law).
    Here, after Line Finders accepted the settlement agreement, Devon signed it
    and sent it to Line Finders for execution. Though Line Finders did not sign it, the
    6
    Appellate Case: 21-6119     Document: 010110738905          Date Filed: 09/14/2022   Page: 7
    parties thereafter jointly tendered Mr. Elsasser’s demand to the insurer as specified in
    the settlement agreement. Under these circumstances, notwithstanding Line Finders’
    failure to sign, the settlement agreement was binding. 1
    b. Mistake & Fraud
    Line Finders contends the settlement agreement was predicated on a mistake of
    fact and fraud. Line Finders asserts (1) it accepted the settlement agreement because
    it mistakenly believed Mr. Elsasser would not make a demand; and (2) Devon knew
    of Mr. Elsasser’s demand before it signed the settlement agreement on June 11, and
    its failure to timely disclose that fact constitutes constructive fraud.
    (1) Mistake of fact
    A unilateral mistake of fact as to a material term of a contract may be grounds
    for rescission. See Watkins v. Grady Cnty. Soil & Water Conservation Dist.,
    
    438 P.2d 491
    , 495 (Okla. 1968). But a unilateral mistake rarely warrants recission
    unless “the ‘mistake’ goes to a material term of the agreement itself”—that is,
    “[w]hen the language of the contract contains a latent ambiguity and one of the
    parties is in fact assenting to something different from what the other party agrees
    to.” Shoels, 
    375 F.3d at 1066-67
    .
    1
    Line Finders denies that it jointly tendered Elsasser’s demand to its insurer
    “in accordance with the terms of the Settlement Agreement,” but it admits that it
    jointly tendered the demand to the insurer. Aplt. App. at 155, ¶ 16 (quotations
    omitted). And the settlement agreement states that “[i]n the event Marcus Murschel
    or Michael El[s]asser takes any action to advance his claim against Devon, the
    Parties will jointly submit a claim to [the insurer] to defend, indemnify, and hold
    harmless Devon against such claim.” Id. at 126, ¶ 4.
    7
    Appellate Case: 21-6119    Document: 010110738905        Date Filed: 09/14/2022    Page: 8
    Line Finders suggests it made “a unilateral mistake of fact going to the essence
    of the contract” by believing Mr. Elsasser would not submit a demand. Aplt.
    Opening Br. at 18 (brackets and quotations omitted). But it does not identify any
    latent ambiguity in the settlement agreement underlying its mistaken belief, perhaps
    because the agreement expressly recognized the possibility that Mr. Elsasser could
    make a demand, and the agreement set forth the parties’ obligations if he did:
    In the event Marcus Murschel or Michael El[s]asser takes any
    action to advance his claim against Devon, the Parties will jointly
    submit a claim to [the insurer] to defend, indemnify, and hold harmless
    Devon against such claim. If [the insurer] does not promptly and
    unequivocally assume the defense and agree to indemnify Devon . . .
    then [Line Finders] promptly will defend and indemnify Devon . . . .
    Aplt. App. at 126, ¶ 4. Because Line Finders’ alleged mistaken belief does not go to
    a material term of the settlement agreement, it does not fall under the rule allowing
    for rescission based on a unilateral mistake.
    Indeed, Line Finders argues it mistakenly assumed Mr. Elsasser would not
    make a demand because he had not yet made a demand, and that Devon knew about
    the demand when it signed the settlement agreement. 2 In the district court,
    Line Finders explained that when it agreed to Devon’s counter-offer on April 8:
    Marcus Murschel had taken no action on his claim for a year and
    Michael Elsasser had not made a demand, despite the fact that the
    [explosion] had occurred two-and-a-half years previously. Therefore,
    Line Finders felt comfortable with the concept that, if Murschel or
    Elsasser took steps to advance their claims and further if the parties’
    2
    Line Finders’ brief on appeal is vague on this point, stating that “whereas
    Mr. Elsasser had not asserted his claim at all when the [settlement agreement] was
    first transmitted to Line Finders, he had filed a demand two days before Devon
    executed the [settlement agreement].” Aplt. Opening Br. at 16-17.
    8
    Appellate Case: 21-6119    Document: 010110738905        Date Filed: 09/14/2022    Page: 9
    insurer denied coverage, then Line Finders would defend and indemnify
    Devon. The likelihood that either Murschel or Elsasser would seek to
    prosecute a claim seemed remote at the time.
    Out of the blue, however, Elsasser made a demand on Devon
    through counsel on June 9th. . . . Given this fundamental change of
    essential facts, Line Finders did not sign the proposed final settlement
    agreement.
    Aplt. App. at 152 (emphasis added).
    The problem, though, is that in the interim—between April 8 and June 9—Line
    Finders had accepted the settlement agreement on May 21, fully recognizing that
    Mr. Elsasser could make a demand, which he did on June 9. Thus, Line Finders was
    already bound by the settlement agreement, which expressly contemplated that
    Mr. Elsasser could make a demand. Line Finders may not rescind or repudiate the
    settlement agreement simply because things did not turn out the way it hoped they
    would. See 27 Williston on Contracts § 70:8 (4th ed. May 2022 update) (“Avoidance
    of a contract is not permitted just because one party is disappointed in the hope that
    the facts accord with his wishes.”). It is irrelevant that Devon signed the settlement
    agreement on June 11 knowing Mr. Elsasser had made a demand because, again, by
    then the parties had already reached the settlement agreement, which memorialized
    their shared understanding that Mr. Elsasser could pursue his claims.
    (2) Fraud
    Line Finders also contends Devon’s failure to promptly disclose the Elsasser
    demand constitutes constructive fraud. Although Line Finders does not expressly
    characterize this argument as alleging fraud in the inducement, it relies on authority
    9
    Appellate Case: 21-6119     Document: 010110738905        Date Filed: 09/14/2022     Page: 10
    evaluating a claim of fraud in the inducement based on non-disclosure of material
    facts, see Sutton v. David Stanley Chevrolet, Inc., 
    475 P.3d 847
    , 852-54 (Okla. 2020),
    and contends that “[c]ontracts executed because of fraud may be rescinded,” Aplt.
    Opening Br. at 19. According to Line Finders, Devon had a duty to promptly
    disclose Mr. Elsasser’s demand under the MSSA and its failure to do so justifies
    rescission of the settlement agreement. 3
    Fraud in the inducement is a “misrepresentation as to the terms, quality or
    other aspects of a contractual relation, venture or other transaction that leads a person
    to agree to enter into the transaction with a false impression or understanding of the
    risks, duties, or obligations she has undertaken.” Harkrider v. Posey, 
    24 P.3d 821
    ,
    827 (Okla. 2000) (quotations omitted). If a party’s consent was induced by fraud,
    rescission may be appropriate. See 
    Okla. Stat. tit. 15, § 233
    (1). But “[a] contract
    voidable for fraud in the inducement creates a valid contractual relationship . . . until
    the parties are relieved of their obligation by a decree of recission.” Harkrider,
    24 P.3d at 827.
    Line Finders was not fraudulently induced into accepting the settlement
    agreement. Line Finders agreed to the settlement terms because, although
    Mr. Elsasser could pursue his claims, it apparently thought he would not. Operating
    under this assessment, Line Finders accepted the settlement agreement on May 21.
    3
    To be clear, the relevant contract here is the settlement agreement, not the
    MSSA. Although Line Finders cites the MSSA as the source of Devon’s duty to
    promptly disclose the Elsasser demand, the question is whether the failure to disclose
    the demand induced Line Finders to accept the settlement agreement.
    10
    Appellate Case: 21-6119    Document: 010110738905        Date Filed: 09/14/2022       Page: 11
    At that time, Mr. Elsasser had not yet made a demand, so Devon could not have
    misrepresented whether he would. Indeed, Devon did not receive Mr. Elsasser’s
    demand until June 9. Given this chronology, Line Finders’ assertion of fraud is
    meritless.
    c. Evidentiary hearing
    Line Finders also argues that the district court should have held an evidentiary
    hearing to make factual findings necessary to determine whether there was a valid
    acceptance of the settlement agreement or fraud. “[W]here material facts concerning
    the existence or terms of an agreement to settle are in dispute, the parties must be
    allowed an evidentiary hearing.” Hardage, 982 F.2d at 1496; see Russell v. Bd. of
    Cnty. Comm’rs, 
    1 P.3d 442
    , 445 (Okla. Civ. App. 2000) (“When the terms of the
    settlement agreement are disputed, the trial court should . . . conduct an evidentiary
    hearing.”). An evidentiary hearing also is appropriate to evaluate fraud in the
    inducement. See, e.g., Hai v. Baptist Healthcare of Okla., 
    230 P.3d 914
    , 919
    (Okla. Civ. App. 2009). But “[i]n the absence of fraud, mistake, or accident,
    Oklahoma law is clear:
    [w]here a contract is complete in itself and, as viewed in its entirety, is
    unambiguous, its language is the only legitimate evidence of what the
    parties intended. The intention of the parties cannot be determined from
    the surrounding circumstances, but must be gathered from a four-
    corners’ examination of the contractual instrument in question.”
    Gatz v. Sw. Bank of Omaha, 
    836 F.2d 1089
    , 1095 (8th Cir. 1988) (quoting Mercury
    Inv. Co. v. F.W. Woolworth Co., 
    706 P.2d 523
    , 529 (Okla. 1985)).
    11
    Appellate Case: 21-6119     Document: 010110738905        Date Filed: 09/14/2022    Page: 12
    We have already rejected Line Finders’ allegations of mistake and fraud. The
    record shows there was no mistake because before it accepted the settlement
    agreement, Line Finders recognized that Mr. Elsasser could pursue his claim. Nor
    was there fraud because Devon did not receive Mr. Elsasser’s demand until after Line
    Finders accepted the settlement agreement. An evidentiary hearing was not needed
    to assess the existence of mistake or fraud.
    Similarly, no evidentiary hearing was needed to assess the validity of the
    parties’ acceptance of the settlement agreement. Line Finders agrees it “had no
    further revisions to the Settlement Agreement” as of May 21, Aplt. App. at 154, and
    the record clearly shows it accepted the settlement agreement on that date. Although
    Line Finders disputes the legal implications of not signing the agreement, we
    resolved that issue above as a matter of law.
    Line Finders insists our decision in Hardage required an evidentiary hearing
    because the parties here “disputed offer and acceptance.” Aplt. Br. at 20. Likening
    the circumstances in this case to those in Hardage, Line Finders asserts there was an
    insufficient factual foundation for the district court to determine the parties’ mutual
    assent to the settlement agreement because “‘the court failed to receive sworn
    testimony, subject to cross-examination, or sworn affidavits [or briefing] on this
    formation issue.’” 
    Id. at 21
     (quoting Hardage, 982 F.2d at 1497). Contrary to
    Line Finders’ assertion, however, Hardage is distinguishable and does not require a
    different result.
    12
    Appellate Case: 21-6119    Document: 010110738905        Date Filed: 09/14/2022     Page: 13
    In Hardage, the district court enforced a putative settlement agreement despite
    conflicting testimony from the lawyers involved in settlement negotiations as to
    whether there was a valid agreement. 982 F.2d at 1496. We remanded for an
    evidentiary hearing because the conflicting representations of counsel established a
    material factual dispute as to whether a settlement agreement was reached. See id.
    at 1497. We said that the district court received no sworn testimony subject to
    cross-examination, nor did the court have before it any briefing or affidavits, leaving
    an insufficient factual foundation for the court’s conclusion. See id. at 1496-97.
    In contrast to Hardage, there is no such material factual dispute here. Indeed,
    there are no conflicting factual representations from counsel as to whether there was
    a valid agreement. Instead, counsel dispute the legal implications of the parties’
    conduct, which is plainly evidenced in the record. Based on that evidence, which
    provides an adequate factual foundation, the district court enforced the settlement
    agreement after receiving full briefing from the parties. Given these distinguishing
    features, Line Finders’ reliance on Hardage is misplaced.
    B. Attorney Fees
    Line Finders appeals the district court’s award of attorney fees to Devon under
    the settlement agreement. The settlement agreement contained the following fee
    provision: “If any Party asserts a claim against another Party to enforce the terms
    and conditions of this agreement in any litigation, then the prevailing party shall be
    entitled to recover its reasonable attorneys’ fees, costs, and expense from the
    non-prevailing party.” Aplt. App. at 127, ¶ 5 (emphasis added). Line Finders
    13
    Appellate Case: 21-6119    Document: 010110738905         Date Filed: 09/14/2022       Page: 14
    contends this provision is inapplicable because Devon did not file a claim, but instead
    filed a motion to enforce the settlement agreement. 4
    We review the reasonableness of a fee award for abuse of discretion. We
    review the interpretation of a contractual fee award de novo. See Wiggin Props., LLC
    v. ARCO Bldg., LLC, 
    510 P.3d 1274
    , 1280 (Okla. Civ. App. 2021).
    We agree with the district court that Devon’s motion to enforce the settlement
    agreement was a “claim.” “[W]ords in a contract are to be understood in their
    ordinary sense unless used by the parties in a technical sense, or unless a special
    meaning is given to them by usage.” Koch Fuels, Inc. v. State ex rel. Okla. Tax
    Comm’n, 
    862 P.2d 471
    , 475 (Okla. 1993); see also 11 Williston on Contracts § 32:3
    (4th ed. May 2022 update) (“The plain, common, or normal meaning of language will
    be given to the words of a contract unless the circumstances show that in a particular
    case a special meaning should be attached to them.”). The court correctly observed
    that the plain meaning of a “claim” is “‘the assertion of an existing right.’” Aplt.
    App. at 222 (quoting Black’s Law Dictionary (11th ed. 2019) (brackets omitted)).
    Devon’s motion to enforce asserted its rights under the settlement agreement. It
    therefore qualifies as a “claim,” entitling Devon to its reasonable attorney fees.
    Although Line Finders urges us to interpret “claim” in a technical sense, its
    argument fails. According to Line Finders, a “claim” is “a cause of action submitted
    4
    Line Finders alternatively argued in district court that the fee request should
    be reduced as excessive and because counsel engaged in block-billing. The court
    agreed that the use of block-billing warranted a reduction. It reduced the fee request
    by 15% and awarded $9,962.50.
    14
    Appellate Case: 21-6119     Document: 010110738905        Date Filed: 09/14/2022   Page: 15
    in a discrete set of documents.” Aplt. Opening Br. at 24. Those “documents,” Line
    Finders explains, are pleadings enumerated under Federal Rule of Civil Procedure
    7(a). Line Finders reasons that a pleading “‘states a claim for relief,’” and only a
    cause of action contained in a pleading qualifies as a “claim.” Aplt. Opening Br. at
    24 (quoting Fed. R. Civ. P. 8(a)). But there is no indication the parties used the word
    “claim” in this technical sense in the settlement agreement. The district court did not
    err in its interpretation of the settlement agreement’s fee provision.
    III. CONCLUSION
    We affirm the district court’s judgment.
    Entered for the Court
    Scott M. Matheson, Jr.
    Circuit Judge
    15