Savage Industries v. American Pulverizer ( 1996 )


Menu:
  •        UNITED STATES COURT OF APPEALS Filed 12/27/96
    Tenth Circuit
    Byron White United States Courthouse
    1823 Stout Street
    Denver, Colorado 80294
    (303) 844-3157
    Patrick J. Fisher, Jr.                                                        Elisabeth A.
    Shumaker
    Clerk                                                                         Chief Deputy Clerk
    December 27, 1996
    TO:     All recipients of the captioned order and judgment
    RE:     95-4159, Savage Industries, Inc. v. American Pulverizer Co.
    December 18, 1996
    Please be advised of the following correction to the captioned decision:
    Judge Godbold’s concurrence/dissent has been amended. The revised
    concurrence/dissent is attached. Please substitute it for the one attached to the
    original order and judgment filed December 18, 1996.
    Very truly yours,
    Patrick Fisher, Clerk
    Susan Tidwell
    Deputy Clerk
    UNITED STATES COURT OF APPEALS
    Filed 12/18/96
    TENTH CIRCUIT
    _____________________
    SAVAGE INDUSTRIES, INC.,
    Plaintiff-Counter-Defendant-Appellee,
    v.                                                        No. 95-4159
    (D.C. No. 94-CV-6)
    AMERICAN PULVERIZER COMPANY,                                (D. Utah)
    Defendant-Counter-Claimant-Appellant,
    CHRIS GRIESEDIECK,
    Defendant-Counter-Claimant.
    _____________________
    ORDER AND JUDGMENT *
    _____________________
    Raymond Etcheverry (William J. Stilling with him on the brief) of Parsons Behle
    & Latimer, Salt Lake City, Utah, for Plaintiff-Appellee.
    Francis E. Pennington, III (Kenneth W. Yeates and Craig W. Dallon of Van Cott,
    Bagley, Cornwall & McCarthy with him on the briefs) of Dankenbring, Greiman,
    Osterhold & Hoffmann, P.C., St. Louis, Missouri, for Defendant-Appellant.
    Before BRORBY, GODBOLD ** and McWILLIAMS, Circuit Judges.
    *
    This order and judgment is not binding precedent except under the
    doctrines of law of the case, res judicata and collateral estoppel. The court
    generally disfavors the citation of orders and judgments; nevertheless, an order
    and judgment may be cited under the terms and conditions of 10th Cir. R. 36.3.
    **
    The Honorable John C. Godbold, Senior United States Circuit Judge for
    the Eleventh Circuit, sitting by designation.
    _____________________
    Savage Industries, Inc. ("Savage Industries") brought suit against American
    Pulverizer Company ("American Pulverizer") for negligent misrepresentation,
    breach of warranty, breach of contract and equitable estoppel. The district court
    granted summary judgment in Savage Industries' favor on the issue of American
    Pulverizer's liability for breach of contract, and a bench trial was held on the
    issue of damages. Following a two-day trial, the district court issued detailed
    Findings of Fact and Conclusions of Law, and entered a Judgment in favor of
    Savage Industries for $499,296.26. Thereafter, American Pulverizer filed a
    motion to amend findings and judgment, which the district court denied.
    American Pulverizer appeals from the district court's judgment and order denying
    its motion to amend findings and judgment.
    I. Factual Background
    In June 1991, Charles T. Main, Inc. contracted with Savage Industries for
    Savage Industries to build a waste coal handling system at the Sunnyside
    Cogeneration Project in Sunnyside, Utah. The contract required Savage
    Industries to provide 200 tons per hour of coal sized less than 1/4 inch to fuel the
    Sunnyside Cogeneration Facility.
    -2-
    Thereafter, American Pulverizer manufactured and sold to Savage
    Industries a "double roll crusher" to process waste coal as part of Savage
    Industries' obligation under its contract with Charles T. Main, Inc. However, the
    performance of the double roll crusher proved unsatisfactory when it produced a
    large amount of oversized material which could not be used as fuel for the
    Sunnyside Cogeneration Facility. In an attempt to solve the problem with the
    crusher, Savage Industries and American Pulverizer entered into an August 1993
    agreement which contemplated installation of a newly designed system -- a
    "Closed Loop System." 1
    Not long after entering the August 1993 agreement, the parties realized the
    Closed Loop System would not provide sufficient output to enable Savage
    Industries to meet its obligation to Charles T. Main, Inc. Consequently, in
    October 1993, Savage Industries and American Pulverizer executed a contract
    which provided for the installation of the "Zeigler System" instead of the Closed
    Loop System. 2 The October 1993 contract required American Pulverizer to
    1
    The Closed Loop System was intended to maximize the crusher's output
    of the specified size of coal by employing a "looped" configuration of conveyors
    that would feed (and re-feed if necessary) oversized coal to the crusher.
    2
    The Zeigler System was intended to recirculate oversized material back
    through a refurbished double roll crusher.
    -3-
    "[r]efurbish the Double Roll Crusher to meet OEM standards and specifications
    on or before November 8, 1993." It also required American Pulverizer to furnish
    all equipment for the Zeigler System, including the conveyor which would
    recirculate oversized material back into the system for crushing. 3
    Three days after entering the October 1993 agreement, American Pulverizer
    notified Savage Industries it was not financially able to perform its obligations
    under the contract. Although American Pulverizer's sales engineer subsequently
    installed newly machined roll segments on the double roll crusher, American
    Pulverizer never refurbished the double roll crusher as the contract required.
    In order to satisfy its contractual obligation to Charles T. Main, Inc.,
    Savage Industries searched for an economical crusher to replace the double roll
    crusher in the Zeigler system. Ultimately, Savage Industries purchased a Canica
    vertical impact crusher which met the output requirements for the Sunnyside
    Facility, and did so at the lowest cost possible by requiring fewer new conveyors
    and screens than the Zeigler System. 4
    3
    The October 1993 contract refers to the recirculating conveyor as the
    Fourth Conveyor (referred to hereinafter as the "CV-111 conveyor").
    4
    Whereas the Zeigler system called for five new conveyors and two new
    screens, the Canica crusher required only two new conveyers and one new screen.
    -4-
    From February 1994 until May 1994, while modifications were being made
    to accommodate the new Canica crusher, Savage Industries rented a different,
    temporary crusher from Canica to meet the fuel requirements at the Sunnyside
    Facility. Savage Industries installed the permanent Canica crusher in May 1994.
    Although the Zeigler System contemplated a closed loop system, whereby
    oversized product would be recirculated back through the system, Savage
    Industries initially elected, due to cost concerns, not to install a CV-111 conveyor
    to "close the loop" on the Canica system. Instead, oversized material was
    removed by conveyor to a stockpile area for reclamation by a front-end loader. In
    order to handle the growing stockpile of oversized material, Savage Industries
    employed additional workers, operated a second front-end loader, and operated its
    loaders two shifts instead of one. Savage Industries had not purchased a CV-111
    conveyor as of the time of trial; however, Savage Industries received capital fund
    approval for the conveyor in June 1995.
    II. Issues Raised on Appeal
    This case was tried before the district court, sitting without a jury, in June
    1995. Following a two-day trial, the district court entered its Findings of Fact
    and Conclusions of Law, awarding Savage Industries damages in the amount of
    -5-
    $499,296.26. Included in the district court's damages award is the sum of
    $62,330.00 for the CV-111 conveyor which Savage Industries had not purchased
    as of the date of trial. 5 Also included in the court's damages award is
    $116,484.93 for additional operating expenses incurred by Savage Industries
    between November 9, 1993, and the end of May 1994. On appeal, American
    Pulverizer contests the damages awarded for the CV-111 conveyor and additional
    operating expense.
    Specifically, American Pulverizer's appeal raises three issues: (1) whether
    the district court erroneously applied Utah law in awarding $62,330.00 to Savage
    Industries for the CV-111 conveyer; (2) whether the $62,330.00 award for the
    CV-111 conveyor is supported by sufficient evidence; and (3) whether the
    $116,484.93 award for additional operating expenses is supported by sufficient
    evidence. After thoroughly reviewing the parties' respective briefs, the entire
    5
    The district court made no specific finding of fact on this particular item
    of damages. However, in discussing the issue of pre-judgment interest in its
    Conclusions of Law, the district court stated "on one substantial item of damage
    Savage has been allowed for the CV 111 Conveyor (i.e., $62,330.00),
    prejudgment interest is obviously inappropriate." This statement clearly implies
    the district court found Savage Industries entitled to $62,330.00 in damages for
    the CV-111 conveyor. The record indicates the omission of this item from its
    Findings of Fact was merely a clerical error. See "Findings of Fact and
    Conclusions of Law," at 16-17 (district court's findings of fact skips from
    paragraph 17 to paragraph 19).
    -6-
    record, and all relevant law, we conclude American Pulverizer's appeal is without
    merit and should be denied.
    III. Analysis
    A. The CV-111 Conveyor
    American Pulverizer contends the district court's award of $62,330.00 for
    the CV-111 conveyor is based upon a misapplication of Utah law and is not
    supported by the evidence. 6 Ordinarily, we apply a clearly erroneous standard in
    reviewing a trial court's determination of the amount of damages resulting from a
    breach of contract. See Paramount Pictures Corp. v. Thompson Theaters, Inc.,
    
    621 F.2d 1088
    , 1091 (10th Cir. 1980).
    "We are not constrained by the clearly erroneous standard, however, when
    the trial court's computation of damages is predicated on a misconception
    of the governing rule of law. Bose Corp. v. Consumers Union of United
    States, Inc., 
    466 U.S. 485
    , 501 (1984) [further citations omitted]." Thus,
    in reviewing challenges to a trial court's determination of damages in a
    breach of contract case, we must distinguish between the challenge to the
    6
    We note Savage Industries asserts American Pulverizer's appeal should be
    dismissed because American Pulverizer failed to raise its arguments before the
    district court. We assume, without deciding, American Pulverizer properly
    presented its arguments to the district court.
    -7-
    computation of the amount from the challenge to the law applied in
    computing that amount.
    EDO Corp. v. Beech Aircraft Corp., 
    911 F.2d 1447
    , 1450 (10th Cir. 1990)
    (quoting Chaparral Resources, Inc. v. Monsanto Co., 
    849 F.2d 1286
    , 1289 (10th
    Cir. 1988)). Here, taking careful note of this distinction, we review de novo
    American Pulverizer's challenge to the law applied by the district court in
    computing damages, while we review American Pulverizer's challenge to the
    sufficiency of the evidence under the clearly erroneous standard.
    1. Trial Court's Application of Utah Law
    American Pulverizer first contends the trial court misapplied Utah law in
    awarding Savage Industries damages for the CV-111 conveyer. Essentially,
    American Pulverizer argues the district court improperly allowed Savage
    Industries to recover both the cost of the Canica System under a "cover" theory
    and the cost of the CV-111 conveyor under a "benefit of the bargain" theory.
    Such a recovery, argues American Pulverizer, is in direct contravention to Utah's
    enactment of the Uniform Commercial Code, which provides an aggrieved buyer
    may either elect to cover and recover the expenses it incurred in covering or it
    may recover damages for non-delivery based upon the benefit of the bargain.
    -8-
    Here, since Savage Industries chose to "cover," American Pulverizer contends it
    is only entitled to recover damages for the costs of acquiring and installing the
    replacement Canica System.
    Savage Industries, on the other hand, argues it is not precluded from
    recovering damages for the CV-111 conveyor because Savage Industries only
    effected a "partial cover" when it purchased and installed the Canica System.
    Unlike the design of the Zeigler System, the Canica System did not have a closing
    loop conveyor. Thus, according to Savage Industries, the purchase of the Canica
    System was merely a "partial cover," and does not bar Savage Industries from
    recovering the economic value of the CV-111 conveyor.
    Under Utah's enactment of the Uniform Commercial Code, where the seller
    of goods in a transaction fails to deliver or repudiates his obligation to do so, the
    buyer may effect cover and receive damages as measured by the difference
    between cover price and the contract price or recover the economic loss of a
    contract as measured by the difference between market price and the contract
    price. Utah Code Ann. §§ 70A-2-711-70A-2-713 (1990). In order to prevent
    double recovery, a buyer may recover the economic loss "only when and to the
    extent that the buyer has not covered." U.C.C. § 2-713 Official Comment 5. The
    -9-
    remedies set forth in Utah's Uniform Commercial Code "shall be liberally
    administered to the end that the aggrieved party may be put in as good a position
    as if the other party had fully performed." Utah Code Ann. § 70A-1-106.
    American Pulverizer has cited no Utah case law in support of its argument
    that the trial court erroneously applied Utah law in awarding Savage Industries
    damages for the CV-111 conveyor. Our review of relevant authorities indicates
    no Utah court nor any other court located in the Tenth Circuit has spoken on the
    issue of whether a buyer may recover "benefit of the bargain" damages in
    situations where the buyer has partially covered. Thus, we must turn to outside
    jurisdictions for guidance.
    In Mann & Parker Lumber Co. v. Wel-Dri, 
    579 F.2d 973
    , 975 (6th Cir.
    1978), the defendant contracted to sell kilns and lumber handling equipment to
    the plaintiff. Thereafter, the defendant repudiated the contract and the plaintiff
    purchased substitute kilns from a third-party. 
    Id. at 976
    . The district court
    denied the plaintiff damages for the defendant's failure to deliver and install the
    lumber handling equipment because the plaintiff had "still not acquired an
    inspection and grading system." 
    Id. at 977
    . On appeal, the Sixth Circuit
    disagreed, stating "we know of no principle of contracts that requires an
    -10-
    aggrieved buyer to purchase substitute goods with respect to each and every part
    of the contract in the event of a total breach of contract, as a condition precedent
    to an award of damages for that breach." 
    Id. at 979
    . Consequently, the Sixth
    Circuit remanded the case for the district court to determine the amount of
    damages resulting from the defendant’s failure to deliver and install the
    equipment. 
    Id. at 980
    .
    Similarly, in Interior Elevator Co. v. Limmeroth, 594, 
    565 P.2d 1074
    , 1075
    (Ore. 1977), the parties entered into a contract whereby the defendant agreed to
    sell the plaintiff 125,801 bushels of wheat. The plaintiff then entered a contract
    with a third-party to provide him with 125,000 bushels of wheat. 565 P.2d. at
    1076. After delivering 120,663 bushels of wheat to the plaintiff, the defendant
    informed the plaintiff he would not be able to supply the remaining portion of
    wheat due under the contract. 
    565 P.2d at 1076-77
    . The plaintiff then covered
    the balance of its contract with the third-party, and filed suit against the
    defendant. 
    565 P.2d at 1076-77
    . The trial court did not allow the plaintiff to
    recover the value of the remaining 801 bushels since the plaintiff did not cover
    this amount. 
    565 P.2d at 1079
    . The Oregon Supreme Court, relying on Comment
    5 to U.C.C. § 2-713, rejected the district court's determination, stating:
    the language emphasized in comment 5 ... makes it clear that the
    drafters of the code contemplated situations in which buyers would
    -11-
    only partially cover. This is precisely what occurred here. The
    plaintiff "covered" only enough to meet its contract obligation to
    Dreyfus. It would appear, therefore, that plaintiff would have been
    entitled to the actual cost of cover, if shown to be reasonable, plus
    damages measured under ORS 72.7130 as to the remaining 801
    bushels.... The fact that plaintiff did not cover the entire amount
    does not bar recovery under ORS 72.7130.
    
    565 P.2d at 1080
    . 7
    As the Oregon Supreme Court concluded in Limmeroth, we believe
    Comment 5 to § 2-713 of the Uniform Commercial Code indicates a buyer who
    has partially covered may also recover damages for economic loss pursuant to
    Utah Stat. Ann. § 70A-2-713 "to the extent he has not covered." Similar to the
    plaintiff in Limmeroth, Savage Industries was committed to perform under a
    contract with a third-party when American Pulverizer repudiated its contract with
    Savage Industries. In order to fulfill its obligations to the Sunnyside Facility,
    Savage Industries purchased and installed the Canica System. However, like the
    plaintiffs in Mann and Limmeroth, Savage Industries only effected a partial cover.
    The Canica crusher did not contain a closed loop configuration, which was part of
    the goods Savage Industries was entitled to under its contract with American
    7
    Oregon Rev. Stat. § 72-7130 is virtually identical to Utah Stat. Ann.
    § 70A-2-713. Similarly Oregon's statutory provisions concerning cover are
    indistinguishable from Utah Stat. Ann. §§ 70A-2-711-70A-2-712. See 
    Or. Rev. Stat. §§ 72.7110-72.7120
     (1995).
    -12-
    Pulverizer.
    As the plaintiff in Mann was permitted to recover damages for the lumber
    handling system and the plaintiff in Limmeroth was entitled to recover damages
    for the 81 bushels of wheat it did not cover, Savage Industries should be
    permitted to recover the economic value of the CV-111 conveyor. Such recovery
    is necessary to comply with Utah Code Ann. § 70A-106's purpose of putting the
    aggrieved party in as good a position as if the other party had fully performed.
    Moreover, if we were to overlook Comment 5's language and prohibit a party
    from recovering benefit of the bargain damages where it has only partially
    covered, we would create an additional hardship for an injured party who must
    cover to satisfy a third-party contract. In order to obtain full recovery, such a
    party would be forced to cover for the value of the entire contract regardless of its
    ability to pay for cover and regardless of the economic circumstances existing at
    the time of cover. We refuse to adopt such a strict interpretation of Utah Code
    Ann. §§ 70A-2-711-13, and we therefore conclude the trial court's determination
    that Savage Industries is entitled to the economic value of the CV-111 conveyor is
    proper and in accordance with Utah law.
    2. Sufficiency of the evidence
    -13-
    American Pulverizer also contends the trial court's damages award for the
    CV-111 conveyor is not supported by sufficient evidence. According to American
    Pulverizer, the record reveals Savage Industries had not purchased the CV-111
    conveyor as of the date of trial nor did it have any definite plans to purchase the
    equipment. American Pulverizer argues "Savage [Industries] should not be
    awarded damages on the basis of mere speculation that it will later obtain and
    install" the conveyor.
    Notwithstanding American Pulverizer's contentions, we believe Savage
    Industries presented sufficient evidence to enable it to recover damages for the
    CV-111 conveyor. In Mann, the Sixth Circuit determined the plaintiff was
    entitled to damages for the lumber handling equipment even though the plaintiff
    had not purchased this equipment. 
    579 F.2d. at 980
    . The Court determined an
    aggrieved buyer need not "purchase substitute goods with respect to each and
    every part of the contract in the event of a total breach." 
    Id. at 979
    .
    Similarly in Continental Sand & Gravel, Inc. v. K & K Sand & Gravel, Inc.,
    
    755 F.2d 87
    , 92 n.5 (7th Cir. 1985), the Seventh Circuit concluded under U.C.C.
    § 2-712, "damages based on cost of repair are recoverable regardless whether the
    repairs are actually undertaken." The court affirmed the award of damages for
    -14-
    estimated repair costs, explaining even "if the repairs are not made, the potential
    market value of the goods is reduced by an amount equivalent to the value which
    would have been added by repair." Id.
    Similar to the Sixth Circuit's determination in Mann and the Seventh
    Circuit's determination in Continental Sand, Savage Industries' failure to purchase
    the CV-111 conveyor does not bar it from recovering damages for the economic
    value of the conveyor. Savage Industries presented evidence at trial showing the
    parties contracted for the installation of a closed loop Zeigler System which
    would recirculate oversized material back through a refurbished double roll
    crusher until the material was reduced to the specified size. Following American
    Pulverizer's breach, Savage Industries partially covered by purchasing a Canica
    crusher which did not contain a closed loop system. In order to place Savage
    Industries in as "good a position as if the other party had fully performed,"
    Savage Industries is entitled to the economic value of the CV-111 conveyor
    pursuant to Utah Code Ann. § 70A-2-713. We thus affirm the trial court’s award
    of $62,330.00 damages for the CV-111 conveyor.
    -15-
    B. Additional Operating Costs
    The district court awarded Savage Industries $116,484.93 in damages for
    additional operating costs incurred as a result of American Pulverizer's failure to
    refurbish the double roll crusher by November 8, 1993. American Pulverizer
    contends the district court's award of additional operating costs was clearly
    erroneous because Savage Industries did not establish these costs were
    proximately caused by American Pulverizer's breach of the October 1993 contract.
    We disagree.
    "'Recovery of damages for a breach of contract is not allowed unless
    acceptable evidence demonstrates that the damages claimed resulted from and
    were caused by the breach.'" Highland Constr. Co. v. Union Pac. R.R. Co., 
    683 P.2d 1042
    , 1047 (Utah 1984) (quoting Boyajian v. United States, 
    423 F.2d 1231
    ,
    1235 (Ct. Cl. 1970)). The costs must be tied to the fault of the defendant, 
    id.,
     and
    a plaintiff may only recover those costs directly attributable to the defendant's
    breach. Boyajian, 
    423 F.2d at
    1235 (citing Saddler v. United States, 
    287 F.2d 411
    (Ct. Cl. 1961).
    Here, the October 1993 contract called for the installation of a closed loop
    Zeigler System which would recirculate oversized material back through a
    -16-
    refurbished double roll crusher until the material was reduced to the specified
    size. One of the main reasons the parties contracted for the Zeigler System was to
    eliminate the expense of having to use a front-end loader to move oversized
    material back into the system for crushing. The October 1993 contract required
    American Pulverizer to "[r]efurbish the Double Roll Crusher to meet OEM
    standards [by] November 8, 1993." American Pulverizer explicitly represented in
    the contract the refurbished double roll crusher would produce 175 tons per hour
    of crushed product, with at least 85% of the finished crushed product being 1/4
    inch or less.
    The record in this case clearly reveals American Pulverizer breached its
    contract with Savage Industries by failing to refurbish the double roll crusher. At
    trial, in support of its claims for damages, Savage Industries presented testimony
    from Shawn Reddington, Savage Industries' Project Manager for the Sunnyside
    Cogeneration Project. According to Mr. Reddington, "a mountain of oversized
    material" continued to build-up following American Pulverizer's failure to
    refurbish the double roll crusher. Mr. Reddington testified Savage Industries was
    compelled to expend additional operating expenses in order to handle this
    growing stockpile of oversized material. Specifically, Savage Industries brought
    in additional workers, operated a second front-end loader, and operated its front-
    -17-
    end loaders for two shifts instead of one. Mr. Reddington opined that Savage
    Industries would not have incurred any additional operating expenses if American
    Pulverizer had fulfilled its contractual obligation to bring the double roll crusher
    up to O.E.M. standards by November 8, 1993.
    From Mr. Reddington's testimony, we believe the trial court reasonably
    could have concluded American Pulverizer's breach of contract proximately
    caused Savage Industries to sustain additional operating costs. If American
    Pulverizer had performed as required under its contract, the Zeigler System would
    have been installed. The Zeigler System would have produced 175 tons per hour
    of crushed product, and recirculated oversized material back through the system,
    eliminating the time and expense of using a front-end loader to haul the oversized
    product back into the system. However, since the Zeigler System was not
    installed, "a mountain of oversized product" accrued, and, according to Mr.
    Reddington, Savage Industries was forced to incur extra costs for labor and
    equipment to deal with this product. Clearly, Savage Industries presented
    sufficient evidence from which the trial judge reasonably could have concluded
    Savage Industries' additional operating expenses were directly attributable to
    American Pulverizer's breach. We therefore affirm the district court's order and
    judgment awarding damages to Savage Industries for additional operating
    -18-
    expenses.
    III. CONCLUSION
    For the reasons stated above, we AFFIRM the district court's damages
    awards of $62,330.00 for the CV-111 conveyor and $116,484.93 for additional
    operating costs.
    Entered for the Court:
    WADE BRORBY
    United States Circuit Judge
    -19-
    No. 95-4159, SAVAGE INDUSTRIES, INC., Plaintiff-Appellee, versus
    AMERICAN PULVERIZER COMPANY, Defendant-Appellant.
    GODBOLD, Senior Circuit Judge, concurring in part and dissenting in part:
    I concur except with respect to damages of $62,330 that appear to have
    been awarded for a conveyor that plaintiff was found to be entitled to but has not
    yet purchased. On this issue I would reverse or, at a minimum, vacate and
    remand.
    As I understand the facts -- and they are not easy to understand -- there are
    several phases in the history of this case.
    Phase 1:      Defendant agreed to install a double-roll crusher. It was not
    satisfactory because it produced an excess of oversized material.
    Phase 2:      The parties agreed on a substitute "closed loop" system that
    would recirculate oversized crushed material back into the system to be crushed
    again. Soon thereafter the parties realized that the proposed closed loop system
    would not produce sufficient output of materials (Opinion of this court, Mss. p.
    3).
    Phase 3:      The parties then agreed to install the "Zeigler system," and an
    agreement for this was executed. It was agreed that defendant would furnish
    equipment for the Zeigler system, including a conveyor that would recirculate
    oversized material back into the system for recrushing. To implement this
    agreement, plaintiff bought a Canica crusher, which plaintiff, in its proposed
    finding 9, agrees was a "cost effective alternative" to the original crusher. It has
    been awarded damages for the cost of the Canica.
    Phase 4: As an incident of the Zeigler system plaintiff installed a
    recirculating system to recirculate product back through the crusher. The
    requirement to recirculate oversized material was met. Plaintiff's proposed
    finding 10 reads:
    10. In order to achieve the output contemplated by the parties
    for the Zeigler System, as set forth in paragraph 9 of the Contract,
    Savage installed a system for recirculating oversized produce back
    through the Canica crusher. The system achieved the same result as
    the Zeigler System was intended to achieve, but did so with fewer
    conveyors and screens than were called for in the Zeigler System.
    The Canica crusher was installed in May 1994. For some five to six
    months before that time the recirculating system in place was producing an excess
    of oversized crushed material. Plaintiff claimed that the excess required it to
    move materials by front-end loader, which increased its expenses. Plaintiff was
    awarded $116,484.93 for this expense. After May 1994 the Canica crusher was
    fully operative, and plaintiff has claimed no damages from costs of moving excess
    oversized material thereafter.
    Several problems are presented by this court's decision.
    It is not clear that plaintiff suffered any economic loss after May 1994.
    The $62,330 is the cost of a new conveyor to move material through the
    recirculating system as installed. Plaintiff says it will enable it to make the
    system into a closed loop system, and this court agrees that plaintiff is entitled to
    -2-
    the cost of a conveyor to achieve that design. But it is not clear that plaintiff is
    entitled to the components of a closed loop design. It is not clear from the
    evidence and the district court's findings whether the recirculating system, as
    installed, is the equivalent of a closed loop design. It is not disputed that the
    recirculating system worked as to volume of output. But, with respect to quality,
    the evidence is not clear to me, nor are the district court's findings. Plaintiff
    claimed damages for a period to May 1984, when the Canica crusher was
    installed, because the system produced an excess of oversized material that had to
    be moved with front-end loaders. It was awarded those damages. The situation
    after May 1994 is cloudy. For that period plaintiff claimed no damages arising
    from excess of oversized material. Indeed plaintiff says that the Canica crusher
    "achieved the same result as contemplated." Plaintiff was entitled to show that
    after May 1994 the recirculating system, as installed, including the Canica
    crusher, was not the equivalent of a closed loop design, in expected life, cost of
    repairs, or some other similar way. No such deficiency has been proved.
    The award of $62,330 is not supported by adequate district court findings.
    First, this court holds, in footnote 5, that the absent findings are implied and were
    omitted through clerical error, and it infers an intent by the district court to award
    the $62,330. In another case this action by an appellate court might be
    appropriate. In this case, in view of the considerations I have set out, this is not
    -3-
    appropriate. Second, the district court found that plaintiff "properly covered
    APCO's breach of the contract." (Finding 4.) This court, in a finding essential to
    its decision and without explanation, holds that plaintiff "only effected a    partial
    cover" and is entitled to a balance of $62,330.          Moreover, the fact situation is
    further clouded by the question whether plaintiff has any need for another
    conveyor. The Zeigler system called for five new conveyors. Savage installed
    instead the recirculating system that, it says, required only two new conveyors. It
    purchased and installed one new conveyor. In its proposed finding 11 H(1)
    plaintiff says: "In order to eliminate the need for four of the conveyors
    contemplated under contract, Savage relocated and refurbished a conveyor from
    the original crusher system." It is not clear why Savage, having met the need for
    four conveyors by relocating equipment and, having purchased one new one, has
    not met the requirement for five.
    This case is different from   Mann & Parker Lumber Co. v. Wel-Dri       , 
    579 F.2d 973
     (6th Cir. 1978), and    Interior Elevator Co. v. Limmeroth     , 
    565 P.2d 1074
    (Or. 1977) (en banc). In    Mann & Parker the seller contracted to supply dry kilns
    and lumber handling equipment but failed to do so. The purchaser sued. The
    district court misapplied a liquidated damage provision as it related to the kilns,
    and the court of appeals remanded for redetermination of those damages. 
    579 F.2d at 979
    . As to lumber handling equipment, the district court denied damages
    -4-
    because the purchaser had not purchased complete substitute systems. This was
    remanded, on the ground the purchaser was not required to purchase substitute
    goods for every part of the contract.   
    Id.
     There was no issue of whether a
    different and substituted lumber handling system performed the same as the
    system contracted for, indeed there was no substitute system.
    In Interior Elevator the seller agreed to supply 125,801 bushels of wheat
    but breached after delivering less than that. Purchaser covered to the extent of
    125,000 bushels that it had contracted to sell to a third party. The district court
    denied recovery for the 801 bushels. The court of appeals reversed, holding that
    the fact that purchaser did not cover the entire amount did not bar recovery. 
    565 P.2d at 1080
    . The purchaser suffered an economic loss of the discrete item
    consisting of 801 bushels. There was, obviously, no issue of whether 25,000
    bushels had the same economic value as 25,801 bushels.
    I would reverse the award of $62,330 for a conveyor never purchased or, at
    a minimum, I would remand this issue to the district court to be addressed again
    and for entry of findings that would remove the uncertainties and differences in
    understanding that divide the members of this panel.
    -5-