United States Ex Rel. Belt Con Construction, Inc. v. Metric Construction Co. , 314 F. App'x 151 ( 2009 )


Menu:
  •                                                                         FILED
    United States Court of Appeals
    Tenth Circuit
    UNITED STATES COURT OF APPEALS
    February 25, 2009
    TENTH CIRCUIT
    Elisabeth A. Shumaker
    Clerk of Court
    UNITED STATES OF AMERICA for
    the use of BELT CON
    CONSTRUCTION, INC.,
    Plaintiff/Counter-Defendant/
    Appellee,
    v.                                                      No. 07-2091
    METRIC CONSTRUCTION CO.,                     (D.C. No. CIV-02-1398-JB/LAM)
    INC.; SAFECO INSURANCE                              (D. New Mexico)
    COMPANY OF AMERICA,
    Defendants/Counter-Claimants/
    Appellants.
    ORDER AND JUDGMENT *
    Before BRISCOE, TYMKOVICH, and GORSUCH, Circuit Judges.
    Belt Con Construction, Inc. (“Belt Con”) brought a Miller Act action
    pursuant to 40 U.S.C. §§ 270a–270d against Metric Construction Co. Inc.,
    (“Metric”) arising out of contracts to construct a Federal Law Enforcement
    *
    This order and judgment is not binding precedent, except under the
    doctrines of law of the case, res judicata, and collateral estoppel. It may be cited,
    however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th
    Cir. R. 32.1.
    Training Center Campus (“Training Center”) in New Mexico. Metric responded
    by filing counterclaims. After a bench trial and an order addressing Metric’s
    motion to amend judgment, the United States District Court for the District of
    New Mexico awarded Belt Con damages and concluded Belt Con was the
    prevailing party. Metric now appeals the district court’s denial of two claims
    made in its motion to amend judgment: (1) to reduce Belt Con’s damage award by
    the value of the roof warranties Belt Con did not provide; and (2) to apportion to
    Belt Con damages from delays during construction. Metric contends that the
    district court correctly determined that Belt Con failed to satisfy its contractual
    obligation to provide roof warranties, but wrongly decided that there was
    insufficient evidence to determine the value of the warranties. As regards
    damages caused by delay, Metric contends that the district court wrongly
    determined that any delays attributable to Belt Con were concurrent with delays
    caused by others and that given the evidence presented, concurrent delays could
    not be apportioned. We have jurisdiction pursuant to 
    28 U.S.C. § 1291
    , and
    affirm.
    I
    Metric contracted with the General Services Administration (“GSA”) to
    build dormitories, and physical training and security buildings. Metric also
    contracted with the GSA to build two firing ranges. Metric subcontracted with
    Belt Con for masonry work on the dormitories and physical training building.
    2
    The construction project was not completed on time.
    As a result of the construction delays, GSA withheld liquidated damages
    from its contract payment to Metric. Metric disputed this decision and filed
    claims against the United States, contending that GSA caused the delays. Metric
    and GSA resolved these claims in a settlement agreement. The terms of the
    settlement agreement include the following language:
    The GSA maintains that it properly withheld and is entitled to
    liquidated damages on the Dormitory project and the Range project.
    Metric concedes some liability for the late completion of the
    projects, but maintains that it is entitled to compensation for some
    delay and changed or extra work performed by Metric on the
    projects.
    Aplt. App’x Vol. II at 280.
    After the settlement between GSA and Metric, Belt Con filed the present
    action. Belt Con alleged that Metric failed to pay Belt Con all of the money it
    owed to Belt Con under its subcontract and that Belt Con was entitled to
    additional compensation for delays and extra work. Among other defenses,
    Metric responded that Belt Con failed to complete the contracted work on
    schedule. Additionally, Metric brought a counterclaim against Belt Con for
    clean-up costs Metric incurred after Belt Con completed its work. Metric also
    argued that any award to Belt Con should be reduced by the value of the roof
    warranties Belt Con failed to provide, and by the value of the liquidated damages
    GSA assessed against Metric that were in fact caused by Belt Con’s delay.
    3
    The district court held a four-day bench trial. The district court found that
    California law governed the contract between Metric and Belt Con. Applying
    California law to its factual findings, the district court determined that Belt Con
    was entitled to the unpaid balance on the contract, plus interest. The district
    court, however, did not grant Belt Con’s requests for delay damages. Regarding
    Metric’s counterclaims, the district court awarded Metric its requested clean-up
    costs. Despite finding that the contract required Belt Con to provide roof
    warranties and that Belt Con failed to provide them, the district court concluded
    that “Metric has not proved by a preponderance of the evidence damages for Belt
    Con’s failure to provide the roof warranties.” Aplt. App’x Vol. I at 155.
    Similarly, the district court denied Metric’s request for liquidated damages
    resulting from Belt Con’s delays. As regards attorney fees and costs, the court
    found that Belt Con was the prevailing party.
    In response to the district court’s Findings of Fact and Conclusions of Law
    entered after the bench trial, Metric filed a motion to amend judgment. Metric
    asked the district court to apportion some of the delay to Belt Con, and offset the
    contract balance awarded to Belt Con by the value of the roof warranties and the
    “pipe identification work” that Belt Con did not provide. Aplt. App’x Vol. I at
    219. The court reduced the award by the value of the pipe identification work,
    corrected scriveners errors in its prior findings, and denied the balance of
    Metric’s motion. Metric now appeals, arguing that the district court erred by not
    4
    reducing Belt Con’s award by the value of the roof warranties and by not
    apportioning any delay to Belt Con.
    II
    A.    Roof Warranties
    Metric contends the district court erred as a matter of law in its rulings
    regarding the roof warranties. It appears that Metric agrees with the district
    court’s findings of fact on this issue. Because Metric’s challenge involves only
    the application of legal principles to undisputed facts, our review is de novo. See
    Hollern v. Wachovia Sec., Inc., 
    458 F.3d 1169
    , 1175 n.4 (10th Cir. 2006)
    (applying this standard in the context of attorney fees).
    After the bench trial, the district court addressed the roof warranties issue
    in its Findings of Fact and Conclusions of Law. The court found that GSA
    requested roof warranties from Metric, who in turn in its contract with Belt Con
    required Belt Con to provide them. Belt Con did not provide the roof warranties
    to Metric. In its later Memorandum Opinion and Order, the court noted that Belt
    Con stated “it was not going to provide the warranties until Metric paid Belt Con
    all the money to which Belt Con felt it was entitled.” Aplt. App’x Vol. I at 231.
    Metric asked other roofing contractors to provide warranties, but they declined to
    warrant another contractor’s work. 
    Id.
     149–50; 154–55. The district court later
    clarified that “Metric was able to obtain only one quotation for a roof warranty
    [from another roofer] in the amount of $118,000.” Id. at 231. Although the
    5
    district court acknowledged that “Metric remains liable to the GSA for any
    warranty items that may arise relating to the roof,” the district court found that
    “[t]he GSA has not called on Metric to honor the warranty, and Metric has not
    performed any warranty work.” Id. at 154–55; 232. “[T]he GSA called Belt Con
    directly several times to repair the roof . . . Belt Con responded to each call and
    performed work on the roof even when Belt Con felt that the warranties did not
    cover the repairs.” Id. at 232. In the Memorandum and Opinion addressing
    Metric’s motion to amend, the district court considered Metric’s damages
    regarding roof warranties to be the difference between Metric’s settlement amount
    with the GSA, and the hypothetical amount that Metric would have requested if
    the warranties were provided. Id. The district court found that “Metric does not
    know how much less it took in settlement because of the warranty issue.” Id.
    The district court concluded the testimony regarding the value of the warranties
    that was based upon another roofer’s offer was “speculative and conjecture.” Id.
    at 155; 256. After trial and after considering Metric’s motion to amend, the
    district court concluded that “Metric has not . . . proved that it has been
    damaged.” Id. at 155; 256–57 (“Metric failed to demonstrate that it suffered any
    damages.”). The district court denied Metric’s motion to amend judgment based
    upon Belt Con’s failure to provide the roof warranties.
    Metric agrees with the district court’s factual findings, but contends that
    the district court misapplied the law regarding contractual damages. First, Metric
    6
    argues that the district court “misapplied the ‘reasonable certainty’ rule and
    confused the distinction between uncertainty as to amount with uncertainty of
    existence.” Aplt. Br. at 21. To support this argument, Metric relies on the facts
    that it contracted with Belt Con for the roof warranties, did not receive them, and
    remains liable to the GSA for “roof warranty issues.” Id. Metric also argues its
    failure to receive the roof warranties was the present loss of a contractual right,
    and not “future damages” as characterized by the district court. Second, Metric
    argues that if the amount of damages—the value of the roof warranties—is
    difficult to calculate, any disadvantage arising from that difficulty should be
    borne by Belt Con and not Metric. Similarly, Metric argues that because of the
    nature of Belt Con’s breach, the evidence Metric presented was the best available
    evidence and provides a sufficient basis for the court to approximate Metric’s
    damages. Metric concludes “[c]ertainly there is no evidence in the record to
    suggest that the value of the roof warranties was zero[; i]t is illogical to presume
    the warranty has no value where warranties are present protection against
    unknowns and uncertain future liabilities.” Aplt. Br. at 29. 1
    1
    Metric also argues that the district court could have created an equitable
    remedy forcing Belt Con to deliver the roof warranties. Belt Con responds that
    this argument was not presented to the district court. In its reply, Metric does not
    dispute this assertion or reference where in the record this argument was
    previously made. Absent extraordinary circumstances, we will not consider
    arguments raised for the first time on appeal. Governor of Kan. v. Kempthorne,
    
    516 F.3d 833
    , 841 (10th Cir. 2008) (citation omitted.)
    7
    We agree with the district court that California law governs this contract.
    We look to the conflict of law rules of New Mexico, the forum state, to determine
    which state’s laws control. Mountain Fuel Supply v. Reliance Ins. Co., 
    933 F.2d 882
    , 887–88 (10th Cir. 1991). Unless it would result in a violation of
    “fundamental principles of justice,” New Mexico courts apply the law of the state
    where the parties executed the contract. Demir v. Farmers Tex. County Mut. Ins.
    Co., 
    140 P.3d 1111
    , 1113–14 (N.M. Ct. App. 2006) (“When differences between
    the law of the forum state and the law of the state where the contract was
    executed concern only contract interpretation, we will apply the law of the state
    where the parties entered the contract.”). Belt Con and Metric executed the
    contract at issue in California. Aplt. App’x Vol. I at 151. Neither party disputes
    that California law applies.
    Under California law, every contract action requires the establishment of “a
    causal connection between the breach and the damages sought.” Thompson Pac.
    Const., Inc. v. City of Sunnyvale, 
    66 Cal. Rptr. 3d 175
    , 188 (Cal. Ct. App. 2007).
    In the context of building construction, the amount of damages is the difference
    between the contract price and the price of completing the contract work.
    Fairlane Estates, Inc. v. Carrico Const. Co., 
    39 Cal. Rptr. 35
    , 40 (Cal. Ct. App.
    1964). Damages that are not causally connected with the breach of a contract are
    not recoverable. Patent Scaffolding Co. v. William Simpson Const. Co., 
    64 Cal. Rptr. 187
    , 191–92 (Cal. Ct. App. 1967). Damages that result from a liability to a
    8
    third party are not recoverable unless the party seeking the damages “proves to a
    reasonable certainty that the liability could and would be enforced by the third
    party” or that the party seeking the damages “could and would satisfy the
    obligation.” Green Wood Indus. Co. v. Forceman Int’l Dev. Group Inc., 
    67 Cal. Rptr. 3d 624
    , 632 (Cal. Ct. App. 2007).
    Accordingly, the existence of a mere liability is not necessarily the
    equivalent of actual damage. This is because the fact of damage is
    inherently uncertain in such circumstances. The facts that a third
    party has demanded payment by the plaintiff of a particular liability
    and plaintiff has admitted such liability are not, by themselves,
    sufficient to support an award of damages for that liability, because
    that third party may never attempt to force the plaintiff to satisfy the
    alleged obligation, and plaintiff may never pay the obligation.
    
    Id. at 633
     (stating that such reasoning applies whether the claim sounds in
    contract or tort).
    Metric attempts to base its alleged damages on the district court’s finding
    that Metric remains liable to the GSA for roof warranty issues. Metric argues that
    its damages should be the present value of the protection from future liability.
    Aplt. Br. at 23 (“[As] a direct result of Belt[]Con’s refusal to furnish the roof
    warranties, Metric has lost the protection against possible liability that it
    contracted for.”). To support this argument, Metric cites the California Supreme
    Court’s opinion in Caminetti v. Manierre, 
    142 P.2d 741
    , 745 (Cal. 1943), for the
    statement: “The courts are not so impotent that they will permit a total loss of
    such a right merely because of a claimed uncertainty or difficulty in determining
    9
    the extent to which the insured may be damaged by the breach of the promise.”
    The California Supreme Court, however, went on to state, “Of course, the proof
    must establish with reasonable certainty and probability that damages will result
    in the future to the person wronged. And the nature of the damages should be
    ascertainable.” Caminetti, 142 P.2d at 745 (citations omitted).
    The requirement of proof of damages with “reasonable certainty and
    probability that damages will result in the future” is where Metric’s claim falls
    short. Id. Metric has not provided any evidence related to the probability that
    GSA will hold it liable for the roof warranties. Metric’s only evidence related to
    the value of the roof warranties consists of hearsay testimony that one roofer
    would provide substitute roof warranties for the amount of $118,000, which
    Metric’s president was unsure he would accept, and that if Metric had the
    warranties, it may have tried to settle with the GSA for a greater amount. The
    district court questioned the credibility and reliability of this evidence. On the
    other hand, there was evidence that the GSA called Belt Con for roof repairs and
    that Belt Con responded in each instance and provided the work requested.
    Because there is no evidence indicating a probability that GSA would hold Metric
    liable, and there is evidence that GSA has not held Metric liable, the existence of
    Metric’s liability to the GSA is insufficient to establish actual damages. We
    conclude that the district court did not err in denying Metric’s motion to reduce
    Belt Con’s award by the value of the roof warranties.
    10
    B.    Apportioning the Delays
    Metric also challenges the district court’s decision to not attribute any of
    the construction delays to Belt Con. Metric challenges the district court’s legal
    analysis and its factual conclusions. We review issues of law de novo and the
    challenged fact findings for clear error. Hjelle v. Mid-State Consultants, Inc.,
    
    394 F.3d 873
    , 879 (10th Cir. 2005) (“If a finding of fact, we review only for clear
    error . . . ; but if an issue of law, our review is de novo.”) (citations omitted).
    After the bench trial, the district court denied Metric’s request for
    liquidated damages resulting from delays Metric attributed to Belt Con. The
    district court determined that it would not grant Metric’s request without evidence
    of the amount of delay attributable to Belt Con. The district court found, “Metric
    and other subcontractors delayed the FLETC project concurrently with Belt Con.”
    Aplt. App’x Vol. I at 155. The district court also noted, “because Metric did not
    prove by a preponderance of the evidence how much, if any, delay should be
    attributed to Belt Con, any award of damages would be speculative.” 
    Id.
    In the Memorandum and Opinion addressing Metric’s motion to amend
    judgment, the district court expanded upon its factual findings and the legal basis
    for its conclusion. The district court stated that the project’s scheduling created
    problems during construction and hindered the court’s efforts to trace the causes
    of the delays. Aplt. App’x Vol. I at 222–23. The district court also found that
    “two of the largest culprits of delay—the GSA and R&R Concrete Contractors,
    11
    Inc. (“R&R[”])—[were] not parties to the case.” Id. at 222. Although Metric and
    Belt Con presented expert testimony regarding the project’s time line and the
    necessary order of benchmarks—the critical path 2—the district court “did not find
    [Metric’s expert’s] methodology, evidence, or testimony reliable.” Id. at 224.
    “Both experts that testified at the trial apportioned the construction delays
    between Belt Con and R&R.” Id. at 226.
    According to the findings of the district court, the critical path began on the
    first floor of “Building 21” and continued through Building 19. Id. at 224. “Belt
    Con admits that its masonry work on [Building 21’s first] floor was completed
    two days late.” Id. at 228. In its analysis regarding this work, the district court
    also considered that Metric did not deliver the entire first floor, as provided in the
    schedule, when Belt Con began working. Metric did not claim any delays
    associated with Belt Con’s work on Building 19’s first floor. Regarding Belt
    Con’s work on Building 19’s second floor, Belt Con’s expert “determined that
    Belt Con completed the work eight days late,” but that “there were concurrent
    delays” attributable to Belt Con and R&R. Id. at 230. When asked to clarify how
    the delays were concurrent, Belt Con’s expert stated, “They’re running—They’re
    both delaying the work. They are not exactly at the same time. Both of them
    2
    A delay along the critical path delays completion of the entire project.
    Morrison Knudsen Corp. v. Fireman’s Fund Ins. Co., 
    175 F.3d 1221
    , 1231–32
    (10th Cir. 1999).
    12
    caused additional delay . . . .” 
    Id.
     The district court noted that Belt Con’s expert
    did not quantify what portions of the delay were concurrent and what portions
    were sequential. On the other hand, the district court also found that “Metric’s
    expert . . . concluded that [the delays related to Building 19’s second floor] did
    not delay the project.” 
    Id.
     Regarding Building 19’s third floor, the district court
    found that Belt Con’s expert testified that the delays were concurrent.
    Based on these expanded findings, the district court again declined to
    apportion the delays and reduce the amount of damages awarded to Belt Con.
    The district court stated, “Metric is correct that the Court can, where appropriate
    and the evidence so supports, apportion delay . . . The Court will not hesitate to
    undertake that task where appropriate. Metric has not, however, with its factual
    presentation or its legal arguments, convinced the Court that it should do so in
    this case.” Id. at 244. Although the district court acknowledged that California
    law allowed courts to apportion damages for sequential delays, the court found
    that the delays were not sequential. The district court rejected Metric’s
    contentions that the delays at issue were sequential, reasoning “the Court cannot
    determine that Belt Con’s delays were sequential when there was never a reliable
    project schedule in place.” Id. at 254.
    Significantly, the district court questioned Metric’s credibility in its effort
    to attribute fault for the delays to Belt Con. Id. at 225 (“Metric’s shifting position
    undercut its credibility with the Court.”). Before this action began, Metric
    13
    submitted a claim to the GSA with a delay analysis that attributed all of the delay
    to the GSA. This analysis consisted of a “twenty-page, single-spaced report with
    thirty-five pages of exhibits” and according to Metric’s president was “made in
    good faith . . . and complete to the best of [his] knowledge and belief.” Id. at
    248. Based on this, the district court determined that “Metric did not equitably
    allocate delay damages in good faith, but arrived at [its expert’s] analysis for
    purposes of litigation.” Id. at 249. The district court concluded its analysis of the
    allocation of delays by agreeing with Metric’s initial analysis that the GSA
    caused all of the delays directly or indirectly.
    Metric raises four arguments challenging the district court’s conclusions
    regarding the allocation of damages caused by delay. First, Metric argues that
    California law favors enforcing liquidated damages clauses and apportioning
    delay damages. Second, Metric contends that courts can apportion sequential and
    concurrent delays both as a matter of law, and as a result of a provision in the
    contract (Article 8) between Metric and Belt Con. Third, Metric asserts, “There
    was sufficient evidence presented . . . to allow the trial court to allocate the
    delay.” Aplt. Br. at 38. Lastly, Metric argues that some of the delays were
    sequential. Belt Con responds that the district court’s findings were correct,
    highlighting Metric’s prior analysis attributing the delays to the GSA.
    California courts apportion contractual liquidated damages “where delays
    in construction projects have been caused by both the owner and by the
    14
    contractor.” Stop Loss Ins. Brokers, Inc. v. Brown & Toland Med. Group, 
    49 Cal. Rptr. 3d 609
    , 621 (Cal. Ct. App. 2006) (citing Jasper Constr., Inc. v. Foothill
    Junior Coll. Dist., 
    153 Cal. Rptr. 767
     (Cal. Ct. App. 1979); Nomellini Constr. Co.
    v. California ex rel. Dep’t of Wat. Res., 
    96 Cal. Rptr. 682
     (Cal. Ct. App. 1971)).
    In Nomellini, the California Court of Appeals rejected the notion that “where
    delays are caused on both sides there is no way to ‘apportion damages[.]’” 
    96 Cal. Rptr. at 686
    . Instead, the California Court of Appeals reasoned that
    “[q]uantum of delay in terms of time is all that is being apportioned. That is an
    uncomplicated fact finding process.” 
    Id.
     Following Nomellini, the California
    Court of Appeals noted the importance of the contractual language allowing
    apportionment. Jasper, 
    153 Cal. Rptr. at 774
     (listing “because the contract
    contained an explicit provision allowing apportionment” and the distinctions
    between public and private contracts as the two reasons for applying
    apportionment).
    We are unaware of, nor does Metric provide, 3 California law addressing
    apportionment of concurrent delays. The reasoning of Nomellini suggests that
    California would not apportion concurrent delays, but such a determination is
    3
    Although Metric devotes several pages to its assertion that “Both
    Sequential and Concurrent Delay Can Be Apportioned,” the only legal support for
    this argument is a citation to a case from the United States Court of Federal
    Claims. As stated, because California is the place of execution for the contract,
    we apply California law unless it contravenes New Mexico public policy. Metric
    has not addressed apportionment of delays under New Mexico law.
    15
    unnecessary for our present analysis. Following the court’s direction in Jasper,
    we turn to the present contractual provision that addresses apportioning
    concurrent delays. Article 8 of the contract states in pertinent part:
    If delays are caused by more than one subcontractor, Contractor shall
    equitably allocate the damages for delay among the Contractor and
    those subcontractors responsible for the delay, and the Contractor’s
    decision as to the allocation shall be final and binding on all
    subcontractors as long as the decision is made in good faith.
    Aplt. App’x Vol. II at 261–62. The district court found that Metric did not
    allocate the damages in good faith, relying on Metric’s initial delay analysis that
    attributed all of the delay to the GSA. Although Metric does not argue that this
    finding is incorrect, Metric dismisses the “so-called ‘delay analysis’ [as] a
    document prepared by Metric’s counsel in litigation advocating the position of its
    client prior to any discovery.” Aplt. Reply Br. at 8. This argument does not
    nullify the district court’s conclusion that “Metric did not equitably allocate delay
    damages in good faith, but arrived at [its trial expert’s] analysis for purposes of
    litigation.” Aplt. App’x Vol. I at 249. Moreover, as noted by the district court,
    the contract “is silent . . . with regard to what happens if Metric’s allocation was
    not done in good faith.” Id. at 249.
    We conclude that the district court’s findings of fact and conclusions of
    law regarding the apportionment of damages in this case are correct. The court
    looked to the applicable contractual language and found Metric did not allocate
    concurrent damages in good faith. Consequently, we turn to Metric’s argument
    16
    that the delays were sequential, not concurrent.
    Metric bases its argument on the testimony of Belt Con’s expert. While
    testifying about the construction of Building 19, the expert had this exchange with
    counsel:
    A. On the second and third floor there are concurrent
    delays between the masonry and concrete work.
    Q. So does that mean that the concrete delay and the
    masonry delay are running at the same time, during the same
    period of time?
    A. No. They’re running—They’re both delaying the work.
    They are not exactly at the same time. Both of them caused
    additional delay to the floor construction.
    Aplt. App’x Vol. IV at 776. Metric concludes this argument by asserting, “If the
    delays are truly concurrent delays and are simultaneously caused by two
    subcontractors, each should bear a portion of the prime contractor’s delay damages
    . . . .” Aplt. Br. at 40.
    This testimony is insufficient for us to determine that the district court’s
    factual findings were clearly erroneous. The district court heard Metric’s expert
    testify that Belt Con’s work on the second floor of Building 19 was not part of the
    critical path. The district court found that “Belt Con’s expert testified that there
    were concurrent delays between the masonry and concrete [on the third floor of
    Building 19].” Aplt. App’x Vol. I at 247. Metric’s reference to a statement where
    Belt Con’s expert equivocated slightly does not establish that these findings were
    clear error. See Pencro Assocs., Inc. v. Sprint Spectrum, L.P., 
    499 F.3d 1151
    ,
    17
    1161–62 (10th Cir. 2007) (“[P]ointing to conflicting evidence inconsistent with the
    district court’s finding is insufficient, standing alone, to establish clear error, for
    every trial is replete with conflicting evidence, and in a bench trial, it is the district
    court, which enjoys the benefit of live testimony and has the opportunity to weigh
    firsthand to weigh credibility and evidence, that has the task of sorting through and
    making sense of the parties’ competing narratives.”) (quotation omitted). We
    conclude that the district court did not err in denying Metric’s motion to amend
    judgment to attribute some of the construction delay to Belt Con.
    III
    We affirm the judgment of the district court.
    Entered for the Court
    Mary Beck Briscoe
    Circuit Judge
    18
    07-2091, United States of America for the use of Belt Con Construction, Inc. v.
    Metric Construction Co.
    GORSUCH, J., Circuit Judge, concurring in part and dissenting in part.
    I fully concur in the court’s conclusion that Metric failed to adduce sufficient
    evidence about the value of the roof warranties Belt Con failed to supply. As the
    court notes, under California law a party must establish proof of damages with
    competent evidence affording “reasonable certainty.” Caminetti v. Manierre, 
    142 P.2d 741
    , 745 (Cal. 1943). In this case, however, the only evidence Metric
    proffered was hearsay, the credibility of which the district court understandably
    found insufficiently reliable.
    The court proceeds, however, to offer an additional basis for rejecting
    Metric’s roof warranty claim, holding that Metric was required as a matter of law
    to demonstrate GSA was likely to hold it liable for work subject to Belt Con’s
    (unproduced) warranties. But it is far from clear that California law holds
    insurance contracts to lack any recoverable value until and unless a claim under
    them is made or probable; indeed, such a conclusion appears at odds with the
    California Supreme Court’s decision in Caminetti. 1 In any event, I see no need to
    1
    In Caminetti, the California Supreme Court faced a case in which holders
    of noncancellable disability insurance policies sought damages from defendants
    for the fact that their policies were liquidated in a company restructuring. 142
    P.2d at 742-43. The defendants argued that the plaintiffs might never suffer
    damages because they might die before becoming disabled. The Court squarely
    rejected this argument, noting that “[t]he effect of that argument would be to
    render wholly valueless the noncancellable feature of the policy, a definite and
    concrete promise of the insurer.” Id. at 745. It continued “[t]hat the insureds will
    (continued...)
    reach such a legal holding, given Metric’s failure to adduce any competent
    evidence whatsoever of the warranties’ value.
    On the separate question of liability for delays, the parties before us, as well
    as the district court, recognized that there are two potential bases for holding Belt
    Con liable for delays it caused the project. First, Belt Con could be held liable
    under a contractual provision providing that a subcontractor would be responsible
    for delays allocated to them by Metric so long as the allocation was “made in good
    faith.” Aplt. App. at 139-140. And second, Belt Con could be held liable as a
    matter of California law. The district court held that Metric did not allocate delays
    in “good faith,” and therefore proceeded to consider whether, as a matter of law, it
    could perform the allocation itself. It held it could not, concluding that the delays
    at issue were concurrent, not sequential, and that California law did not permit the
    allocation of concurrent delays.
    Like the court today, I find the district court did not clearly err in concluding
    that Metric did not allocate delays in good faith and in finding that the delays were
    concurrent and not sequential. Unlike the court, however, I do not think these dual
    1
    (...continued)
    be damaged in the instant case is clear. They have forever lost the protection
    against possible loss which was secured to them by their policies. They have lost
    the chance they had to be specifically benefitted by that protection.” Id. at 746.
    The Court then proceeded to state that the preferred damage award would be to
    grant the plaintiff damages according to the “replacement rule,” namely the cost
    of similar insurance from another insurer. Id. at 747.
    -2-
    determinations end the matter. There remains the question whether California law
    permits the court to allocate concurrent delays. The court concludes that the
    reasoning of Nomellini, a 1971 case from the California Court of Appeals,
    “suggests that California would not apportion concurrent delays,” but that “such a
    determination is unnecessary” for its present analysis. Maj. Op. at 15-16 (citing
    Nomellini Constr. Co. v. California, 
    19 Cal.App.3d 240
    , 246 (1971)). With respect
    to my colleagues, I believe such a determination, one way or the other, is necessary
    to resolve this case – otherwise we are left with a conclusion by the court that
    delays were concurrent, but no explanation why those delays cannot be
    apportioned.
    Moreover, I read California law as permitting the allocation of concurrent
    delays of the type encountered in this case. Nominelli suggests as much, where the
    court stated that:
    categorical statements that where delays are caused on both sides there is no
    way to ‘apportion damages’ are an absurdity. . . . Quantum of delay in terms
    of time is all that is being apportioned. That is an uncomplicated fact finding
    process. That is what courts are for.
    
    19 Cal.App.3d at 246
    . While I can envision a case in which delays attributable to
    distinct parties are so intertwined that it is impossible to separate them
    meaningfully, this is not such a case. Both parties presented experts that did
    apportion the delays attributable to Belt Con – the experts differed only as to the
    number of attributable days of delay, and neither party argued to the district court
    -3-
    that apportionment of delays was an impossibly complicated task. And if the fact
    finding in this case was not impossibly complicated for the parties, I fail to see how
    it was impossibly complicated, as a matter of law, for the court. Indeed, resolution
    of factually intensive disputes “is what courts are for.” Id. at 246; cf. Robinson v.
    United States, 
    261 U.S. 486
    , 489 (1923) (upholding damage award and stating
    “[h]ere the fault of the respective parties was not so clearly distributed in time, and
    it may have been difficult to determine, as a matter of fact, how much of the delay
    was attributable to each. But the Court of Claims has done so in this case.”).
    -4-