    MILCOR I, LLC,
    Plaintiff - Appellant,
    v.                                                         No. 18-8000
    (D.C. No. 2:16-CV-00163-NDF)
    SANDY K. LUERS, individually; ERIC                        (D. Wyoming)
    CARR in his official capacity as Riverton
    Community Development Director; DAVE
    PASKETT, individually and in his official
    capacity as Riverton Building Inspector;
    GARY W. BURNETTE, individually;
    TERRY BETTS in his official capacity as
    Riverton Construction Board of Appeals
    Chairman; JOHN L. BAKER, individually;
    RICHARD P. GARD in his official
    capacity as Riverton Mayor; MARTIN
    CANNAN, LEE MARTINEZ, HOLLY
    JIBBEN, SEAN PETERSON, individually;
    MIKE BAILEY individually and in his
    official capacity as Riverton City Council
    Member; KYLE LARSON, REBECCA
    SCHATZA, KARLA BORDERS, TIM
    HANCOCK, in their official capacities as
    Riverton City Council Members,*
    Defendants - Appellees.
    _________________________________
    *
    When a public officer who is a party to an appeal ceases to hold office, “[t]he
    public officer’s successor is automatically substituted as a party.” Fed. R. App. P.
    43(c)(2). For those Defendants-Appellees who no longer hold office, we have
    substituted their successors as to the official-capacity claims.
    ORDER AND JUDGMENT**
    _________________________________
    Before LUCERO, McHUGH, and MORITZ, Circuit Judges.
    _________________________________
    Milcor I, LLC (“Milcor”) seeks damages from the City of Riverton, Wyoming
    (“City”) and several City officials under 42 U.S.C. § 1983 for violations of
    procedural and substantive due process, and a state breach-of-contract claim. The
    district court granted summary judgment for the defendants on Milcor’s due process
    claims and dismissed the state contract claim without prejudice. Milcor now
    challenges the district court’s grant of summary judgment, which we affirm.
    I.     BACKGROUND
    Milcor owned and operated a Days Inn in Riverton, Wyoming. In 2013, Milcor
    proposed to remodel the hotel—at that time a single two-story structure where all the
    doors to motel rooms opened directly to the outside—by adding an adjacent two-
    story structure that would connect to the original structure by an enclosed corridor.1
    In support of the proposed renovations, Milcor submitted building plans to the City.
    Citing § 903.3.1 of the 2006 International Building Code (“IBC”), these plans stated
    that a fire sprinkler system would be installed consistent with National Fire
    Protection Association (“NFPA”) Standard 13. The plans also stated, pursuant to IBC
    **
    This order and judgment is not binding precedent, except under the doctrines
    of law of the case, res judicata, and collateral estoppel. It may be cited, however, for
    its persuasive value consistent with Federal Rule of Appellate Procedure 32.1 and
    Tenth Circuit Rule 32.1.
    1
    The proposed renovations also included the addition of a business area.
    2
    907.2.2, that no fire alarm system would be installed in the business area; however,
    the plans did not say whether a fire alarm system would be installed in the new
    guestrooms.
    The City granted Milcor a building permit for the renovations, along with a
    “plan review report” advising that “[f]ire sprinkler system plans shall be submitted
    for review prior to installation” and that “[s]moke alarms shall be installed per IBC
    Section 907.2.10.” Suppl. App. at 105–07. The report also stated that the “plan
    review . . . represents a list of corrections necessary to comply with the requirements”
    of the relevant building codes, that “[t]he approval of plans and specifications does
    not permit the violation of any section of federal, state, or local regulations,” and that
    [t]he issuance of a permit based on plans, specifications, and other data
    shall not prevent the City of Riverton from thereafter requiring the
    correction of errors in said plans, specifications and other data, or from
    preventing building operations being carried on when in violation of any
    federal, state or local ordinance, rule or regulation.
    
    Id. at 107.
    But the report neither mentioned the need to install a fire alarm system nor
    referenced any section of the IBC governing fire alarm systems.
    In June 2014, Milcor submitted fire sprinkler system plans to the City that the
    City approved. In the same month, Dave Paskett, a city inspector, performed a
    “rough-in inspection” and raised the need to install a fire alarm system. Afterwards,
    Mr. Paskett and Sandy Luers (the City’s Director of Community Development and
    Building Official) met with Kent Milligan, the hotel’s general manager. The parties
    dispute the nature of the meeting: Ms. Luers contends she advised Mr. Milligan of
    the need for a fire alarm system, while Mr. Milligan does not recall any discussion of
    3
    a fire alarm system. Milcor then completed construction without installing a fire
    alarm system.
    On December 8, 2014, Milcor requested a final inspection of its renovations.
    Mr. Paskett refused to perform the inspection until Milcor installed an operational
    fire alarm system.2 Mr. Milligan sent Ms. Luers a letter protesting Mr. Paskett’s
    refusal to perform a final inspection, contending that a fire alarm system was never
    part of the building plans the City had approved and that the project’s architect had
    concluded the IBC did not require installation of a fire alarm system. In a response to
    Mr. Milligan’s letter, Ms. Luers stated that while the business section of the addition
    did not need a fire alarm system, the new guestrooms did because they did not open
    directly onto a public way, exit court, or yard.
    On December 30, 2014, Milcor inquired in an email about formally contesting
    the City’s decision, but did not actually request an appeal until more than six months
    later, on July 8, 2015. Instead, Milcor began renting at least some of its newly-built
    guestrooms without the required certificate of occupancy. On September 14, 2015,
    the Riverton Board of Appeals (“Board”) dismissed Milcor’s appeal as untimely.
    Milcor continued renting its rooms without a certificate of occupancy until
    February 5, 2016, when the City advised Milcor by letter of the alleged code
    2
    Mr. Paskett contends he also refused to perform the inspection for another
    reason: because the addition lacked an operational fire suppression system. Milcor
    denies that Mr. Paskett cited the lack of a fire suppression system as a basis for
    refusing the inspection and contends that it had installed a fire suppression system.
    We need not resolve this factual dispute.
    4
    violation and ordered Milcor to either install a fire alarm system within thirty days
    (during which period Milcor would have to perform hourly fire watches) or “cease
    renting of all rooms.” App. at 213–214. Mr. Milligan requested a hearing to appeal
    this letter, arguing the City was “attempt[ing] to strong arm [him] into submitting to
    installation of a fire monitoring system that was never contemplated in the original
    plans or building permit issued by the City”; he sought relief in the form of “an order
    that the City immediately issue certificates of occupancy.” Suppl. App. at 182–83.
    The Board dismissed the appeal, holding that it addressed the same issues as the July
    2015 appeal that the Board had already dismissed as untimely. Milcor appealed that
    dismissal to the Riverton City Council, which upheld the Board’s decision on
    March 16, 2016.
    In June 2016, Milcor filed a complaint in the U.S. District Court for the
    District of Wyoming, naming the defendants in both their individual and official
    capacities. The complaint alleged due process violations and requested a temporary
    restraining order and a preliminary injunction ordering the City to issue a certificate
    of occupancy. The district court ordered the City to perform an inspection of the fire
    alarm and fire suppression systems and to issue a certificate of occupancy if the
    systems were “in compliance with the intent and purpose of the applicable codes.”
    App. at 29–30.
    The City retained Albert Rood, an inspector with the Wyoming State Fire
    Marshal’s Office, to perform the ordered inspection. In December 2016, Mr. Rood
    performed the inspection and concluded that Milcor needed to install a fire alarm
    5
    system, noting “[t]he current fire alarm system d[id] not meet NFPA standards to
    alert all areas of the building” and “[t]he fire alarm system plan submittal ha[d] never
    been approved by the city.” App. at 37. Mr. Rood also noted several other
    deficiencies in the fire alarm system.
    Concluding it was financially unsustainable to keep the Days Inn open or to
    complete the required installations, Milcor closed the motel in March 2017. Milcor
    filed an amended complaint based on 42 U.S.C. § 1983, alleging: (1) procedural and
    substantive due process claims based on the City preventing Milcor from renting
    guestrooms in the pre-renovation portion of the hotel; (2) procedural and substantive
    due process claims based on the City’s refusal to issue a certificate of occupancy
    after Milcor completed the renovation in accord with the building plans previously
    approved by the City; and (3) a breach of contract claim under Wyoming law. In
    September 2017, the defendants moved for summary judgment on Milcor’s claims,
    asserting qualified immunity and offering affidavits from Ms. Luers, Mr. Paskett, and
    Mr. Rood. Along with a response to this motion, Milcor moved to strike Mr. Rood’s
    affidavit in its entirety and portions of Mr. Paskett’s and Ms. Luers’s affidavits.
    In a single order, the district court denied Milcor’s motions to strike and
    granted summary judgment for the defendants. On Count One of the amended
    complaint, the district court concluded there was no evidence from which the jury
    could find the defendants threatened to prevent Milcor from renting rooms in the pre-
    renovation portion of the Days Inn. On Count Two, the district court found no
    procedural due process violation because it concluded Milcor lacked a protected
    6
    property interest in a certificate of occupancy absent compliance with local building
    codes, and that Milcor had failed to meet its burden of clearly establishing the
    absence of any IBC violation.3 As for Milcor’s substantive due process claim, the
    district court found no deprivation of a fundamental right. Having dismissed all
    federal-law claims prior to trial, the court declined to exercise supplemental
    jurisdiction over Count Three and dismissed Milcor’s state-law breach of contract
    claim without prejudice. See United States v. Botefuhr, 
    309 F.3d 1263
    , 1273 (10th
    Cir. 2002) (“[A] district court should normally dismiss supplemental state law claims
    after all federal claims have been dismissed, particularly when the federal claims are
    dismissed before trial.”). Milcor timely appealed.
    II.   DISCUSSION
    Milcor challenges the district court’s grant of summary judgment and denial of
    its motions to strike. We begin with a discussion of the appropriate standard of
    review. Then, we apply that standard in assessing the correctness of the district
    court’s grant of summary judgment.4
    3
    The district court ruled against Milcor’s procedural due process claims on
    two additional grounds: (1) Milcor failed to identify a City policy responsible for the
    alleged constitutional deprivation and thus could not prevail on an official-capacity
    claim; and (2) Milcor had failed to avail itself of the procedures the City made
    available when it did not timely appeal Mr. Paskett’s refusal to perform the final
    inspection. We need not reach these grounds because we agree with the district court
    that Milcor lacked a property interest protected by the due process clause.
    4
    Because we affirm the district court’s grant of summary judgment on the
    basis that Milcor lacked a property interest in a certificate of occupancy, we need not
    reach any questions of disputed fact. Accordingly, we do not address Milcor’s
    challenges to the district court’s denial of its motions to strike the affidavits.
    7
    A. Standard of Review
    We review a district court’s rulings on summary judgment de novo, applying
    the same standards as the district court. Universal Underwriters Ins. Co. v. Winton,
    
    818 F.3d 1103
    , 1105 (10th Cir. 2016). Summary judgment is appropriate if “there is
    no genuine dispute as to any material fact and the movant is entitled to judgment as a
    matter of law.” Fed. R. Civ. P. 56(a); see also Celotex Corp. v. Catrett, 
    477 U.S. 317
    ,
    322–23 (1986); Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 250 (1986). On
    appeal we “examine the record and all reasonable inferences that might be drawn
    from it in the light most favorable to the non-moving party.” Merrifield v. Bd. of Cty.
    Comm’rs, 
    654 F.3d 1073
    , 1077 (10th Cir. 2011) (quotation marks omitted). “In
    reviewing a grant of summary judgment, we need not defer to factual findings
    rendered by the court.” Lincoln v. BNSF Ry. Co., 
    900 F.3d 1166
    , 1180 (10th Cir.
    2018) (internal quotation marks omitted). Furthermore, “we can affirm on any ground
    supported by the record, as long as the appellant has had a fair opportunity to address
    that ground.” Alpine Bank v. Hubbell, 
    555 F.3d 1097
    , 1108 (10th Cir. 2009) (internal
    quotation marks omitted).
    B. Analysis
    The Due Process Clause of the Fourteenth Amendment protects persons from
    state-imposed deprivations “of life, liberty, or property, without due process of law.”
    U.S. Const. amend. XIV, § 1; see also Greene v. Barrett, 
    174 F.3d 1136
    , 1140 (10th
    Cir. 1999). The clause “has two components: procedural due process and substantive
    due process.” 
    Greene, 174 F.3d at 1140
    n.1. Although Milcor raised substantive due
    8
    process claims before the district court and alluded to such claims in oral argument, it
    never raised those arguments in its briefing to this court. Milcor also failed to argue
    any official-capacity procedural due process claims in its briefing before us. We
    generally “decline[] to consider arguments that are not raised, or are inadequately
    presented, in an appellant’s opening brief.” Bronson v. Swensen, 
    500 F.3d 1099
    , 1104
    (10th Cir. 2007). Accordingly, we limit our review to Milcor’s procedural due
    process claims against the defendants in their individual capacities.
    Because Milcor directs its due process complaint against individuals who have
    asserted qualified immunity, to prevail, Milcor must show “(1) the defendant[s]
    violated a constitutional right and (2) the constitutional right was clearly
    established.” Courtney v. Okla. ex rel. Dep’t of Pub. Safety, 
    722 F.3d 1216
    , 1222
    (10th Cir. 2013) (quotation marks omitted). Looking to the first prong of this
    standard,5 we conclude Milcor has failed to demonstrate the violation of any
    constitutional right implicated by the denial of a certificate of occupancy.
    Here, the question is whether the City violated Milcor’s right to procedural due
    process by refusing to issue a certificate of occupancy. “The Fourteenth Amendment
    proscribes a state from, among other things, depriving a party of ‘property without
    due process of law.’” Hyde Park Co. v. Santa Fe City Council, 
    226 F.3d 1207
    , 1210
    (10th Cir. 2000) (quoting U.S. Const. amend. XIV, § 1). Determining whether a
    5
    In reviewing a district court’s ruling on a qualified immunity defense, “[w]e
    have discretion to address either prong of this standard first.” Cox v. Glanz, 
    800 F.3d 1231
    , 1246 (10th Cir. 2015) (quotation marks omitted).
    9
    procedural due process violation has occurred entails “a two-step inquiry: (1)
    whether the plaintiff has shown the deprivation of an interest in ‘life, liberty, or
    property’ and (2) whether the procedures followed by the government in depriving
    the plaintiff of that interest comported with ‘due process of law.’” Elliot v. Martinez,
    
    675 F.3d 1241
    , 1244 (10th Cir. 2012) (quoting Ingraham v. Wright, 
    430 U.S. 651
    ,
    673 (1977)). For the first step of this inquiry, where a plaintiff alleges a deprivation
    of property without due process, we must consider whether the alleged deprivation is
    of an interest protected by the Fourteenth Amendment. Hyde Park 
    Co., 226 F.3d at 1210
    .
    To determine whether Milcor had a protected property interest in a certificate
    of occupancy, we look to state law. Cleveland Bd. of Educ. v. Loudermill, 
    470 U.S. 532
    , 539 (1985) (“Property interests are not created by the Constitution; ‘they are
    created and their dimensions are defined by existing rules or understandings that stem
    from an independent source such as state law. . . .’” (quoting Bd. of Regents of State
    Coll.’s v. Roth, 
    408 U.S. 564
    , 577 (1972))); Hulen v. Yates, 
    322 F.3d 1229
    , 1240
    (10th Cir. 2003) (“Thus, constitutionally protected property interests are created and
    defined by statute, ordinance, contract, implied contract and rules and understandings
    developed by state officials.”); Cole v. Ruidoso Mun. Sch., 
    947 F.2d 903
    , 906 (10th
    Cir. 1991). “In order to create a property interest, the state statute or regulation must
    give the recipient ‘a legitimate claim of entitlement to [the benefit allegedly
    deprived].’” 
    Greene, 174 F.3d at 1140
    (quoting 
    Roth, 408 U.S. at 576
    ). “Detailed
    10
    procedures in a state statute or regulation are not, by themselves, sufficient to create a
    property interest.” 
    Id. Milcor fails
    to demonstrate any “legitimate claim of entitlement to” a
    certificate of occupancy under Wyoming law. The only case Milcor adduces in
    support of its burden, Snake River Venture v. Board of County Commissioners, Teton
    County, 
    616 P.2d 744
    (Wyo. 1980), misses the mark. In Snake River Venture, a
    county issued a building permit to a developer even though the project conflicted
    with a municipal 
    ordinance. 616 P.2d at 746
    –47. The county later revoked the permit,
    arguing it had lacked the authority to lawfully issue a permit in the first place, and
    the developer sought an injunction to enforce the validity of its building permit. 
    Id. at 748.
    In its opinion denying an injunction, the Wyoming Supreme Court explained
    that when an entity receives a building permit and begins actual construction in
    reliance on the earlier approval, it acquires a property interest in the building permit.
    
    Id. at 750.
    Because the developer had not begun construction, it lacked a property
    interest in its building permit. 
    Id. Importantly, however,
    the decision never addressed
    the right to a certificate of occupancy and so Snake River Venture does not support
    Milcor’s claim of a property interest here.
    Apart from Snake River Venture, Milcor cites no Wyoming case law, nor did
    our research reveal any, that would elucidate whether a certificate of occupancy is a
    protected property interest. Moreover, courts considering the question in other states
    have generally rejected the notion of a protected property interest in a certificate of
    occupancy, emphasizing that the issuance or non-issuance of a certificate falls within
    11
    a city’s police powers and fundamentally implicates its “ability to protect the health,
    safety, and welfare of the public.” See, e.g., Patzer v. City of Loveland, 
    80 P.3d 908
    ,
    911–12 (Colo. App. 2003) (rejecting argument that completion of project in accord
    with approved building plans entitled entity to certificate of occupancy where
    issuance might endanger public safety) (collecting cases).
    Thus, because Milcor has failed to show a property interest in a certificate of
    occupancy under Wyoming law,6 Milcor does not satisfy its burden of showing the
    deprivation of a constitutional right and therefore cannot prevail on its procedural
    due process claim.
    III.   CONCLUSION
    We AFFIRM the district court’s decision.
    Entered for the Court
    Carolyn B. McHugh
    Circuit Judge
    6
    Milcor asserts, without support or explanation:
    [B]ecause the trial court chose to dismiss the state law claims [without
    prejudice], this Court must assume that Plaintiff did have a property
    interest under Wyoming law in completing construction pursuant to the
    plans on which the building permit was issued. It would not be
    appropriate at this stage of the case for this court to attempt to resolve
    any uncertainty in the law of Wyoming as to the property interest that
    was deprived by due process of law.
    Appellant’s Br. at 53–54. Milcor is mistaken. Although we express no view on
    the merits of a state breach of contract claim, we properly assessed and
    rejected the merits of Milcor’s federal claim under § 1983.
    12