Mid-America AG Network, Inc. v. Monkey Island Development Authority ( 2004 )


Menu:
  •                                                                           F I L E D
    United States Court of Appeals
    Tenth Circuit
    UNITED STATES COURT OF APPEALS
    JUL 8 2004
    FOR THE TENTH CIRCUIT
    PATRICK FISHER
    Clerk
    MID-AMERICA AG NETWORK,
    INCORPORATED, a Kansas
    corporation,
    Plaintiff-Counter-                       No. 03-5138
    Defendant-Appellee,                (D.C. No. 02-CV-105-EA)
    (N.D. Okla.)
    v.
    MONKEY ISLAND DEVELOPMENT
    AUTHORITY, an Oklahoma public
    trust,
    Defendant-Counter-
    Claimant-Appellant.
    ORDER AND JUDGMENT            *
    Before KELLY , Circuit Judge, BRORBY , Senior Circuit Judge, and        BRISCOE ,
    Circuit Judge.
    After examining the briefs and appellate record, this panel has determined
    unanimously to grant the parties’ request for a decision on the briefs without oral
    *
    This order and judgment is not binding precedent, except under the
    doctrines of law of the case, res judicata, and collateral estoppel. The court
    generally disfavors the citation of orders and judgments; nevertheless, an order
    and judgment may be cited under the terms and conditions of 10th Cir. R. 36.3.
    argument. See Fed. R. App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore
    ordered submitted without oral argument.
    Appellant Monkey Island Development Authority (MIDA) appeals the
    district court’s judgment in favor of Appellee Mid-America AG Network,
    Incorporated (Mid-America). Mid-America filed the underlying lawsuit against
    MIDA seeking a declaratory judgment and injunctive relief to enforce a contract
    between the parties involving a shopping center lease.   1
    The district court
    exercised diversity jurisdiction under 
    28 U.S.C. § 1332
    , and, after a bench trial,
    entered a judgment in Mid-America’s favor. We have appellate jurisdiction under
    
    28 U.S.C. § 1291
    , and we affirm.
    BACKGROUND
    On December 1, 1997, the parties entered into a lease agreement whereby
    Mid-America would construct a strip shopping mall on land owned by MIDA near
    an existing airport. Mid-America was to pay annual rent of $3,750 to MIDA, and,
    in exchange, Mid-America had the right to rents paid by tenants of the shopping
    mall for the lease’s thirty-year primary term. The lease required Mid-America to
    construct a sewage disposal system to serve the facility. Mid-America
    constructed the strip mall and installed a sewage lagoon system near the property.
    1
    MIDA filed counterclaims against Mid-America, which the district court
    denied. MIDA has not appealed that ruling, so we do not consider it.
    -2-
    The airport property was operated by Paul Staten, who sent invoices to
    Mid-America for the annual lease payments. Mr. Staten did business as the Grand
    Lake Regional Airport. Mid-America made the lease payments without incident
    until the payment for 2001 was made. Mid-America’s 2001 payment was made
    payable to Grand Lake Regional Airport, as was its 1998 payment. The payments
    for 1999 and 2000 were payable to MIDA. MIDA asserts that Mid-America
    defaulted the lease by failing to make the 2001 payment.
    In February 2002, Mid-America filed the underlying action seeking
    declaratory and injunctive relief to prevent MIDA from invalidating the lease.
    MIDA counterclaimed for cancellation of the lease and various money damages.
    Mid-America did not make the lease payment on the due date of September 1,
    2002. MIDA mailed a notice of default on October 24, 2002. Mid-America then
    requested permission to pay the 2002 lease payment into the court registry, which
    the district court denied on November 20. Mid-America mailed the lease payment
    to MIDA on December 3; it crossed in the mail with MIDA’s notice of
    termination of the lease. MIDA deposited the 2002 lease payment into its
    account.
    The district court held a two-day bench trial on the issues of whether the
    lease payments for 2001 and 2002 were made as the lease required, and whether
    the sewage lagoon complied with the lease. Based on its extensive findings of
    -3-
    fact and conclusions of law, the court entered judgment in favor of Mid-America
    on its claims for relief and against MIDA on its counterclaims.
    FEDERAL JURISDICTION
    MIDA challenges the federal court’s diversity jurisdiction on the ground
    that the amount in controversy does not exceed $75,000, as required by 
    28 U.S.C. § 1332
    (a).   2
    It asserts that the amount in controversy is $3,750, which represents
    the rental payment for 2002 that was not yet paid when suit was filed, and that the
    shopping center is MIDA’s property. Mid-America responds that it spent
    approximately $1,000,000 to construct the shopping center and that it is entitled
    to collect in excess of $800,000 in future rents under the lease.
    We review de novo the district court’s determination that the amount in
    controversy was sufficient to invoke federal court jurisdiction.     Watson v.
    Blankinship , 
    20 F.3d 383
    , 386 (10th Cir. 1994). If the amount in controversy
    claimed by the plaintiff is apparently made in good faith, the jurisdictional
    minimum is met, unless it “appear[s] to a legal certainty that the claim is really
    for less than the jurisdictional amount.”     St. Paul Mercury Indem. Co. v. Red Cab
    Co. , 
    303 U.S. 283
    , 288-89 (1938). In actions such as this one in which the
    plaintiff seeks declaratory or injunctive relief, “the amount in controversy is
    2
    There is no dispute that the parties are diverse.
    -4-
    measured by the value of the object of the litigation.”     Hunt v. Wash. State Apple
    Adver. Comm’n , 
    432 U.S. 333
    , 347 (1977). “To determine the amount in
    controversy, we look to the pecuniary effect an adverse declaration will have on
    either party to the lawsuit.”   City of Moore v. Atchison, Topeka, & Santa Fe Ry.
    Co. , 
    699 F.2d 507
    , 509 (10th Cir. 1983).
    In response to MIDA’s jurisdictional challenge, Mid-America filed an
    affidavit stating that if the lease were terminated, it would “suffer a loss in the
    range of $812,000 to $1.2 million.” Aplee. Supp. App. at 15. The affidavit is
    uncontroverted, and the district court properly considered it.    See Okla. Retail
    Grocers Ass’n v. Wal-Mart Stores, Inc.     , 
    605 F.2d 1155
    , 1159-60 (10th Cir. 1979).
    We conclude that the future payments anticipated under the lease met the
    jurisdictional minimum and that the district court’s exercise of jurisdiction was
    correct.
    MIDA’S CLAIMS
    MIDA argues on appeal that the district court erred in ruling that
    Mid-America did not forfeit its rights under the lease by failing to make the
    annual rental payments for 2001 and 2002. It also maintains that the district court
    erred in rejecting its claim that the sewage lagoon violated the lease.
    -5-
    ANALYSIS
    Standards of Review
    “In an appeal from a bench trial, we review the district court’s factual
    findings for clear error and its legal conclusions de novo.”     Keys Youth Servs.,
    Inc. v. City of Olathe , 
    248 F.3d 1267
    , 1274 (10th Cir. 2001).    In this case based
    on diversity jurisdiction, we must reach the same legal conclusions the state’s
    highest court would reach. Blanke v. Alexander, 
    152 F.3d 1224
    , 1228 (10th Cir.
    1998). There is no dispute here that Oklahoma state law controls.
    2001 Lease Payment
    MIDA argues that Mid-America did not make the 2001 lease payment. It
    contends that the district court erred in holding that Grand Lake Regional Airport
    was authorized to act as its agent. MIDA claims only that the contract does not
    specify that any entity except Mr. Staten, personally, was named as MIDA’s
    agent. MIDA does not dispute the district court’s findings that (1) Mr. Staten was
    MIDA’s agent for collecting the lease payments from Mid-America, among other
    duties; (2) Mid-America’s 1998 lease payment was payable to Grand Lake
    Regional Airport; (3) MIDA formally terminated Mr. Staten as its agent in
    October 2001, after Mid-America’s lease payment had been made;
    (4) Mid-America was not informed prior to October 2001 that Mr. Staten had
    been terminated as MIDA’s agent; (5) Mr. Staten accounted to MIDA for the
    -6-
    2001 payment; and (6) MIDA was aware that Mr. Staten was issuing invoices on
    Grand Lake Regional Airport letterhead to Mid-America for the annual lease
    payments, and acquiesced in that practice.
    Under Oklahoma law, Mid-America was entitled to rely on Mr. Staten’s
    status as MIDA’s agent in making the 2001 lease payment to his company, Grand
    Lake Regional Airport.     See, e.g., Home State Bank of Hobart v. Sullins    , 
    178 P.2d 86
    , 88 (Okla. 1947) (“Where an agency apparently covering the subject matter in
    question is established or admitted, the principal has the burden of proving any
    special limitations of authority and notice to, or knowledge by, the adverse party
    of such limitations.”) (citation omitted);   see also Bank of Okla., N.A. v. Briscoe   ,
    
    911 P.2d 311
    , 317 (Okla. Ct. App. 1995) (holding that in agency relationship,
    where principal has acquiesced in agent’s unauthorized conduct, he may be
    estopped from denying liability for agent’s acts). Accordingly, we will not
    disturb the district court’s ruling.
    Sewage Lagoon
    MIDA claims that the sewage lagoon Mid-America constructed in 1999 did
    not comply with the requirements set out in the lease agreement. The district
    court found that MIDA did not register any objection to the sewage lagoon system
    until January 2002, and in fact, had been enthusiastic about the sewage lagoon’s
    design at the time it was constructed. Further, MIDA was fully aware of the
    -7-
    system’s location and design at the time it was designed and built. The district
    court held (1) notice of a change in the lease was not required because the sewage
    lagoon was not a substantial change; (2) even if it was a substantial change,
    MIDA had approved it; (3) the parties acquiesced in the sewage lagoon’s
    construction; (4) the lease should be interpreted to conform to the parties’
    conduct; (5) the lease was altered by the executed oral agreement to construct the
    sewage lagoon; and (6) by consenting to the construction and failing to object for
    more than two years, MIDA waived any right to claim the sewage lagoon
    breached the lease.
    On appeal, MIDA argues only that the sewage lagoon cannot be maintained
    on its property under the theories of laches, estoppel, waiver, adverse possession,
    or prescriptive easement. It does not challenge the district court’s other rulings.
    Issues not argued to the appellate court are deemed waived.     Ruiz v. McDonnell ,
    
    299 F.3d 1173
    , 1182 n.4 (10th Cir. 2002),     cert. denied , 
    538 U.S. 999
     (2003).
    Accordingly, because MIDA has waived objection to the district court’s alternate
    holdings, we affirm on those grounds.
    2002 Lease Payment
    Finally, we address MIDA’s claim that the district court erred in denying
    termination of the lease for Mid-America’s failure to make the 2002 payment in
    accordance with the lease terms. As related above, the district court denied
    -8-
    Mid-America’s request to pay the 2002 installment into the court registry.
    Thereafter, the payment was sent to MIDA, but after the due date and after MIDA
    had sent notice of default. Mid-America’s payment and MIDA’s notice of
    termination crossed in the mail. MIDA cashed the check. The district court held
    that the deadline for payment was equitably tolled during the time Mid-America’s
    motion was pending, payment was made soon after the motion was denied, and
    MIDA was not prejudiced by the equitable tolling.
    MIDA argues that the district court erred in invoking the doctrine of
    equitable tolling under these circumstances. It maintains that on the date the
    court denied its motion, Mid-America still had eight days before the termination
    period expired, but it did not make payment within that time.
    We review a district court’s decision to apply equitable tolling for an abuse
    of discretion.   United States v. Clymore , 
    245 F.3d 1195
    , 1198 (10th Cir. 2001).
    Oklahoma law abhors a forfeiture.     City of Tulsa, ex rel. Tulsa Airport Auth. v.
    Air Tulsa, Inc. , 
    851 P.2d 519
    , 523 (Okla. 1992). A contract clause providing for
    forfeiture upon non-payment is considered as security for payment; equity may
    avoid forfeiture by granting adequate compensation.       Whitehurst v. Ratliff ,
    
    181 P.2d 545
    , 548-49 (Okla. 1947). Here, terminating the long-term lease would
    afford MIDA a windfall by forfeiting Mid-America’s million-dollar construction
    for late payment of the relatively small sum of $3,750.     Cf. McCombs Realty, Inc.
    -9-
    v. W. Auto Supply Co. , 
    641 N.W.2d 77
    , 81-82 (Neb. Ct. App. 2002) (invoking
    equitable principles to deny lease forfeiture where lessee acted in good faith,
    payment was tendered promptly after lessee realized payment had not been made,
    and termination would result in forfeiture of $1 million investment for failure to
    pay $100 annual payment). Under these circumstances, we find no abuse of
    discretion in the district court’s decision to equitably toll the deadline for
    Mid-America to pay the 2002 lease payment.
    CONCLUSION
    The judgment of the district court is AFFIRMED.
    Entered for the Court
    Mary Beck Briscoe
    Circuit Judge
    -10-