Glover Construction v. Babbitt ( 1999 )


Menu:
  •                                                                         F I L E D
    United States Court of Appeals
    Tenth Circuit
    UNITED STATES COURT OF APPEALS
    FEB 5 1999
    TENTH CIRCUIT
    PATRICK FISHER
    Clerk
    GLOVER CONSTRUCTION CO.,
    INC.,
    Plaintiff-Appellant,
    v.                                        No. 97-7122
    (D.C. No. 95-CV-467-B)
    BRUCE BABBITT, Secretary of                             (E.D. Okla.)
    Department of Interior,
    Defendant-Appellee.
    ORDER AND JUDGMENT *
    Before EBEL, BRISCOE, and LUCERO, Circuit Judges.
    After examining the briefs and appellate record, this panel has determined
    unanimously that oral argument would not materially assist the determination of
    this appeal. See Fed. R. App. P. 34(a)(2); 10th Cir. R. 34.1(G). Therefore, the
    case is ordered submitted without oral argument.
    Plaintiff Glover Construction Company brought this action alleging
    *
    This order and judgment is not binding precedent, except under the
    doctrines of law of the case, res judicata, and collateral estoppel. The court
    generally disfavors the citation of orders and judgments; nevertheless, an order
    and judgment may be cited under the terms and conditions of 10th Cir. R. 36.3.
    defendant failed to require the Bureau of Indian Affairs to require the Cherokee
    Nation to abide by the provisions of the Federal Acquisition Regulations (FARS),
    
    48 C.F.R. § 1
     et seq . The district court denied Glover Construction’s request for
    injunctive relief and dismissed the action. We dismiss this appeal on mootness
    grounds, and do not address the more difficult questions of standing and
    jurisdiction.
    On June 15, 1995, the Cherokee Nation of Oklahoma began soliciting bids
    for construction of “Greasy Road.” Four construction companies responded to the
    bid: Mouache-Capote Construction, Frix Foster Construction, Hub Construction,
    and Glover Construction. At the bid unsealing, the bid of Hub Construction was
    rejected as nonresponsive to the solicitation. The bid of Mouache-Capote was the
    lowest, followed by the bid of Frix Foster Construction, and then Glover
    Construction. Although the bid of Mouache-Capote failed to include unit prices,
    its bid did include the number of units and the total price for each specific item.
    Thus, the unit price was readily ascertainable from the face of the bid. The
    Cherokee Nation did not reject the bid of Mouache-Capote as nonresponsive
    under 
    48 C.F.R. § 14.301
    , but allowed it to correct its bid. The contract was
    awarded to Mouache-Capote.
    Glover Construction filed this action, contending defendant, through the
    Bureau of Indian Affairs (BIA), failed to require the Cherokee Nation to adhere to
    -2-
    federal procurement standards. The Cherokee Nation was allegedly bound by
    such regulations after negotiating for their application in accordance with 25
    U.S.C. § 458cc(e). Glover Construction sought injunctive relief requiring
    defendant to direct the BIA to order the Cherokee Nation to set aside the bid of
    Mouache-Capote Construction as nonresponsive and to rebid the project in
    accordance with federal standards. In its amended complaint, Glover
    Construction alleged that during construction of the road the Cherokee Nation had
    permitted Mouache-Capote Construction to increase the contract price by over
    $100,000 without requiring bids, which was not in accordance with the contract
    modification requirements of FARS and 41 U.S.C. § 254b. The district court held
    the failure to explicitly list unit prices was not a material alteration, but was a
    correctable “minor irregularity” under the regulations, and that Glover
    Construction was not entitled to injunctive relief because it had not shown
    irreparable harm.
    The Greasy Road was completed no later than May 20, 1997. Therefore,
    Glover Construction’s claims for injunctive relief to require rebidding for the
    contract award and for subsequent contract modifications are moot.       See
    Columbian Rope Co. v. West , 
    142 F.3d 1313
    , 1316 (D.C. Cir. 1998);
    Neighborhood Transp. Network, Inc. v. Pena       , 
    42 F.3d 1169
    , 1171-72 (8th Cir.
    1994).
    -3-
    The only remaining issue is Glover Construction’s request for an injunction
    requiring defendant to direct the Cherokee Nation to abide by the regulations
    during future bidding of projects. In essence, Glover Construction assumes the
    situation that occurred here will be exactly replicated in the future and asks that
    an injunction issue now to insure it is protected later.
    These circumstances do not present an ongoing case or controversy over
    which this court may exercise jurisdiction under Article III.   See Jones v.
    Temmer , 
    57 F.3d 921
    , 922 (10th Cir. 1995). At best, Glover Construction’s
    argument is construed as one invoking the “capable of repetition, yet evading
    review” exception to the mootness doctrine.       See Fischbach v. New Mexico
    Activities Ass’n , 
    38 F.3d 1159
    , 1161 (10th Cir. 1994). That exception does not
    save the claim as there is no “reasonable expectation” that Glover Construction
    will suffer the same injury,   see West , 
    142 F.3d at 1317
    , and no reason for this
    court to assume the issue is not capable of meaningful review if Glover
    Construction is subjected to the same allegedly unlawful treatment in the future,
    see Pena , 
    42 F.3d at 1172
    .    See also Jones , 
    57 F.3d at 923
     (rejecting argument
    that claim is not moot based on possibility that legislature could reinstate law as
    “too conjectural and speculative to avoid a finding of mootness”).
    We add that Glover Construction’s request for injunctive relief is nothing
    more than an artfully phrased prayer for the court to require Cherokee Nation to
    -4-
    obey the law in the future. Such injunctions are not appropriately issued.    See
    Hughey v. JMS Dev. Corp. , 
    78 F.3d 1523
    , 1531 (11th Cir. 1996) (“[A]ppellate
    courts will not countenance injunctions that merely require someone to obey the
    law.”) (internal quotation omitted);   Epstein Family Partnership v. Kmart Corp.      , 
    13 F.3d 762
    , 771 (3d Cir. 1994) (recognizing while “an injunction may be framed to
    bar future violations that are likely to occur, . . . [b]road non-specific language
    that merely enjoins a party to obey the law or comply with an agreement . . . does
    not give the restrained party fair notice of what conduct will risk contempt”)
    (internal quotation omitted).
    Glover Construction’s appeal is DISMISSED as moot.
    Entered for the Court
    Mary Beck Briscoe
    Circuit Judge
    -5-