MidAmerica C2L Incorporated v. Siemens Energy, Inc. ( 2022 )


Menu:
  • USCA11 Case: 20-11266      Date Filed: 02/15/2022   Page: 1 of 47
    [PUBLISH]
    In the
    United States Court of Appeals
    For the Eleventh Circuit
    ____________________
    No. 20-11266
    ____________________
    MIDAMERICA C2L INCORPORATED,
    a Nevada corporation,
    Plaintiff-
    Counter Defendant-
    Appellant,
    SECURE ENERGY, INC.,
    a Nevada Corporation,
    Plaintiff-Appellant,
    versus
    SIEMENS ENERGY INC.,
    a Delaware corporation,
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 2 of 47
    2                       Opinion of the Court                20-11266
    Defendant-
    Counter Claimant-
    Appellee.
    ____________________
    Appeal from the United States District Court
    for the Middle District of Florida
    D.C. Docket No. 6:17-cv-00171-PGB-LRH
    ____________________
    Before NEWSOM, BRANCH, and LAGOA, Circuit Judges.
    LAGOA, Circuit Judge:
    This case is about a business relationship gone bad. In 2006,
    Secure Energy, Inc.—with the intention of opening a coal gasifica-
    tion plant in Illinois—approached Siemens Energy, Inc., about pur-
    chasing some gasifiers and other related equipment. By 2007, the
    parties had entered into a formal contract, under which Secure
    would buy the equipment on a payment plan and Siemens would
    continue to provide updates and repairs to the gasification reactors.
    Two problems quickly arose. First, the price of natural gas
    fell in 2009. As a result, Secure had to change its business plan mul-
    tiple times and could not keep up with its payments to Siemens.
    Second, Siemens’s gasification equipment began having problems,
    USCA11 Case: 20-11266          Date Filed: 02/15/2022       Page: 3 of 47
    20-11266                 Opinion of the Court                            3
    as discovered by one of Siemens’s other clients in 2010. By 2012,
    Siemens began implementing several substantial modifications to
    its gasifiers in order to get them working properly, but, because
    Secure had never gotten its plant up and running, Siemens left Se-
    cure out of the loop. In 2015, Siemens decided to exit the gasifica-
    tion market entirely, but promised to continue supporting its exist-
    ing projects, including Secure’s.
    These problems created the perfect storm for litigation. Se-
    cure—never having opened, let alone used, its gasification equip-
    ment—was commercially failing. Secure still owed Siemens mil-
    lions of dollars for the equipment and had just become aware that
    the equipment it purchased years earlier had issues. In 2016, after
    Siemens decided to leave the gasification market, Secure and its
    subsidiary MidAmerica C2L Incorporated 1 sued Siemens, bringing
    various fraud- and contract-based claims. Siemens—which was still
    owed some thirteen million dollars under the contract and which
    had given Secure multiple payment extensions on that amount—
    filed a counterclaim against Secure for breach of contract.
    Years into the litigation, Secure sought leave to amend its
    complaint, which the district court denied due to its untimeliness.
    Later, the district court excluded Secure’s expert witness, Dr. Her-
    bert Kosstrin, for relying on an unreliable methodology, and
    granted summary judgment in Siemens’s favor on each of Secure’s
    1 Forpurposes of this opinion, we refer to MidAmerica as Secure unless oth-
    erwise expressly noted.
    USCA11 Case: 20-11266             Date Filed: 02/15/2022         Page: 4 of 47
    4                          Opinion of the Court                        20-11266
    affirmative claims. The case thus proceeded to trial only on Sie-
    mens’s counterclaim. Prior to trial, the district court excluded evi-
    dence Secure sought to introduce in support of its breach-of-con-
    tract affirmative defense. The jury returned a full verdict in Sie-
    mens’s favor on its counterclaim, and Secure timely appealed.
    On appeal, we are asked to determine four discrete issues:
    (1) whether the district court abused its discretion in excluding Se-
    cure’s expert witness; (2) whether the district court erred in enter-
    ing summary judgment in Siemens’s favor; (3) whether the district
    court abused its discretion in denying Secure leave to amend its
    complaint; and (4) whether the district court abused its discretion
    in excluding certain evidence at trial and afterwards denying Se-
    cure’s motion for a new trial.
    I.      FACTUAL AND PROCEDURAL BACKGROUND
    Secure was formed in 2006 2 for the purpose of developing
    and constructing a facility in Decatur, Illinois, to convert coal into
    synthetic natural gas using a process called coal gasification. 3 To
    that end, Secure began shopping around for a Basic Engineering
    2 Secure’s subsidiary, Secure Energy Decatur, LLC, was formed shortly after
    this time and was the original entity contracting with Siemens.
    3 Gasification converts carbonaceous, fossil-fuel based material (e.g., coal) into
    gas (e.g., synthetic natural gas) by feeding pulverized coal (called feedstock)
    into large pieces of equipment called gasifiers. See Ronald W. Breault, Gasifi-
    cation Processes Old and New: A Basic Review of the Major Technologies; 3
    Energies 216, 218 (2010), https://www.mdpi.com/1996-1073/3/2/216.
    USCA11 Case: 20-11266       Date Filed: 02/15/2022   Page: 5 of 47
    20-11266              Opinion of the Court                       5
    Design Package (“BEDP”) and Product Design Package (“PDP”)
    from a coal gasification technology provider, eventually contacting
    Siemens. Lars Scott and Jack Kenny, the two founders of Secure,
    met with Rolf Rüsseler and Harry Morehead of Siemens. During
    these meetings, Siemens represented to Secure that Secure was
    purchasing a proven technology from Siemens, as it started the
    equipment’s design in the mid-1970s and it had over twenty years
    of experience in coal gasification. Additionally, Siemens repre-
    sented that its current 500-megawatt gasifiers—which Secure was
    interested in—employed a technologically advanced cooling-
    screen system that accepted a wide range of feedstock and could
    achieve “up to >99%” carbon conversion rates. And Siemens had
    already sold the 500-megawatt gasifiers to one customer in China.
    Impressed with these representations, Secure decided to use
    Siemens for its equipment and technology needs. On July 24, 2007,
    Secure and Siemens entered into a “Memorandum of Understand-
    ing” memorializing the parties’ intention for Secure to purchase
    from Siemens two 500-megawatt gasifiers, associated equipment,
    engineering services, and a process license.
    On December 21, 2007, Secure and Siemens entered into a
    formal contract (the “2007 Contract”) whereby Secure would pur-
    chase Siemens’s products and services for €27,715,000 plus
    $1,717,000—in total, approximately $40 million. The 2007 Con-
    tract and every subsequent contract at issue here included a merger
    clause, which stated that neither “party will be bound by any prior
    obligations, conditions, warranties or representations.” Secure
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 6 of 47
    6                      Opinion of the Court                20-11266
    promptly paid to Siemens the $40 million called for in the 2007
    Contract.
    Secure and Siemens also entered into a licensing agreement
    (the “2007 LSA”) whereby Secure licensed Siemens’s technology
    for approximately €11.7 million. Secure was to pay the €11.7 mil-
    lion licensing fee pursuant to an agreed upon fee schedule within
    the 2007 LSA.
    The burners—a core component of Siemens’s gasifiers—
    were delivered to Secure in Decatur, Illinois, in March 2009. Se-
    cure alleges that the pins in the cooling screen of the burners were
    too short and out of specification, although Siemens disputes this
    characterization. However, Secure only became aware of this al-
    leged defect during the litigation—it never actually opened or put
    into operation the Siemens gasifiers after it took possession of
    them.
    The price of natural gas dropped precipitously in 2009; as a
    result, Secure abandoned its original plan of converting coal to nat-
    ural gas and began planning to build a coal-to-gasoline gasification
    plant instead. But because the plot of land Secure had acquired in
    Decatur could not accommodate this change, Secure decided to
    move its plant to West Paducah, Kentucky.
    Secure’s new plans in Kentucky required no changes to the
    Siemens gasification equipment, and the parties continued their
    business relationship. On March 31, 2010, Secure and Siemens en-
    tered into a Completion Agreement (the “2010 Completion
    USCA11 Case: 20-11266       Date Filed: 02/15/2022    Page: 7 of 47
    20-11266               Opinion of the Court                       7
    Agreement”), which terminated the parties’ previous agreements
    in the 2007 Contract and 2007 LSA, as well as a new License Agree-
    ment (the “2010 LSA”). The 2010 Completion Agreement also stip-
    ulated that Siemens had met its performance goals under the 2007
    Contract and 2007 LSA and released both parties from any claim
    related to those contracts. In addition, the 2010 LSA included a
    warranty extension on the gasifiers (which would have otherwise
    expired in 2011) upon Secure’s payment of a €1 million fee, but Se-
    cure never paid the fee. The 2010 LSA also set forth terms for pay-
    ing the licensing fee under the agreement, requiring: (1) Secure to
    pay Siemens €300,000 at the “Contract Date”; (2) €700,000 within
    five business days of the date of “Closing of New Equity” or July
    31, 2010, whichever was later; (3) €10.2 million upon “Financial
    Close,” but no later than August 30, 2011 (unless otherwise agreed
    to by the parties); and (4) €1.2 million when “Acceptance” oc-
    curred, but no later than December 31, 2014.
    At around the same time Siemens was working with Secure,
    Siemens sold five 500-megawatt burners to a client which installed
    the burners at its coal to polypropylene plant in China (“NCPP”).
    These burners were first used in October 2010. Immediately, there
    were problems. The burners that Siemens had used were having
    trouble converting the Chinese coal into synthetic gas. The pilot
    burner was also “unreliable” and had to be removed twenty-five
    times on two of the gasifiers at NCPP in the first two months. The
    cooling screens also had issues, with the flame from the burner hit-
    ting them at an awkward angle.
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 8 of 47
    8                      Opinion of the Court                 20-11266
    Siemens explains away these problems by referring to the
    fact that the Chinese client used below-grade coal in the gasifiers at
    NCPP and loaded the incorrect fuel source into the burners. And
    Siemens admits that some of the parts of the gasifiers required re-
    pair but maintains that none of the gasifiers were defective. In any
    event, it is beyond dispute that, from 2010 to 2012, NCPP experi-
    enced numerous problems and the Chinese client went forward
    and made “optimizations and modifications” at NCPP. At one
    point, the Chinese client sought payment from Siemens for the is-
    sues it corrected related to NCPP, and by 2014, the Chinese client
    had replaced its Siemens burners with burners from a Chinese en-
    gineering firm.
    Internal Siemens documents from this time period identified
    the problems. In October 2012, Rüsseler sent an internal Siemens
    email in which he explained that the “message” to Secure should
    be to “scrap the equipment, we’ll start over again.” On November
    13, 2012, Siemens circulated an internal memo discussing the
    needed improvements to the burners, which estimated that the im-
    provements would take 8,520 engineering hours. At this point, Se-
    cure had changed its business plan again, this time planning a coal-
    to-methanol plant at its Kentucky location.
    On July 18, 2012, Secure and Siemens entered into a new
    Completion Agreement (“2012 Contract”) and License Agreement
    (“2012 LSA”) (collectively, “2012 Contracts”). The 2012 LSA in-
    cluded a merger clause that terminated all prior agreements. Pur-
    suant to the 2012 LSA, Secure was required to pay Siemens a €12.48
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 9 of 47
    20-11266               Opinion of the Court                         9
    million licensing fee. The 2012 LSA recognized that Secure had
    already paid €300,000 in 2010, meaning that Secure still owed Sie-
    mens €12.18 million under the 2012 LSA. Secure was required to
    pay the remaining €12.18 million as follows: (1) €10.932 million
    upon “Financial Close”—defined as the moment “construction fi-
    nancing for the [p]roject ha[d] been arranged,” i.e., once Secure had
    secured financing—but no later than February 28, 2013; and (2)
    €1.248 million when “Acceptance” occurred—defined by the par-
    ties as once specified reliability and performance tests were success-
    fully completed and demonstrated— but no later than December
    31, 2015. The 2012 LSA also provided that, in the event Secure fails
    to make payment when due, and after the 15-business-day cure pe-
    riod, Siemens would have the right to terminate the agreement and
    Secure would owe Siemens ninety-two percent of the licensing fee
    if Financial Close had not yet occurred. The 2012 Contracts substi-
    tuted MidAmerica, Secure’s subsidiary, for Secure as the contract-
    ing party.
    Not long thereafter, Secure sought to obtain a construction
    and financing contract for its plant from a company called SK En-
    gineering & Construction. Siemens agreed to meet with SK and
    Secure to help Secure acquire that agreement. During the meeting,
    Siemens communicated with SK that Siemens would be imple-
    menting the improvements it learned at NCPP so long as Secure
    agreed to pay for them. Siemens estimated that it would take
    around 8,500 engineering hours to complete. In December 2012,
    however, Siemens suggested internally that incorporating these
    USCA11 Case: 20-11266       Date Filed: 02/15/2022    Page: 10 of 47
    10                     Opinion of the Court                20-11266
    changes would “tie up resources at a time when [Siemens] need[ed]
    them more urgently elsewhere” and that, when offering these
    changes to Secure, Siemens should make “the price and schedule
    for this change order . . . so unattractive that [Secure] cannot draw
    th[e] option.”
    In early 2013, Siemens was in the process of pitching to a
    new client—the Texas Clean Energy Project (“TCEP”). Because it
    used a Chinese contractor, TCEP was aware of the problems the
    Siemens’s burners had at NCPP and asked for reassurance that
    there were solutions to the problems that occurred with the equip-
    ment there. Siemens responded that there were, detailing twenty-
    eight changes to the design—the design that Secure still had—that
    would be implemented before the TCEP project got underway.
    Secure did not make the license fee payment that came due
    on February 28, 2013. At the time, the Siemens gasifiers Secure
    purchased had not been opened. And by now, Secure’s business
    was crumbling, with internal documents indicating “substantial
    doubt about [Secure’s] ability to continue as a going concern.” In-
    deed, as of December 2012, Secure admitted that, “[i]n order to
    continue the coal gasification project, [it must] obtain grants, debt
    financing or additional equity investment.”
    In May 2014, Secure emailed Siemens asking when Secure
    could expect an updated BEDP and asking about the viability of its
    equipment. Internally, Siemens stated that “very little to nothing
    can be re-used [sic] and we would have to start from scratch.”
    USCA11 Case: 20-11266      Date Filed: 02/15/2022     Page: 11 of 47
    20-11266               Opinion of the Court                      11
    By March 2015, Secure stopped making payroll payments to
    its employees. In July 2015, Secure advised Siemens that there
    might be “new life for [its] project,” as SK had introduced Secure
    to a group in Houston that were interested in partnering with it on
    the Kentucky plant. But Secure was never able to obtain the nec-
    essary financing for a coal-to-fertilizer plant at the Kentucky site
    that it hoped would give it that new life. Secure then missed the
    December 2015 licensing fee payment due to Siemens under the
    2012 LSA. By the end of 2015, Secure had not paid any of the li-
    censing fees under the 2012 Contracts, except for the down pay-
    ment, and it had suspended its business operations.
    At the same time, the market constraints that were squeez-
    ing Secure had the same effect on Siemens. By mid-2015, Siemens
    decided to exit the gasification market. On a February 2, 2016, call
    between Secure and Siemens, Siemens told them of its decision.
    Secure interpreted the call as an anticipatory repudiation of the
    contract—i.e., Secure believed that Siemens was communicating it
    would not honor the contract.
    On February 11, 2016, Secure demanded recission of the
    2007 Contract and the return of all monies paid by Secure to Sie-
    mens pursuant to that contract. On February 17, 2016, Siemens
    informed Secure that Siemens would not violate any contractual
    obligation even though Siemens was closing its coal gasification
    business.
    In March 2016, Siemens proposed extending the license fee
    payment deadline and the deadline for completing “performance
    USCA11 Case: 20-11266           Date Filed: 02/15/2022        Page: 12 of 47
    12                        Opinion of the Court                      20-11266
    tests.” Secure rejected the offer, so Siemens revoked it and de-
    manded payment of the approximately €11.5 million termination
    fee owed pursuant to the 2012 LSA.
    Secure filed suit against Siemens in July 2016, in Illinois state
    court. Siemens removed the case to federal court, and the case was
    transferred to the Middle District of Florida. Secure amended its
    complaint on April 21, 2017. Secure brought six counts: (1) breach
    of contract; (2) breach of warranty of fitness; (3) fraudulent misrep-
    resentation by Siemens as to support of the project; (4) fraudulent
    misrepresentation for failure to disclose defects 4; (5) recission for
    fraud, and (6) recission for lack of consideration. All in all, Secure
    sought approximately $86 million in damages—$40 million for the
    loss of value of the equipment and technology it purchased and $46
    million for its expenses designing and engineering its plants—and
    claimed that Siemens anticipatorily repudiated by exiting the gasi-
    fication market. Siemens answered and asserted a counterclaim for
    breach of contract, seeking payment of the termination fee owed
    under the 2012 LSA plus interest. Secure filed a reply to Siemens’s
    counterclaim which asserted various affirmative defenses, includ-
    ing that Siemens “materially breached the terms and conditions” of
    the 2012 LSA.
    Secure voluntarily dismissed its fraudulent misrepresenta-
    tion claim for support of project. In an order on Siemens’s motion
    4 The  fraudulent misrepresentation claim for Siemens’s alleged failure to dis-
    close design defects was voluntarily dismissed.
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 13 of 47
    20-11266               Opinion of the Court                        13
    for partial dismissal, the district court determined that Secure’s re-
    scission for lack of consideration claim was limited to misrepresen-
    tations and omissions following March 31, 2010 (the date the par-
    ties entered into the 2010 Contract) because the 2010 Contract
    waived and released all previous claims.
    The litigation moved into discovery. Over a year and a half
    after the deadline to amend pleadings had passed—and just two
    weeks before the close of fact discovery—Secure asked the district
    court for leave to amend its complaint so that it could plead new
    facts and alternative legal theories of recovery. Secure based its
    motion exclusively on Federal Rule of Civil Procedure 15, concern-
    ing leave to amend, but did not address Federal Rule of Civil Pro-
    cedure 16, which concerns modifications to scheduling orders. The
    magistrate judge denied the motion. The magistrate judge ex-
    plained that the motion was brought under the wrong rule, noting
    that Secure failed to address the requirements of Rule 16(b)(4), and
    concluded that Secure had not demonstrated good cause to sup-
    port belated amendment of the complaint. On February 5, 2019,
    Secure moved to continue the trial date in order to file an amended
    complaint. That motion was also denied for failure to provide
    good cause. After summary judgment was entered in Siemens’s
    favor on Secure’s affirmative claims, Secure renewed its motion to
    continue the trial and amend its complaint. And again, its motion
    was denied.
    Because Secure’s claims were premised in large part on de-
    fects in the BEDP and the gasification burners, it retained an expert,
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 14 of 47
    14                     Opinion of the Court                 20-11266
    Dr. Herbert Kosstrin, to testify as to their defective nature. Dr.
    Kosstrin was prepared to testify that (1) Siemens’s BEDP and gasi-
    fication equipment were defective; and (2) their defective nature
    prevented Secure from obtaining financing to complete their
    plants; and (3) the gasification equipment was worthless except for
    scrap value. Siemens moved to exclude Dr. Kosstrin under Daub-
    ert v. Merrell Dow Pharmaceuticals, Inc., 
    509 U.S. 579
     (1993), ar-
    guing that he did not inspect the equipment purchased by Secure,
    that he utilized an unreliable methodology, and that his testimony
    would be unhelpful to the jury. The district court granted the mo-
    tion and excluded Dr. Kosstrin’s expert opinion and testimony. In
    its order, the district court explained that Dr. Kosstrin’s opinion
    was not based on any reliable methodology, e.g., by testing or con-
    ducting computer modeling on the equipment; was gleaned exclu-
    sively from internal Siemens documents that the jury could view
    itself; did not adequately compare the Secure project to the NCPP
    project, including because his comparison lacked sufficient analysis
    and he failed to consider the data regarding the coal used at NCPP;
    and that his conclusions consisted entirely of his own ipse dixit.
    The district court also excluded Dr. Kosstrin’s opinion re-
    garding the value of the equipment because it found he lacked the
    requisite qualification to testify as an expert on the value of the
    equipment and he never conducted an appraisal analysis. Follow-
    ing the exclusion of Dr. Kosstrin, the district court took up the par-
    ties’ cross motions for summary judgment. The district court de-
    nied Secure’s motion for summary judgment. The district court
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 15 of 47
    20-11266               Opinion of the Court                        15
    granted Siemens’s motion for summary judgment in part and dis-
    missed all of Secure’s affirmative claims against Siemens. The dis-
    trict court held that four of the claims—breach of implied war-
    ranty, fraudulent misrepresentation, recission-fraud, and recission-
    lack of consideration—were premised on the “same ‘material de-
    sign defects’ allegations” and that, because Secure had no expert to
    testify that the gasification equipment was in fact defective, Secure
    had no evidence to support these claims.
    With respect to Secure’s breach of contract claim, the dis-
    trict court held that Secure’s breach of contract claim was limited
    to the repudiation theory it alleged in its Complaint and that Secure
    failed to prove that its damages were the direct and proximate re-
    sult of Siemens’s alleged conduct to support that theory of liability.
    The district court denied Siemens’s motion for summary judgment
    on Siemens’s counterclaim.
    Following the summary judgment orders, the case pro-
    ceeded to trial only on Siemens’s counterclaim for breach of con-
    tract, premised on the 2012 LSA. Prior to trial, Siemens filed a mo-
    tion in limine seeking to exclude: (1) nonpleaded, dismissed, re-
    leased, or rejected claims including alleged defects, misrepresenta-
    tions, fraudulent concealments, and any theory that Secure is ex-
    cused from nonperformance of the 2012 LSA except for the antici-
    patory repudiation theory; (2) evidence concerning alleged prob-
    lems at the NCPP plant; and (3) evidence related to the alleged fail-
    ure to inform or provide improvements under the 2012 LSA; as
    well as other evidence that Siemens argued was irrelevant to its
    USCA11 Case: 20-11266       Date Filed: 02/15/2022    Page: 16 of 47
    16                     Opinion of the Court                20-11266
    counterclaim and Secure’s defenses. The district court granted Sie-
    mens’s motion, thereby limiting Secure’s affirmative defense that
    Siemens breached the 2012 LSA to Secure’s anticipatory repudia-
    tion theory.
    At the conclusion of trial, Secure made a motion for judg-
    ment as a matter of law—arguing that the evidence demonstrated
    that Siemens repudiated the 2012 LSA and that Secure did not
    breach the agreement. The district court denied the motion.
    The jury returned its verdict on March 4, 2020, in which it
    rejected Secure’s anticipatory repudiation defense and awarded
    Siemens $13,200,395.50 in damages. After the jury verdict, Secure
    renewed its motion for judgment as a matter of law and, in the al-
    ternative moved for a new trial because, among other reasons, the
    district court excluded evidence that Siemens failed to perform un-
    der the 2012 LSA. The district court denied both motions and held,
    with respect to the exclusion of evidence related to Siemens’ al-
    leged breach, that Secure’s new defense of an alleged breach unre-
    lated to anticipatory repudiation was untimely and failed to articu-
    late a material breach. Secure filed this timely appeal.
    II.    STANDARDS OF REVIEW
    We review for abuse of discretion a district court’s decisions
    regarding the admissibility of expert testimony. Gen. Elec. Co. v.
    Joiner, 
    522 U.S. 136
    , 142–43 (1997); accord United States v. Frazier,
    
    387 F.3d 1244
    , 1259 (11th Cir. 2004) (en banc) (“This Court has uni-
    formly applied the deferential abuse-of-discretion review that
    USCA11 Case: 20-11266        Date Filed: 02/15/2022      Page: 17 of 47
    20-11266                Opinion of the Court                         17
    Joiner mandates.”). We will find an abuse of discretion only if the
    district court’s ruling was “manifestly erroneous.” Joiner, 
    522 U.S. at 142
     (quoting Spring Co. v. Edgar, 
    99 U.S. 645
    , 658 (1878)); Fra-
    zier, 
    387 F.3d at 1258
    . A district court of course abuses its discretion
    when it applies the wrong legal standard. Frazier, 
    387 F.3d at 1259
    .
    We review an order granting summary judgment de novo,
    applying the same legal standards as the district court. Amy v. Car-
    nival Corp., 
    961 F.3d 1303
    , 1308 (11th Cir. 2020). We view the ev-
    idence in the light most favorable to the non-movant and draw all
    reasonable inferences in his favor. Haves v. City of Miami, 
    52 F.3d 918
    , 921 (11th Cir. 1995). “Summary judgment is appropriate if ‘the
    evidence before the court shows that there is no genuine issue as
    to any material fact and that the moving party is entitled to a judg-
    ment as a matter of law.’” McCullough v. Antolini, 
    559 F.3d 1201
    ,
    1204 (11th Cir. 2009) (quoting Haves, 
    52 F.3d at 921
    ); Fed. R. Civ.
    P. 56(a)).
    We review a district court’s denial of a motion for a new trial
    for abuse of discretion. McGinnis v. Am. Home Mortg. Servicing,
    Inc., 
    817 F.3d 1241
    , 1255 (11th Cir. 2016). “[N]ew trials should not
    be granted on evidentiary grounds unless, at a minimum, the ver-
    dict is against the great—not merely the greater—weight of the ev-
    idence.” Lamonica v. Safe Hurricane Shutters, Inc., 
    711 F.3d 1299
    ,
    1312–13 (11th Cir. 2013) (quoting St. Luke’s Cataract & Laser Inst.,
    P.A. v. Sanderson, 
    573 F.3d 1186
    , 1200 n. 16 (11th Cir.2009)). Re-
    latedly, we review the district court’s grant of a motion in limine
    for abuse of discretion. Cabello v. Fernandez-Larios, 402 F.3d
    USCA11 Case: 20-11266            Date Filed: 02/15/2022   Page: 18 of 47
    18                      Opinion of the Court                  20-11266
    1148, 1161 (11th Cir. 2005) (per curiam). Under the abuse-of-dis-
    cretion standard, we may reverse a decision of the dis-
    trict court only if the court applies an incorrect legal standard, fol-
    lows improper procedures in making its determination, or makes
    findings of fact that are clearly erroneous. Luxottica Grp., S.p.A. v.
    Airport Mini Mall, LLC, 
    932 F.3d 1303
    , 1311 (11th Cir. 2019). And,
    a “district court has wide discretion in determining the relevance
    of evidence produced at trial.” Cabello, 402 F.3d at 1161. Even
    relevant evidence may be excluded “if its probative value is sub-
    stantially outweighed by a danger of . . . unfair prejudice, . . . un-
    due delay, wasting time, or needlessly presenting cumulative evi-
    dence.” Fed. R. Evid. 403.
    III.      ANALYSIS
    On appeal, Secure contends that the district court erred in:
    (1) excluding Dr. Kosstrin’s testimony; (2) granting summary judg-
    ment; (3) denying its requests to file an amended complaint; and
    (4) denying Secure’s motion for a new trial on the grounds that Se-
    cure was barred from presenting evidence that Siemens breached
    the 2012 LSA. We address each argument in turn.
    A. Did the district court err in excluding Dr. Kosstrin?
    Our analysis regarding the admissibility of expert testimony
    begins with Federal Rule of Evidence 702, which provides:
    A witness who is qualified as an expert by knowledge,
    skill, experience, training, or education may testify in
    the form of an opinion or otherwise if:
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 19 of 47
    20-11266               Opinion of the Court                        19
    (a) the expert’s scientific, technical, or other special-
    ized knowledge will help the trier of fact to under-
    stand the evidence or to determine a fact in issue;
    (b) the testimony is based on sufficient facts or data;
    (c) the testimony is the product of reliable principles
    and methods; and
    (d) the expert has reliably applied the principles and
    methods to the facts of the case.
    As explained by the Supreme Court, the purpose of the ex-
    pert admissibility rules is to enlist the federal courts as “gatekeep-
    ers” tasked with screening out “speculative” and “unreliable expert
    testimony.” Kilpatrick v. Breg, Inc., 
    613 F.3d 1329
    , 1335 (11th Cir.
    2010) (quoting Daubert v. Merrell Dow Pharm., Inc., 
    509 U.S. 579
    ,
    597 (1993)). In this Circuit, we have distilled the expert admissibil-
    ity inquiry into the following three factors:
    (1) the expert is qualified to testify competently re-
    garding the matters he intends to address;
    (2) the methodology by which the expert reaches his
    conclusions is sufficiently reliable as determined by
    the sort of inquiry mandated in Daubert; and
    (3) the testimony assists the trier of fact, through the
    application of scientific, technical, or specialized ex-
    pertise, to understand the evidence or to determine a
    fact in issue.
    City of Tuscaloosa v. Harcros Chems., Inc., 
    158 F.3d 548
    , 562 (11th
    Cir. 1998) (footnote omitted). We have also noted that “[w]hile
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 20 of 47
    20                     Opinion of the Court                 20-11266
    there is inevitably some overlap among the basic requirements—
    qualification, reliability, and helpfulness—they remain distinct con-
    cepts and the courts must take care not to conflate them.” Frazier,
    
    387 F.3d at
    1260 (citing Quiet Tech. DC-8, Inc. v. Hurel-Dubois UK
    Ltd., 
    326 F.3d 1333
    , 1341 (11th Cir. 2003)).
    Here, the district court rested its exclusion of Dr. Kosstrin’s
    opinions on the qualifications and reliability prongs. Regarding an
    expert’s qualifications, we have explained that:
    we observe that experts may be qualified in various
    ways. While scientific training or education may pro-
    vide possible means to qualify, experience in a
    field may offer another path to expert status. In fact,
    the plain language of Rule 702 makes this clear: expert
    status may be based on “knowledge, skill, experi-
    ence, training, or education.” (emphasis added). The
    Committee Note to the 2000 Amendments of Rule
    702 also explains that “[n]othing in this amendment is
    intended to suggest that experience alone . . . may not
    provide a sufficient foundation for expert testimony.”
    Fed. R. Evid. 702 advisory committee’s note (2000
    amends.).
    Of course, the unremarkable observation that an ex-
    pert may be qualified by experience does not mean
    that experience, standing alone, is a sufficient founda-
    tion rendering reliable any conceivable opinion the
    expert may express. As we observed in Quiet Tech-
    nology, “while an expert’s overwhelming qualifica-
    tions may bear on the reliability of his proffered
    USCA11 Case: 20-11266        Date Filed: 02/15/2022      Page: 21 of 47
    20-11266                Opinion of the Court                         21
    testimony, they are by no means a guarantor of relia-
    bility. . . . [O]ur caselaw plainly establishes that one
    may be considered an expert but still offer unreliable
    testimony.” 
    326 F.3d at
    1341–42. Quite simply, un-
    der Rule 702, the reliability criterion remains a dis-
    crete, independent, and important requirement for
    admissibility.
    
    Id.
     at 1260–61 (alterations in original).
    As to the reliability prong, we have noted that “[r]ulings on
    admissibility under Daubert inherently require the trial court to
    conduct an exacting analysis of the proffered expert’s methodol-
    ogy.” McCorvey v. Baxter Healthcare Corp., 
    298 F.3d 1253
    , 1257
    (11th Cir. 2002). The Supreme Court has identified a number of
    factors for courts to consider in conducting that analysis, including:
    (1) whether the theory or technique can be, and has been, tested;
    (2) whether the theory or technique has been subjected to peer re-
    view and publication; (3) the known or potential rate of error; and
    (4) whether the theory has attained general acceptance in the rele-
    vant scientific community. See Daubert, 
    509 U.S. at
    593–94. Im-
    portantly, “nothing in either Daubert or the Federal Rules of Evi-
    dence requires a district court to admit opinion evidence that is
    connected to existing data only by the ipse dixit of the expert,” and
    the “court may conclude that there is simply too great an analytical
    gap between the data and the opinion proffered.” Joiner, 
    522 U.S. at 146
    .
    In this case, Secure retained Dr. Kosstrin to testify as to three
    issues: (1) “the defects in the Siemens Equipment and
    USCA11 Case: 20-11266        Date Filed: 02/15/2022      Page: 22 of 47
    22                      Opinion of the Court                  20-11266
    Technology—as evidenced by Siemens’s first test of its designs at
    NCPP—prevented Appellants’ gasifiers from meeting their con-
    tractually-guaranteed performance”; (2) “the defects prevented [Se-
    cure] from obtaining financing for their project”; and (3) “in light
    of the defects, the Equipment and Technology have only scrap
    value.”
    Dr. Kosstrin, who holds a Ph.D. in Mechanical and Aero-
    space Engineering from Cornell University, has forty years of ex-
    perience in the alternative energy field, including alternative fuels.
    In preparing his testimony and reaching his conclusions, he re-
    viewed a number of documents that Siemens produced in discov-
    ery, including documents related to the design of the gasifiers. In
    his report, Dr. Kosstrin makes clear that this is all he reviewed, stat-
    ing “the basis for this opinion is a review of exhibits and infor-
    mation concerning the NCPP plant’s operations up to the signing
    of the 2012 [LSA].”
    Dr. Kosstrin’s methodology was as follows. Because Sie-
    mens had shipped nearly identical burners to their Chinese client
    at NCPP, Dr. Kosstrin hypothesized that, if those burners were ex-
    periencing problems, then the Secure burners would as well. His
    report thus detailed the design of the NCPP burners, explained the
    problems experienced at NCPP, and stated that Secure would have
    experienced the same problems with its Siemens burners, if Secure
    had ever opened and used them.
    The district court excluded Dr. Kosstrin’s expert testimony,
    and in its order, identified a number of problems with Dr.
    USCA11 Case: 20-11266      Date Filed: 02/15/2022     Page: 23 of 47
    20-11266               Opinion of the Court                      23
    Kosstrin’s testimony: (1) “Dr. Kosstrin did not perform any testing
    on the Secure equipment, because it was never installed”; (2) “Dr.
    Kosstrin did not conduct any computer modeling or simulations of
    the Secure equipment’s performance . . . , and he did not com-
    municate with anyone involved in the NCPP plant to determine
    why they made changes to the equipment”; (3) Dr. Kosstrin’s ex-
    pert report contained “no opinions on how the coal at the NCPP
    plant compared to the design coal for the Secure project”—i.e.,
    while acknowledging that the NCPP plant used a grade of coal that
    was outside the range specified by Siemens in the contract with
    NCPP, Dr. Kosstrin did not account for how this might affect the
    performance of the burners; (4) Dr. Kosstrin did not conduct an
    individual cost analysis for the hypothetical corrective measures
    and could not say whether the modifications were inexpensive; (5)
    Dr. Kosstrin knew that the Chinese operators ran the gasifier at be-
    low minimum load but “did not perform an analysis to determine
    whether NCPP was complying with the minimum load case, or the
    impact on operations”; (6) Dr. Kosstrin “did not consider alterna-
    tive designs that Siemens should have employed”; and (7) he failed
    “to compare the Secure BEDP to any other BEDP for coal gasifica-
    tion.” (emphasis added). In short, the district court excluded Dr.
    Kosstrin’s testimony as to design defects because he did not run any
    analysis on the equipment at issue and compared the equipment to
    the NCPP equipment in a manner that failed to account for two
    variables that Siemens listed in the contract as causing problems
    with the burners.
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 24 of 47
    24                      Opinion of the Court                 20-11266
    As to the third issue on which Dr. Kosstrin sought to tes-
    tify—that the equipment had only “scrap value”—the district court
    found that Dr. Kosstrin lacked the requisite qualifications to testify
    on the subject, noting that Kosstrin is “not a certified appraiser” and
    “has never performed an appraisal analysis.”
    Under our deferential standard of review, we cannot con-
    clude that the district court abused its discretion in excluding Dr.
    Kosstrin’s testimony. Our caselaw makes clear that, in order for a
    methodology to be reliable, the expert must be able to adequately
    explain how the data he relied on led him to his conclusions. In a
    case such as this one—where the expert notes that many factors
    could have contributed to the defect at issue—this means the ex-
    pert must be able to explain his consideration of the other alterna-
    tive causes. See, e.g., Guinn v. AstraZeneca Pharms. LP, 
    602 F.3d 1245
    , 1253 (11th Cir. 2010) (per curiam) (noting that an expert
    “need not rule out all possible alternative causes,” but “must at
    least consider other factors that could have been the sole cause of
    the plaintiff’s injury”). Caselaw on this point is legion.
    Frazier is one such case. There, the expert was prepared to
    testify as to the transfer of hairs and bodily fluids during a sexual
    assault. 
    387 F.3d at 1252
    . But the expert “offered precious little in
    the way of a reliable foundation or basis for his opinion.” 
    Id. at 1265
    . While the expert was eminently qualified to testify and
    formed his opinion based on his experience in the field, we affirmed
    the exclusion of his testimony because he never explained how he
    was able to reach his opinion. 
    Id.
     Because he did not so explain,
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 25 of 47
    20-11266               Opinion of the Court                        25
    we said that “it would be very difficult indeed for the district court
    (or for that matter the jury) to make even an informed assessment,
    let alone to verify” that the opinion was reliable. 
    Id.
     We reempha-
    sized that “it remained the burden of the proponent of this testi-
    mony to explain how that experience led to the conclusion he
    reached.” 
    Id.
    Hughes v. Kia Motor Corp., 
    766 F.3d 1317
     (11th Cir. 2014),
    is another such example. In Hughes, the expert sought to testify
    that the plaintiff would not have sustained a fatal injury had her
    automobile been equipped with a “shut-off switch,” claiming to
    have reached this conclusion “based on the scientific method” but
    “without further explaining how he tested his hypothesis to sup-
    port his conclusions.” 
    Id.
     at 1329–30. Relying on Frazier, we con-
    cluded that the district court did not abuse its discretion in exclud-
    ing the expert’s testimony. Id. at 1329. And we noted that the ex-
    pert was unable to account for other factors that contributed to the
    death, such as the impact of the semi-truck, admitting that he
    lacked sufficient information to rule out any other causes. Id. at
    1330.
    Both cases hold obvious relevance to the issue presented. In
    both Frazier and Hughes, we affirmed the exclusion of expert evi-
    dence because the proponent of that testimony was unable to link
    the expert’s methodology—or lack thereof—to his conclusions.
    The same is true here. The district court concluded that Dr.
    Kosstrin was unable to adequately explain how he reached his con-
    clusions other than by pointing to the NCPP plant—which, as
    USCA11 Case: 20-11266        Date Filed: 02/15/2022      Page: 26 of 47
    26                      Opinion of the Court                  20-11266
    already mentioned, had a slew of additional variables not present
    in the Secure situation. As we have previously stated, “[s]omething
    [does not] become ‘scientific knowledge’ just because [it is] uttered
    by a scientist; nor can an expert’s self-serving assertion that his con-
    clusions were derived by the scientific method be deemed conclu-
    sive.” McDowell v. Brown, 
    392 F.3d 1283
    , 1299 (11th Cir. 2004)
    (quoting Daubert, 43 F.3d at 1315–16). Indeed, the “trial court’s
    gatekeeping function requires more than simply ‘taking the ex-
    pert’s word for it.’” Fed. R. Evid. 702 advisory committee’s note to
    2000 amendment (citing Daubert, 43 F.3d at 1319). Here, Dr.
    Kosstrin provided nothing but his word and own ipse dixit. He
    pointed to the NCPP plant and said, without any verifiable meth-
    odology or consideration of the factors unique to that plant, that
    Secure would have experienced the same problems. The district
    court thus did not abuse its discretion by excluding his testimony.
    The same is also true of the district court’s decision to ex-
    clude Dr. Kosstrin’s testimony related to the value of the burners.
    Even setting aside the district court’s ruling as to qualifications on
    this issue, Dr. Kosstrin’s valuation of the gasifiers was based exclu-
    sively on his conclusion that the gasifiers were defective. Because
    that opinion was unreliable, his opinion as to value is also neces-
    sarily so.
    B. Did the district court err in granting summary judgment?
    As noted above, the district court entered summary judg-
    ment in Siemens’s favor on each of Secure’s claims against it.
    USCA11 Case: 20-11266          Date Filed: 02/15/2022        Page: 27 of 47
    20-11266                  Opinion of the Court                            27
    Before analyzing the claims on a count-by-count basis, however,
    two preliminary issues bear mentioning.
    First, the parties have both waived any arguments regarding
    which state’s law should apply. In the district court, the parties dis-
    puted whether the law of Kentucky, Missouri, or Florida law
    should apply to the non-contract claims. 5 In the district court’s or-
    der granting summary judgment, the court applied Florida law to
    each of the non-contract claims. And on appeal, neither party ar-
    gues that the district court erred in doing so.
    Choice of law is not jurisdictional. See Keeton v. Hustler
    Mag., Inc., 
    465 U.S. 770
    , 778 (1984) (“The question of the applica-
    bility of New Hampshire’s statute of limitations to claims for out-
    of-state damages presents itself in the course of litigation only after
    jurisdiction over respondent is established, and we do not think
    that such choice of law concerns should complicate or distort the
    jurisdictional inquiry.”). And, as such, it is waivable if the parties
    abandon the issue on appeal. See Mesa Air Grp. v. Delta Air Lines,
    Inc., 
    573 F.3d 1124
    , 1128 (11th Cir. 2009) (finding that where a party
    had failed to present a choice-of-law issue to the trial court, the is-
    sue was waived on appeal). Accordingly, we apply Florida law to
    all of the non-contract claims.
    Second, the district court granted summary judgment
    against Secure on four of its claims—breach of implied warranty of
    5 There is no dispute that New York law applies to the contract claims.
    USCA11 Case: 20-11266           Date Filed: 02/15/2022         Page: 28 of 47
    28                         Opinion of the Court                      20-11266
    fitness, fraudulent misrepresentation, recission-fraud, and recis-
    sion-lack of consideration—based solely on the theory that, be-
    cause these claims were premised on a design defect, Secure
    needed an expert witness to testify as to the defect. And because
    Dr. Kosstrin had been excluded—properly, as we have already con-
    cluded—Secure had no such expert testimony. The district court,
    however, did not identify a single case holding that a plaintiff is re-
    quired to present expert testimony to bring a claim for fraud or
    breach of implied warranty. Instead, the district court borrowed
    language from cases discussing the causation element in negligence
    and strict liability actions and applied it here. For example, the dis-
    trict court cited Small v. Amgen, Inc., 723 F. App’x 722, 726 (11th
    Cir. 2018), an unpublished products liability case from this Court,
    for the proposition that “in complex cases where a jury is asked to
    assess complex medical or scientific issues outside the scope of a
    layperson’s knowledge, an expert’s testimony is required.” In do-
    ing so, the district court ignored the first clause of the sentence stat-
    ing “[r]egarding discovery and proof of causation.” Indeed, each of
    the cases cited by the district court (and Siemens) were focused
    only on the element of causation in tort suits.
    In Lucas v. Firestone Tire & Rubber Co., 
    458 F. 2d 495
    , 497
    (5th Cir. 1972), 6 we were confronted head-on with the task of
    6 See Bonner v. City of Prichard, 
    661 F.2d 1206
    , 1207 (11th Cir. 1981) (en banc)
    (adopting as binding precedent all of the decisions of the former Fifth Circuit
    prior to October 1, 1981).
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 29 of 47
    20-11266                Opinion of the Court                        29
    “mak[ing] the initial determination as to the state of Florida law
    governing breach of implied warranty cases as that law applies to
    the question presented, i.e., whether plaintiff must introduce the
    testimony of an expert that the [product] was defective.” We an-
    swered that question in the negative: “There is no burden on plain-
    tiff to prove a specific defect by an expert witness as distinguished
    from other proof. The fact of a malfunction and also of a defect
    may be proven by direct or circumstantial evidence.” 
    Id.
     We are
    aware of no case post-dating Lucas that stands for the contrary po-
    sition, and neither party has directed our attention to one. As such,
    we apply the rule of Lucas and hold that Florida law does not re-
    quire plaintiffs in contract cases to prove the defective nature of the
    product at issue with expert testimony.
    Although the district court’s reason for granting summary
    judgment was incorrect, we can, of course, affirm on any basis sup-
    ported by the record. See Lucas v. W.W. Grainger, Inc., 
    257 F.3d 1249
    , 1256 (11th Cir. 2001). We thus will analyze each of Secure’s
    claims to determine whether the district court correctly granted
    summary judgment.
    1. Count 1: Anticipatory Repudiation
    The parties agree that New York law governs the contract
    claims in this case, including Secure’s anticipatory repudiation
    claim. Under New York law, “[a]nticipatory repudiation occurs
    when, before the time for performance has arisen, a party to a con-
    tract declares his intention not to fulfill a contractual duty.” Lu-
    cente v. Int’l Bus. Machs. Corp., 
    310 F.3d 243
    , 258 (2d Cir. 2002).
    USCA11 Case: 20-11266      Date Filed: 02/15/2022    Page: 30 of 47
    30                     Opinion of the Court               20-11266
    An anticipatory breach of contract—also known as an
    anticipatory repudiation—“can be either a statement
    by the obligor to the obligee indicating that the obli-
    gor will commit a breach that would of itself give the
    obligee a claim for damages for total breach or a vol-
    untary affirmative act which renders the obligor una-
    ble or apparently unable to perform without such a
    breach.”
    Princes Point LLC v. Muss Dev. L.L.C., 
    87 N.E.3d 121
    , 133 (N.Y.
    2017) (quoting Norcon Power Partners v. Niagara Mohawk Power
    Corp., 
    705 N.E.2d 656
    , 659 (N.Y. 1998)). For an anticipatory repu-
    diation to occur, “the expression of intent not to perform by the
    repudiator must be ‘positive and unequivocal.’” 
    Id.
     (quoting Te-
    navision, Inc. v. Neuman, 
    379 N.E.2d 1166
    , 1168 (N.Y. 1978)); see
    also Rachmani Corp. v. 9 E. 96th St. Apartment Corp., 
    211 A.D. 2d 262
    , 267 (N.Y. App. Div. 1995) (requiring a “definite and final com-
    munication of the intention to forego performance before the an-
    ticipated breach may be the subject of legal action”). “Mere expres-
    sion of difficulty in tendering the required performance, for exam-
    ple, is not tantamount to a renunciation of the contract.” Rach-
    mani, 211 A.D. at 267.
    While an anticipatory breach obviates the need for the non-
    breaching party to tender performance, the nonbreaching party
    must nonetheless demonstrate that it was “ready, willing[,] and
    able to perform its obligations under the contract” at the time its
    performance would have been due in order to recover damages.
    Inter-Power of N.Y. Inc. v. Niagara Mohawk Power Corp., 686
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 31 of 47
    20-11266               Opinion of the Court                        
    31 N.Y.S.2d 911
    , 913 (N.Y. App. Div. 1999); accord Towers Charter &
    Marine Corp. v. Cadillac Ins. Co., 
    894 F.2d 516
    , 523 (2d. Cir. 1990).
    This principle is merely an application of the general rule that the
    complaining party must demonstrate that the breach caused him
    injury; “[t]o do this he must prove that he intended to and was able
    to perform when his performance was due.” Scholle v. Cuban-
    Venezuelan Oil Voting Tr., 
    285 F.2d 318
    , 320 (2d Cir. 1960).
    In addition, causation is an essential element of the claim.
    See Bausch & Lomb Inc. v. Bressler, 
    977 F.2d 720
    , 728, 731 (2d Cir.
    1992). The plaintiff “must demonstrate that the damages were
    caused by and are ‘directly traceable to the [defendant’s] breach.’”
    
    Id. at 731
     (alteration in original) (quoting Kenford Co. v. County of
    Erie, 
    493 N.E.2d 234
    , 235 (N.Y. 1986)). Where the ultimate trans-
    action would have failed, and where the plaintiff’s claimed dam-
    ages would have resulted even if no breach occurred, the plaintiff
    cannot prove that his damages resulted from the defendant’s con-
    duct. See 
    id.
     (affirming the district court judgment because the
    plaintiff sought “to recover for a loss on a transaction separate from
    the transaction that gave rise to the breach”).
    Secure claims that Siemens anticipatorily breached by leav-
    ing the coal gasification market because, in doing so, Siemens
    demonstrated that it would not honor its obligations under the
    2012 LSA. The district court identified two problems with the an-
    ticipatory repudiation claim: (1) that Secure could not prove causa-
    tion, and (2) that Secure could not prove it was ready, willing, and
    able to perform. We agree with the district court.
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 32 of 47
    32                     Opinion of the Court                 20-11266
    First, Secure is unable to prove causation. The district court
    determined that there was no evidence of a causal relationship be-
    tween Siemens’s anticipatory repudiation and the damages Secure
    sought because Secure, at the time of the alleged repudiation, had
    not obtained the necessary financing for its project. Furthermore,
    the district court noted that Secure’s claimed damages from the
    “useless equipment and technology” would have resulted regard-
    less of whether Siemens exited the gasification market. Secure re-
    sponds by pointing to the fact that their proposed EPC financiers
    were troubled by the performance of the Siemens gasifiers. But
    there is an obvious problem with Secure’s theory: the discussion
    with the financiers occurred in 2012 while the alleged repudiation
    occurred more than three years later, in February 2016. Secure has
    not presented any record evidence tying an inability to secure fi-
    nancing after Siemens’s alleged breach and, as such, has no evi-
    dence of causation. We can affirm on this basis alone.
    Second, the “ready, willing, and able” requirement also bars
    recovery. New York law requires the “plaintiff alleging an antici-
    patory breach of contract [to] show (1) that the defendant insisted
    upon terms not contained in the contract; and (2) that the plaintiff
    was ‘ready, willing, and able to perform its own obligations under
    the contract when performance was due.’” United States v. Hon,
    
    17 F.3d 21
    , 26 (2d Cir. 1994) (quoting Towers Charter, 
    894 F.2d at 523
    ). The district court concluded that Secure was not ready, will-
    ing, and able to perform because Secure was in financial ruin and
    had missed multiple payments on the contract before the alleged
    USCA11 Case: 20-11266        Date Filed: 02/15/2022      Page: 33 of 47
    20-11266                Opinion of the Court                          33
    repudiation. We agree. For Secure to succeed on its anticipatory
    repudiation claim under New York law, Secure had to show that,
    at the time Siemens exited the gasification market (and thus, in Se-
    cure’s telling, anticipatorily repudiated the contract), Secure was
    able to perform its own obligations. But because Secure had al-
    ready missed multiple payments under the contract at that time,
    Secure itself was already in breach, and thus unready and unable to
    perform. And finally, we note that when Siemens decided to exit
    the gasification market in 2015, it promised to continue supporting
    its existing projects, including Secure’s.
    Therefore, the district court did not err in granting summary
    judgment as to Count 1.
    2. Count 2: Breach of Implied Warranty
    Under New York law, a contract may explicitly disclaim any
    implied warranties. To disclaim a warranty of fitness for purpose,
    it is sufficient for the contract to state that that “[t]here are no war-
    ranties which extend beyond the description on the face hereof.”
    See 
    N.Y. U.C.C. § 2
    –316(2). If the written disclaimer is agreed-
    upon, “a party cannot justifiably rely on a representation that is
    specifically disclaimed in an agreement.” Dallas Aerospace, Inc. v.
    CIS Air Corp., 
    352 F.3d 775
    , 785 (2d Cir. 2003); see also, e.g., Maltz
    v. Union Carbide Chems. & Plastics Co., 
    992 F. Supp. 286
    , 304
    (S.D.N.Y. 1998) (relying on New York law and explaining that an
    implied warranty of fitness for a particular purpose claims fail as
    matter of law if purchase agreement specifically disclaims them).
    USCA11 Case: 20-11266      Date Filed: 02/15/2022     Page: 34 of 47
    34                     Opinion of the Court                20-11266
    In this case, the 2012 LSA—as well as the initial 2007 Con-
    tract and the 2010 LSA—contained a disclaimer of any implied war-
    ranties, including for a particular purpose. Specifically, the con-
    tracts disclaimed, in all capital letters, “all other warranties and
    guarantees, whether statutory, expressed or implied, including all
    implied warranties of merchantability and fitness for purpose, and
    all warranties arising from course of dealing or usage of trade.”
    The district court denied Siemen’s motion to dismiss this
    claim so that Secure could pursue a theory that the contract was
    unconscionable. Secure, however, failed to do so in the district
    court and does not attempt to do so here. Unable to show uncon-
    scionability, Secure’s claim must fail. Because the contract dis-
    claims any warranties of fitness, the breach of implied warranty
    claim was appropriately dismissed at summary judgment.
    As discussed earlier, we apply Florida law to the remainder
    of Secure’s claims. And as previously noted, Secure voluntarily dis-
    missed Count 3, which asserted fraudulent inducement based on
    Siemens’s alleged misrepresentations regarding its support for the
    project after it had already made the strategic decision to exit the
    gasification business, and is not a subject of this appeal.
    3. Count 4 & Count 5: Fraudulent Misrepresentation – Failure to
    Disclose Defects & Recission - Fraud
    Secure’s two fraud claims—for which it seeks both damages
    and recission of the contract—are premised on the same theory:
    because Siemens was “aware of several material design defects in
    USCA11 Case: 20-11266         Date Filed: 02/15/2022       Page: 35 of 47
    20-11266                 Opinion of the Court                           35
    the” gasifiers that were not discoverable by Secure and “had de-
    monstrably superior knowledge of the material defects,” Siemens
    had a “duty to disclose to plaintiffs the existence of [the] material
    design defects.” These fraud claims are thus premised solely on the
    notion that the gasifiers are, in fact, defective.
    These claims fail because they are, in essence, simply a re-
    statement of Secure’s contract and breach of warranty claims. Flor-
    ida’s independent-tort doctrine requires a fraud claim to be “inde-
    pendent of a breach of contract claim”—i.e., for the “fraud allega-
    tions” to be “separate and distinct from defendants’ performance
    under the contract.” Glob. Quest, LLC v. Horizon Yachts, Inc., 
    849 F.3d 1022
    , 1031 (11th Cir. 2017). This is because a “breach of con-
    tract, alone, cannot constitute a cause of action in tort. . . . It is only
    when the breach of contract is attended by some additional con-
    duct which amounts to an independent tort that such a breach can
    constitute [a separate action in tort].” Elec. Sec. Sys. Corp. v. S. Bell
    Tel. & Tel. Co., 
    482 So.2d 518
    , 519 (Fla. Dist. Ct. App. 1986); ac-
    cord HTP, Ltd. v. Lineas Aereas Costarricenses, S.A., 
    685 So. 2d 1238
    , 1239 (Fla. 1996) (noting that the independent tort doc-
    trine “requires proof of facts separate and distinct from the breach
    of contract”).
    Florida courts routinely apply the independent tort doctrine
    to dismiss tort claims that are in fact founded on a contractual duty.
    In Electronic Security Systems, for example, a corporation entered
    into a contract with the Southern Bell telephone company for the
    placement of an advertisement in the yellow pages. 482 So. 2d at
    USCA11 Case: 20-11266       Date Filed: 02/15/2022    Page: 36 of 47
    36                     Opinion of the Court                20-11266
    518. That contract had a limited liability provision that limited the
    corporation’s remedy to liquidated damages. See id. at 519. When
    the advertisement did not appear in the directory, as contemplated
    by the contract, the corporation sued Southern Bell under both
    contract and tort theories. See id. The Florida appellate court sum-
    marily dismissed each of the corporation’s tort claims under the
    independent tort doctrine, concluding that the only duty at issue in
    the case was contractual. See id.
    The same is true here. Recall the relevant facts. The fraud
    claims are not—and indeed could not—be premised on any fraud-
    ulent misrepresentation or omission that pre-dated the parties’ con-
    tractual relationship. This is because the 2010 Completion Agree-
    ment that the parties signed released both parties of any claims that
    pre-dated that agreement. In other words, Secure’s claim is that
    the fraud post-dated the 2010 Completion Agreement and predated
    the 2012 Completion Agreement and 2012 LSA. The question thus
    becomes: before the 2012 Completion Agreement and 2012 LSA
    were signed, where did Siemens’s duty of disclosure come from—
    was it the common law duty to disclose (as required for a fraud
    claim) or its contractual duty to perform (which would foreclose a
    fraud claim)? The answer is obviously the latter. Before the 2012
    Completion Agreement and 2012 LSA were signed, Siemens’s duty
    to share information with Secure, and to deliver conforming prod-
    ucts, arose from the parties’ 2010 and 2007 agreements. This was
    the preliminary opinion formed by the district court at the motion
    to dismiss stage, and Secure has not presented evidence or legal
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 37 of 47
    20-11266                Opinion of the Court                        37
    authority establishing an independent common-law duty to dis-
    close since that time. Siemens’s performance guarantees and dis-
    closure guarantees were duties it owed to Secure by contract. And,
    even if Secure was fraudulently induced into the original 2007
    agreement, Secure not only waived all fraud claims in the 2010
    Contract, but it voluntarily dismissed its claim for fraudulent in-
    ducement during the course of this litigation. Therefore, the dis-
    trict court did not err in granting summary judgment on this claim.
    4. Count 6: Recission-Lack of Consideration
    Turning to the last count, Florida law does not recognize the
    claim of recission based on lack of consideration. See Webb v. Kirk-
    land, 
    899 So. 2d 344
    , 346 (Fla. Dist. Ct. App. 2005) (noting that,
    “[w]ith respect to recission, a court of equity will ordinarily rescind
    or cancel an instrument only for fraud, accident or mistake and not
    because of the mere want or failure of consideration” (quoting Ren-
    nolds v. Rennolds, 
    312 So. 2d 538
    , 541 (Fla. Dist. Ct. App. 1975))).
    While the caselaw does hypothesize that a case might exist where
    lack of consideration should result in equitable, rather than legal,
    relief, Secure does not identify any case in which a Florida court
    has granted such relief. And, in any event, Secure does not even
    attempt to show that legal relief would be insufficient here.
    ***
    Accordingly, although the district court erred in its conclu-
    sion that Florida law requires expert testimony regarding the de-
    fective nature of a product in contract-based actions, we affirm the
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 38 of 47
    38                      Opinion of the Court                 20-11266
    district court’s grant of summary judgment in Siemens’s favor on
    Secure’s claims.
    C. Did the district court err in denying leave to amend?
    Next, we address the district court’s denials of Secure’s mo-
    tions for leave to amend. As noted above, we “will only reverse a
    district court’s denial of a motion to amend in instances in which
    the district court has clearly abused its discretion.” Henson, 770
    F.2d at 1574. Normally, to acquire permission to amend one’s
    pleading, a litigant need only establish the relatively lenient stand-
    ard of Rule 15(a), which states that leave shall be granted “when
    justice so requires.” However, when a party moves to amend their
    complaint after the deadline for doing so set by the district court in
    its scheduling order, a litigant must also “show good cause why
    leave to amend the complaint should be granted.” Smith v. Sch.
    Bd. of Orange Cnty., 
    487 F.3d 1361
    , 1366 (11th Cir. 2007) (per cu-
    riam); see also Fed. R. Civ. P. 16(b); Sosa v. Airprint Sys., Inc., 
    133 F.3d 1417
    , 1419 (11th Cir.1998) (per curiam) (“If we considered
    only Rule 15(a) without regard to Rule 16(b), we would render
    scheduling orders meaningless and effectively would read Rule
    16(b) and its good cause requirement out of the Federal Rules of
    Civil Procedure.”). We have recognized that Rule 16’s “good cause
    standard precludes modification [of the scheduling order] unless
    the schedule cannot be met despite the diligence of the party seek-
    ing the extension.” See Sosa, 
    133 F.3d at 1418
     (quoting Fed. R. Civ.
    P. 16 advisory committee’s note); see also Johnson v. Mammoth
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 39 of 47
    20-11266                Opinion of the Court                        39
    Recreations, Inc., 
    975 F.2d 604
    , 609 (9th Cir. 1992) (“If [a] party was
    not diligent, the [good cause] inquiry should end.”).
    In this case, Secure filed its first amended complaint on April
    21, 2017. Following a scheduling conference, the district court en-
    tered a scheduling order on May 18, 2017, which set a deadline to
    amend pleadings for June 1, 2017. Due to joint motions by the par-
    ties, the scheduling order was twice amended, but neither amend-
    ment changed the deadlines for amending pleadings.
    Secure first moved for leave to amend its complaint on De-
    cember 28, 2018—already more than a year after the deadline to
    amend pleadings had passed. Secure sought leave to amend its
    complaint to add new factual allegations and legal theories of re-
    covery, based largely on having finally completed its review of the
    large amount of documents produced to it by Siemens, as well as
    the depositions of current and former Siemens employees. The
    magistrate judge denied that motion, noting that “the breadth of
    document production was directly related to the breadth of [Se-
    cure’s] discovery requests, and Secure could not cry foul over get-
    ting what it asked for. Nor did Secure identify any testimony from
    the depositions that related to the proposed amendments. In addi-
    tion, the magistrate judge noted that discovery had already been
    ongoing for two years, and Secure provided no explanation as to
    why it was unable to uncover the information sooner. Finally, the
    magistrate judge noted that Secure had relied on the incorrect legal
    standard—Rule 15 instead of Rule 16.
    USCA11 Case: 20-11266       Date Filed: 02/15/2022    Page: 40 of 47
    40                     Opinion of the Court                20-11266
    Just a few days later, Secure moved to extend the trial date,
    in what it now admits was nothing but a ruse to amend its com-
    plaint. Because this was nothing more than an attempt to circum-
    vent the court’s previous order, it was summarily denied for essen-
    tially the same reasons.
    Eventually, the district court granted Siemens’s motion for
    summary judgment and denied Secure’s motion for summary
    judgment. After those rulings—and more than two years after the
    deadline to amend pleadings had passed, and just a few weeks be-
    fore trial was scheduled to commence—Secure moved for leave to
    amend its complaint a third time. The district court denied that
    request. In its denial, the district court forcefully reminded Secure
    that its litigation tactics “in this regard run dangerously close to
    sanctionable actions under [Federal Rule of Civil Procedure] 11.”
    We had occasion to apply Rule 16 to similar circumstances
    to these in Smith v. School Board of Orange County. There, the
    plaintiff sought leave to amend his complaint (after the deadline for
    doing so set by the scheduling order) because, in his view, discov-
    ery had “produced new violations of the [l]aw that must be ad-
    dressed within the counts of the complaint.” 
    487 F.3d at 1367
     (al-
    teration in original). The district court denied leave to amend be-
    cause the defendant’s motion for summary judgment had already
    been pending for a month and because the plaintiff failed to explain
    why the facts underlying the amendment were undiscoverable pre-
    viously. See 
    id.
     We affirmed, noting the “extreme untimeliness of
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 41 of 47
    20-11266               Opinion of the Court                        41
    [the plaintiff’s] motion and his lack of a complete showing of good
    cause.” 
    Id.
    The district court’s rulings here were not an abuse of discre-
    tion for the same reasons articulated in Smith. To satisfy Rule 16,
    a litigant must show that it could not meet the scheduling order
    “despite the diligence of the” litigant. Sosa, 
    133 F.3d at 1418
    . Here,
    Secure was seeking leave to replead already-dismissed claims and
    add new facts and theories of recovery, including a fraudulent in-
    ducement claim that Secure says it was able to plead “with greater
    particularity,” more than a year after the deadline to amend plead-
    ings had passed. But, as Secure admitted, the facts that formed the
    basis of its amendment were available “at the earliest just prior to
    the amendment deadline.” (emphasis added). What Secure actu-
    ally complains of, then, is not that the facts were not ascertainable,
    but that it took Secure too long to conduct discovery. That is not
    due diligence. And it is thus not good cause. We affirm the district
    court’s denials of leave to amend.
    D. Did the district court err in denying Siemens’s ability to
    present its affirmative defense?
    The final issue for our consideration concerns the district
    court’s order denying Secure’s motion for a new trial and the dis-
    trict court’s related ruling on Siemens’s motion in limine. At issue
    is the scope of evidence Secure was permitted to present at trial.
    As noted previously, the only affirmative breach-of-contract claim
    that Secure advanced throughout the trial was an anticipatory re-
    pudiation claim. However, defensively (i.e., in response to
    USCA11 Case: 20-11266       Date Filed: 02/15/2022     Page: 42 of 47
    42                     Opinion of the Court                 20-11266
    Siemens’s breach of contract counterclaim regarding the 2012
    LSA), Secure asserted a broader breach-of-contract based affirma-
    tive defense. As its eighth affirmative defense, Secure asserted that
    “[t]o the extent Siemens seeks recovery in contract, Siemens mate-
    rially breached the terms and conditions of said contract and is en-
    titled to no relief thereon.”
    In its motion in limine, Siemens sought clarification as to
    whether Secure would present evidence only of anticipatory repu-
    diation or whether Secure would be permitted to present evidence
    of other alleged breaches of contract, which Secure had not yet
    raised in the litigation. Specifically, the other theories that Secure
    sought to introduce evidence of were: (1) Siemens breached the
    contracts by delivering defective gasification equipment; and (2)
    Siemens breached the contracts by failing to inform Secure of avail-
    able improvements to the gasification equipment and technology.
    The district court granted Siemens’s motion in limine and
    excluded any evidence Secure sought to present regarding the
    above-listed theories of breach of contract. Thereafter, Secure re-
    raised this issue in its motion for a new trial. In granting Siemens’s
    motion in limine and denying Secure’s motion for a new trial, the
    district court gave a number of justifications for its decision to ex-
    clude this evidence. First, the district court noted that Secure was
    attempting to advance a trial-by-surprise strategy. This affirmative
    defense, and the facts related to that defense, were not pled. And
    Secure’s own affirmative claim for breach of contract was premised
    exclusively on Siemens’s alleged anticipatory repudiation.
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 43 of 47
    20-11266                Opinion of the Court                        43
    Therefore, to allow Secure to present both a defense based on both
    anticipatory repudiation and other alleged breaches of contract
    was, in the eyes of the district court, fundamentally unfair to Sie-
    mens. Second, the district court noted that the failure to provide
    notice of improvements was not a material breach of the contract
    at issue. Third, and perhaps most importantly, the district court
    found that the evidence was not relevant, noting that Secure’s new
    theories of breach of contract (very much unlike the anticipatory-
    repudiation theory) could not have excused its performance under
    Siemens’s counterclaim because that counterclaim was only for the
    termination fee under the 2012 LSA.
    On appeal, Secure asks for reversal based only on the second
    theory it sought to add as part of its affirmative defense, arguing
    that the district court erred when it excluded evidence related to
    Siemens’s alleged breach in failing to notify Secure of improve-
    ments.
    We find no abuse of discretion in the district court’s ruling
    based on the relevant facts at issue here. On July 3, 2012, the parties
    entered into the 2012 LSA. That contract terminated and released
    all claims under the previous agreements between the parties and
    required Secure to make an approximately €12 million license fee
    payment. Two provisions of that contract are at issue here. First,
    under § 5.1, the 2012 LSA required Siemens to inform Secure “of
    any Improvements to the Technology which are developed or ac-
    quired and released for commercial application by Siemens,” and
    Secure had an option to contract for those improvements for an
    USCA11 Case: 20-11266       Date Filed: 02/15/2022    Page: 44 of 47
    44                     Opinion of the Court                20-11266
    additional fee. Second, under § 11.3.1, the 2012 LSA allowed Sie-
    mens to terminate the contract if Secure “fails to make any pay-
    ment when due” provided Siemens provided Secure a fifteen-day
    cure period. If Siemens exercised that option, the 2012 LSA pro-
    vided that Secure would owe to Siemens ninety-two percent of the
    licensing fee (more than €11 million). After Secure missed the
    deadline on its license fee payment, Siemens, in February 2016, of-
    fered Secure an extension on the deadline to pay. After Secure re-
    fused that extension, Siemens exercised its option to terminate the
    contract and, after providing Secure a cure period, invoiced Secure
    for ninety-two percent of the licensing fee.
    The issue is whether Siemens’s alleged breach of § 5.1 might
    somehow excuse Secure’s performance under § 11.3.1. As an initial
    matter, we agree with the district court that Secure should not be
    permitted to raise this theory because Secure had not put Siemens
    on notice of it. See Proctor v. Fluor Enters., Inc., 
    494 F.3d 1337
    ,
    1350 (11th Cir. 2007) (“In deciding waiver issues under [Fed. R. Civ.
    P.] Rule 8(c), this Court [examines] whether a plaintiff had notice
    of the unpled defense or was prejudiced by the lack of notice.”).
    The Federal Rules of Civil Procedure make clear that a defendant
    raising an affirmative defense must “affirmatively state” it. Fed. R.
    Civ. P. 8(c). And this requires, at the minimum, putting the plain-
    tiff on notice of the nature of the defense. See Blonder-Tongue
    Lab’ys, Inc. v. Univ. of Ill. Found., 
    402 U.S. 313
    , 350 (1971) (“The
    purpose of [Fed. R. Civ. P. 8(c)] is to give the opposing party no-
    tice.”).
    USCA11 Case: 20-11266        Date Filed: 02/15/2022     Page: 45 of 47
    20-11266                Opinion of the Court                        45
    In this case, Secure asserted a boilerplate affirmative defense,
    alleging only that Siemens’s breached the contract without any
    identification of either the legal theory of breach or the contractual
    provision at issue. And when Siemens moved for summary judg-
    ment on its breach of contract counterclaim regarding the 2012
    LSA, Secure responded to that motion without referencing § 5.1 of
    the contract. Given that Secure’s theory of breach of contract, as
    shown by its affirmative claim and its response to Siemens’s mo-
    tions, was premised only on anticipatory repudiation, we cannot
    say that the district court abused its considerable discretion on evi-
    dentiary matters by excluding Secure’s evidence relating to differ-
    ent breach-of-contract theories at trial.
    Moreover, the district court was also correct that the defense
    was legally inadequate, and therefore irrelevant. “In diversity ac-
    tions, we look to state law to inform the determination of whether
    a certain defense is ‘any other matter constituting an avoidance or
    affirmative defense’ under the federal rule.” Proctor, 
    494 F.3d at 1350
     (quoting Troxler v. Owens-Illinois, Inc., 
    717 F.2d 530
    , 532�
    (11th Cir. 1983)� . Here, New York law, which governs the contract
    claims, allows breach of contract to be raised as an affirmative de-
    fense. See L & L Excavating Corp. v. Abcon Assocs., Inc., 
    594 N.Y.S.2d 818
    , 820 (N.Y. App. Div. 1993). However, a “party’s obli-
    gation to perform under a contract is only excused where the other
    party’s breach of the contract is so substantial that it defeats the
    object of the parties in making the contract.” Frank Felix Assocs.,
    Ltd. v. Austin Drugs, Inc., 
    111 F.3d 284
    , 289 (2d Cir. 1997) (applying
    USCA11 Case: 20-11266       Date Filed: 02/15/2022    Page: 46 of 47
    46                     Opinion of the Court                20-11266
    New York Law). In other words, “a non-breaching party’s obliga-
    tion to perform is excused only when there is a material breach by
    the other party.” AKTIV Assets LLC v. Centerbridge Partners,
    L.P., No. 653259/2019, 
    2019 WL 7165927
    , at *7 (N.Y. Sup. Ct. Dec.
    24, 2019) (citing Smoley v. Carole Hochman Design Grp., Inc., 
    79 A.D.3d 540
    , 541 (1st Dep’t 2010)). And whether a breach is material
    can be decided as a matter of law. See id.; Cont’l Ins. Co. v. RLI
    Ins. Co., 
    555 N.Y.S.2d 325
    , 328 (N.Y. App. Div. 1990); see also Frank
    Felix Assocs., 
    111 F.3d at 289
    . “[I]n determining whether [a] mate-
    rial breach relieves non-breaching party’s obligation to perform,
    ‘the extent to which the agreement provides for performance with-
    out delay’ should be considered.” Frank Felix Assocs., 
    111 F.3d at 289
     (quoting Restatement (Second) of Contracts § 242(c)).
    The district court ruled that, as a matter of law, the breach
    asserted by Secure was not material, in part because the 2012 LSA
    did not impose any deadline on Siemens to provide notice of the
    improvement and Secure had to pay for any improvements. Id.
    (“In determining if [Siemens’s] breach defeated the object of the
    [2012 LSA], we must consider the special purpose of the contract”
    and look to “the extent to which the injured party will be deprived
    of the benefits [it] reasonably expected”(citing Restatement (Sec-
    ond) of Contracts § 241)). Moreover, the record evidence estab-
    lishes that Siemens did provide Secure notice of design improve-
    ments on October 31, 2012, during a call between SK, Siemens, and
    Secure, in which Siemens indicated that it would include the design
    improvements if Secure paid for the re-engineering. At the time of
    USCA11 Case: 20-11266       Date Filed: 02/15/2022   Page: 47 of 47
    20-11266               Opinion of the Court                      47
    Secure’s breach, then, Secure was already aware of the improve-
    ments. Secure, however, missed its licensing fee payments due in
    February 2013 and December 2015 after Siemens provided notice
    of the improvements. Indeed, Secure stipulated that it was unable
    to perform under the terms of the 2012 LSA and therefore could
    not have paid for the improvements, as the district court held, even
    if Secure had chosen to obtain them. As such, the notice for those
    improvements could not have been the reason Secure itself
    breached the contract.
    The district court was thus right to conclude that Siemens’s
    alleged breach—not providing notice of the improvements
    sooner—was not material to the contract. Because the contract did
    not impose any time limitation on when notice of improvements
    should be given, and because the record evidence established that
    Secure had notice of the improvements before Secure failed to ten-
    der payment, Siemens’s breach was irrelevant to the claim pre-
    sented.
    IV.    CONCLUSION
    For the foregoing reasons, we affirm.
    AFFIRMED.