Southern Pan Services v. U.S. Department of Labor , 685 F. App'x 692 ( 2017 )


Menu:
  •                Case: 16-13417       Date Filed: 04/11/2017       Page: 1 of 14
    [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 16-13417
    ________________________
    Agency No. 08-0866
    SOUTHERN PAN SERVICES,
    Petitioner,
    versus
    U.S. DEPARTMENT OF LABOR,
    Respondent.
    ________________________
    Petition for Review of a Decision of the
    Occupational Safety and Health Review Commission
    ________________________
    (April 11, 2017)
    Before ROSENBAUM, JULIE CARNES, and GILMAN, * Circuit Judges.
    PER CURIAM:
    *
    Honorable Ronald Lee Gilman, United States Circuit Judge for the Sixth Circuit, sitting
    by designation.
    Case: 16-13417       Date Filed: 04/11/2017      Page: 2 of 14
    This case comes before the Court on appeal from the Occupational Safety
    and Health Review Commission’s (“Commission”) final decision finding that
    Appellant Southern Pan Services (“Southern Pan”) willfully violated two safety
    regulations promulgated pursuant to the Occupational Safety and Health Act
    (“OSHA”). We find no error.
    I.
    Because the facts of this case have been thoroughly recounted in the
    Commission’s decisions, we do not repeat them in detail here.                      To briefly
    summarize, this case arises out of the collapse of a partially constructed, six-story,
    poured-in-place concrete parking garage in Jacksonville, Florida. When the garage
    “pancaked” to the ground on December 6, 2007, one Southern Pan employee was
    killed and others were seriously injured.
    Southern Pan was hired as a subcontractor on the construction project. As
    part of its work, Southern Pan was specifically tasked with obtaining the shoring
    and reshoring1 drawings for the garage. Southern Pan was then responsible for
    building and installing the shoring and reshoring formwork to support the wet
    1
    A “shore” is defined by OSHA regulations as a “supporting member that resists a
    compressive force imposed by a load.” 
    29 C.F.R. § 1926.700
    (b)(7). It is placed on the level
    immediately below that which is currently being built and is used to support the formwork before
    and during the concrete pour. “Reshoring” is defined as “the construction operation in which
    shoring equipment (also called reshores or reshoring equipment) is placed, as the original forms
    and shores are removed, in order to support partially cured concrete and construction loads.” 
    29 C.F.R. § 1926.700
    (b)(6). Reshoring is placed on the completed levels below and does not
    support the structure, but carries the load of the wet concrete placed above.
    2
    Case: 16-13417    Date Filed: 04/11/2017   Page: 3 of 14
    concrete loads during the construction process and placing the concrete loads for
    some of the concrete pours (although not the one that was being poured at the time
    of the accident).
    At the time of the garage’s collapse, Southern Pan had switched to the 1-
    over-2 shoring method, resulting in Southern Pan having removed the shoring and
    reshoring from the first three levels of the garage. It had done so in contravention
    of the engineering drawings at the site, which showed shoring and reshoring
    extending to the ground. When shoring and reshoring extends to the ground, the
    weight of any newly poured concrete loads is transferred through the formwork
    and is not carried by the structural elements of the partially constructed garage.
    Once the shoring and reshoring is removed from the lower levels, though, the
    structure itself must bear the weight of any newly poured wet concrete.
    On December 6, 2007, as another subcontractor was pouring the concrete for
    a portion of the sixth floor of the garage, the structure became unable to support
    the added weight of the newly poured wet concrete, in the absence of the shoring
    and reshoring continuing to the ground. The garage collapsed, an employee died,
    and other employees sustained numerous injuries.
    The Secretary of Labor (“Secretary”) investigated the incident and on June
    2, 2008, cited Southern Pan for two willful violations of OSHA. In the first willful
    violation, the Secretary found that Southern Pan violated 
    29 C.F.R. § 1926.701
    (a)
    3
    Case: 16-13417      Date Filed: 04/11/2017    Page: 4 of 14
    by failing to “have a qualified person determine if the formwork . . . would be
    capable of supporting the additional load of the wet concrete, exposing the
    employees to a structural collapse hazard.” In the second, the Secretary found
    Southern Pan to have willfully violated 
    29 C.F.R. §1926.703
    (a)(2) for failing to
    have all “[d]rawings or plans, including all revisions, for the . . . formwork
    (including shoring equipment) . . . available at the jobsite.” 2 Over the course of
    several written decisions, the Commission ultimately affirmed the willful-violation
    citations and assessed a total penalty of $125,000.00 against Southern Pan.
    On appeal to this Court, Southern Pan raises four issues. First, Southern Pan
    challenges the Commission’s application of 
    29 C.F.R. § 1926.701
    (a), arguing that
    the regulation does not apply to Southern Pan because it was not the employer
    “directly responsible for the concrete operations” at the time of the garage’s
    collapse. Second, Southern Pan argues that 
    29 C.F.R. § 1926.703
    (a)(2) did not
    require the creation of drawings showing the 1-over-2 shoring method. Third and
    fourth, Southern Pan challenges the Commission’s decisions that Southern Pan
    willfully violated each of 
    29 C.F.R. § 1926.701
    (a) and 
    29 C.F.R. §1926.703
    (a)(2),
    arguing that both findings of willful violations are not supported by substantial
    evidence.
    2
    The Secretary also cited Southern Pan for two “serious” violations of OSHA, but the
    Commission vacated both of these citations, and they are not before this Court on appeal.
    4
    Case: 16-13417    Date Filed: 04/11/2017   Page: 5 of 14
    II.
    Commission decisions “are entitled to considerable deference on appellate
    review.” Fluor Daniel v. Occupational Safety & Health Review Comm’n, 
    295 F.3d 1232
    , 1236 (11th Cir. 2002). We review the Commission’s findings of fact to
    determine whether they are supported by substantial evidence, which is “more than
    a scintilla.” J.A.M. Builders, Inc. v. Herman, 
    233 F.3d 1350
    , 1352 (11th Cir. 2000)
    (quoting Lewis v. Callahan, 
    125 F.3d 1436
    , 1440 (11th Cir. 1997)). We have
    noted that the Commission’s finding of willfulness is a finding of fact. Fluor
    Daniel, 
    295 F.3d at 1236
    .
    As for the Commission’s legal determinations, we review them for whether
    they are “arbitrary, capricious, an abuse of discretion, or otherwise not in
    accordance with law.”       
    5 U.S.C. § 706
    (2)(A).       Like our review of the
    Commission’s factual findings, this is a “highly deferential standard” of review.
    Fluor Daniel, 
    295 F.3d at 1236
    .
    We have carefully reviewed the administrative record, considered the
    parties’ arguments, and heard oral argument in this case. We now conclude that
    the Commission correctly applied 
    29 C.F.R. § 1926.701
    (a) to Southern Pan and
    that substantial evidence supports the Commission’s determination that Southern
    Pan willfully violated 
    29 C.F.R. § 1926.701
    (a) and 
    29 C.F.R. § 1926.703
    (a)(2).
    A.
    5
    Case: 16-13417     Date Filed: 04/11/2017   Page: 6 of 14
    With respect to Southern Pan’s first challenge, we affirm the Commission’s
    decision applying 
    29 C.F.R. § 1926.701
    (a) to Southern Pan as an “exposing
    employer.” The Commission’s decision concluded that Southern Pan had violated
    § 1926.701(a) when “construction loads were placed on a concrete structure or
    portion of a concrete structure without the employer having determined, based on
    information received from a person who was qualified in structural design, that the
    structure or portion of the structure was capable of supporting the loads.” Southern
    Pan argues that 
    29 C.F.R. § 1926.701
    (a) should not apply to it because the
    Secretary’s preamble to the final rule places responsibility for employee safety
    with the “person directly responsible for the concrete operations.” See Concrete
    and Masonry Construction Safety Standards, 
    53 Fed. Reg. 22,612
    -01, 22,617.
    Here, the parties agree that the “person directly responsible for the concrete
    operations” was not Southern Pan.
    But as the Commission’s decision emphasizes, and as we agree, this
    language in the rule’s preamble does not preclude application of the Commission’s
    multi-employer worksite doctrine (also referred to as the “exposing-employer
    doctrine”) to this case. As the Commission noted, “long-standing Commission
    precedent hold[s] that an employer whose own employees are exposed to a hazard
    or violative condition—an ‘exposing employer’—has a statutory duty to comply
    6
    Case: 16-13417     Date Filed: 04/11/2017     Page: 7 of 14
    with a particular standard even where it did not create or control the hazard.” See
    Anning-Johnson Co., 
    4 BNA OSHC 1193
    , 1198-99 (No. 3694, 1976).
    Here, the Commission correctly found that Southern Pan’s employees were
    exposed to the violative condition at the time of the garage’s collapse. As an
    exposing employer, then, Southern Pan was required under OSHA to “do what
    [was] ‘realistic’ under the circumstances to protect its employees from the hazard
    to which a particular standard is addressed even though literal compliance with the
    standard may [have been] unrealistic.” 
    Id. at 1199
    . Because Southern Pan did not
    undertake realistically available safety measures to protect its employees, the
    Commission correctly found that Southern Pan had violated § 1926.701(a).
    The Fifth Circuit’s decision in Southeast Contractors, Inc. v. Dunlop, 
    512 F.2d 675
     (5th Cir. 1975),3 does not preclude our application of 
    29 C.F.R. § 1926.701
    (a) to Southern Pan under the exposing-employer doctrine. The single-
    paragraph, per curiam opinion in Southeast Contractors refers favorably to former
    OSHA Chairman Moran’s dissent in that case, which Southern Pan argues supports
    its position.      In its entirety, our predecessor court’s opinion in Southeast
    Contractors states:
    It is unnecessary that we decide the constitutionality of
    the Occupational Safety and Health Act of 1970 and its
    3
    This Court is bound by the decisions issued by the Fifth Circuit prior to October 1,
    1981. See Bonner v. City of Prichard, 
    661 F.2d 1206
    , 1209 (11th Cir. 1981) (en banc).
    7
    Case: 16-13417     Date Filed: 04/11/2017    Page: 8 of 14
    enforcement procedures established by sections 5, 6, 8, 9,
    10, 11, 12, and 17, which matter is also pending and
    under submission before another panel of this Court in
    Atlas Roofing Company, Inc. v. Secretary of Labor, No.
    73-2249. We are in agreement with the well-reasoned
    dissent of Chairman Moran of the Occupational Safety
    and Health Review Commission in this matter, and
    especially with that portion pertaining to the general rule
    that a contractor is not responsible for the acts of his
    subcontractors or their employees; accordingly, that the
    tractor driver was not an employee of respondent.
    Therefore, respondent was not using the motor vehicle
    involved in this case at the time of the accident within the
    meaning of 
    29 C.F.R. § 1926
    .-601(b)(4), and the majority
    ruling of the Commission is erroneous.
    
    Id. at 675
    .
    Chairman Moran’s dissent, as referenced in Southeast Contractors, states
    that “there can be no violation of the Act by a respondent for failure to comply
    with a standard which charges some other employer with the duty of implementing
    the standard,” Southeast Contractors, Inc., 
    1 BNA OSHC 1713
    , 1716 (No. 1445,
    1974). But Southeast Contractors was decided in 1975, which was before the
    Commission articulated the current exposing-employer doctrine in Anning-Johnson
    in 1976. See Anning-Johnson Co., 4 BNA OSHC at 1198-99. And after Anning-
    Johnson, the Fifth Circuit concluded that the exposing-employer doctrine was
    reasonable. See Central of Ga. R. Co. v. Occupational Safety & Health Review
    Comm’n, 
    576 F.2d 620
    , 624 (5th Cir. 1978) (stating that “we think that the
    Commission’s allocation of burdens [in Anning-Johnson] is appropriate”).
    8
    Case: 16-13417     Date Filed: 04/11/2017   Page: 9 of 14
    Applying the exposing-employer doctrine, Southern Pan could have easily
    taken realistic measures to protect its employees from the hazard to which the
    standard in § 1926.701(a) is addressed—namely, complying with the shoring and
    reshoring drawings. The Commission did not abuse its discretion in applying the
    exposing-employer doctrine to Southern Pan under these circumstances.
    B.
    Having determined that the standard in 
    29 C.F.R. § 1926.701
    (a) applies to
    Southern Pan as an exposing employer, we must next consider whether the
    Commission’s finding that Southern Pan willfully violated 
    29 C.F.R. § 1926.701
    (a) rests on substantial evidence. After thorough consideration, and for
    all of the reasons discussed in the Commission’s decision, we find that it does.
    First, substantial evidence underlies the Commission’s finding that Southern
    Pan did not take reasonable measures, under the circumstances, to protect its
    employees from the hazard, particularly since (1) Southern Pan knowingly
    removed shoring and reshoring from the first three levels of the garage in deviation
    from the only engineering drawings it had; and (2) Southern Pan thereafter
    knowingly failed to provide inspectors with accurate drawings in order to
    determine if the structure could handle the additional load of wet concrete.
    Further, substantial evidence also supports the Commission’s classification
    of Southern Pan’s violation as willful. This Court has explained that a willful
    9
    Case: 16-13417     Date Filed: 04/11/2017    Page: 10 of 14
    violation is, “in its simplest form, ‘an intentional disregard of, or plain indifference
    to, OSHA requirements.’” Fluor Daniel, 
    295 F.3d at 1239
    .
    Here, the Commission relied on testimony from Southern Pan supervisors
    showing that they knew that Section 1926.701(a) required them to determine
    before each pour that the garage structure could withstand the added weight of
    newly poured wet concrete loads.           The testimony also showed that these
    supervisors knew that the lives of Southern Pan employees depended on these
    updated load-bearing calculations, yet the supervisors failed to make the
    calculations before removing the shoring and reshoring that preceded the pouring
    of more wet concrete onto the structure. In addition, the ALJ discredited one
    supervisor’s testimony that the shoring was removed as the result of a
    miscommunication. The ALJ found that testimony from other supervisors showed
    that that was not the case.          In short, substantial evidence supports the
    Commission’s finding that Southern Pan knew it needed revised load-bearing
    calculations once it removed the shoring and reshoring from the first three levels of
    the garage under OSHA standards but that Southern Pan voluntarily chose not to
    prepare such calculations.
    C.
    We also affirm the Commission’s finding that Southern Pan willfully
    violated 
    29 C.F.R. § 1926.703
    (a)(2). First, the Commission did not act arbitrarily
    10
    Case: 16-13417     Date Filed: 04/11/2017   Page: 11 of 14
    or capriciously in affirming the Secretary’s citation of Southern Pan under §
    1926.703(a)(2) for failing to maintain all plans, including revisions, on the jobsite.
    Southern Pan did not have written plans at the jobsite calling for its switch to 1-
    over-2 shoring and the resulting removal of shoring and reshoring from the first
    three levels of the garage. As the parties have stipulated, the only plans at the
    jobsite showed shoring and reshoring to the ground. So Southern Pan’s removal of
    the shoring and reshoring from the first three levels was in clear deviation from the
    plans at the jobsite. Southern Pan’s switch to the 1-over-2 shoring method was a
    “revision” for which § 1926.703(a)(2) plainly requires an updated drawing or plan.
    As the Commission reasonably explained, “[a]n employer’s obligation to
    create a drawing or plan that accurately represents the existing formwork is clear
    from the language of § 1926.703(a)(2), which requires that the ‘[d]rawings or
    plans, includ[e] all revisions.’ Indeed, OSHA has recognized that this provision is
    intended to prevent accidents that could result from improperly erected formwork,
    and written plans enable this protective purpose to be met.”
    Southern Pan argues that it should not be held liable under 
    29 C.F.R. § 1926.703
    (a)(2) because it complied, alternatively, with the standard laid out in 
    29 C.F.R. § 1926.703
    (e) for testing the strength of concrete before removing shoring.
    The Commission, however, concluded that § 1926.703(a)(2) and § 1926.703(e) are
    11
    Case: 16-13417    Date Filed: 04/11/2017   Page: 12 of 14
    not alternative standards but, rather, impose different obligations and work in
    tandem. We agree.
    As the Commission correctly explained, § 1926.703(e) addresses only the
    situation where shoring and reshoring is removed and no subsequent loads are then
    added. Section 1926.703(e)(2), for example, states that “[r]eshoring shall not be
    removed until the concrete being supported has attained adequate strength to
    support its weight and all loads in place upon it.” 
    29 C.F.R. § 1926.703
    (e)(2).
    This standard says nothing about the circumstances at issue here—where reshoring
    was being removed and then more loads were added—and is not a substitute for
    the requirement to have accurate written plans on the jobsite. Mere compliance
    with testing the strength of concrete under one circumstance is not a substitute for
    a jobsite requirement addressing a wholly separate circumstance.
    Second, we agree with the Commission that Southern Pan had the requisite
    knowledge of its Section 1926.703(a)(2) violation. Unlike the facts in Comtran
    Group, Inc. v. United States Department of Labor, 
    722 F.3d 1304
    , 1316 (11th Cir.
    2013), here, the facts do not support an understanding that a single supervisor went
    “rogue.” Rather, multiple Southern Pan supervisors knew that the shoring and
    reshoring was being removed from the first three levels of the garage in
    contravention of the only engineering plans at the site, and they ratified this
    conduct.
    12
    Case: 16-13417    Date Filed: 04/11/2017   Page: 13 of 14
    For example, testimony from Southern Pan supervisors shows that they
    visited and inspected the site multiple times over the course of the 46 days during
    which the shoring and reshoring was removed; they knew that revised plans did
    not exist at the site to reflect their removal of the shoring and reshoring; and yet
    they failed to order any revised plans. So substantial evidence underlies the
    Commission’s finding that Southern Pan had “eyes and ears” at the site, and this
    knowledge can be fairly imputed to Southern Pan.
    Finally, substantial evidence supports the Commission’s classification of
    Southern Pan’s violation of 
    29 C.F.R. § 1926.703
    (a)(2) as willful. Under the
    substantial-evidence standard, this Court does “not reweigh or re-examine the
    credibility choices made by the factfinder.” See Kelliher v. Veneman, 
    313 F.3d 1270
    , 1277 (11th Cir. 2002).       Here, the Commission heard testimony from
    Southern Pan employees and supervisors and determined that, despite knowing the
    importance of having written shoring plans at the site and knowing that the only
    plans at the site showed shoring and reshoring to the ground, multiple Southern
    Pan supervisors oversaw and ordered the removal of the shoring and reshoring on
    the first three levels of the garage over many days. The Commission cited this
    abundant testimony in support of its finding that the Southern Pan supervisors
    possessed “willful states of mind.” We find no error.
    13
    Case: 16-13417   Date Filed: 04/11/2017   Page: 14 of 14
    For the foregoing reasons, we affirm the Commission’s determination that
    Southern Pan willfully violated 
    29 C.F.R. § 1926.701
    (a) and 
    29 C.F.R. § 1926.703
    (a)(2).
    AFFIRMED.
    14