Mallory & Evans Contractors & Engineers, LLC v. Tuskegee University ( 2012 )


Menu:
  •                                                                       [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT           FILED
    ________________________ U.S. COURT OF APPEALS
    ELEVENTH CIRCUIT
    MARCH 27, 2012
    No. 11-10940
    JOHN LEY
    ________________________
    CLERK
    D.C. Docket No. 3:10-cv-00026-WKW-CSC
    MALLORY & EVANS CONTRACTORS & ENGINEERS, LLC,
    Plaintiff-Appellant,
    versus
    TUSKEGEE UNIVERSITY,
    Defendant-Appellee.
    ________________________
    Appeal from the United States District Court
    for the Middle District of Alabama
    ________________________
    (March 27, 2012)
    Before DUBINA, Chief Judge, COX, Circuit Judge, and HUNT,* District Judge.
    PER CURIAM:
    *
    Honorable Willis B. Hunt, Jr., United States District Judge for the Northern District of
    Georgia, sitting by designation.
    This case involves a contract dispute between the Plaintiff, Mallory & Evans
    Contractors & Engineers, LLC, and the Defendant, Tuskegee University.1 Mallory
    & Evans claims that Tuskegee has not paid it the full amount due under their contract.
    Tuskegee claims that Mallory & Evans failed to satisfy a condition precedent for
    payments in excess of the specified contract price. The district court agreed with
    Tuskegee. After thoughtfully considering the parties’ briefs, and with the benefit of
    oral argument, we find no reversible error. Therefore, we affirm.
    I. FACTS
    In 2009, Tuskegee contracted with Mallory & Evans for certain dormitory
    renovations. It is undisputed that the parties contemplated a fixed contract price for
    this work. It is also undisputed that the contract included the terms of Tuskegee’s
    Purchase Order. Item number 6 of the Purchase Order provided: “Prior approval must
    be granted by the Purchasing Department [of Tuskegee] if total exceeds amount
    1
    We raised earlier concerns about the district court’s jurisdiction in this case. Mallory &
    Evans invoked the court’s diversity jurisdiction. But because Mallory & Evans is a limited liability
    company, it must allege the citizenship of its members. See Rolling Greens MHP, L.P. v. Comcast
    SCH Holdings, L.L.C., 
    374 F.3d 1020
    , 1022 (11th Cir. 2004). The complaint did not identify the
    members of Mallory & Evans and did not allege their citizenship. After we raised this concern, we
    allowed Mallory & Evans to amend its complaint to allege the citizenship of its members. Mallory
    and Evans did so, but Tuskegee denied these allegations. On January 20, 2012, we entered a limited
    remand order and directed the district court to make jurisdictional findings about the citizenship of
    the members of Mallory & Evans. On remand, Tuskegee moved to amend its answer and admit that
    the members of Mallory & Evans are citizens of Georgia. The district court granted that motion.
    We are now satisfied that the district court had jurisdiction under 
    28 U.S.C. § 1332
    .
    2
    listed.” (Dkt. 31-4 at 2.) The amount listed was $3,850,535.00. The parties agree
    that Item number 6 created a condition precedent for payments in excess of $3.85
    million—namely, prior approval of those payments by Tuskegee’s Purchasing
    Department.
    It is undisputed that Mallory & Evans performed work outside the scope of the
    original renovation contract. But significantly, the renovation contract contains no
    relevant provision which excludes this additional work from the fixed contract price
    of $3.85 million or which protects Mallory & Evans from unforeseen contingencies.
    Instead, Mallory & Evans tried to modify the original contract (and increase the
    contract price) through proposed change orders. These proposed change orders
    identified the work not requested in the original contract. They also estimated the
    cost of this additional work.
    Over the course of the project, Mallory & Evans submitted the four proposed
    change orders relevant to this appeal to Clifford Wesson, Tuskegee’s construction
    manager. Pursuant to Tuskegee’s policy, Wesson was to review any proposed change
    order and, if the order caused the project to exceed the contract price, forward it to
    Tuskegee’s Purchasing Department for approval. If the proposed change order did
    not cause the project to exceed the contract price, Wesson did not have to forward it
    to the Purchasing Department. Mallory & Evans’s initial estimates for the cost of the
    3
    relevant proposed change orders kept the dormitory renovations within budget.
    Wesson instructed Mallory & Evans to proceed with the work, but did not forward
    the proposed change orders to the Purchasing Department.
    Additionally, over the course of the renovation, Tuskegee purchased equipment
    for Mallory & Evans to install. Because Tuskegee is exempt from state sales tax,
    these purchases (described as Tax Packages) allowed Tuskegee and Mallory & Evans
    to realize substantial tax savings. Mallory & Evans initially credited these Tax
    Packages toward Tuskegee’s final bill.
    In September 2009, Mallory & Evans had substantially completed its work and
    submitted its final pay request. That request sought payment for approximately
    $765,000. Tuskegee’s payments, including the Tax Packages for which it claimed
    credit, already totaled about $3.45 million. Thus, Mallory & Evans’s final pay
    request brought the project’s total cost to $4.2 million—roughly $400,000 more than
    the amount listed in the contract. Tuskegee refused to pay that amount, and instead
    paid about $380,000—the difference between what it had already paid (including the
    Tax Packages) and the $3.85 million contract price.
    II. PROCEDURAL HISTORY
    Mallory & Evans brought this suit to recover what it contends it is still owed
    under the contract. Before the district court, the parties agreed that Item number 6
    4
    created a valid condition precedent for payments in excess of $3.85 million. The
    court found that Tuskegee did not breach the renovation contract when it refused to
    pay more than $3.85 million because Mallory & Evans had not satisfied the condition
    by getting prior approval from Tuskegee’s Purchasing Department. Mallory & Evans
    countered that Tuskegee waived the condition precedent by clothing Wesson with
    apparent authority to approve the proposed change orders, and thereby to authorize
    payments in excess of the contract price.2 The district court rejected that argument
    and entered summary judgment for Tuskegee. In a Fed. R. Civ. P. 59 motion, Mallory
    & Evans asked the court to reconsider. In that motion, Mallory & Evans argued, for
    the first time, that Tuskegee had not paid the full contract price and that Tuskegee had
    ratified Wesson’s actions. The district court rejected these arguments as untimely and
    on their merits. Mallory & Evans now appeals the district court’s grant of summary
    judgment and the denial of its Rule 59 motion.
    III. ISSUES ON APPEAL
    Mallory & Evans raises the following issues on the appeal: (1) has Tuskegee
    paid the full contract price; (2) did Tuskegee waive the condition precedent in
    2
    Mallory & Evans also sought recovery under an implied contract theory and under the
    equitable doctrines of quantum meruit and unjust enrichment. The district court rejected these
    arguments as barred by the existence of an express contract covering the same subject matter. See,
    e.g., Brannan & Guy, P.C. v. City of Montgomery, 
    828 So. 2d 914
    , 921 (Ala. 2002); Kennedy v.
    Polar-BEK & Baker Wildwood P’ship, 
    682 So. 2d 443
    , 447 (Ala. 1996). Mallory & Evans has not
    pursued these claims on appeal.
    5
    Item number 6 when Wesson failed to forward the proposed change orders to the
    Purchasing Department; (3) did Tuskegee waive the condition precedent in
    Item number 6 by clothing Wesson with apparent authority to approve the proposed
    change orders; and (4) did Tuskegee waive the condition precedent in Item number
    6 by ratifying Wesson’s approval of the proposed change orders?
    IV. STANDARD OF REVIEW
    We review a grant of summary judgment de novo and apply the same standards
    that bound the district court. See Midrash Sephardi, Inc., v Town of Surfside, 
    366 F.3d 1214
    , 1222–23 (11th Cir. 2004) (citation omitted).
    We review the denial of a Rule 59 motion for abuse of discretion. Lockard v.
    Equifax, Inc., 
    163 F.3d 1259
    , 1267 (11th Cir. 1998). A party cannot use a Rule 59
    motion to “relitigate old matters, raise argument[s] or present evidence that could
    have been raised prior to the entry of judgment.” Michael Linet, Inc. v. Village of
    Wellington, Fla., 
    408 F.3d 757
    , 763 (11th Cir. 2005) (citation omitted).
    V. DISCUSSION
    The district court properly granted summary judgment in this case. It is
    undisputed that Item number 6 made prior approval from Tuskegee’s Purchasing
    Department a condition precedent under the contract for payments in excess of $3.85
    6
    million. It is undisputed that Mallory & Evans never obtained prior approval for its
    costs in excess of that amount.
    Instead, Mallory & Evans contends that Tuskegee waived the condition
    precedent in Item number 6 because Wesson failed to forward its proposed change
    orders to Tuskegee’s Purchasing Department. It says that after it had submitted the
    proposed change orders to Wesson, it had done all it could do to obtain approval of
    those orders. Therefore, it says we should excuse its failure to satisfy the condition.
    Mallory & Evans’s argument is misguided. Item number 6 clearly requires that
    “[p]rior approval must be granted by the Purchasing Department if total exceeds
    amount listed.” (Dkt. 31-4 at 2.) Mallory & Evans cannot seriously contend that the
    mere submission of a proposed change order would guarantee the Purchasing
    Department’s approval of that order, even if Wesson had already given it his blessing.
    The contract plainly required “prior approval” from the Purchasing Department
    before Tuskegee would pay more than $3.85 million under the contract. If Mallory
    & Evans wanted to get paid for change orders that caused the project’s costs to
    exceed $3.85 million, it should have parked its equipment and waited for the
    Purchasing Department’s approval. When Mallory & Evans kept working without
    that approval, it did so at its peril. And, Mallory & Evans’s own records show that
    7
    it knew the Purchasing Department had not approved any of the relevant proposed
    change orders before it largely finished the work. Thus, this argument fails.
    Mallory & Evans also contends that Tuskegee clothed Wesson with apparent
    authority to approve the proposed change orders and, thereby authorize payments in
    excess of $3.85 million. Apparent authority exists when a principal represents that
    an agent has authority to act and a third party reasonably relies on that representation
    to his detriment. See McLemore v. Hyundai Motor Mfg. Ala., LLC, 
    7 So. 3d 318
    , 329
    (Ala. 2008). Here, Mallory & Evans bore the burden of establishing Wesson’s
    apparent authority to approve payments in excess of $3.85 million. See Johnson v.
    Shenandoah Life Ins. Co., 
    281 So. 2d 636
    , 640 (Ala. 1973). But Mallory & Evans
    identified no representations by Tuskegee which even suggest that Wesson had such
    authority. Moreover, the plain language of Item number 6 put Mallory & Evans on
    notice that Wesson lacked such authority. Because these are the only two arguments
    Mallory & Evans offered in opposition to Tuskegee’s motion for summary judgment,
    we affirm the grant of summary judgment.
    We also affirm the denial of Mallory & Evans’s Rule 59 motion. In that
    motion, Mallory & Evans raised two new arguments: (1) that Tuskegee did not pay
    it the full contract price because the Tax Packages were erroneously credited to its
    final bill, and (2) that Tuskegee ratified Wesson’s approval of the relevant change
    8
    orders.3 The district court rejected these arguments as an attempt to “relitigate old
    matters, raise argument[s] or present evidence that could have been raised prior to the
    entry of judgment.” Michael Linet, Inc., 
    408 F.3d at 763
     (citation omitted). This was
    not an abuse of discretion.
    Although we are not required to address the substance of Mallory & Evans’s
    new arguments, we note that the district court properly rejected them on the merits.
    First, Mallory & Evans contends that Tuskegee has not paid it the full contract price.
    It claims that the district court erroneously credited the value of the Tax Packages
    toward Tuskegee’s final bill. After subtracting these amounts from the final bill,
    Mallory & Evans claims that an unpaid balance of nearly $550,000 remains on the
    contract price. This argument is belied by Mallory & Evans own statements during
    this case. In its brief in opposition to summary judgment, Mallory & Evans treated
    the $3.85 million contract price as including the Tax Packages. In its summary
    judgment order, the district court found it undisputed that Tuskegee had paid the full
    contract price. Only later, after entry of judgment, did Mallory & Evans claim the
    contract price did not include the Tax Packages. The district court properly rejected
    this argument as meritless.
    3
    In its initial brief, Mallory & Evans treats these arguments as if it raised them in opposition
    to Tuskegee’s motion for summary judgment. They did not, and we review them accordingly.
    9
    Mallory & Evans also contends that Tuskegee ratified Wesson’s approval of
    the relevant proposed change orders. A principal ratifies an agent’s actions when:
    (1) the agent’s actions are unauthorized, see Tuskegee Inst. v. May Refrigeration Co.,
    
    344 So. 2d 156
    , 158 (Ala. 1977); and (2) the principal accepts the benefits of those
    actions with “full knowledge of all the material facts” or when he could have learned
    of those facts through “reasonable diligence,” see Dusenberry v. First Nat’l Bank of
    Birmingham, 
    122 So. 2d 716
    , 721 (Ala. 1960). Even if we assume that Wesson’s
    actions were unauthorized, Mallory & Evans offered no evidence showing that
    Tuskegee knew the relevant proposed change orders would cause the project’s costs
    to exceed $3.85 million. Nor was Tuskegee in a position to discover the true costs
    of those proposed change orders. In fact, Mallory & Evans did not know the final
    costs of the proposed change orders as late as two weeks prior to submitting its final
    pay request in September 2009. (Dkt. 65 at 9.) By that time, Mallory & Evans had
    already done most of the work. If Mallory & Evans did not know the true costs at
    that late date, it cannot seriously contend that Tuskegee could have discovered them
    by exercising reasonable diligence. Thus, this argument fails on the merits.
    VI. CONCLUSION
    The undisputed facts show that Mallory & Evans failed to satisfy a condition
    precedent under the contract to receive payments in excess $3.85 million. Tuskegee
    10
    did not clothe Wesson with apparent authority to waive that condition. The district
    court properly granted summary judgment. The district court also properly rejected
    the arguments made in Mallory & Evans’s Rule 59 motion.
    AFFIRMED.
    11