Colsa Corp. v. Martin Marietta ( 1998 )


Menu:
  •                                                           PUBLISH
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    _______________
    No. 97-6206
    _______________
    D. C. Docket No. CV 94-H-1361-NE
    COLSA CORPORATION, a corporation organized
    and existing under the laws of Delaware with its
    principle place of business within the State
    of Alabama,
    Plaintiff-Counter-
    Defendant-Appellant,
    versus
    MARTIN MARIETTA SERVICES, INC., a corporation
    organized and existing under the laws of the State
    of Delaware with its principle place of business
    within the State of Maryland,
    Defendant-Counter-
    Claimant-Appellee.
    ______________________________
    Appeal from the United States District Court
    for the Northern District of Alabama
    ______________________________
    (January 23, 1998)
    Before BIRCH, Circuit Judge, HILL and KRAVITCH, Senior Circuit
    Judges.
    PER CURIAM:
    Plaintiff Colsa Corporation (“Colsa”) appeals the district
    court’s grant of summary judgment for Martin Marietta (“Martin
    Marietta”) on Colsa’s antitrust claims. We AFFIRM.
    I. BACKGROUND
    At issue in this case is a government contract to provide
    “operation and maintenance” services to the United States Navy
    in support of the Atlantic Fleet Weapons Training Facility located
    in Roosevelt Roads, Puerto Rico (the Contract). For many years,
    Martin Marietta, or one of its predecessors in interest,1 had been
    awarded the Contract. In March 1990, Martin Marietta and Colsa
    entered a “Teaming Agreement,” which provided that Colsa would
    assist Martin Marietta to obtain the Contract and then Colsa would
    support Martin Marietta by providing software services under the
    Contract.   This support was contingent, however, on Martin
    Marietta being awarded the Contract.
    1
    To  avoid   confusion,   “Martin   Marietta”   includes   its
    predecessors in interest.
    2
    On April 15, 1991, Martin Marietta was awarded the Contract
    for a base period of six months, with four one-year options
    exercisable by the government.       On May 15, 1991, Martin
    Marietta entered into a fixed price subcontract with Colsa whereby
    Colsa agreed to provide a limited number of personnel to support
    Martin Marietta in performing the Contract.
    The government exercised subsequent options on the first of
    October 1991, 1992, and 1993.        On each occasion, Martin
    Marietta entered into a subcontract with Colsa; Colsa served as
    the subcontractor for Martin Marietta until June 1994.       The
    Contract was scheduled to be re-solicited and awarded in 1995.
    In February 1994, Colsa entered into a teaming agreement
    with Raytheon, a competitor of Martin Marietta, concerning the
    next procurement of the Contract. Martin Marietta learned about
    Colsa’s new agreement with a competitor and began to consider
    Colsa to be a competitive threat. In May 1994, Martin Marietta
    provided Colsa with notice that it was terminating the subcontract
    3
    with Colsa, effective June 12, 1994 (prior to the end of the third
    option period).2 That the termination of the subcontract was not
    related to performance problems by Colsa is undisputed. Martin
    Marietta did not enter into a subcontract for the fourth option
    period (beginning in October 1994). The government announced
    the rebidding of the Contract in October 1994. In October 1996,
    the new Contract was awarded to ITT.
    On June 7, 1994, Colsa filed this action against Martin
    Marietta for violations of Section 2 of the Sherman Act due to anti-
    competitive conduct in the termination of the subcontract. Colsa
    specifically contends that Martin Marietta sought to create or to
    maintain a monopoly through illegal competitive conduct. The
    2
    Colsa, however, contends that prior to October 1993, Martin
    Marietta knew that it would not reteam with Colsa and sought to
    reteam with a competitor -- Tower Systems.       Colsa claims that
    Martin Marietta secretly concealed this intention in order to
    string Colsa along until it was too late for it to re-team with
    another competitor for the rebid process.      As a result, Colsa
    argues that it had to forgo discussions about reteaming with ITT or
    Loral between September and December 1993, as it was waiting to
    hear from Martin Marietta.       Martin Marietta claims that it
    terminated the subcontract with Colsa because it teamed with
    Raytheon in February 1994, thereby making it a competitive threat.
    4
    district court granted summary judgment in favor of Martin
    Marietta on the antitrust claim because Colsa failed to show that
    Martin Marietta had market power in the relevant market, a
    prerequisite to a monopolization claim.3 Colsa appeals.
    3
    Neither party, nor the court below, addresses the issue of
    whether Martin Marietta has market power. Instead, they focus on
    the definition of “relevant market,” which can affect whether a
    party has market power. Colsa contended that the relevant market
    in this case is the Contract alone.     On the other hand, Martin
    Marietta argued that the relevant market extended far beyond the
    one Contract at issue here, and included other operation and
    maintenance contracts performed elsewhere.      The district court
    found that Colsa failed to define adequately the relevant market
    which, in turn, apparently prevented a finding that Martin Marietta
    had sufficient market power to sustain an antitrust claim.
    5
    II. DISCUSSION4
    The issue on appeal is whether the district court erred by
    granting summary judgment for Martin Marietta after concluding
    that Colsa failed to define properly the relevant market. Summary
    judgment orders are reviewed de novo. Scala v. City of Winter
    Park, 
    116 F.3d 1396
    , 1398 (11th Cir. 1997). Summary judgment
    is appropriate if, after viewing all the evidence in favor of the non-
    moving party, there is no genuine issue on any material fact.
    Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322,
    
    106 S. Ct. 2548
    , 2552, 
    91 L. Ed. 2d 265
    (1986); Adickes v. S.H.
    4
    As a preliminary matter, we disagree with Colsa’s contention
    that merely because the definition of “relevant market” is a
    factual question, summary judgment is inappropriate.       Summary
    judgment is clearly available even for factual issues.         See
    American Key Corp. v. Cole Nat’l Corp., 
    762 F.2d 1569
    , 1579 (11th
    Cir. 1985).     Further, the fact that two witnesses provided
    testimony, in favor of Colsa, regarding the relevant market cannot
    preclude summary judgment. Colsa states that its witnesses were
    experts in government procurement -- not federal antitrust law.
    The issue in this case, however, is the definition of “relevant
    market” -- an antitrust term as defined by antitrust law.
    Therefore, the witnesses could offer nothing more than lay opinion
    testimony.   We have stated that “[c]onstruction of a relevant
    economic market or a showing of monopoly power in that market
    cannot . . . be based upon lay opinion testimony.” 
    Id. 6 Kress
    & Co., 
    398 U.S. 144
    , 157, 
    90 S. Ct. 1598
    , 1608, 
    26 L. Ed. 2d
    142 (1970).
    The district court determined that Colsa improperly defined
    the relevant market and granted summary judgment for Martin
    Marietta based on that conclusion. While we agree that summary
    judgment was appropriate, we do so on a different basis.5 As
    stated, Colsa’s argument does not show how Martin Marietta’s
    conduct was anticompetitive so as to support an antitrust claim.
    The Contract at issue in this case has two aspects: (1)
    service of the Contract and (2) procurement of the Contract.
    Colsa expressly states that the alleged antitrust violation is Martin
    Marietta’s “termination of [Colsa’s] subcontract in June 1994.”
    Colsa asserts that this was predatory conduct intended to
    “eliminat[e Colsa] as a competitor in violation of Section 2 of the
    Sherman Act.” In addition, Colsa contends that the only relevant
    5
    "[T]his court may affirm the district court where the
    judgment entered is correct on any legal ground regardless of the
    grounds addressed, adopted or rejected by the district court.”
    Bonanni Ship Supply, Inc. v. United States, 
    959 F.2d 1558
    , 1561
    (11th Cir. 1992) (citing cases).
    7
    time is the one that covers the termination of the subcontract and
    specifically rejects the district court’s analysis of the case from the
    standpoint of the Contract procurement.6
    In other words, Colsa appears only to argue that Martin
    Marietta, by terminating Colsa’s subcontract for services, engaged
    in anticompetitive conduct during the service of the Contract.7 We
    fail to see how this conduct can be characterized as
    anticompetitive for several reasons. First, Colsa cannot claim that
    6
    This is presumably the result of the fact that neither Colsa
    nor Martin Marietta was awarded the Contract during the subsequent
    procurement, thereby making the claim that Martin Marietta had
    sufficient market power to monopolize the procurement process
    difficult to maintain.
    7
    As a result, the cases cited by Colsa in support of its
    argument are inapplicable for several reasons. First, the cases
    are not controlling authority.     Second, two of the cases cited
    involve claims of anticompetitive conduct during the procurement
    process. See National Reporting Co. v. Alderson Reporting Co., 
    763 F.2d 1020
    (8th Cir. 1985); F. Buddie Contracting, Inc. v.
    Seawright, 
    595 F. Supp. 422
    (N.D. Ohio 1984). Colsa does not make
    such a claim in this case. Simply because those cases involved
    public contracts, does not make them relevant. Third, the other
    case cited by Colsa involved a joint venture contract -- as opposed
    to a subcontract -- whereby each party was awarded the government
    contract, albeit through a joint entity. See Tower Air, Inc. v.
    Federal Express Corp., 956 F. Supp 270 (E.D.N.Y. 1996). This case
    is completely different. Martin Marietta alone -- and not a single
    entity comprised of Colsa and Martin Marietta -- was awarded the
    contract. The fact that the subcontract was labeled a “Teaming
    Agreement” did not create a joint venture relationship giving each
    party some right to the public contract.
    8
    Martin Marietta monopolized -- or attempted to monopolize -- its
    own contract by terminating a subcontract. All contracts involve,
    in some sense, a monopoly over the performance of the contract,
    which is necessarily controlled by the parties to the contract. It is
    not anticompetitive for Martin Marietta (a party to the Contract) to
    exclude Colsa (a non-party to the Contract) from performing
    services under the Contract. Any rights that Colsa may have
    against Martin Marietta sound in contract instead of antitrust law.8
    For these reasons, we find that the district court did not err
    by granting summary judgment for Martin Marietta. Colsa has
    failed to allege anticompetitive conduct upon which an antitrust
    claim could be predicated.
    AFFIRMED.
    8
    In fact, this case seems to involve nothing more than a
    breach of contract claim.    The alleged improper conduct is the
    termination of a subcontract. Further, the injury alleged by Colsa
    is damage “to its business interests in the amount of $1,485,189
    which represents the amount remaining to be paid under its current
    fixed price contract and the amount negotiated under the remaining
    option.”   The remedy sought appears to involve purely contract
    damages.
    9