Sierra Club v. Georgia Power Co. ( 1999 )


Menu:
  •                                                                                   [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT                         FILED
    U.S. COURT OF APPEALS
    ELEVENTH CIRCUIT
    07/14/99
    THOMAS K. KAHN
    No. 98-9011                         CLERK
    D. C. Docket No. 5:97-CV-78-3(HL)
    SIERRA CLUB, a public-interest corporation,
    Plaintiff-Appellant,
    versus
    GEORGIA POWER COMPANY,
    Defendant-Appellee.
    Appeal from the United States District Court
    for the Middle District of Georgia
    (July 14, 1999)
    Before MARCUS, Circuit Judge, HILL, Senior Circuit Judge, and FERGUSON*,
    District Judge.
    ______________
    *Honorable Wilkie D. Ferguson, Jr., U. S. District Judge for the Southern District of Florida,
    sitting by designation.
    PER CURIAM:
    This is an interlocutory appeal from the district court’s denial of Appellant
    Sierra Club’s motion for a preliminary injunction pursuant to 28 U.S.C. § 1292(a).
    The preliminary injunction would have directed the Georgia Power Company
    (Georgia Power) to comply with the pollutant discharge limits of its National Pollutant
    Discharge Elimination System permit (the permit) issued by the Environmental
    Protection Agency.
    Under the permit, Georgia Power is authorized to discharge heated wastewater
    from its coal-fired electricity generation facility (the plant) into Lake Sinclair near
    Milledgeville, Georgia, subject to the numerical temperature limits of “90 degrees
    Fahrenheit or 5 degrees above intake temperature.” Sierra Club contends that Georgia
    Power can achieve this heat limit by reducing the amount of power generated at the
    plant. Georgia Power contends that it cannot do so without, contrary to the public
    interest, impacting upon the level of power generated throughout its entire electrical
    system.
    Following the presentation of evidence and argument at hearing, the district
    court agreed with Georgia Power. It concluded that the potential harm to the general
    public from a reduction of electrical power or thermal loading into the lake,
    outweighed the potential injury to lakeside residents if the plant continued to operate
    2
    at its current output pendente lite. Accordingly, the district court denied Sierra Club’s
    motion for a preliminary injunction.
    The grant or denial of a preliminary injunction is a decision within the sound
    discretion of the district court. United States v. Lambert, 
    695 F.2d 536
    , 539 (11th Cir.
    1983)(citation omitted). On appeal from the grant or denial of a preliminary
    injunction, we do not review the intrinsic merits of the case. 
    Id. “It is
    the function of
    the trial court to exercise its discretion in deciding upon and delicately balancing the
    equities of the parties involved.” 
    Id., citing Tatum
    v. Blackstock, 
    319 F.2d 397
    , 401-
    02 (5th Cir. 1963). A preliminary injunction is a “drastic” remedy, and we will
    disturb the denial of a preliminary injunction only if the district court abused its
    discretion. Crochet v. Housing Authority of Tampa, 
    37 F.3d 607
    , 610 (11th Cir. 1994)
    citing Café 207, Inc. v. St. Johns County, 
    989 F.2d 1136
    , 1137 (11th Cir. 1993).
    There is adequate evidence in the record to support the district court’s ruling
    that the grant of a preliminary injunction would be adverse to the public interest. See
    
    Lambert, 695 F.2d at 539
    . It is apparent from the record that the only way to reduce
    thermal loading to the lake (during the summer of 1998, when meteorological
    conditions throughout the southeastern United States were much warmer than normal)
    would have been substantially to reduce or eliminate electrical generation, to the great
    disadvantage of the general public. Further evidence reflects that fish kills resulting
    3
    from warm lake temperatures were temporary, not significant, and limited to a small
    percentage of the lake. Expert testimony concluded that the loss of fish “should not
    hurt the health of the lake in general” and that in the thirty years of plant operation,
    fish kills occurred in only six of those years, and then generally only during summer
    heat waves of extreme temperature. In order to meet Sierra Club’s demands, the plant
    would have to be shut down during extremely hot days, when demand for power is
    greatest.
    We do not review the intrinsic merits of the case. 
    Lambert, 695 F.2d at 539
    .
    It is the function of the district court to exercise its discretion and delicately to balance
    the equities of the parties involved. 
    Id. The district
    court was correct in concluding
    that a steady supply of electricity during the summer months, especially in the form
    of air conditioning to the elderly, hospitals and day care centers, is critical.1
    Under these circumstances, we certainly cannot state that the district court
    abused its discretion in declining to issue a preliminary injunction. We affirm the
    judgment of the district court.
    AFFIRMED.
    1
    A plan has for some time been proposed by Georgia Power to build a forty million
    dollar cooling tower to prevent the risk of future violations. This proposed relief is under review
    by national and state administrative agencies.
    4