ACMG of Louisiana, Inc. v. Towers Perrin Inc. ( 2010 )


Menu:
  •                                                           [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT            FILED
    ________________________ U.S. COURT OF APPEALS
    ELEVENTH CIRCUIT
    No. 09-15395                  AUGUST 4, 2010
    ________________________              JOHN LEY
    CLERK
    D. C. Docket No. 04-01338-CV-RWS-1
    ACMG OF LOUISIANA, INC.,
    ACMG, INC.,
    Plaintiffs-Appellants,
    versus
    TOWERS PERRIN INC.,
    Defendant-Appellee.
    ________________________
    Appeal from the United States District Court
    for the Northern District of Georgia
    _________________________
    (August 4, 2010)
    Before DUBINA, Chief Judge, PRYOR and MARTIN, Circuit Judges.
    PER CURIAM:
    ACMG of Louisiana, Inc. and ACMG, Inc. (“ACMG”) appeal the district
    court’s order granting defendant Towers Perrin, Inc. (“Towers Perrin”) summary
    judgment on their breach of contract, indemnification, and contribution claims and
    taxing against them the costs of the litigation. Towers Perrin prevailed on its
    motion for summary judgment by arguing that ACMG’s breach of contract claim
    was untimely and that the contribution and indemnity claims were legally deficient.
    After reviewing the record, reading the parties’ briefs, and having the benefit of
    oral argument, we affirm the district court’s grant of summary judgment and its
    order awarding costs to Towers Perrin.
    I. BACKGROUND
    This dispute involves three primary entities: Vantage Health Plan of
    Louisiana, Inc. (“Vantage”), a health insurance plan; ACMG, the administrator of
    the insurance plan; and Towers Perrin, the consulting firm that provided ACMG
    with the rate model used in calculating premiums for the plan. Amidst alleged
    poor plan performance, Vantage terminated ACMG’s management agreement and
    sued ACMG for breach of contract in Louisiana. ACMG settled the case by
    relinquishing claims to future payment under the contract and surrendering
    Vantage stock. In turn, Vantage assigned to ACMG its claims against Towers
    Perrin for breach of contract.
    ACMG sued Towers Perrin via a third party complaint in the Louisiana
    2
    litigation. ACMG moved to amend the complaint on May 3, 2004, to add claims
    against Towers Perrin, a motion the court granted on August 9, 2004. ACMG
    never served Towers Perrin with the third party complaint, however, but
    voluntarily dismissed the action immediately after filing the amended complaint on
    August 9. Meanwhile, on May 13, 2004, ACMG commenced this action against
    Towers Perrin in the Northern District of Georgia. ACMG asserted the breach of
    contract claims assigned to it by Vantage as well as direct contribution and
    indemnification claims against Towers Perrin, claiming that it was forced to settle
    the Vantage suit because of Towers Perrin’s mistakes. After granting summary
    judgment in favor of Towers Perrin, the district court ordered ACMG to pay
    Towers Perrin’s litigation costs under 
    28 U.S.C. § 1920
     (2006).
    II. STANDARD OF REVIEW
    We review a grant of summary judgment de novo. Fanin v. U.S. Dep’t of
    Veterans Affairs, 
    572 F.3d 868
    , 871 (11th Cir. 2009). We review a district court’s
    award of costs to the prevailing party for abuse of discretion. Chapman v. AI
    Transp., 
    229 F.3d 1012
    , 1039 (11th Cir. 2000).
    III. DISCUSSION
    ACMG first objects to the district court’s determination that the Georgia
    renewal statute did not save its time-barred breach of contract action because
    ACMG did not serve Towers Perrin in the Louisiana suit before dismissal.
    3
    Georgia law allows the recommencement of an otherwise untimely claim if it was
    timely brought elsewhere:
    When any case has been commenced in either a state or federal court
    within the applicable statute of limitations and the plaintiff
    discontinues or dismisses the same, it may be recommenced in a court
    of this state or in a federal court either within the original applicable
    period of limitations or within six months after the discontinuance or
    dismissal, whichever is later . . . .
    
    Ga. Code Ann. § 9-2-61
    (a) (2007).
    ACMG contends that Georgia courts would interpret the statutory term
    “commenced” with reference to the law of the state where the action was brought.
    Cf. Walker v. Armco Steel Corp., 
    446 U.S. 740
    , 752–53, 
    100 S. Ct. 1978
    , 1986
    (1980) (holding that a federal court in a diversity action must look to the law of the
    forum state to determine when the action is commenced). We have no indication
    that Georgia courts, however, would look outside the law of Georgia to determine
    when an action is “commenced” under the renewal statute. E.g., Collins v. W. Am.
    Ins. Co., 
    368 S.E.2d 772
    , 773 (Ga. Ct. App. 1988) (citing Georgia case law for the
    proposition that an out of state action dismissed for lack of subject matter
    jurisdiction was void and therefore had not been commenced). As a result,
    ACMG’s unserved Louisiana lawsuit is ineligible for renewal because it was never
    commenced. See Hobbs v. Arthur, 
    444 S.E.2d 322
    , 323 (Ga. 1994) (holding that a
    4
    lawsuit “is void if service was never perfected”). We conclude from the record that
    the district court correctly determined that the Georgia statute of limitations barred
    the breach of contract claim asserted here.
    ACMG next asserts error in the district court’s conclusion that it failed to
    state a claim for either indemnity or contribution in the complaint. A claim for
    indemnity arises only when a party pays damages on behalf of another. See
    Restatement (Third) of Torts: Apportionment of Liability § 22 cmt. b (2000)
    (“[A]n indemnitee must extinguish the liability of the indemnitor to collect
    indemnity. The indemnitee may do so either by a settlement . . . or by satisfaction
    of judgment that by operation of law discharges the indemnitor from liability.”);
    see also Carr v. Nodvin, 
    342 S.E.2d 698
    , 702 (Ga. Ct. App. 1986) (noting that an
    indemnitor “is entitled to restitution from the other for expenditures properly made
    in the discharge of such liability” (internal quotation marks omitted)). The same is
    true of contribution—a responsible party must pay some portion on behalf of
    another before he has a right to recover that portion. Tenneco Oil Co. v. Templin,
    
    410 S.E.2d 154
    , 159 (Ga. Ct. App. 1991) (noting that contribution is available only
    when one tortfeasor has paid more than his fair share of the damages). Because
    ACMG did not extinguish or mitigate Towers Perrin’s liability in its settlement
    with Vantage, but rather received assignment of claims against Towers Perrin, no
    5
    right of indemnity or contribution exists. We conclude therefore that the district
    court correctly granted summary judgment on these claims.
    ACMG finally raises a number of other objections to the costs taxed against
    it, primarily arguing that the charges for data copying, duplication, transcripts, and
    depositions were unreasonable. Its argument, however, raises no facts from which
    we find an abuse of discretion on the part of the district court in awarding these
    costs.
    IV. CONCLUSION
    We conclude that ACMG’s belated breach of contract claim is not saved by
    Georgia’s renewal statute. Moreover, the district court correctly granted summary
    judgment in favor of Towers Perrin on ACMG’s contribution and indemnity
    claims. We also find no abuse of discretion in the district court’s award of costs.
    AFFIRMED.
    6