The Florida Paraplegic Assoc. v. Uccello Immobilie , 227 F.3d 1347 ( 2000 )


Menu:
  •                                                                                   [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    FILED
    ------------------------------------------- U.S. COURT OF APPEALS
    No. 99-13156                     ELEVENTH CIRCUIT
    SEPTEMBER 22, 2000
    -------------------------------------------- THOMAS K. KAHN
    CLERK
    D. C. Docket No. 97-00173-CV-DMM
    EDWARD RESNICK, an individual,
    Plaintiff-Appellee,
    versus
    UCCELLO IMMOBILIEN GMBH, INCORPORATED, a
    foreign corporation doing business in Florida,
    G & K INVESTMENTS MANAGEMENT, INC., a Florida
    corporation,
    Defendants-Appellants.
    ----------------------------------------------------------------
    Appeal from the United States District Court
    for the Southern District of Florida
    ----------------------------------------------------------------
    (September 22, 2000)
    Before EDMONDSON, BARKETT and RONEY, Circuit Judges.
    PER CURIAM:
    Uccello Immobilien, GMBH (“Defendant”), seeks to reverse a liquidated
    damages award ordered pursuant to a settlement agreement with Edward Resnick
    (“Plaintiff”),1 and to reverse the denial of a motion to extend the time of
    performance. Because the liquidated damages award was punitive, and because the
    district court did not abuse its discretion in denying the motion to extend time of
    performance, we vacate in part and affirm in part.
    A.
    Plaintiff and Defendant entered into a settlement agreement to bring
    Defendant’s office building into compliance with the American with Disabilities
    Act (“ADA”), 42 U.S.C. § 12182, et seq.2 The settlement required Defendant to
    begin construction for the accommodations 30 days after the district court
    approved the settlement (subject to Defendant obtaining the necessary building
    permits) and to complete the construction four months later. If Defendant could
    1
    Four plaintiffs initially sued Defendant for alleged ADA violations. Resnick is the only
    plaintiff that moved to enforce the settlement agreement with Defendant; thus he is the only
    plaintiff for purposes of this appeal.
    2
    The accommodations required by the settlement agreement include these things: (1) on-site
    disabled parking spaces with a curb cut; (2) a passenger drop-off area with a curb cut; (3) an on-
    street disabled parking space with a curb cut; (4) a fire alarm system with 75 candela strobe
    lights; (5) lower bank counters with enough space for knee clearance; (6) accessible hardware on
    doors; (7) lower drinking fountains; (8) braille in the elevator and on door jambs; (9) a lower
    emergency telephone in the elevator; and (10) accessible restrooms with signs indicating such.
    2
    not complete the project in a timely fashion due to circumstances beyond its
    control, then Defendant would be afforded a reasonable delay upon agreement of
    the parties or by court order. Otherwise, delay in completion would result in
    liquidated damages of $100 per day plus costs and fees.
    On 4 December 1997, the district court approved the settlement and retained
    enforcement authority. See Kokkonen v. Guardian Life Ins. Co. of Amer., 114 S.
    Ct. 1673, 1677 (1994). Defendant did not apply for a building permit until August
    1998. When Plaintiff visited the building in January 1999, he observed that the
    accommodations required by the settlement had not been completed; Plaintiff,
    however, was still able to transact his business in the building. At Plaintiff’s
    request, an ADA consultant then inspected the building to confirm which
    accommodations required by the settlement remained incomplete.
    Plaintiff on 2 March 1999 filed a Motion to Enforce the Settlement against
    Defendant. After filing four extensions to reply to Plaintiff’s motion, Defendant
    responded in June 1999, at which time Defendant also moved to enlarge the time to
    satisfy the settlement.
    The district court ordered Defendant to complete the accommodations, to
    pay Plaintiff’s attorney’s fees and costs, and to pay liquidated damages of
    3
    $18,500.003 to a charity as designated by Plaintiff. The court also denied
    Defendant’s motion for an extension of time to complete the accomodations.
    Defendant now appeals.
    B.
    We review a court’s decision to enforce a settlement agreement for an abuse
    of discretion. Hayes v. National Serv. Indus., 
    196 F.3d 1252
    , 1254 (11th Cir.
    1999). An error of law is an abuse of discretion per se. Alikhani v. United States,
    
    200 F.3d 732
    , 734 (11th Cir. 2000). Principles governing general contract law
    apply to interpret settlement agreements. Schwartz v. Florida Bd. of Regents, 
    807 F.2d 901
    , 905 (11th Cir. 1987); Crosby Forrest Products, Inc. v. Byers, 
    623 So. 2d 565
    , 567 (Fla. Dist. Ct. App. 1993). And, even though this settlement agreement
    arose under the ADA, state contract law directs our analysis here.4 See Hayes, 196
    3
    The district court ordered Defendant to pay $100 per day for each day the improvements
    were not complete, dating back to 2 January 1999, four months after the city granted the building
    permit, until 7 July 1999, the day of the order.
    4
    We generally disfavor federal common law and apply it in only rare instances concerning
    “rights and obligation of the United States, interstate and international disputes implicating the
    conflicting rights of States or our relations with foreign nations, and admiralty cases.” Kobatake
    v. E.I. DuPont Nemours and Co., 
    162 F.3d 619
    , 624 n.3 (11th Cir. 1998) (quoting Texas
    Industries, Inc. v. Radcliff Materials, Inc., 
    101 S. Ct. 2061
    , 2067 (1981)); see also City of
    Huntsville v. City of Madison, 
    24 F.3d 169
    , 172 n.3 (11th Cir. 1994). Because this settlement
    agreement is between two private parties, federal common law does not apply. Cf. Brewer 
    v. 4 F.3d at 1253
    (applying state law to construction and enforceability of settlement
    agreement arising under Title VII); 
    Schwartz, 807 F.2d at 905
    (same).
    Liquidated damages arising from breach of contract are appropriate when
    (1) damages from the breach are not readily ascertainable, and (2) the sum
    stipulated is not grossly disproportionate to the damages reasonably expected to
    follow from the breach. MCA Television Ltd. v. Public Interest Corp., 
    171 F.3d 1265
    , 1271 (11th Cir. 1999); Hyman v. Cohen, 
    73 So. 2d 393
    , 401 (Fla. 1954) (en
    banc). But liquidated damages are inappropriate when they serve only to punish
    the breaching party. Lefemine v. Baron, 
    573 So. 2d 326
    , 328-29 (Fla. 1991).
    For the first element, potential damages arising from breach of this
    settlement agreement are not readily ascertainable. Handicapped persons who are
    inconvenienced or harmed by Defendant’s failure to comply with the settlement
    agreement may suffer some damage of varying degrees from Defendant’s potential
    breach of contract. Thus, some amount of liquidated damages might be
    appropriate in this context.
    The amount of liquidated damages provided by the settlement agreement,
    Muscle Shoals Bd. of Educ., 
    790 F.2d 1515
    , 1519 (11th Cir. 1986) (applying federal common
    law to interpret EEOC predetermination settlement agreement negotiated by EEOC); Eatmon v.
    Bristol Steel & Iron Works, Inc., 
    769 F.2d 1503
    , 1516 (11th Cir. 1985) (applying federal
    common law to interpret executive order conciliation agreement between government and
    employer).
    5
    however, is grossly disproportionate to the damages reasonably expected to flow
    from the breach. While liquidated damages may or may not precisely compensate
    for the actual breach, the disparity may not be so great as to compensate minimal
    damages with substantial sums. See MCA Television 
    Ltd., 171 F.3d at 1271
    (“Parties may not [] use [liquidated damages] provisions as a way to secure for
    themselves greater damages in the event of a breach than contract law would
    normally allow.”).
    In this case, Plaintiff entered the building in January 1999 and saw that the
    settlement requirements had not been met; he seemingly was not denied use of the
    building based on his handicap and was still able to complete his business there.
    Plaintiff has not alleged that he suffered monetary damages due to the breach; yet
    he seeks to enforce a $18,500 liquidated damages award. Absent the liquidated
    damages provision, Plaintiff would be entitled to minimal damages at best for the
    breach. The gross disparity between the stipulated amount of liquidated damages
    and the damages flowing from the beach causes the damages provision to fail.
    That the district court ordered the damages award to be paid to a charity as
    directed by Plaintiff further establishes that this award was punitive and that
    Plaintiff suffered no actual damages from the breach. Plaintiff seeks no personal
    compensation for the breach; payment to the charity serves only to penalize
    6
    Defendant for nonperformance, much like payment to a public entity for violation
    of a local ordinance.
    Plaintiff and the district court rely on Six Cos. of Cal. v. Joint Hwy Dist. No.
    13, 
    110 F.2d 620
    (9th Cir.), rev’d on other grounds, 
    61 S. Ct. 186
    (1940), to argue
    that liquidated damages may be awarded when the breach inconveniences a group
    intended to benefit from the contract. In that case, the court awarded a
    municipality liquidated damages under a contract to build a highway and tunnel.
    The court held that, even where a municipality suffers no actual damages from the
    breach, liquidated damages are available for the “inconvenience and loss which
    will flow to its inhabitants for whose benefit the improvement is intended and at
    whose cost it is to be built.” 
    Id. at 625.
    Six Cos. of Cal. is inapplicable to and distinguishable from the present facts.
    This contract does not involve a public entity, but instead a private charitable
    organization and disabled persons. Unlike public funds used to construct a major
    highway, the intended beneficiaries (disabled people who are denied access to
    Defendant’s building) under the contract are not paying for the improvements. In
    addition, Plaintiff has not asserted that he has even been inconvenienced or
    suffered loss from the breach. See Multitech Corp. v. St. Johns Bluff Investment
    Corp., 
    518 So. 2d
    . 427, 433 (Fla. Dict. Ct. App. 1988) (finding it inequitable to
    7
    enforce liquidated damages for breach that “bore no significance to the
    [plaintiff]”).
    Liquidated damages are permissible where the award is intended as
    compensation for failure to perform. The liquidated damages provision at issue
    here, however, is a penalty intended to induce performance of the settlement
    agreement. See 
    Hyman, 73 So. 2d at 398
    ; Multitech Corp., 
    518 So. 2d
    at 432. The
    settlement agreement does not apportion liquidated damages based on the different
    accommodations not completed; Defendant is subject to the same penalty whether
    substantial or only minor improvements are incomplete. See 
    Hyman, 73 So. 2d at 398
    ; Smith v. Newell, 
    20 So. 249
    , 251 (Fla. 1896). Even Plaintiff in his filings
    refers to the liquidated damages clause as a penalty.
    We vacate the award of liquidated damages because the award is grossly
    disproportionate to damages reasonably expected to flow from the breach and is
    solely punitive.
    C.
    The district court did not abuse its discretion in denying Defendant’s motion
    to extend the time for performance. The settlement agreement provided that, if
    8
    circumstances beyond Defendant’s control delayed performance, then the parties
    could agree to a reasonable delay. If the parties could not agree, then the court
    could extend the time. Sixteen months after the settlement agreement, Defendant
    moved to extend the time to complete performance, which the court denied.
    Defendant’s two excuses – the city required Defendant to upgrade the fire
    alarm system in the building and the general contractor needed to be replaced after
    suffering a severe car wreck in July 1998 – do not justify Defendant’s failure to
    complete, in a timely way, at least some of the accommodations sought in
    Plaintiff’s Motion to Enforce. Thus, the district court properly acted within its
    discretion in denying the motion to extend time.
    D.
    Pursuant to the terms of the settlement agreement, the district court properly
    awarded Plaintiff, as the prevailing party, attorney’s fees, costs and expert fees
    incurred in litigating at the district court.5 The settlement agreement entitles the
    prevailing party in an enforcement action to an award of such fees.
    Notwithstanding our decision to set aside the award of liquidated damages, we
    5
    Plaintiff’s motion for fees and costs related to the appeal is DENIED.
    9
    affirm the district court’s decision to award fees and costs for the proceedings in
    district court.
    We remand to the district court to determine the appropriate amount of fees
    and costs to be awarded to Plaintiff.
    VACATED in part, AFFIRMED in part, and REMANDED.
    10
    RONEY, Circuit Judge, dissenting:
    I respectfully dissent. I would affirm the district court’s decision.
    To we who are fully able, it may seem that a disabled person suffers minimal
    damage when a building does not conform to the legal requirements, but for the
    person whom those regulations seek to protect, the harm may be far more than
    minimal. Obviously this is virtually impossible to quantify in economic terms.
    That is the exact reason that the law provides for liquidated damages. Otherwise
    there is no way to enforce compliance.
    The appellant made an agreement. There is no just reason why it should not
    pay damages for failure to fulfill the terms of that agreement. Certainly, if the
    requirement was in the form of a mandatory injunction rather than a settlement
    agreement, the assessment of the minimal amount here for violation of that
    injunction would not be questioned by this Court. Although this is an individual
    case, not a class action, the settlement agreement was intended to benefit others
    than the plaintiff and it seems to me the district court’s decision should be
    reviewed with that in mind.
    11