Avenue Clo IV, LTD. v. Bank of America, NA , 723 F.3d 1287 ( 2013 )


Menu:
  •          Case: 12-11815   Date Filed: 07/26/2013   Page: 1 of 26
    [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 12-11815
    ________________________
    D.C. Docket Nos. 1:09-md-02106-ASG, 1:09-cv-23835-ASG
    AVENUE CLO FUND, LTD.,
    et. al.,
    Plaintiffs,
    AVENUE CLO IV, LTD.,
    AVENUE CLO V, LTD.,
    AVENUE CLO VI, LTD.,
    BRIGADE LEVERAGED CAPITAL STRUCTURES FUND, LTD.,
    BATTALION CLO 2007-I LTD.,
    CASPIAN CAPITAL PARTNERS, L.P.,
    CASPIAN SELECT CREDIT MASTER FUND, LTD.,
    ING PRIME RATE TRUST,
    ING SENIOR INCOME FUND,
    ING INTERNATIONAL (II) -SENIOR BANK LOANS EURO,
    ING INVESTMENT MANAGEMENT CLO I, LTD.,
    ING INVESTMENT MANAGEMENT CLO II, LTD.,
    ING INVESTMENT MANAGEMENT CLO III, LTD.,
    ING INVESTMENT MANAGEMENT CLO IV, LTD.,
    ING INVESTMENT MANAGEMENT CLO V, LTD.,
    VENTURE II CDO 2002, LIMITED,
    VENTURE III CDO LIMITED,
    VENTURE IV CDO LIMITED,
    VENTURE V CDO LIMITED,
    VENTURE VI CDO LIMITED,
    VENTURE VII CDO LIMITED,
    VENTURE VIII CDO LIMITED,
    VENTURE IX CDO LIMITED,
    VISTA LEVERAGED INCOME FUND,
    Case: 12-11815   Date Filed: 07/26/2013   Page: 2 of 26
    VEER CASH FLOW CLO, LIMITED,
    MARINER LDC,
    GENESIS CLO 2007-1 LTD.,
    CANPARTNERS INVESTMENTS IV, LLC,
    SCROGGIN CAPITAL MANAGEMENT II,
    SCROGGIN INTERNATIONAL FUND LTD.,
    SCROGGIN WORLDWIDE FUND LTD.,
    CASPIAN ALPHA LONG CREDIT FUND, L.P.,
    SOLA LTD,
    MONARCH MASTER FUNDING, LTD.,
    SOLUS CORE OPPORTUNITIES MASTER FUND LTD.,
    CANTOR FITZGERALD SECURITIES,
    OLYMPIC CLO I, LTD.,
    SHASTA CLO I, LTD.,
    WHITNEY CLO I LTD.,
    SAN GABRIEL CLO I LTD.,
    SIERRA CLO II LTD.,
    NORMANDY HILL MASTER FUND, L.P.,
    SPCP GROUP, LLC,
    VENURE CAPITAL MASTER FUND, LTD.,
    Plaintiffs - Appellants,
    versus
    SUMITOMO MITSUI BANKING CORPORATION,
    et al.,
    Defendants,
    BANK OF AMERICA, NA,
    Defendant - Appellee.
    ________________________
    Appeal from the United States District Court
    for the Southern District of Florida
    ________________________
    (July 26, 2013)
    2
    Case: 12-11815       Date Filed: 07/26/2013      Page: 3 of 26
    Before TJOFLAT and MARTIN, Circuit Judges, and BUCKLEW, * District Judge.
    MARTIN, Circuit Judge:
    This case is one of many resulting from the failure of the project to build a
    Fontainebleau Resort in Las Vegas. The Fontainebleau Las Vegas was a hotel and
    casino development project on an approximately 24.4 acre parcel at the north end
    of the Las Vegas Strip. Here, a group of lenders and their successors in interest
    (Term Lenders) appeal the District Court’s grant of summary judgment in favor of
    Bank of America. See In re Fontainebleau Las Vegas Contract Litigation MDL
    No. 2106, No. 09-MD-02106-CIV, 
    2012 WL 930290
    , *1 (S.D. Fla. March 19,
    2012). After careful review, and with the benefit of oral argument, we affirm in
    part, reverse in part, and remand for further proceedings consistent with this
    opinion.
    I. FACTUAL BACKGROUND
    This case is a contract dispute related to the funding of the development of
    the Fontainebleau Las Vegas (the Project). See In re Fontainebleau, 
    2012 WL 930290
    , at *1–49. On one side of the dispute are the Term Lenders, which loaned
    money to Fontainebleau Las Vegas, LLC and Fontainebleau Las Vegas II, LLC
    (the Borrowers). The Borrowers’ parent company, Fontainebleau Resorts, LLC,
    was the developer of the Fontainebleau Las Vegas. On the other side of the
    *Honorable Susan C. Bucklew, United States District Judge for the Middle District of Florida,
    sitting by designation.
    3
    Case: 12-11815       Date Filed: 07/26/2013      Page: 4 of 26
    dispute is Bank of America, which was the Disbursement Agent responsible under
    the funding agreements for disbursing the Term Lenders’ funds to the Borrowers.
    A. THE FUNDING STRUCTURE
    At the beginning, the Project’s budget was $2.9 billion, with $1.85 billion to
    be funded by a senior secured debt facility (Senior Credit Facility). 1 The Senior
    Credit Facility was set up by the Credit Agreement and consisted of three
    components: a $700 million Initial Term Loan Facility; a $350 million Delay Draw
    Term Loan Facility; and an $800 million Revolving Loan Facility.
    The Term Lenders own Initial Term Loan and Delay Draw Term Loan
    notes. The Initial Term Loans were due on the closing date. The Delay Draw
    Term Loans and Revolving Loans were disbursed on a periodic basis under the
    terms of the Disbursement Agreement. Bank of America was the Disbursement
    Agent responsible for distributing the funds under the terms of the Disbursement
    Agreement.
    B. DISPERSING THE MONEY
    The process set up for the Borrowers to get the money had a lot of moving
    parts. The Credit Agreement required the Borrowers to first submit a Notice of
    Borrowing to the Administrative Agent (Bank of America). This would prompt
    1
    The balance of the Project was funded by a $675 million Second Mortgage Note offering and a
    $400 million Retail Facility. The Retail Facility was the sole source of funding for the retail
    portion of the Fontainebleau Las Vegas. The resort budget included $83 million in costs that
    were to be funded through the Retail Facility.
    4
    Case: 12-11815     Date Filed: 07/26/2013   Page: 5 of 26
    the Term Lenders and/or Revolving Lenders to give the money to the
    Administrative Agent. If the Notice of Borrowing included the proper information
    and the Borrowers submitted no more than one Notice per month, the
    Administrative Agent would transfer the loan funds into the Bank Proceeds
    Account. One difference between the Delay Draw Term Loans and Revolving
    Loans was that “the proceeds of each Delayed Draw Term Loan [was] applied first
    to repay in full any then outstanding Revolving Loans . . . and second, to the extent
    of any excess, [was] credited to the Bank Proceeds Account.”
    Once funds were in the Bank Proceeds Account, the Borrowers had to
    submit another request, called the Advance Request, which included a series of
    general representations and certifications, to the Disbursement Agent (Bank of
    America). When it received the Advance Request, Bank of America, as
    Disbursement Agent, as well as the Construction Consultant were required to
    review the Advance Request and determine whether all the required documentation
    was provided. The Construction Consultant was also required to deliver a
    certificate to Bank of America either approving or disapproving the Advance
    Request.
    Under the Disbursement Agreement, the next step turned on whether the
    conditions precedent set forth in Article 3 of the Disbursement Agreement were
    5
    Case: 12-11815        Date Filed: 07/26/2013        Page: 6 of 26
    satisfied.2 If the conditions precedent were met, Bank of America, in its role as
    Disbursement Agent, was required to execute an Advance Confirmation Notice
    and the funds would be disbursed to the Borrowers. If, on the other hand, the
    conditions precedent were not met then Bank of America was required to issue a
    Stop Funding Notice. Bank of America’s duties as Disbursement Agent, with
    respect to determining whether the conditions precedent were or were not satisfied,
    is one of the disputes between the parties that will be the subject of our discussion
    in Part IV.A of this Order.
    C. MONEY DISPERSED DURING THE TIME IN DISPUTE
    For each Advance Request from September 2008 through March 2009, Bank
    of America, as Disbursement Agent, received the required Advance Request
    certifications from the Borrowers, the Construction Consultant, the contractor, and
    the architect. Throughout this period Bank of America continued to disburse funds
    to the Borrowers and never issued a Stop Funding Notice.
    However, the Term Lenders have pointed to a number of events, beginning
    in September 2008, which they say “caused the failures of multiple conditions
    precedent.” They delineate these events as: “the Lehman bankruptcy and the
    2
    The conditions included, for example, that “[n]o Default or Event of Default shall have
    occurred and be continuing”; “there shall not have occurred any change in the economics or
    feasibility of constructing and/or operating the Project, or in the financial condition, business or
    property of Fontainebleau, any of which could reasonably be expected to have a Material
    Adverse Effect”; and “the Retail Agent and the Retail Lenders shall . . . make any Advances
    required of them.” Other conditions that the parties believe are relevant to this case are set forth
    in §§ 3.3.2, 3.3.8, 3.3.21, and 3.3.24 of the Disbursement Agreement.
    6
    Case: 12-11815      Date Filed: 07/26/2013      Page: 7 of 26
    funding of the Retail Facility; Fontainebleau’s failure to disclose anticipated
    Project costs; repudiation by the FDIC of First National Bank of Nevada’s
    commitments; select lenders’ failure to fund with respect to the March 2009
    Advance; and the ‘untimely’ submission of the March 2009 Advance.” See In re
    Fontainebleau, 
    2012 WL 930290
    , at *15. How much Bank of America knew about
    these events is another source of dispute between the parties. That dispute will be
    the subject of our discussion in Part IV.B of this Order.
    In April 2009, the “Total Revolving Commitments” were ended because the
    Revolving Lenders determined that there had been Events of Default. In May
    2009, Bank of America commissioned a “cost-complete review” of the Project,
    which revealed that Fontainebleau had been concealing cost overruns. Finally, on
    June 9, 2009, the Borrowers and some of their affiliates filed for bankruptcy.
    II. PROCEDURAL HISTORY
    On January 15, 2010, the Term Lenders filed a Second Amended Complaint
    alleging, as relevant to this appeal, that Bank of America breached the
    Disbursement Agreement. 3 Following discovery, the parties filed cross-motions
    for summary judgment.
    3
    The Complaint also alleged breach of the Credit Agreement, breach of the implied covenant of
    good faith and fair dealing, and requested declaratory relief.
    7
    Case: 12-11815     Date Filed: 07/26/2013   Page: 8 of 26
    The District Court granted summary judgment in favor of Bank of America
    because it determined that “the Term Lenders, with all inferences in their favor,
    have failed to raise a genuine issue of material fact as to whether Bank of America,
    as Disbursement Agent or Bank Agent, breached the Disbursement Agreement, or
    whether Bank of America acted with bad faith, gross negligence, or willful
    misconduct.” In re Fontainebleau, 
    2012 WL 930290
    , at *26. In reaching that
    conclusion, the District Court made several preliminary findings. First, the District
    Court held that “[i]n determining whether the conditions precedent to an Advance
    Request were satisfied, Bank of America was explicitly authorized to rely on
    Fontainebleau’s certifications . . . and was explicitly not required to conduct ‘any
    independent investigation as to the accuracy, veracity, or completeness’ of those
    certifications.” 
    Id. at *28. Second,
    the District Court determined that “Bank of
    America, as Disbursement Agent, did not act in bad faith or with gross negligence
    or willful misconduct in performing its duties under the Disbursement Agreement.”
    
    Id. at *34. Third,
    the District Court found that there was no evidence on summary
    judgment that Bank of America breached the Disbursement Agreement by
    disbursing funds despite having actual knowledge that a condition precedent was
    not satisfied. 
    Id. at * 35.
    The Term Lenders timely filed a Notice of Appeal on March 22, 2012.
    8
    Case: 12-11815     Date Filed: 07/26/2013   Page: 9 of 26
    III. STANDARD OF REVIEW
    “This Court reviews the granting of summary judgment de novo, applying
    the same legal standards which bound the district court.” Whatley v. CNA Ins.
    Companies, 
    189 F.3d 1310
    , 1313 (11th Cir. 1999). “Summary judgment is
    appropriate only when there is no genuine issue as to any material fact and . . . the
    moving party is entitled to a judgment as a matter of law.” 
    Id. (quotation marks omitted).
    “An issue of fact is material if it ‘might affect the outcome of the suit
    under governing law’” and it is “genuine ‘if the evidence is such that a reasonable
    jury could return a verdict for the nonmoving party.’” Western Grp. Nurseries,
    Inc. v. Ergas, 
    167 F.3d 1354
    , 1360 – 61 (11th Cir. 1999) (quoting Anderson v.
    Liberty Lobby, Inc., 
    466 U.S. 242
    , 248, 
    106 S. Ct. 2505
    , 2510 (1986)).
    All “evidence must be viewed in the light most favorable to the party
    opposing the motion for summary judgment.” Blackston v. Shook and Fletcher
    Insulation Co., 
    764 F.2d 1480
    , 1482 (11th Cir. 1985). The Court “must avoid
    weighing conflicting evidence or making credibility determinations.” Stewart v.
    Booker T. Washington Ins., 
    232 F.3d 844
    , 848 (11th Cir. 2000). “All reasonable
    inferences arising from the undisputed facts should be made in favor of the
    nonmovant, but an inference based on speculation and conjecture is not
    reasonable.” 
    Blackston, 764 F.2d at 1482
    (internal citation omitted).
    9
    Case: 12-11815    Date Filed: 07/26/2013      Page: 10 of 26
    IV. DISCUSSION
    In its appeal, the Term Lenders argue that the District Court erred in
    granting summary judgment to Bank of America because: 1) it based its
    determination on a misunderstanding of Bank of America’s duties under the
    Disbursement Agreement; 2) there remain genuine issues of material fact about
    whether Bank of America breached the Disbursement Agreement; and 3) there
    remain genuine issues of material fact about whether Bank of America was grossly
    negligent. We will discuss each of these issues in turn.
    A. BANK OF AMERICA’S DUTIES UNDER THE DISBURSEMENT
    AGREEMENT
    In ruling on the summary judgment motion, the District Court necessarily
    had to determine what Bank of America’s duties were under the relevant portions
    of the Disbursement Agreement. Both parties agree that if the conditions
    precedent were satisfied, Bank of America was supposed to deliver an Advance
    Confirmation Notice so that the Term Lenders’ funds could be disbursed to the
    Borrowers. Both parties also agree that if any of the relevant conditions precedent
    were not satisfied Bank of America was required to issue a Stop Funding Notice.
    The parties disagree, however, on whether Bank of America had an affirmative
    duty to determine that the conditions precedent were satisfied or whether Bank of
    America was permitted to rely on the Borrowers’ certifications that the conditions
    precedent were satisfied unless it had actual knowledge to the contrary.
    10
    Case: 12-11815      Date Filed: 07/26/2013     Page: 11 of 26
    The District Court determined that “[t]he Disbursement Agreement imposed
    on Bank of America no duty to inquire or investigate whether [the Borrower’s]
    representations that all conditions precedent had been met were accurate.” In re
    Fontainebleau, 
    2012 WL 930290
    , at *48. For the reasons set out here, we agree
    with this determination.
    “Under New York Law, the initial interpretation of a contract is a matter of
    law for the court to decide.” Alexander & Alexander Servs., Inc. v. These Certain
    Underwriters at Lloyd’s, London, 
    136 F.3d 82
    , 86 (2d Cir. 1998) (quotation marks
    omitted). 4 A court must enforce a contract provision that is “complete, clear and
    unambiguous on its face . . . according to the plain meaning of the terms.”
    Greenfield v. Phillies Records, Inc., 
    780 N.E.2d 166
    , 170 (N.Y. 2002). When
    interpreting a contract, a court should look at the whole agreement and try to give
    meaning to all of the contract’s provisions. See RLI Ins. Co. v. Smiedala, 
    947 N.Y.S.2d 850
    , 853 (App. Div. 2012). But, in the face of any inconsistency
    between a general provision and specific provisions, the specific provisions
    prevail. See Muzak Corp. v. Hotel Taft Corp., 
    133 N.E.2d 688
    , 690 (N.Y. 1956).
    The specific provision of the Disbursement Agreement that most directly
    addresses this issue is § 9.3.2. That section explains that:
    Notwithstanding anything else in this Agreement to the contrary, in
    performing its duties hereunder, including approving any Advance
    4
    The Disbursement Agreement says that it is to be governed by New York law. [D.A. § 11.6]
    11
    Case: 12-11815     Date Filed: 07/26/2013     Page: 12 of 26
    Requests . . . the Disbursement Agent shall be entitled to rely on
    certifications from the Project Entities . . . as to the satisfaction of any
    requirements and/or conditions imposed by this Agreement.
    The clear language of this provision supports Bank of America’s interpretation of
    its duties under the Disbursement Agreement: Bank of America had to determine
    that the conditions precedent were satisfied, but in doing so it was permitted to rely
    on the Borrower’s certifications.
    Bank of America, as Disbursement Agent, would not have been permitted to
    rely on the Borrowers’ certifications that the conditions precedent were met if it
    had actual knowledge to the contrary. If Bank of America actually knew that a
    condition precedent was not satisfied, it would not be commercially reasonable to
    interpret the Agreement to allow Bank of America to disregard that knowledge by
    pointing to a certification by the Borrower, which it knows to be false. See In re
    Lipper Holdings, LLC, 
    766 N.Y.S.2d 561
    , 562 (App. Div. 2003) (explaining that a
    contract “should not be interpreted to produce a result . . . commercially
    unreasonable, or contrary to the reasonable expectations of the parties” (internal
    citations omitted)).
    However, if Bank of America merely had information that was inconsistent
    with the Borrowers’ certification, it did not have an affirmative duty to determine
    whether the condition precedent was actually satisfied. Section 9.3.2 does not
    include any language requiring Bank of America, as Disbursement Agent, to verify
    12
    Case: 12-11815    Date Filed: 07/26/2013    Page: 13 of 26
    the accuracy of the Borrowers’ certifications. Instead, immediately following the
    language quoted above, § 9.3.2 includes language suggesting that the opposite is
    true:
    The Disbursement Agent shall not be required to conduct any
    independent investigation as to the accuracy, veracity or
    completeness of any such items . . . .
    In addition, according to § 9.10 of the Agreement, “nothing in this Agreement . . .
    shall be so construed as to impose” obligations on Bank of America “except as
    expressly set forth herein.”
    Under this interpretation of Bank of America’s duties as Disbursement
    Agent, Bank of America would still have to determine whether each condition
    precedent was satisfied if it did not have a certification it could rely on. For
    example, as the Term Lenders point out, there are some conditions for
    disbursement that the Borrowers could not certify, such as the condition in
    § 3.3.24, requiring that the Bank Agent “receive[] such other documents and
    evidence as are customary . . . as the Bank Agent may reasonably request.” Also,
    it is not hard to imagine a circumstance in which the Borrowers chose not to give
    such a certification or where Bank of America had actual knowledge that the
    certification was false. In situations like these, § 9.3.2 would play no role because
    there would be no certification Bank of America, as Disbursement Agent, could
    rely on when determining whether the condition precedent was satisfied. It is
    13
    Case: 12-11815     Date Filed: 07/26/2013    Page: 14 of 26
    under these circumstances that other provisions of the Agreement – such a § 9.2.1,
    giving Bank of America the right to review information supporting the Advance
    Requests, and § 2.5.1, requiring that Bank of America “specify, in reasonable
    detail, the conditions precedent which [it] has determined have not been satisfied”
    – would have had more relevance
    B. DID BANK OF AMERICA BREACH THE DISBURSEMENT
    AGREEMENT?
    Bank of America was permitted to rely on the Borrowers’ certifications
    unless it had actual knowledge that the conditions precedent were not satisfied.
    During the relevant period, the Borrowers certified that the conditions precedent
    were met. Therefore, Bank of America could have only been in breach by
    disbursing funds to the Borrowers if it had actual knowledge that the conditions
    precedent were not satisfied.
    In granting summary judgment to Bank of America, the District Court
    determined that “with all inferences in favor of the Term Lenders, the Term
    Lenders . . . failed to present a genuine issue of material fact as to whether Bank of
    America, as Disbursement Agent or Bank Agent, had actual knowledge of the
    failure of any conditions precedent to disbursement.” In re Fontainebleau, 
    2012 WL 930290
    , at *48. For the reasons we will outline here, we have come to a
    different conclusion.
    14
    Case: 12-11815     Date Filed: 07/26/2013    Page: 15 of 26
    As detailed in the District Court’s thorough opinion, the Term Lenders
    contend that Bank of America should have stopped disbursing funds to the
    Borrowers because, at some point between September 2008 and March 2009, Bank
    of America became aware of certain events, discussed below, that it knew caused
    the failure of seven separate conditions precedent listed in § 3.3 of the
    Disbursement Agreement. 
    Id. at *8–9, 15–24.
    Under the terms of that agreement,
    once the Bank of America knew that conditions precedent were not satisfied, it was
    required to issue a Stop Funding Notice to temporarily halt disbursal of the funds.
    1. Lehman Brothers’ Bankruptcy and Failure to Fund
    Lehman Brothers Holdings, Inc. (Lehman) was the largest lender under the
    Retail Facility and the Administrative Agent of the Retail Facility. No one
    disputes that Lehman filed for bankruptcy on September 15, 2008. Neither is it
    disputed that Fontainebleau funded Lehman’s approximately $2.5 million share of
    the September 2008 Retail Advance and essentially funded Lehman’s portion of
    the Retail Advances from December 2008 through March 2009 by reimbursing
    ULLICO, a Co-Lender under the Retail Facility, for funding those amounts.
    The failure of Lehman may have caused the failure of several conditions
    precedent in and of itself. For example, Fontainebleau’s funding of Lehman’s
    share of the September Retail Advance was a failure of the condition in § 3.3.23,
    requiring that the Retail Lenders make all advances required of them. Also, if
    15
    Case: 12-11815        Date Filed: 07/26/2013       Page: 16 of 26
    Lehman’s bankruptcy was a “change in the economics” of the Project “which
    could reasonably be expected to have a Material Adverse Effect,” there would have
    been a failure of the condition in § 3.3.11, requiring that no such change shall have
    occurred. 5
    What the parties do dispute is whether Bank of America had actual
    knowledge of these events and whether the impact of these events on the
    conditions precedent was such that the disbursing of funds constituted a breach of
    contract. The Term Lenders argue that Bank of America had actual knowledge
    that Lehman did not fund its share of the September Retail Advance and that
    Fontainebleau paid the money for Lehman. In support of this view of the facts, the
    Term Lenders point to a number of things: 1) a series of letters from Highland
    Capital Management, one of the original term lenders, alerting Bank of America to
    the serious impact Lehman’s bankruptcy could have on the Project and suggesting
    that Fontainebleau funded Lehman’s share of the September Retail Advance; 2)
    testimony by McLendon Rafeedie, the primary contact at TriMont Real Estate
    5
    The Term Lenders also argue that Lehman’s bankruptcy and its failure to fund could have led
    to the failure of several other conditions precedent in the Disbursement Agreement: § 3.3.21,
    requiring that the Bank Agent shall not have become aware of information that is materially
    inconsistent with the information disclosed to them; § 3.3.3, requiring that no “Default or Event
    of Default” has occurred and is continuing ; and § 3.3.2, requiring that the Borrowers’
    representation that there was no “Event of Default” was true in all material respects. Our
    analysis of Bank of America’s actual knowledge applies equally to these conditions precedent
    even though we do not specifically discuss them. The Term Lenders made other arguments on
    appeal about why genuine issues of material fact remain with respect to Bank of America’s
    knowledge of the failure of these conditions. However, our analysis in this section makes it
    unnecessary for us to address them.
    16
    Case: 12-11815     Date Filed: 07/26/2013   Page: 17 of 26
    Advisors, Inc. about TriMont’s role as servicer of the Retail Facility, explaining
    that he knew Fontainebleau funded for Lehman and suggesting that it was possible
    that he informed Bank of America about this; 3) an October 2008 meeting among
    executives of Fontainebleau, Bank of America, and certain Retail Co-Lenders
    where the implications of Lehman’s bankruptcy were discussed; and 4)
    Fontainebleau’s suspicious evasiveness on the topic of Lehman’s bankruptcy and
    its nonresponsive answers to Bank of America’s questions about who funded
    Lehman’s share of the September Advance.
    As the District Court’s opinion details, there are ways to discount each of
    these categories of evidence as showing, at most, a reason that Bank of America
    should have been suspicious that Fontainebleau funded Lehman’s share of the
    September Retail Advance. See In re Fontainebleau, 
    2012 WL 930290
    , at *37–40.
    However, taken together and viewed in the light most favorable to the Term
    Lenders, we conclude that this circumstantial evidence creates a genuine issue of
    material fact with respect to whether Bank of America had actual knowledge that
    Fontainebleau paid Lehman’s share of the September Retail Advance. Cf. United
    States v. Santos, 
    553 U.S. 507
    , 521, 
    128 S. Ct. 2020
    , 2029 (2008) (explaining that
    the “knowledge element” of the offense “will be provable (as knowledge must
    almost always be proved) by circumstantial evidence”).
    17
    Case: 12-11815     Date Filed: 07/26/2013   Page: 18 of 26
    Forwarding a similar argument, the Term Lenders also say that Bank of
    America had actual knowledge that Lehman’s bankruptcy was a “change in the
    economics . . . which could reasonably be expected to have a Material Adverse
    Effect.” To support this proposition, the Term Lenders highlight: 1) the large share
    of the Retail Facility that Lehman was responsible for funding; 2)
    contemporaneous statements made by Bank of America employees about the
    potential impact Lehman’s bankruptcy would have on the Project together with
    their later explanations of those statements; 3) the letters from Highland Capital
    Management mentioned above; and 4) discussions at the October 2009 meeting
    (also mentioned above) about the impact of Lehman’s bankruptcy on the Project
    and the Retail Co-Lenders’ unwillingness to pay Lehman’s portion if Lehman was
    unable to pay.
    The District Court’s opinion accurately details how, despite Lehman’s
    bankruptcy, “there was no indication that there would be a shortfall in Retail Funds
    or that the Retail Lenders would fail to honor their obligations under the Retail
    Facility.” In re Fontainebleau, 
    2012 WL 930290
    , at * 17. However, when taken
    together and viewed in the light most favorable to the Term Lenders, we conclude
    that the Term Lenders’ evidence raises a genuine question of material fact about
    whether Bank of America had actual knowledge that Lehman’s bankruptcy was a
    18
    Case: 12-11815       Date Filed: 07/26/2013      Page: 19 of 26
    change in the economics of the Project “which could reasonably be expected to
    have a Material Adverse Effect.” (emphasis added).
    2. First National Bank of Nevada’s Repudiation, Cost Overruns, and the
    Default of Several Delay Draw Term Lenders
    That several other events of consequence happened during the period of
    September 2008 through 2009 is also undisputed. First, in late December 2008,
    the Federal Deposit Insurance Corporation, which had been appointed as receiver
    of First National Bank of Nevada (a Delay Draw Term Loan and Revolving Loan
    Lender), formally repudiated First National Bank of Nevada’s unfunded Senior
    Credit Facility commitments. These commitments amounted to $1,666,666 under
    the Delay Draw Term Loan and $10,000,000 under the Revolver Loan.
    Second, in January and March 2009, the Construction Consultant issued
    Project Status Reports expressing concerns that the Borrowers’ Anticipated Cost
    Report did not accurately reflect increases in the Project budget. In March, the
    Consultant issued a Construction Consultant Advance Certificate declaring that
    there were material errors in the Advance Request and that the budget did not
    accurately reflect costs. By the end of March, the Borrowers increased the Project
    budget by more than $114,000,000.6
    6
    The Borrowers first increased construction costs by $64,854,000. Based on the Construction
    Consultant’s Advance Certificate, the Borrowers increased the budget by another $50,000,000.
    19
    Case: 12-11815       Date Filed: 07/26/2013      Page: 20 of 26
    Third, in March 2009, the Borrowers submitted a Notice of Borrowing
    requesting a Delay Draw Term Loan for the entire $350 million facility.
    Guggenheim (which controlled five Delay Draw Term Loan investment funds) and
    Z Capital Finance, LLC (a Delay Draw Term Lender) failed to give Bank of
    America funds as they were obligated to under the Credit Agreement.
    Guggenheim’s portion of the Delay Draw Term Loan was $10,000,000 and Z
    Capital was responsible for $11,666,666. Despite their failure to fund, Bank of
    America included these commitments as “Available Funds” to calculate whether
    the Project was “In Balance.”
    No one disputes that these events may be relevant to several conditions
    precedent. For example, if either First National Bank of Nevada’s repudiation or
    Guggenheim’s and Z Capital’s failures to fund “could reasonably be expected to
    result in a Material Adverse Effect,” this would have been an Event of Default
    under the Credit Agreement. Based on this, the condition in § 3.3.3 of the
    Disbursement Agreement would not have been satisfied. 7 Also, if these events,
    7
    This condition required that “No Default or Event of Default shall have occurred and be
    continuing.” “Event of Default” was defined as being an “Event of Default under any of the
    Facility Agreements.” One “Event of Default” under the Credit Agreement was any breach or
    default by any party to the agreements of any term of the agreements provided that it “could
    reasonably be expected to result in a Material Adverse Effect.”
    If Bank of America had actual knowledge that the condition in § 3.3.3 was not satisfied
    because there was an “Event of Default,” the condition in § 3.3.2 would also be implicated
    because Bank of America would have had actual knowledge that Fontainebleau’s representation
    that there was no “Event of Default” was not “true and correct.”
    20
    Case: 12-11815     Date Filed: 07/26/2013    Page: 21 of 26
    considered together with Lehman’s bankruptcy, amounted to a “change in the
    economics” of the Project “which could reasonably be expected to have a Material
    Adverse Effect,” then the condition in § 3.3.23 would not have been satisfied.
    However, the parties do dispute whether these events did, in fact, cause
    failures of the conditions precedent and whether Bank of America had actual
    knowledge of the failures. The primary basis for the District Court’s determination
    that these events did not constitute failures of conditions precedent, which Bank of
    America urges us to adopt, was its determination that each of these events was not
    material, as a matter of law. See In re Fontainebleau, 
    2012 WL 930290
    , at *43–44.
    In arguing to defeat this materiality determination by the District Court, and to
    support their own view that these events “could reasonably be expected to have a
    Material Adverse Effect,” the Term Lenders: 1) take issue with the District Court’s
    finding that the loan amounts of the Senior Credit Facility that were not available
    due to First National Bank of Nevada’s repudiation and Guggenheim’s and Z
    Capital’s failures to fund were immaterial as a matter of law; 2) point out that, as
    the District Court acknowledged, Guggenheim’s and Z Capital’s failures to fund
    caused the Project’s budget to be out of balance; 3) highlight Bank of America’s
    recognition of how difficult it would be to secure alternative lenders; and 4) argue
    that “[t]he intricate, interlocking agreements reflected the reality that no reasonable
    21
    Case: 12-11815   Date Filed: 07/26/2013    Page: 22 of 26
    lender would fund without assurances that other lenders would also fund to
    completion.”
    Considering all of this together, the Term Lenders have raised genuine
    issues of material fact about whether there were “Events of Default” to the extent
    that these events “could reasonably be expected to have a Material Adverse Effect”
    and whether Bank of America had actual knowledge of this fact. Cf. e.g., Lucas v.
    Fla. Power & Light Co., 
    765 F.2d 1039
    , 1040–41 (11th Cir. 1985) (explaining that
    “questions of materiality” are “[m]ixed questions of law and fact” that “involve
    assessments peculiarly within the province of the trier of fact”); Willjeff, LLC v.
    United Realty Mgmt. Corp., 
    920 N.Y.S.2d 495
    , 497 (N.Y. App. Div. 2011)
    (explaining that materiality is generally a question for the finder of fact unless “the
    evidence concerning the materiality is clear and substantially uncontradicted”).
    Even if First National Bank of Nevada’s repudiation, and Guggenheim’s and Z
    Capital’s failures to fund could not have been expected to result in a Material
    Adverse Effect when considered one by one, taken together and in conjunction
    with the large increase in the Project budget and Lehman’s bankruptcy, we have no
    problem concluding there is a genuine issue of material fact regarding whether
    Bank of America knew that there was a “change in the economics” of the Project
    22
    Case: 12-11815       Date Filed: 07/26/2013       Page: 23 of 26
    “which could reasonably be expected to have a Material Adverse Effect,” thereby
    implicating the condition in § 3.3.11. 8
    C. WAS BANK OF AMERICA GROSSLY NEGLIGENT?
    Under § 9.10 of the Disbursement Agreement, Bank of America, as
    Disbursement Agent, had no responsibility “except for any bad faith, fraud, gross
    negligence or willful misconduct” and could not be held liable for any loss “except
    as a result of [its] bad faith, fraud, gross negligence or willful misconduct.” Under
    New York law, these are high standards. For example, New York law defines
    gross negligence as “conduct that evinces a reckless disregard for the rights of
    others or smacks of intentional wrongdoing,” Colnaghi, U.S.A., Ltd. v. Jewelers
    Protection Servs., Ltd., 
    81 N.Y.2d 821
    , 823–24 (N.Y. 1993) (quotation marks
    omitted), or “the failure to exercise even slight care,” Food Pageant, Inc. v.
    Consolidated Edison Co., Inc., 
    54 N.Y.2d 167
    , 172 (N.Y. 1981).
    However, “[g]enerally, the particular standard of care which a defendant is
    judged against in a given case is a factual matter for the jury.” Food Pageant, 
    Inc., 54 N.Y.2d at 172
    . Thus, “[w]here the inquiry is to the existence or nonexistence of
    gross negligence . . . the question . . . [is] a matter for jury determination.” 
    Id. at 8 The
    Term Lenders argue that Bank of America was in breach of the Disbursement Agreement
    because it disbursed funds even though it had actual knowledge that seven conditions precedent
    had failed. Because we have concluded that there were genuine issues of material fact as to five
    of these conditions, we decline to address the remaining two conditions precedent. Neither will
    we address Term Lenders’ arguments about several other purported failures of the conditions
    precedent we have discussed. We leave it to the District Court to reevaluate these issues, as
    necessary, in light of this opinion and further proceedings before that court.
    23
    Case: 12-11815     Date Filed: 07/26/2013   Page: 24 of 26
    173. “While gross negligence may be found as a matter of law in some limited
    instances,” Trump Int’l Hotel & Tower v. Carrier Corp., 
    524 F. Supp. 2d 302
    , 315
    (S.D.N.Y. 2007), it cannot be resolved as a matter of law in this case.
    Here, there is an issue of fact about whether Bank of America was grossly
    negligent. For example, under our interpretation of the Disbursement Agreement,
    Bank of America would have been in breach of the Agreement if it disbursed the
    Term Lenders’ funds to the Borrowers even though it had actual knowledge that
    any one of the conditions precedent had failed. We have discussed why we believe
    there are genuine issues of material fact about whether Bank of America had actual
    knowledge that a number of conditions precedent had failed. In addition to those
    things we discussed, the Term Lenders have also established a dispute of material
    fact on the subject of whether Bank of America had actual knowledge that some of
    these conditions precedent had failed months before it disbursed funds to the
    Borrowers or that Bank of America had actual knowledge that some of these
    conditions precedent had failed for several different reasons. A jury could find that
    the cumulative effect of Bank of America’s disbursing funds despite having actual
    knowledge about the failure of many different conditions precedent amounted to
    gross negligence. A jury could also find that certain conditions precedent were so
    material to the Agreement that Bank of America’s conduct, including disbursing
    24
    Case: 12-11815     Date Filed: 07/26/2013     Page: 25 of 26
    funds to the Borrowers, showed a reckless disregard for the Term Lenders’ rights
    to the extent it knew that those conditions were not satisfied.
    V. SEALED DOCUMENTS
    Many of the documents filed in this case, including the parties’ motions for
    summary judgment and appeal briefs, were filed under seal. An example of the
    documents filed under seal is the Disbursement Agreement, which is central to this
    case. This same document was publicly filed in other proceedings, including a
    case we heard at oral argument on the same day as this one.
    At the request of the court, the parties have filed a joint letter agreeing that
    the underlying Agreements and many of the other documents in the record should
    be unsealed. The parties also listed certain documents they wish to continue to
    keep under seal. Upon remand of this case to the District Court, the Clerk is
    directed to unseal all of the documents in the record, except those delineated in the
    parties’ request to retain them as sealed.
    VI. CONCLUSION
    Having concluded that under the Disbursement Agreement Bank of America
    was permitted to rely on the Borrowers’ certifications that the conditions precedent
    were satisfied unless it had actual knowledge to the contrary, and finding that there
    remain genuine issues of material fact about whether Bank of America had such
    knowledge and whether its actions amounted to gross negligence, we affirm in part
    25
    Case: 12-11815     Date Filed: 07/26/2013   Page: 26 of 26
    and reverse in part the District Court’s order. Specifically, we affirm the District
    Court’s denial of the Term Lenders’ Motion for Partial Summary Judgment and the
    District Court’s interpretation of Bank of America’s obligations under the
    Disbursement Agreement. We reverse the District Court’s grant of summary
    judgment in favor of Bank of America. We also remand the case to the District
    Court for further proceedings consistent with this opinion.
    AFFIRMED IN PART, REVERSED IN PART, and REMANDED
    26