D&M Carriers LLC v. M/V Thor Spirit ( 2014 )


Menu:
  •              Case: 13-13280    Date Filed: 09/22/2014   Page: 1 of 17
    [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 13-13280
    Non-Argument Calendar
    ________________________
    D.C. Docket No. 9:11-cv-80722-KAM
    D & M CARRIERS LLC,
    a foreign corporation,
    d.b.a. Freymiller, Inc.,
    Plaintiff - Counter Defendant - Appellant,
    versus
    M/V Thor Spirit
    along with her engines, boilers, machinery, masts,
    rigging, tackle, equipment and supplies, tools, pumps,
    gear, furniture, appliances, and fishing gear and other
    appurtenances and apparel, having Serial No. VSC57045D506, in rem
    a.k.a. M/V Spirit
    a.k.a. M/V Elation,
    INAN TAPTIK,
    a foreign individual, in personam,
    Defendants - Appellees,
    ABLE BOAT TRANSPORT, LLC,
    a Florida Limited Corporation, in personam,
    Defendant - Counter Claimant.
    Case: 13-13280        Date Filed: 09/22/2014      Page: 2 of 17
    ________________________
    Appeal from the United States District Court
    for the Southern District of Florida
    ________________________
    (September 22, 2014)
    Before ED CARNES, Chief Judge, and RESTANI, * Judge, and ROBRENO, **
    District Judge.
    PER CURIAM:
    This appeal arises out of a dispute concerning the overland transport of a 57-
    foot yacht. Inan Taptik, a citizen and resident of Turkey, contracted with Able
    Boat Transport, LLC to have the yacht transported from Missouri to Florida.
    Unknown to Taptik, Able Boat then subcontracted with D & M Carriers to
    transport the boat. Because of a variety of unforeseen circumstances, D & M was
    able to haul the boat only to Georgia, and it did so at a cost that was well above the
    amount Taptik had agreed to pay in his contract with Able Boat.
    Seeking to recover the costs it incurred, D & M filed suit in federal court
    asserting three claims: an in rem claim against the yacht, a breach of contract
    *
    Honorable Jane A. Restani, United States Court of International Trade Judge, sitting by
    designation.
    **
    Honorable Eduardo C. Robreno, United States District Judge for the Eastern District of
    Pennsylvania, sitting by designation.
    2
    Case: 13-13280         Date Filed: 09/22/2014        Page: 3 of 17
    claim against Able Boat, and a breach of contract claim against Taptik. 1 After
    conducting a bench trial, the district court entered judgment in favor of Taptik and
    the vessel. This is D & M’s appeal.
    I.
    In 2011 Taptik purchased through a telephone auction a 57-foot Viking
    Sport Cruiser yacht –– the Thor Spirit –– that was located in Table Rock,
    Missouri.2 On March 24, 2011, he entered into an agreement with Able Boat to
    have the yacht transported from Missouri to Fort Lauderdale, Florida. The contract
    provided that Able Boat would transport the vessel for a flat fee of $16,500, but it
    incorrectly noted that the boat had an overall height of only 13 feet 6 inches. On
    March 25, 2011, Able Boat entered into a carrier contract with D & M to transport
    the boat from Missouri to Florida. D & M agreed to haul the boat for a flat fee of
    $10,750. That agreement was premised on the assumption that the boat was no
    taller than fourteen feet.
    On March 29, 2011, D & M truck driver Rocky Clark arrived with his
    tractor-trailer at the marina in Missouri where the Thor Spirit was located. Taptik
    was also present at the marina. Because Taptik did not speak any English, his
    1
    While this litigation was pending, Able Boat filed for bankruptcy and the district court
    stayed the case as to it. See 11 U.S.C. § 362(a)(1). The claim against Able Boat is not at issue in
    this appeal.
    2
    This opinion recounts the facts based on the district court’s post-trial findings of fact
    that are undisputed by the parties.
    3
    Case: 13-13280     Date Filed: 09/22/2014    Page: 4 of 17
    employee and translator, Murat Varol, was with him. Clark introduced himself to
    Varol and handed him his D & M business card. Varol believed that Clark worked
    for Able Boat because Taptik’s contract stated that Able Boat would transport the
    boat and Able Boat’s managing partner had told Varol and Taptik that “his driver
    [was] coming to pick up the boat.” While they were at the marina, Taptik never
    spoke to Clark or anyone else from D & M.
    After the marina staff loaded the Thor Spirit onto his trailer, Clark realized
    that the yacht was not 13 feet 6 inches tall, as stated in the contracts, but was
    instead 17 feet 7 inches tall. The true height of the boat had a substantial impact
    on Clark’s planned route because any load taller than 17 feet could not travel on
    the interstate. Based on the new height, Clark had to take a much longer and more
    circuitous route to Florida. He also had to hire escorts, conduct route surveys in
    several states, and obtain over-sized load permits for each state he would be
    passing through.
    Because of the changed circumstances, on April 5, 2011, Able Boat
    modified its contracts with Taptik and D & M. Taptik agreed to pay a flat rate of
    $38,000 to Able Boat for its services, although the modified contract also provided
    that the final cost could be as low as $36,000 “depending on regulation during
    transport.” Able Boat also modified its contract with D & M. That contract
    4
    Case: 13-13280        Date Filed: 09/22/2014         Page: 5 of 17
    provided that D & M would transport the boat to Florida for $28,000 plus the cost
    of any bucket trucks and police escorts that might be needed during transport.
    Clark made slow progress because of the height of the Thor Spirit. He could
    not drive on the interstate and his crew of escorts had to lift more than 20,000
    power lines, tree limbs, and streetlights over the course of the trip. He travelled
    only 90 to 120 miles per day instead of his usual pace of 400 miles per day. He
    was also delayed waiting for permits to travel through various states with his load.
    When he attempted to bring the boat into Florida, the state’s department of
    transportation refused to give him permission to travel on the state’s highways. As
    a result, Able Boat directed Clark to deliver the boat to St. Mary’s, Georgia. It
    then notified Taptik and Varol that the boat could not enter Florida and that it
    would be brought to St. Mary’s. 3
    After Able Boat directed Clark to deliver the boat to St. Mary’s, D & M and
    Able Boat began discussing the extensive costs that D & M had incurred to pay for
    bucket trucks and escorts along its route. Taptik and Varol were not included in
    those discussions about the additional charges. On May 12, 2011, Able Boat
    submitted a bill to Taptik for all of the charges incurred by D & M, which came to
    3
    Varol flew from Turkey to the United States to recover the boat. He obtained
    possession of the yacht and hired a captain to sail it down to its intended destination in Ft.
    Lauderdale.
    5
    Case: 13-13280       Date Filed: 09/22/2014       Page: 6 of 17
    $85,839.81. Neither Taptik nor Varol ever agreed to pay additional fees or costs
    above the $38,000 that had been agreed to in the modified contract with Able Boat.
    D & M repeatedly sought payment from Able Boat for the extra costs Clark
    had incurred during transportation. Able Boat agreed to pay $35,097.81 and to
    split with D & M the cost of a route survey; however, Able Boat never paid D & M
    the promised amount. Instead, D & M received only $17,122. In an attempt to
    recover the full costs it had incurred, D & M filed a complaint in the Southern
    District of Florida seeking to establish a maritime lien on the Thor Spirit. 4 D & M
    contended that it was entitled to a maritime lien on the Thor Spirit because it had
    provided “necessaries” to the vessel by transporting it to Georgia. 5 D & M also
    asserted breach of contract claims against Taptik and Able Boat.
    The district court held a bench trial on the claims asserted against the Thor
    Spirit and Taptik. It dismissed the breach of contract claim against Taptik based
    on improper service of process. The court also concluded that D & M was not
    entitled to a maritime lien on the Thor Spirit because it had failed to prove that it
    4
    The claim against the Thor Spirit led United States Marshals to seize the yacht in Ft.
    Lauderdale.
    5
    Title 46 of the U.S. Code provides that “necessaries” include “repairs, supplies, towage,
    and the use of a dry dock or marine railway.” 46 U.S.C. § 31301(4). For purposes of this
    appeal, we need not decide whether the services D & M provided to the Thor Spirit qualify as
    “necessaries” within the meaning of the statute.
    6
    Case: 13-13280      Date Filed: 09/22/2014    Page: 7 of 17
    had provided necessaries to the yacht “on the order of the owner or a person
    authorized by the owner.” See 46 U.S.C. 31342(a).
    II.
    As an initial matter, we must determine whether we have jurisdiction to
    consider D & M’s appeal even though its claim in this case against Able Boat has
    not yet been resolved. “Ordinarily . . . an order adjudicating fewer than all the
    claims in a suit, or adjudicating the rights and liabilities of fewer than all the
    parties, is not a final judgment from which an appeal may be taken.” Lloyd
    Noland Found., Inc. v. Tenet Health Care Corp., 
    483 F.3d 773
    , 777 (11th Cir.
    2007). Pursuant to Federal Rule of Civil Procedure 54(d), however, the district
    court entered a partial final judgment in favor of Taptik and the Thor Spirit. See
    Fed. R. Civ. P. 54(d) (stating that a district court may enter a final judgment “as to
    one or more, but fewer than all, claims or parties” when the district court
    determines that there is “no just reason for delay”). In order for Rule 54(d)
    certification to be proper, two requirements must be satisfied. First, the partial
    judgment must be “both ‘final’ and a ‘judgment.’” Lloyd Noland Found., 
    Inc., 483 F.3d at 777
    (quoting Curtiss-Wright Corp. v. Gen. Elec. Co., 
    446 U.S. 1
    , 7, 
    100 S. Ct. 1460
    , 1464 (1980)). Second, there must be “no ‘just reason for delay’ in
    certifying it as final and immediately appealable.” 
    Id. (quoting Curtiss-Wright
    Corp., 446 U.S. at 8
    , 100 S.Ct. at 1465).
    7
    Case: 13-13280     Date Filed: 09/22/2014    Page: 8 of 17
    Both of those requirements are met in this case. The district court’s
    judgment in favor of Taptik and the Thor Spirit is a “final judgment” as to the
    claims against them because it fully disposed of all of the claims against those two
    defendants. See 
    id. at 777.
    Nor is there any just reason to delay hearing D & M’s
    appeal; the appeal does not depend on the resolution of any of the claims between
    D & M and Able Boat and it is unclear whether the claims between those two
    parties will ever be resolved. Although Able Boat’s bankruptcy case was closed in
    November 2012, neither D & M nor Able Boat has moved to lift the district court’s
    stay of the claims involving Able Boat, and D & M has asserted that its claim
    against Able Boat was discharged in the bankruptcy proceedings. Accordingly, the
    district court properly granted the Rule 54(b) certification.
    III.
    D & M raises several issues on appeal. First, D & M contends that it was
    entitled to a maritime lien because it qualified as a “master” or “the person
    entrusted with the management of the vessel at the port of supply” within the
    meaning of 46 U.S.C. § 31341. Second, it contends that the district court
    erroneously concluded that it was not entitled to a maritime lien because it had not
    provided necessaries upon the order of the vessel’s owner or an agent of the owner.
    Third, it contends that the district court abused its discretion by not allowing
    D & M to serve Taptik with process the day that the bench trial began.
    8
    Case: 13-13280       Date Filed: 09/22/2014        Page: 9 of 17
    When a district court sitting in admiralty conducts a bench trial, 6 we review
    the court’s factual findings for clear error and its conclusions of law de novo.
    Venus Lines Agency, Inc. v. CVG Int’l Am., Inc., 
    234 F.3d 1225
    , 1228 (11th Cir.
    2000). The clear error standard recognizes the trial court’s “unique
    opportunity . . . to evaluate the credibility of witnesses and to weigh the evidence.”
    Inwood Labs., Inc. v. Ives Labs., Inc., 
    456 U.S. 844
    , 855, 
    102 S. Ct. 2182
    , 2189
    (1982). “It is the exclusive province of the judge in non-jury trials to assess the
    credibility of witnesses and to assign weight to their testimony,” Hearn v. McKay,
    
    603 F.3d 897
    , 904 (11th Cir. 2010) (alteration and quotation marks omitted), and
    “[w]e accord great deference to the district court’s credibility determinations,”
    United States v. Clay, 
    376 F.3d 1296
    , 1302 (11th Cir. 2004). In a bench trial, the
    judge is “free to choose among alternative reasonable interpretations of the
    evidence,” see United States v. Tampas, 
    493 F.3d 1291
    , 1298 (11th Cir. 2007), and
    its “choice between permissible views cannot be clear error,” United States v.
    Ndiaye, 
    434 F.3d 1270
    , 1305 (11th Cir. 2006). We will not disturb the district
    court’s factual findings unless we are “left with the definite and firm conviction
    that a mistake has been committed.” Inwood Labs., 
    Inc., 456 U.S. at 855
    , 102
    6
    D & M’s in rem claim, arising under 46 U.S.C. § 31342, conferred admiralty
    jurisdiction on the district court. See Am. Dredging Co. v. Miller, 
    510 U.S. 443
    , 446–47, 
    114 S. Ct. 981
    , 985 (1994) (“An in rem suit against a vessel is, we have said, distinctively an
    admiralty proceeding, and is hence within the exclusive province of the federal courts.”) (citing
    The Moses Taylor, 71 U.S. (4 Wall.) 411, 431 (1866)); The Rock Island Bridge, 73 U.S. (6
    Wall.) 213, 215 (1867) (“The [maritime] lien and the proceeding in rem are, therefore,
    correlative—where one exists, the other can be taken, and not otherwise.”).
    9
    Case: 13-13280     Date Filed: 09/22/2014    Page: 10 
    of 17 S. Ct. at 2189
    (quotation marks omitted). When a district court refuses to extend
    the time a plaintiff has to properly serve a defendant under Federal Rule of Civil
    Procedure 4(m), we review that decision only for an abuse of discretion.
    Horenkamp v. Van Winkle & Co., 
    402 F.3d 1129
    , 1132–33 (11th Cir. 2005).
    A.
    D & M asserts that it had authority to obtain necessaries for the Thor Spirit
    because it qualified as either the yacht’s “master” or “a person entrusted with the
    management of the vessel at the port of supply.” Under the Federal Maritime Lien
    Act, an individual is entitled to a lien on a vessel if he provides necessaries to the
    vessel “on the order of the owner or a person authorized by the owner,” 46 U.S.C.
    § 31342, and certain individuals are presumed to have authority to obtain
    necessaries for a vessel, 
    id. § 31341.
    Those individuals include “the master” and
    “a person entrusted with the management of the vessel at the port of supply.” 
    Id. § 31341(a)(2),
    (3).
    In the district court, D & M never raised the issue of whether it had acted as
    the Thor Spirit’s “master” or whether it had been “entrusted with the management
    of the vessel at the port of supply.” Instead, the sole issue it presented was whether
    Able Boat had acted as Taptik’s “agent” and authorized the expenses that D & M
    incurred during transport. We have said again and again that we will not consider
    “an issue not raised in the district court and raised for the first time in an appeal.”
    10
    Case: 13-13280     Date Filed: 09/22/2014   Page: 11 of 17
    Access Now, Inc. v. Sw. Airlines Co., 
    385 F.3d 1324
    , 1331 (11th Cir. 2004)
    (quotation marks omitted); accord Hurley v. Moore, 
    233 F.3d 1295
    , 1297 (11th
    Cir. 2000) (“Arguments raised for the first time on appeal are not properly before
    this Court.”); Nyland v. Moore, 
    216 F.3d 1264
    , 1265 (11th Cir. 2000) (same);
    Provenzano v. Singletary, 
    148 F.3d 1327
    , 1329 n.2 (11th Cir. 1998) (same).
    Although we have the discretion to consider an argument that was not presented to
    the district court, we do so only when “special circumstances” exist. See Access
    Now, 
    Inc., 385 F.3d at 1332
    (listing five instances when we may consider an
    argument raised for the first time on appeal). None of those special circumstances
    is present here. Therefore, we decline to consider D & M’s argument that it was
    authorized under 46 U.S.C. § 31341(a)(2), (3) to secure necessaries for the Thor
    Spirit.
    B.
    Regarding the issue it did preserve, D & M contends that it was entitled to a
    maritime lien on the Thor Spirit because it provided necessaries upon the order of
    the vessel’s owner or an agent of the owner. See S.E.L. Maduro (Fla.), Inc. v. M/V
    Antonio de Gastaneta, 
    833 F.2d 1477
    , 1482 (11th Cir. 1987) (recognizing, in an
    action to enforce a maritime lien, that a court must determine whether the party
    that secured “necessaries” for the vessel had authority to do so). That contention
    11
    Case: 13-13280     Date Filed: 09/22/2014    Page: 12 of 17
    challenges the district court’s factual findings, so we review only for clear error.
    See Venus Lines Agency, 
    Inc., 234 F.3d at 1228
    .
    The district court found that Taptik did not personally authorize D & M to
    transport the Thor Spirit to Florida or to provide the yacht with “necessaries”
    beyond the cost agreed on with Able Boat. The trial court based its conclusion on
    Taptik’s testimony that Able Boat was the only entity he authorized to transport the
    Thor Spirit after he was drawn to the company by its online advertising, as well as
    several undisputed facts. First, Taptik signed a contract with Able Boat to
    transport the yacht, and he never entered into a contract with D & M. Second,
    Able Boat never told Taptik that it had retained D & M as a subcontractor to
    transport the Thor Spirit, and Taptik thought that Able Boat would be the only
    entity entrusted with his boat. Third, in his modified contract with Able Boat,
    Taptik agreed to pay only a flat rate of $38,000 to have his boat transported. In
    light of that testimony and those undisputed facts, the district court did not clearly
    err when it concluded that Taptik did not personally authorize D & M to transport
    the Thor Spirit and secure “necessaries” for the transportation. See Inwood Labs.,
    
    Inc., 456 U.S. at 855
    , 102 S.Ct. at 2189.
    The district court also found that Taptik did not have an agent who
    authorized D & M’s expenditures. That conclusion is a finding of fact that we
    review only for clear error. See Naviera Neptuno S.A. v. All Int’l Freight
    12
    Case: 13-13280     Date Filed: 09/22/2014    Page: 13 of 17
    Forwarders, Inc., 
    709 F.2d 663
    , 665 (11th Cir. 1983) (“Federal maritime law
    embraces the principles of agency, and under those principles the existence of an
    agency relationship is a question of fact.”) (citation omitted); see also Archer v.
    Trans/Am. Servs., Ltd., 
    834 F.2d 1570
    , 1572–73 (11th Cir. 1988) (noting that “the
    existence of an agency relationship is a question of fact” that we review only for
    clear error). An agency relationship can be created in two ways. First, a principal
    may create an agency relationship by vesting a person with “actual authority” to
    make decisions that will have legal consequences for the principal. See
    Restatement (Third) of Agency § 3.01 (2006). “Actual authority . . . is created by a
    principal’s manifestation to an agent that, as reasonably understood by the agent,
    expresses the principal’s assent that the agent take action on the principal’s
    behalf.” 
    Id. An agency
    relationship may also be created through “apparent
    authority.” See 
    id. § 3.03.
    “Apparent authority . . . is created by a person’s
    manifestation that another has authority to act with legal consequences for the
    person who makes the manifestation, when a third party reasonably believes the
    actor to be authorized and the belief is traceable to the manifestation.” 
    Id. “Apparent authority”
    does not exist unless the principal indicates (through words
    or conduct) to the third party that another person is authorized to act as the
    principal’s agent. See 
    id. 13 Case:
    13-13280     Date Filed: 09/22/2014   Page: 14 of 17
    The district court concluded that Able Boat could not have authorized on
    Taptik’s behalf the expenditures that D & M incurred because Able Boat was not
    Taptik’s agent. First, the court found that Able Boat did not have express authority
    to act as Taptik’s agent. That finding was based on two pieces of evidence: (1)
    Taptik’s testimony that he never authorized Able Boat to act as his agent, and (2)
    the contract between Taptik and Able Boat, which did not contain any language
    authorizing Able Boat to act as Taptik’s agent. Second, the court found that Able
    Boat lacked apparent authority to act as Taptik’s agent. The court based that
    finding on evidence presented at trial showing that Taptik never spoke to any
    person affiliated with D & M. As a result, D & M could not have believed, based
    on any representation from Taptik, that Able Boat was authorized to act as his
    agent. See Restatement (Third) of Agency § 3.03. After viewing the record as a
    whole, we are not “left with the definite and firm conviction” that Able Boat was
    authorized to act as Taptik’s agent. See Inwood Labs., 
    Inc., 456 U.S. at 855
    , 102
    S.Ct. at 2189. The district court’s finding was not clearly erroneous.
    The district court also found that Varol was not Taptik’s agent, and therefore
    he could not have authorized on Taptik’s behalf the additional expenses that
    D & M incurred during transport. The court based that conclusion on testimony
    from Taptik and Varol that: (1) Taptik involved Varol in his transaction only for
    the limited purpose of acting as his English language translator, (2) Taptik
    14
    Case: 13-13280    Date Filed: 09/22/2014   Page: 15 of 17
    instructed Varol “never to do anything without asking him first,” and (3) Varol
    never represented to D & M that he was Taptik’s agent. That testimony, which the
    district court expressly credited, supports its conclusion that Varol did not have
    express authority to act as Taptik’s agent for purposes of authorizing D & M’s
    expenditures. The district court also found that Varol lacked apparent authority to
    act as Taptik’s agent. That conclusion is supported by testimony, which the district
    court credited, that Taptik could not have represented to D & M that Varol was his
    agent because he never spoke to any person affiliated with D & M. In light of the
    record as a whole, the district court did not clearly err in concluding that Varol was
    not Taptik’s agent for purposes of authorizing D & M to secure necessaries for the
    Thor Spirit.
    Because the district court did not clearly err in finding that D & M’s
    expenditures were not authorized by Taptik or his agent, D & M was not entitled to
    a maritime lien on the Thor Spirit. See S.E.L. Maduro (Fla.), 
    Inc., 833 F.2d at 1482
    .
    C.
    Finally, although D & M does not challenge the district court’s conclusion
    that Taptik was never properly served, it contends that the district court abused its
    discretion by not allowing it to serve Taptik with process the day that the bench
    trial began — nearly seventeen months after the complaint had been filed. Under
    15
    Case: 13-13280      Date Filed: 09/22/2014       Page: 16 of 17
    the Federal Rules of Civil Procedure, a plaintiff usually has 120 days to serve
    process on a defendant.7 Fed. R. Civ. P. 4(m). The district court has the discretion
    to extend that time limit, even where the plaintiff fails to show “good cause” for its
    failure to serve the defendant within the required 120 days. 
    Horenkamp, 402 F.3d at 1132
    .
    In this case, the district court did not abuse its discretion when it refused to
    allow D & M to serve Taptik at trial nearly a year and a half after the complaint
    had been filed. D & M never asked the court for leave to serve Taptik beyond the
    120-day time period, and it never attempted to show why it had delayed 17
    months. Taptik challenged D & M’s service of process as early as July 2011,
    which was 16 months before the bench trial, but D & M did not take any steps to
    perfect service on him until he made a special appearance in the United States to
    testify at the trial in this case. D & M did not exercise reasonable diligence in
    attempting to properly serve Taptik and it has failed to show good cause for its
    delay. Therefore, the district court did not abuse its discretion when it prevented
    D & M from serving Taptik on the morning of the bench trial. Because the district
    court did not abuse its discretion in preventing D & M from serving Taptik at trial
    7
    That time limit does not apply when a plaintiff is attempting to serve process on an
    individual in a foreign country. See Fed. R. Civ. P. 4(f). But see Lozano v. Bosdet, 
    693 F.3d 485
    , 489 (5th Cir. 2012) (“Rule 4(f) authorizes a without-prejudice dismissal when the court
    determines in its discretion that the plaintiff has not demonstrated reasonable diligence in
    attempting service.”). However, it is undisputed that D & M never attempted to serve Taptik in
    Turkey.
    16
    Case: 13-13280      Date Filed: 09/22/2014      Page: 17 of 17
    and D & M does not challenge the finding that Taptik was never properly served,
    the district court did not err when it dismissed D & M’s breach of contract claim
    against Taptik.
    IV.
    For the reasons discussed, we affirm the district court’s judgment in favor of
    Taptik and the Thor Spirit.
    AFFIRMED. 8
    8
    This appeal was originally scheduled for oral argument but was removed from the oral
    argument calendar by unanimous agreement of the panel under 11th Cir. R. 34-3(f).
    17