Bamberger Rosenheim, Ltd. v. OA Development, Inc. , 862 F.3d 1284 ( 2017 )


Menu:
  •                Case: 16-16163        Date Filed: 07/17/2017      Page: 1 of 10
    [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 16-16163
    ________________________
    D.C. Docket No. 1:15-cv-04460-ELR
    BAMBERGER ROSENHEIM, LTD.,
    (ISRAEL),
    Plaintiff-Appellant,
    versus
    OA DEVELOPMENT, INC.,
    (UNITED STATES),
    Defendant-Appellee.
    ________________________
    Appeal from the United States District Court
    for the Northern District of Georgia
    ________________________
    (July 17, 2017)
    Before MARTIN, JILL PRYOR, and MELLOY, * Circuit Judges.
    *
    Honorable Michael J. Melloy, United States Circuit Judge for the Eighth Circuit, sitting
    by designation.
    Case: 16-16163      Date Filed: 07/17/2017     Page: 2 of 10
    MELLOY, Circuit Judge:
    In this international arbitration dispute, we consider whether courts must
    defer to an arbitrator’s interpretation of a venue provision in a concededly valid
    agreement to arbitrate. We conclude that questions of arbitral venue, even those
    arising in international arbitration, are presumptively for the arbitrator to decide.
    Accordingly, because the arbitrator in the present case arguably interpreted the
    arbitral-venue provision at issue, we defer to that interpretation.          See Oxford
    Health Plans LLC v. Sutter, 
    133 S. Ct. 2064
    , 2068 (2013). We therefore affirm the
    district court’s confirmation of the arbitral award.
    I.
    Appellant Bamberger Rosenheim, Ltd. (“Profimex”), 1 an Israeli company,
    raises capital for real estate investments.         Appellee OA Development, Inc.
    (“OAD”), an American company incorporated in the state of Georgia, develops
    real estate. In 2008, Profimex and OAD entered into a Solicitation Agreement.
    The Solicitation Agreement provided for the arbitration of disputes as follows:
    Any disputes with respect to this Agreement or the performance of the
    parties hereunder shall be submitted to binding arbitration proceedings
    conducted in accordance with the rules of the International Chamber
    of Commerce. Any such proceedings shall take place in Tel Aviv,
    Israel, in the event the dispute is submitted by OAD, and in Atlanta,
    Georgia, in the event the dispute is submitted by Profimex.
    1
    Profimex Ltd. is Bamberger Rosenheim’s wholly-owned subsidiary. The parties both
    refer to the appellant as Profimex, and we will continue that practice.
    2
    Case: 16-16163     Date Filed: 07/17/2017    Page: 3 of 10
    After relations between the parties deteriorated, Profimex commenced
    arbitration in Atlanta against OAD for breach of contract. In the same Atlanta
    arbitration, OAD submitted a counterclaim alleging that Profimex had defamed
    OAD in statements to Israeli investors. Profimex objected to the counterclaim’s
    arbitration in Atlanta, arguing “that a ‘dispute submitted by OAD’ [must] be
    arbitrated in Tel Aviv, Israel.” The arbitrator, however, determined that venue for
    the defamation counterclaim was proper in Atlanta, in part, because the “dispute”
    was submitted by Profimex. The arbitrator ultimately found Profimex liable on
    OAD’s defamation counterclaim.
    Profimex filed a petition to vacate the arbitrator’s defamation award in
    federal district court, and OAD filed a petition to confirm the award. Profimex
    raised several grounds for vacatur and defenses against confirmation. The district
    court, nevertheless, confirmed the award.
    II.
    “We review confirmations of arbitration awards and denials of motions to
    vacate arbitration awards under the same standard, reviewing the district court’s
    findings of fact for clear error and its legal conclusions de novo.” Frazier v.
    CitiFinancial Corp., LLC, 
    604 F.3d 1313
    , 1321 (11th Cir. 2010).               “Because
    arbitration is an alternative to litigation, judicial review of arbitration decisions is
    ‘among the narrowest known to the law.’” AIG Baker Sterling Heights, LLC v.
    3
    Case: 16-16163     Date Filed: 07/17/2017   Page: 4 of 10
    Am. Multi-Cinema, Inc., 
    508 F.3d 995
    , 1001 (11th Cir. 2007) (quoting Del Casal
    v. E. Airlines, Inc., 
    634 F.2d 295
    , 298 (5th Cir. Unit B Jan. 1981)). This “limited
    judicial review . . . ‘maintain[s] arbitration’s essential virtue of resolving disputes
    straightaway.’” Oxford Health 
    Plans, 133 S. Ct. at 2068
    (alteration in original)
    (quoting Hall St. Assocs., LLC v. Mattel, Inc., 
    552 U.S. 576
    , 588 (2008)). “If
    parties could take ‘full-bore legal and evidentiary appeals,’ arbitration would
    become ‘merely a prelude to a more cumbersome and time-consuming judicial
    review process.’” 
    Id. (quoting Hall
    St. 
    Assocs., 552 U.S. at 588
    ).
    On appeal, Profimex argues that the district court erred in confirming the
    arbitral award under the New York Convention.               See Convention on the
    Recognition and Enforcement of Foreign Arbitral Awards, opened for signature
    June 10, 1958, 21 U.S.T. 2517, 330 U.N.T.S. 3 (entered into force with respect to
    the United States Dec. 29, 1970) (“New York Convention”). The New York
    Convention is codified under Chapter 2 of the Federal Arbitration Act (“FAA”), 9
    U.S.C. §§ 201–08, and applies to “non-domestic” arbitral agreements and awards.
    Indus. Risk Insurers v. M.A.N. Gutehoffnungshütte GmbH, 
    141 F.3d 1434
    , 1441
    (11th Cir. 1998). Arbitral awards are non-domestic “when one of the parties to the
    arbitration is domiciled or has its principal place of business outside of the United
    States.” 
    Id. Such awards
    “must be confirmed unless appellants can successfully
    assert one of the seven defenses against enforcement of the award enumerated in
    4
    Case: 16-16163        Date Filed: 07/17/2017      Page: 5 of 10
    Article V of the New York Convention.” 
    Id. (emphasis added).
    Here, Profimex
    asserts that “the arbitral procedure was not in accordance with the agreement of the
    parties.” New York Convention, Art. V(1)(d).
    Profimex also contends the district court erred in denying its petition to
    vacate the award under Chapter 1 of the FAA, 9 U.S.C. §§ 1–16, which governs
    domestic arbitration. Indus. Risk 
    Insurers, 141 F.3d at 1440
    . Under 9 U.S.C. § 10,
    a court “may make an order vacating the award” provided the petitioner establishes
    one of several grounds for vacatur. In the present case, Profimex argues that “the
    arbitrator[ ] exceeded [his] powers.” 9 U.S.C. § 10(a)(4).2
    We see no reason to analyze Profimex’s arguments under the New York
    Convention or § 10(a)(4) separately. In both arguments, Profimex asserts the
    arbitrator improperly applied the arbitral-venue provision in the parties’ agreement
    to arbitrate. According to Profimex, the venue provision required arbitration of the
    defamation counterclaim in Tel Aviv, Israel. By arbitrating the counterclaim in
    Atlanta, Profimex argues, “the arbitral procedure was not in accordance with the
    2
    We assume, without deciding, that § 10 applies to the award in the present case.
    Compare Indus. Risk 
    Insurers, 141 F.3d at 1445
    –46 (refusing to apply a domestic ground for
    vacatur and stating that the “[New York] Convention’s enumeration of defenses is exclusive”),
    with Yusuf Ahmed Alghanim & Sons v. Toys “R” Us, Inc., 
    126 F.3d 15
    , 20–21 (2d Cir. 1997)
    (holding that the FAA’s domestic grounds for vacatur apply to non-domestic arbitral awards
    rendered in the United States); see also BG Grp. PLC v. Republic of Arg., 
    134 S. Ct. 1198
    , 1208
    (2014) (stating an arbitral “award may be ‘set aside or suspended by a competent authority of the
    country in which, or under the law of which, that award was made’” (quoting New York
    Convention, Art. V(1)(e)).
    5
    Case: 16-16163     Date Filed: 07/17/2017   Page: 6 of 10
    agreement of the parties,” New York Convention, Art. V(1)(d), and “the
    arbitrator[ ] exceeded [his] powers,” 9 U.S.C. § 10(a)(4).
    The dispositive issue in the present case is whether this Court must defer to
    the arbitrator’s venue determination.     Ordinarily, “it is up to the parties to
    determine whether a particular matter is primarily for arbitrators or for courts to
    decide.” BG 
    Grp., 134 S. Ct. at 1206
    . However, “[i]f the contract is silent on the
    matter of who primarily is to decide ‘threshold’ questions about arbitration, courts
    determine the parties’ intent with the help of presumptions.” 
    Id. “On the
    one
    hand, courts presume that the parties intend courts, not arbitrators, to decide what
    we have called disputes about ‘arbitrability.’ These include questions such as
    ‘whether the parties are bound by a given arbitration clause,’ or ‘whether an
    arbitration clause in a concededly binding contract applies to a particular type of
    controversy.’” 
    Id. (quoting Howsam
    v. Dean Witter Reynolds, Inc., 
    537 U.S. 79
    ,
    84 (2002)). “On the other hand, courts presume that the parties intend arbitrators,
    not courts, to decide disputes about the meaning and application of particular
    procedural preconditions for the use of arbitration.” 
    Id. at 1207.
    Procedural
    questions “are generally for the arbitrators themselves to resolve.” Klay v. United
    Healthgroup, Inc., 
    376 F.3d 1092
    , 1109 (11th Cir. 2004).
    As suggested by its arguments, Profimex concedes that the arbitration clause
    in the Solicitation Agreement was binding. Similarly, Profimex does not dispute
    6
    Case: 16-16163   Date Filed: 07/17/2017   Page: 7 of 10
    that the arbitration clause applied to the defamation counterclaim.          Profimex
    merely argues that the arbitration was conducted in the wrong arbitral venue. We
    hold, consistent with at least four other circuits, “that disputes over the
    interpretation of forum selection clauses in arbitration agreements raise
    presumptively arbitrable procedural questions.” UBS Fin. Servs., Inc. v. W. Va.
    Univ. Hosps., Inc., 
    660 F.3d 643
    , 655 (2d Cir. 2011); see also Cent. W. Va.
    Energy, Inc. v. Bayer Cropscience LP, 
    645 F.3d 267
    , 273–74 (4th Cir. 2011);
    Ridge at Red Hawk, LLC. v. Schneider, 
    493 F.3d 1174
    , 1178 & n.3 (10th Cir.
    2007); Richard C. Young & Co., Ltd. v. Leventhal, 
    389 F.3d 1
    , 5 (1st Cir. 2004).
    Such clauses determine where an arbitration is conducted, “not whether there is a
    contractual duty to arbitrate at all.” See BG 
    Grp., 134 S. Ct. at 1207
    (“The
    provision before us is of the . . . procedural[ ] variety. . . . It determines when the
    contractual duty to arbitrate arises, not whether there is a contractual duty to
    arbitrate at all.”).
    Our review of the arbitrator’s venue determination, therefore, is limited to
    “whether the arbitrator (even arguably) interpreted the parties’ contract, not
    whether he got its meaning right or wrong.” Oxford Health 
    Plans, 133 S. Ct. at 2068
    . Here, in deciding whether venue for the counterclaim was proper in Atlanta,
    the arbitrator engaged with the language of the venue provision and determined
    that the “dispute” was submitted by Profimex. Thus, “the briefest glance at the
    7
    Case: 16-16163     Date Filed: 07/17/2017    Page: 8 of 10
    [award] reveals that the arbitrator in this case arguably ‘interpreted the [venue
    provision].’” See S. Commc’ns Servs., Inc. v. Thomas, 
    720 F.3d 1352
    , 1359 (11th
    Cir. 2013) (quoting Oxford Health 
    Plans, 133 S. Ct. at 2068
    ). “The arbitrator’s
    construction holds, however good, bad, or ugly.” Oxford Health 
    Plans, 133 S. Ct. at 2071
    .
    Profimex, primarily relying on three cases, nevertheless argues that the
    arbitrator’s interpretation is not entitled to deference. We disagree. First, our
    decision in Sterling Financial Investment Group, Inc. v. Hammer, 
    393 F.3d 1223
    (11th Cir. 2004), does not stand for the proposition that arbitral venue is a question
    for the courts to resolve independently. In that case, we simply held “that a federal
    district court . . . has jurisdiction to enforce a forum selection clause in a valid
    arbitration agreement that has been disregarded by the arbitrators.” 
    Id. at 1225.
    Indeed, by allowing arbitration to proceed in Texas, the arbitrator in Sterling
    Financial clearly disregarded an unambiguous venue provision that only provided
    for arbitration in Florida. See 
    id. at 1224.
    We did not hold that courts should
    review arbitral-venue provisions de novo; in Sterling Financial, it could not be said
    that the arbitrator even arguably interpreted the parties’ contract.
    Second, to the extent it is indistinguishable, we decline to follow Polimaster
    Ltd. v. RAE Systems, Inc., 
    623 F.3d 832
    (9th Cir. 2010). In Polimaster, a divided
    panel of the Ninth Circuit, applying the New York Convention, held that an
    8
    Case: 16-16163        Date Filed: 07/17/2017        Page: 9 of 10
    arbitrator incorrectly applied an arbitral-venue provision somewhat similar to the
    provision in the present case. 
    Id. at 837.
    3 The panel’s holding rested on its
    conclusion that the provision was “not ambiguous.” 
    Id. The dissent,
    however,
    concluded that the provision was susceptible to more than one reasonable
    interpretation and that the arbitrator’s interpretation was thus entitled to deference.
    
    Id. at 844
    (Clifton, J., dissenting). Here, by contrast, we cannot say that the venue
    provision is reasonably susceptible to only one interpretation. And, in any event,
    we note that the Polimaster court failed to engage in any analysis as to whether
    arbitral venue is a question of arbitrability.
    Finally, the international character of the arbitration does not change our
    calculus. Profimex argues that, in international arbitration, “disputes regarding
    forum selection . . . are more akin to ‘questions of arbitrability’ than procedural
    questions arising out of the arbitration.” To support this contention, Profimex
    points to Scherk v. Alberto-Culver Co., 
    417 U.S. 506
    (1974). In Scherk, the
    Supreme Court stated that “[a] contractual provision specifying in advance the
    forum in which disputes shall be litigated and the law to be applied is . . . an almost
    indispensable precondition to achievement of the orderliness and predictability
    essential to any international business transaction.” 
    Id. at 516.
    But Scherk did not
    3
    The contract provided that arbitration was to be conducted “at the defendant’s site,” i.e.,
    “the geographical location of the defendant’s principal place of business.” 
    Polimaster, 623 F.3d at 834
    . “[R]easoning that the contract did not specify where counterclaims should be brought,”
    the arbitrator, much like the present case, allowed a counterclaim to be arbitrated in the same
    country as the initial claim. 
    Id. at 835.
                                                     9
    Case: 16-16163       Date Filed: 07/17/2017       Page: 10 of 10
    concern the choice between different arbitral forums; rather, Scherk concerned
    whether a particular dispute should be resolved in arbitration or in court. 
    Id. at 509–10.
    And, while venue may impact the rules and laws applicable in international
    arbitration, see, e.g., Karaha Bodas Co., LLC v. Perusahaan Pertambangan Minyak
    Dan Gas Bumi Negara, 
    364 F.3d 274
    , 290–91 (5th Cir. 2004), we see no reason
    why arbitral venue must be a question presumptively reserved to the courts. See
    
    Howsam, 537 U.S. at 83
    (“[O]ne might call any potentially dispositive gateway
    question a ‘question of arbitrability’ . . . . The [Supreme] Court’s case law,
    however, makes clear that . . . the phrase ‘question of arbitrability’ has a far more
    limited scope.”). If parties do not want an arbitrator to resolve arbitral-venue
    disputes, they “may agree to limit the issues they choose to arbitrate.” Stolt-
    Nielsen S.A. v. AnimalFeeds Int’l Corp., 
    559 U.S. 662
    , 683 (2010).4
    AFFIRMED.
    4
    Profimex also argues the arbitrator erred in admitting certain deposition testimony. We
    reject this argument. See Rosensweig v. Morgan Stanley & Co., Inc., 
    494 F.3d 1328
    , 1333 (11th
    Cir. 2007) (“In making evidentiary determinations, arbitrators are not required to ‘follow all the
    niceties observed by the federal courts,’ but they must give the parties a fundamentally fair
    hearing.” (quoting Tempo Shain Corp. v. Bertek, Inc., 
    120 F.3d 16
    , 20 (2d Cir. 1997))); 
    id. at 1333–34
    (upholding arbitrator’s evidentiary decision where there was at least one “reasonable
    basis” for the decision); see also Ministry of Def. & Support for the Armed Forces of the Islamic
    Republic of Iran v. Cubic Def. Sys., Inc., 
    665 F.3d 1091
    , 1096–97 (9th Cir. 2011) (noting that
    the New York Convention’s public-policy defense “applies only when confirmation or
    enforcement of a foreign arbitration award would violate the forum state’s most basic notions of
    morality and justice” (internal quotation marks and citation omitted)).
    10
    

Document Info

Docket Number: 16-16163

Citation Numbers: 862 F.3d 1284, 2017 U.S. App. LEXIS 12729, 2017 WL 3014354

Judges: Martin, Pryor, Melloy

Filed Date: 7/17/2017

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (18)

Scherk v. Alberto-Culver Co. , 94 S. Ct. 2449 ( 1974 )

Polimaster Ltd. v. RAE Systems, Inc. , 623 F.3d 832 ( 2010 )

In the Matter of the Arbitration Between Tempo Shain ... , 120 F.3d 16 ( 1997 )

Ridge at Red Hawk, L.L.C. v. Schneider , 493 F.3d 1174 ( 2007 )

Sterling Financial Investment Group, Inc. v. Hammer , 393 F.3d 1223 ( 2004 )

Karaha Bodas Co. v. Perusahaan Pertambangan Minyak Dan Gas ... , 364 F.3d 274 ( 2004 )

Yusuf Ahmed Alghanim & Sons, W.L.L. v. Toys "R" Us, Inc. ... , 126 F.3d 15 ( 1997 )

Richard C. Young & Co. v. Leventhal , 389 F.3d 1 ( 2004 )

Frazier v. CitiFinancial Corp., LLC , 604 F.3d 1313 ( 2010 )

Klay v. United Healthgroup, Inc. , 376 F.3d 1092 ( 2004 )

AIG Baker Sterling Heights, LLC v. American Multi-Cinema, ... , 41 A.L.R. Fed. 2d 685 ( 2007 )

j-e-pelaez-del-casal-v-eastern-airlines-inc-eastern-airlines-inc , 634 F.2d 295 ( 1981 )

Hall Street Associates, L. L. C. v. Mattel, Inc. , 128 S. Ct. 1396 ( 2008 )

BG Group, PLC v. Republic of Argentina , 134 S. Ct. 1198 ( 2014 )

Rosensweig v. Morgan Stanley & Co., Inc. , 494 F.3d 1328 ( 2007 )

Central West Virginia Energy, Inc. v. Bayer Cropscience LP , 645 F.3d 267 ( 2011 )

UBS Financial Services, Inc. v. West Virginia University ... , 660 F.3d 643 ( 2011 )

Oxford Health Plans LLC v. Sutter , 133 S. Ct. 2064 ( 2013 )

View All Authorities »