William B. Newton v. Duke Energy Florida, LLC , 895 F.3d 1270 ( 2018 )


Menu:
  •               Case: 17-10080     Date Filed: 07/11/2018    Page: 1 of 14
    [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 17-10080
    ________________________
    D.C. Docket No. 0:16-cv-60341-WPD
    WILLIAM B. NEWTON,
    NOREEN ALLISON,
    individually and on behalf of all others similarly situated,
    Plaintiffs – Appellants,
    versus
    DUKE ENERGY FLORIDA, LLC,
    a Florida limited liability company,
    FLORIDA POWER & LIGHT COMPANY,
    a Florida profit corporation,
    Defendants – Appellees.
    ________________________
    Appeal from the United States District Court
    for the Southern District of Florida
    ________________________
    (July 11, 2018)
    Case: 17-10080      Date Filed: 07/11/2018        Page: 2 of 14
    Before TJOFLAT and JORDAN, Circuit Judges, and STEELE, * District Judge.
    TJOFLAT, Circuit Judge:
    In 2006, the Florida Legislature enacted the Florida Renewable Energy
    Technologies and Energy Efficiency Act 1 (the “Act”). The Act authorized the
    Florida Public Service Commission (“PSC”) to create a plan to incentivize energy
    utilities to invest in nuclear power plant construction. 
    Fla. Stat. § 366.93
    (2).
    Acting on this authority, the PSC promulgated a regulation creating the Nuclear
    Cost Recovery System (“NCRS”). 2 If a utility chooses to participate in the NCRS
    and receives PSC approval of its plant construction project, it may preemptively
    charge its customers through an electricity rate increase for “costs incurred in the
    siting, design, licensing, and construction” of the project through its completion.
    
    Id.
     Under the NCRS, the utility retains the funds generated by the rate increase
    even if the project is never completed.
    This is a putative class action. The plaintiffs’ class representatives, William
    Newton and Noreen Allison (“Plaintiffs”), claim that two provisions of the Act
    which authorize the NCRS, Florida Statutes §§ 366.93 and 403.519(4), are invalid
    *
    Honorable John E. Steele, United States District Judge for the Middle District of
    Florida, sitting by designation.
    1
    2006 Fla. Laws ch. 230.
    2
    The original “Nuclear Power Plant Cost Recovery” regulation became effective on
    April 8, 2007. Since then, the regulation has been amended twice, most recently pursuant to
    changes to the Act that were passed by the Florida Legislature in 2013. See 
    Fla. Admin. Code Ann. r. 25-6.0423
    .
    2
    Case: 17-10080       Date Filed: 07/11/2018        Page: 3 of 14
    under the Dormant Commerce Clause (“DCC”), which precludes a state from
    “regulat[ing] Commerce . . . among the several States,” U.S. Const. art. I, § 8, cl. 3,
    and “directly limits the power of the States to discriminate against interstate
    commerce.” New Energy Co. of Ind. v. Limbach, 
    486 U.S. 269
    , 273, 
    108 S. Ct. 1803
    , 1807 (1988). Plaintiffs also claim that the two provisions of the Act are
    preempted by the Atomic Energy Act of 1954,3 
    42 U.S.C. § 2011
     et seq., and the
    Energy Policy Act of 2005, Pub. L. No. 109-58, 
    119 Stat. 594
    . 4
    Plaintiffs did not bring these claims against the State of Florida, the PSC
    (which is charged with implementing and administering the Act), or its members.
    Instead, they seek the Act’s invalidation solely by suing two electric utilities, Duke
    Energy Florida and Florida Power & Light (“Utilities”), who have been collecting
    3
    The Atomic Energy Act was one of Congress’s earliest steps to establish the “dual
    regulation of nuclear-powered electricity generation” in which “the federal government
    maintains complete control of the safety and ‘nuclear’ aspects of energy generation” while “the
    states exercise their traditional authority over the need for additional generating capacity, the
    type of generating facilities to be licensed, land use, ratemaking, and the like.” Pac. Gas & Elec.
    Co. v. State Energy Res. Conservation & Dev. Comm’n, 
    461 U.S. 190
    , 211–12, 
    103 S. Ct. 1713
    ,
    1726 (1983).
    4
    Plaintiffs invoked the District Court’s federal question jurisdiction. 
    28 U.S.C. § 1331
    .
    They also invoked the Court’s supplemental jurisdiction under 
    28 U.S.C. § 1367
     by alleging a
    claim of unjust enrichment under Florida law. After dismissing Plaintiffs’ federal claims, the
    Court declined to exercise its supplemental jurisdiction and did not decide the unjust enrichment
    claim. Plaintiffs argue that the Court abused its discretion in doing so because the claim arises
    under federal law. See Grable & Sons Metal Prods., Inc. v. Darue Eng’g & Mfg., 
    545 U.S. 308
    ,
    314, 
    125 S. Ct. 2363
    , 2368 (2005). Not so. This claim is not within the “special and small
    category” of state law claims which arise under federal law within the meaning of 
    28 U.S.C. § 1331
    . Empire Healthchoice Assurance, Inc. v. McVeigh, 
    547 U.S. 677
    , 699, 
    126 S. Ct. 2121
    ,
    2136 (2006); see also Gunn v. Minton, 
    568 U.S. 251
    , 258, 
    133 S. Ct. 1059
    , 1065 (2013)
    (describing the category of Grable claims as “slim”). We therefore affirm the Court’s dismissal
    of the unjust enrichment claim without prejudice.
    3
    Case: 17-10080       Date Filed: 07/11/2018        Page: 4 of 14
    rate increases from them and their class members for nuclear plant construction
    that has been discontinued.
    Utilities separately moved the District Court to dismiss Plaintiffs’ claims
    pursuant to Federal Rule of Civil Procedure 12(b)(6) on numerous grounds. As to
    the DCC claim, Utilities argued that if a cause of action lies under the DCC, it
    belongs to the States that may have been injured due to Florida’s regulation of
    interstate commerce and not to Plaintiffs, who are Florida utility customers.
    Utilities also argued that they are private parties, not state actors, and, as such,
    could not have violated the DCC. As to the preemption claims, Utilities argued
    that they failed for numerous reasons, including that preemption is a defense, not a
    claim for relief.5 Utilities also argued that the preemption claims failed on the
    merits.
    The District Court dismissed Plaintiffs’ DCC claim for lack of “prudential
    standing” because Plaintiffs were not in the “zone of interests” protected by the
    Clause.6 See Harris v. Evans, 
    20 F.3d 1118
    , 1121 (11th Cir. 1994). It dismissed
    5
    Plaintiffs do not assert a claim for relief under the Atomic Energy Act or the Energy
    Policy Act.
    6
    Although the District Court did not state whether the dismissal of the DCC claim was
    pursuant to Federal Rule of Civil Procedure 12(b)(1) or 12(b)(6), we treat it as having been made
    under Rule 12(b)(6). The Supreme Court’s decision in Lexmark International, Inc. v. Static
    Control Components, Inc., 
    572 U.S. 118
    , 
    134 S. Ct. 1377
     (2014), effectively abolished prudential
    standing (sometimes referred to as statutory standing) as a jurisdictional doctrine that would give
    rise to a Rule 12(b)(1) dismissal without prejudice. Under Lexmark, the question is whether
    Plaintiffs have a valid cause of action, and “the absence of a valid . . . cause of action does not
    implicate subject-matter jurisdiction.” 
    Id.
     at ___, 
    134 S. Ct. at
    1387 n.4 (quoting Verizon Md.,
    4
    Case: 17-10080       Date Filed: 07/11/2018      Page: 5 of 14
    Plaintiffs’ preemption claims based on the Atomic Energy Act and the Energy
    Policy Act on the ground that neither act created a cause of action, express or
    implied. 7 The Court dismissed Plaintiffs’ claims without granting leave to amend.
    Plaintiffs moved the District Court for reconsideration pursuant to Federal
    Rule of Civil Procedure 60(b). The motion focused on the Court’s dismissal of
    their claims without leave to amend. Citing Federal Rule of Civil Procedure
    15(a)(2), which states that “[t]he court should freely give leave [to amend] when
    justice so requires,” Plaintiffs argued that they could cure the deficiencies in their
    complaint if given leave to join the State of Florida as a defendant and to prosecute
    their claims against Utilities under 
    42 U.S.C. § 1983
     on the ground that, in
    increasing their rates under the NCRS, Utilities acted under color of state law.
    The District Court denied the Rule 60(b) motion. Its reading of the motion
    was that Plaintiffs were seeking to bolster their claims against Utilities by joining
    the State as a defendant. This would be futile. “Simply joining the State as a
    party,” the Court explained, “would not suddenly empower Plaintiffs to bring
    constitutional claims against private entities, such as [Utilities].” Dist. Ct. Ord.
    Inc. v. Pub. Serv. Comm’n of Md., 
    535 U.S. 635
    , 642–43, 
    122 S. Ct. 1753
    , 1758 (2002)); see also
    Bank of Am. Corp. v. City of Miami, 581 U.S. ___, 
    137 S. Ct. 1296
    , 1302 (2017) (“The question
    is whether the [provision] grants the plaintiff the cause of action that he asserts.”). As we
    explain later, the District Court correctly dismissed the DCC claim under Rule 12(b)(6).
    7
    The District Court dismissed these claims under Federal Rule of Civil Procedure
    12(b)(6).
    5
    Case: 17-10080        Date Filed: 07/11/2018       Page: 6 of 14
    Denying Mot. for Reconsideration at 4. The Court did not expressly respond to
    Plaintiffs’ request to bring their DCC claim against Utilities under § 1983, but it
    implicitly rejected the request in stating that Utilities were not acting under color of
    state law in participating in the NCRS.
    Plaintiffs appeal the District Court’s judgment, arguing that the allegations
    of their complaint were sufficient to make out their DCC claim and their
    preemption claim under the Atomic Energy Act. 8 They also appeal the Court’s
    denial of their Rule 60(b) motion, arguing that the Court abused its discretion in
    denying the request for leave to amend asserted in the motion.
    I.
    We review de novo the dismissal of a claim under Federal Rule of Civil
    Procedure 12(b)(6). Caver v. Cent. Ala. Elec. Coop., 
    845 F.3d 1135
    , 1147 n.9
    (11th Cir. 2017). In this posture, we accept the factual allegations supporting a
    claim as true and draw all reasonable inferences in favor of the nonmovant. West
    v. Warden, Comm’r, Ala. DOC, 
    869 F.3d 1289
    , 1296 (11th Cir. 2017). We review
    a district court’s denial of leave to amend under the abuse of discretion standard.
    Smith v. Duff & Phelps, Inc., 
    5 F.3d 488
    , 493 (11th Cir. 1993). With these
    principles in hand, we turn to the dismissal of Plaintiffs’ DCC claim, then to their
    8
    Plaintiffs also appeal the dismissal of their unjust enrichment claim. See supra note 4.
    Plaintiffs do not appeal the District Court’s dismissal of their preemption claim based on the
    Energy Policy Act.
    6
    Case: 17-10080       Date Filed: 07/11/2018       Page: 7 of 14
    preemption claim under the Atomic Energy Act. After that, we consider the denial
    of leave to amend.
    II.
    A.
    The “modern law” of the DCC is “driven by concern about ‘economic
    protectionism,’” or, in other words, “regulatory measures designed to benefit in-
    state economic interests by burdening out-of-state competitors.” Dep’t of Revenue
    of Ky. v. Davis, 
    553 U.S. 328
    , 337–38, 
    128 S. Ct. 1801
    , 1808 (2008) (quoting New
    Energy, 
    486 U.S. at 273
    , 
    108 S. Ct. at 1807
    ). If a state law unduly burdens
    competition in another state, the law may be unconstitutional under the DCC. The
    injury contemplated by the DCC, then, is that of an out-of-state person or entity
    harmed by some other state’s action.
    This is far from the case here. Plaintiffs are Florida electric utility
    customers. Utilities are Florida companies. Utilities are not “states” such that their
    actions could give rise to DCC claims from an out-of-state person or entity.
    Plaintiffs’ interests are well beyond the zone the DCC is meant to protect.9 See
    9
    We do not mean to say that an in-state plaintiff can never assert a DCC claim against its
    own state’s law or regulation. That would be incorrect. See, e.g., Fla. Transp. Servs., Inc. v.
    Miami-Dade Cty., 
    703 F.3d 1230
    , 1255–56 (11th Cir. 2012). Rather, here, where Plaintiffs are
    customers in a non-competitive marketplace—subject to regulated monopolies—and Utilities are
    similarly not subject to competition from out-of-state nuclear energy providers, the DCC simply
    “has no job to do.” See Gen. Motors Corp. v. Tracy, 
    519 U.S. 278
    , 303, 
    117 S. Ct. 811
    , 826
    (1997).
    7
    Case: 17-10080     Date Filed: 07/11/2018    Page: 8 of 14
    Harris, 
    20 F.3d at 1121
    . For these reasons, we affirm the dismissal of Plaintiffs’
    DCC claim under Rule 12(b)(6).
    B.
    Next, we turn to Plaintiffs’ preemption claim. It is well-settled that there are
    three types of preemption:
    First, Congress has the authority to expressly preempt state law by
    statute. Second, even in the absence of an express preemption
    provision, the scheme of federal regulation may be so pervasive as to
    make reasonable the inference that Congress left no room for the
    States to supplement it.        Third, federal and state law may
    impermissibly conflict, for example, where it is impossible for a
    private party to comply with both state and federal law, or when the
    state law at issue stands as an obstacle to the accomplishment and
    execution of the full purposes and objectives of Congress.
    Graham v. R.J. Reynolds Tobacco Co., 
    857 F.3d 1169
    , 1293 (11th Cir. 2017) (en
    banc) (Tjoflat, J., dissenting) (citations and quotations omitted) (alterations
    accepted). Plaintiffs rely on the second of these, commonly referred to as “field
    preemption,” and argue that the Atomic Energy Act established the federal
    government as the exclusive authority to regulate the construction of nuclear power
    plants such that they may sue to establish preemption.
    A claim that a plaintiff asserts under state law, in a field that is completely
    preempted, necessarily arises under federal law. See, e.g., Borrero v. United
    Healthcare of N.Y., Inc., 
    610 F.3d 1296
    , 1301 (11th Cir. 2010) (addressing
    complete preemption under ERISA). Despite preemption’s usual character as a
    8
    Case: 17-10080       Date Filed: 07/11/2018       Page: 9 of 14
    defense, we have jurisdiction to consider Plaintiffs’ claim for injunctive relief here.
    Shaw v. Delta Air Lines, Inc., 
    463 U.S. 85
    , 96 n.14, 
    103 S. Ct. 2890
    , 2899 n.14
    (1983) (“A plaintiff who seeks injunctive relief from state regulation, on the
    ground that such regulation is pre-empted by a federal statute which, by virtue of
    the Supremacy Clause of the Constitution, must prevail, thus presents a federal
    question which the federal courts have jurisdiction under 
    28 U.S.C. § 1331
     to
    resolve.”); Ga. Latino All. for Human Rights v. Governor of Ga., 
    691 F.3d 1250
    ,
    1262 (11th Cir. 2012) (holding that there exists “an implied right of action to assert
    a preemption claim seeking injunctive relief”) (citations and internal quotation
    marks omitted).
    Therefore, we address the merits of the claim. In Pacific Gas & Electric Co.
    v. State Energy Resources Conservation & Development Commission, 
    461 U.S. 190
    , 
    103 S. Ct. 1713
     (1983), the Supreme Court turned away a preemption
    challenge to a California law that conditioned the construction of nuclear power
    plants on findings by a state commission that adequate storage facilities and means
    of disposal were available for nuclear waste. The Court first explained that “the
    federal government has occupied the entire field of nuclear safety concerns.”10 
    Id. at 212
    , 103 S. Ct. at 1726 (emphasis added). But the Court concluded that there
    was an economic (and non-safety) rationale for the California law, and this was
    10
    The Pacific Gas Court also described the balance between state and federal regulation
    of nuclear energy production that the Atomic Energy Act codified. See supra note 3.
    9
    Case: 17-10080    Date Filed: 07/11/2018    Page: 10 of 14
    enough to save it from preemption. See id. at 216, 103 S. Ct. at 1728 (“[W]e
    accept California’s avowed economic purpose as the rationale for enacting
    § 25524.2. Accordingly, the statute lies outside the occupied field of nuclear
    safety regulation.”). The Court also rejected a preemption claim based on the
    theory that the California law frustrated the purpose of the Atomic Energy Act,
    which is to promote the use of nuclear power. According to the Court, Congress
    left states room to determine, for economic reasons, whether a nuclear plant or a
    fossil-fuel plant, for example, should be built. See id. at 221–22, 103 S. Ct. at
    1731.
    Where, as here, the federal government has occupied a portion of a given
    field, “the test of preemption is whether the matter on which the state asserts the
    right to act is in any way regulated by the federal government.” Id. at 213, 103 S.
    Ct. at 1727 (citation and internal quotation marks omitted). The NCRS is based on
    an economic rationale—whether flawed or not—that utilities like Duke Energy
    Florida and Florida Power & Light should be able to recoup from their customers
    the costs associated with a project for the construction of a nuclear power plant,
    and that they should not have to return the funds received even if the project is not
    completed. See Smalley v. Duke Energy Fla., Inc., 
    154 So. 3d 439
    , 440 (Fla. Dist.
    Ct. App. 2014).
    10
    Case: 17-10080       Date Filed: 07/11/2018       Page: 11 of 14
    Plaintiffs point to no cases holding (nor authorities suggesting) that state
    laws promoting investment in new nuclear plants, or shifting the costs of nuclear
    plant construction, are preempted by the Atomic Energy Act. That failure is not
    surprising given the language of 
    42 U.S.C. § 2021
    (k) (“Nothing in this section
    shall be construed to affect the authority of any State or local agency to regulate
    activities for purposes other than protection against radiation hazards.”).
    Plaintiffs do cite 
    42 U.S.C. § 2209
     for the proposition that the Atomic
    Energy Act “specifically prohibits [commercial] reactors from receiving
    subsidies.” Br. for Plaintiffs at 27 & n. 91. But § 2209 says only that “[n]o funds
    of the [Atomic Energy] Commission shall be employed in the construction or
    operation” of commercial nuclear reactors. 
    42 U.S.C. § 2209
    . As the NCRS does
    not involve Commission funds, § 2209 does not help Plaintiffs. Therefore, we
    hold that the Atomic Energy Act does not preempt the NCRS. 11
    C.
    Finally, we consider whether the District Court abused its discretion in
    denying Plaintiffs’ request for leave to amend their complaint. Plaintiffs first
    expressed a desire to amend the complaint in the memorandum they filed in
    11
    We held in Liesen v. Louisiana Power & Light Co., 
    636 F.2d 94
    , 95 (5th Cir. Unit A
    Feb. 2, 1981), that the general enforcement provision of the Atomic Energy Act, 
    42 U.S.C. § 2271
    , does not create a private right of action. Because Plaintiffs are not seeking enforcement
    of the Act pursuant to § 2271, Liesen does not bar their preemption claim. See Bonner v. City of
    Prichard, 
    661 F.2d 1206
    , 1207 (11th Cir. 1981) (holding that Fifth Circuit decisions issued on or
    before September 30, 1981 are binding precedent in this Circuit).
    11
    Case: 17-10080     Date Filed: 07/11/2018     Page: 12 of 14
    opposition to Duke Energy Florida’s Rule 12(b) motion to dismiss. In the event
    the Court granted Utilities’ motions, they said, the Court should give them leave to
    amend their DCC claim in order to seek relief under § 1983 on the theory that
    Utilities were acting under color of state law in raising their electricity rates.
    Standing alone, the request possessed no legal effect for two reasons. First,
    “[w]here a request for leave to file an amended complaint simply is imbedded
    within an opposition memorandum, the issue has not been raised properly.” Cita
    Tr. Co. AG v. Fifth Third Bank, 
    879 F.3d 1151
    , 1157 (11th Cir. 2018) (quoting
    Rosenberg v. Gould, 
    554 F.3d 962
    , 967 (11th Cir. 2009)) (alteration in original).
    Second, “[a] request for a court order must be made by motion. The motion must
    be in writing unless made during a hearing or trial.” Fed. R. Civ. P. 7(b)(1). And
    it must “state with particularity the grounds for seeking the order[,] and state the
    relief sought.” 
    Id.
     Plaintiffs’ inclusion of the request for leave in their opposition
    to a motion to dismiss did not constitute a “motion” and thus did not comply with
    this Rule 7(b) command.
    Plaintiffs did request leave to amend in their Rule 60(b) motion. The
    question arises as to whether the request they made in opposing the Rule 12(b)(6)
    dismissal of the DCC claim provided any support for the request they made in the
    Rule 60(b) motion. The answer is no. The request made in opposing the motion to
    dismiss the DCC claim is irrelevant. But did Plaintiffs’ inclusion of a request for
    12
    Case: 17-10080     Date Filed: 07/11/2018    Page: 13 of 14
    leave to amend within their Rule 60(b) motion comport with the Rule 7(b) motion
    requirement? Yes. See Almanza v. United Airlines, Inc., 
    851 F.3d 1060
    , 1075
    (11th Cir. 2017) (explaining that plaintiffs may seek leave to amend in motions
    made pursuant to Federal Rules of Civil Procedure 59(e) or 60(b)(6)).
    Was the request for leave to amend legally sufficient? That depends on what
    the request did or did not contain. When moving the district court for leave to
    amend its complaint, the plaintiff must “set forth the substance of the proposed
    amendment or attach a copy of the proposed amendment” to its motion. Cita Tr.,
    879 F.3d at 1157 (quoting Long v. Satz, 
    181 F.3d 1275
    , 1279 (11th Cir. 1999)).
    The substance of the proposed amendment serves as the functional equivalent of a
    copy of the proposed amendment if it is sufficient on its face to inform the Court of
    the proposal. Plaintiffs did not attach a proposed amended complaint to their Rule
    60(b) motion, so for their request for leave to be legally efficacious, the Rule 60(b)
    motion must have set forth sufficiently the substance of Plaintiffs’ proposed
    amendment. To that end, Plaintiffs said this:
    First, Plaintiffs could have cured the state action defect by naming the
    State as a defendant to their Commerce Clause challenge, or the Court
    itself could have simply ordered the State to join the lawsuit.
    Plaintiffs also could have amended the Complaint to include
    allegations that Defendants acted under color of law. The state action
    requirement of § 1983 is satisfied by the State of Florida’s active
    encouragement of Defendants’ participation in the Nuclear Cost
    Recovery Statute (NCRS) to fulfill state energy goals.
    13
    Case: 17-10080     Date Filed: 07/11/2018    Page: 14 of 14
    Plaintiffs’ Mot. for Reconsideration at 2. On its face, this statement barely
    scratches the surface of what Plaintiffs’ amended complaint would state. It merely
    hypothesizes, in broad strokes, the kinds of amendments that Plaintiffs might have
    been able to make. It clearly does not satisfy Cita Trust’s requirement. In
    addition, neither the State of Florida nor its agencies could be named in or added to
    the lawsuit without violating the Eleventh Amendment, and neither the State of
    Florida nor its agencies are “persons” within the meaning of § 1983. Will v. Mich.
    Dep’t of State Police, 
    491 U.S. 58
    , 
    109 S. Ct. 2304
     (1989). For these reasons, the
    District Court did not abuse its discretion in denying Plaintiffs leave to amend.
    III.
    There is no merit in Plaintiffs’ appeal. Plaintiffs’ complaint failed to state a
    claim for relief. Fed. R. Civ. P. 12(b)(6). The judgment of the District Court is
    accordingly affirmed.
    AFFIRMED.
    14