National Aerotech Aviation, Inc. v. Seaborne Virgin Islands, Inc. , 387 F. App'x 893 ( 2010 )


Menu:
  •                                                          [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FILED
    FOR THE ELEVENTH CIRCUIT   U.S. COURT OF APPEALS
    ________________________   ELEVENTH CIRCUIT
    JULY 19, 2010
    No. 10-10927                   JOHN LEY
    Non-Argument Calendar                CLERK
    ________________________
    D. C. Docket No. 09-CV-3252-RLV
    NATIONAL AEROTECH AVIATION, INC.,
    Petitioner-Appellant,
    versus
    SEABORNE VIRGIN ISLANDS, INC.,
    d.b.a. Seaborne Airlines,
    Respondent-Appellee.
    ________________________
    Appeal from the United States District Court
    for the Northern District of Georgia
    _________________________
    (July 19, 2010)
    Before TJOFLAT, PRYOR and FAY, Circuit Judges.
    PER CURIAM:
    National Aerotech Aviation appeals the summary judgment that confirmed
    an arbitration award of damages to Seaborne Virgin Islands. Seaborne contracted
    with Aerotech to repair an airplane, and after Aerotech failed timely to complete
    those repairs, Seaborne sought and an arbitrator awarded damages against
    Aerotech. Aerotech argues that the district court “improperly and erroneously
    weighed the material facts” in determining whether the arbitrator acted in
    “manifest disregard of the law,” 
    Ga. Code Ann. § 9-9-13
    (b)(5), and Aerotech
    argues, for the first time on appeal, that the district court terminated discovery
    prematurely. We affirm.
    The contract between Seaborne and Aerotech provided that Aerotech would
    return or “redeliver” the airplane to Seaborne by January 15, 2008, and the contract
    provided increased payments for an early delivery and compensation for a late one.
    Article 4.7 stated, “The parties agree that if redelivery of the Aircraft does not
    occur on or before the Redelivery Date, payments made by Seaborne to [Aerotech]
    prior to the Redelivery Date shall constitute full and final settlement of all claims
    by either Party arising from this contract or related to the Aircraft in any other
    way.” Article 6.1 provided, “For each day before the Redelivery Date that
    [Aerotech] redelivers the Aircraft, Seaborne shall pay [Aerotech] $9,780.00 above
    and beyond the Contract Price.” In the event of an untimely return of the airplane,
    2
    Article 6.2 provided that “each day after the Redelivery Date that [Aerotech] fails
    to redeliver the Aircraft, [Aerotech] shall pay Seaborne $8,500.00.” The contract
    also provided that it was to be “governed by and construed in accordance with the
    laws of the State of Georgia” and any dispute was to be resolved by arbitration.
    Seaborne and Aerotech later executed an addendum to the contract, which retained
    the same redelivery date but provided that the parties “agree that no penalty or
    incentive payments under Article 6 (“Performance Incentives”) shall accrue” if
    Aerotech “redelivers the Aircraft on or before February 8, 2008.”
    After Seaborne received the airplane from Aerotech on April 17, 2008,
    Seaborne sought to recover damages from Aerotech under Article 6.2 of the
    contract, and the companies submitted their dispute to arbitration. Aerotech argued
    that Seaborne was “barred from seeking liquidated damages” under Article 6.2
    “because its exclusive remedy [was] the payments made” to Aerotech, as provided
    in Article 4.7. Seaborne referred to Article 6.2 as a “liquidated damages” provision
    and argued that Article 6.2 satisfied the “conditions for allowable damages under
    Georgia law.” Aerotech responded that Article 6.2 provided an “inaccurate
    measure of [Seaborne’s] alleged damages,” and Aerotech argued that Seaborne had
    not “suffered any economic damages.”
    The arbitrator ruled that Seaborne was entitled to recover damages from
    3
    Aerotech. “Reading the contract as a whole” to determine the intentions of the
    parties as required by “Georgia law,” the arbitrator concluded that “the dominant
    purpose of the contract was to perform maintenance, repairs, and overhaul of” the
    airplane “so as to return it to revenue service by the Redelivery Date” and the
    parties had incorporated “[i]ncentives . . . to carry out [that] purpose.” The
    arbitrator also ruled that the failure of Aerotech to “complete work” on the airplane
    “by the Redelivery Date authorizes assessment of negative incentives pursuant to
    Article 6” of the October 2007 addendum to the contract. The arbitrator found that
    Aerotech exceeded the redelivery date by 54 days, which resulted in a “total
    negative incentive” of $459,000. The arbitrator reduced the total negative
    incentive by amounts owed by Seaborne to calculate a “total amount due” by
    Aerotech of $335,453.37.
    Aerotech petitioned the district court to vacate the arbitration award and
    argued that the arbitrator acted in manifest disregard of Georgia law by interpreting
    Article 6.2 as a liquidated damages provision. Seaborne counter-petitioned to
    enforce the award and later moved for summary judgment. Aerotech filed a
    preliminary report and discovery plan, which the district court approved. Aerotech
    later moved for partial summary judgment regarding its interpretation of Article
    6.2.
    4
    The district court granted summary judgment in favor of Seaborne and
    confirmed the arbitration award. The district court ruled that the arbitrator had
    “clearly considered Georgia law with respect to penalty clauses and liquidated
    damages” and had “determined that the performance incentives negotiated by the
    two sophisticated corporations . . . were not penalties but were in the nature of
    liquidated damages.” The district court ruled that the arbitrator had “not ignore[d]
    Georgia law” in its decision.
    Our review of a summary judgment seeking vacatur of an arbitration award
    “‘is plenary, and we apply the same legal standards that bound the district court.’”
    Bruno’s, Inc. v. United Food & Commercial Workers Int’l Union, Local 1657, 
    858 F.2d 1529
    , 1531 (11th Cir. 1988) (quoting Am. Ass’n of Christian Sch. v. United
    States, 
    850 F.2d 1510
    , 1513 (11th Cir. 1988)). Under the Georgia Arbitration
    Code, which the district court applied, “judicial review of an arbitration award is
    limited.” Airtab, Inc. v. Limbach Co., LLC, 
    295 Ga. App. 720
    , 720, 
    673 S.E.2d 69
    , 71 (2009).
    An arbitration award in Georgia may be vacated in only five narrowly
    defined circumstances, one of which is “the arbitrator’s manifest disregard of the
    law.” 
    Ga. Code Ann. § 9-9-13
    (b)(5). As its wording suggests, a “manifest
    disregard of the law” involves more than a “‘misapplication of the law to the
    5
    facts,’” Airtab, 295 Ga. App. at 722, 
    673 S.E.2d at 72
     (quoting Johnson Real Estate
    Invs. v. Aqua Indus., 
    282 Ga. App. 638
    , 640, 
    639 S.E.2d 589
    , 593 (2006)), or even
    an “incorrect interpret[ation of] the law,” BMW Bank of N. Am. v. Short, 
    300 Ga. App. 430
    , 431, 
    685 S.E.2d 390
    , 391 (2009). To warrant relief, the party contesting
    the award must produce evidence that the arbitrator knew of and “deliberately
    ignore[d] applicable law.” Id.; Airtab, 295 Ga. App. at 722, 
    673 S.E.2d at 72
    ; see
    also O.R. Sec., Inc. v. Prof’l Planning Assocs., Inc., 
    857 F.2d 742
    , 747 (11th Cir.
    1988) (applying same test under the Federal Arbitration Act).
    Aerotech argues that the district court “improperly weighed” evidence that
    the arbitrator disregarded Georgia law by “characteriz[ing] Article 6.2 as a
    ‘negative incentive’” and enforcing it as a liquidated damages provision instead of
    as an unenforceable penalty, but we disagree. Article 6 of the contract is titled
    “Performance Incentives.” The arbitrator reasonably construed Article 6.2 as a
    liquidated damages provision.
    Aerotech offered no evidence that the arbitrator deliberately ignored the law.
    Georgia law provides that parties may agree to liquidated damages in their
    contracts, see 
    Ga. Code Ann. §§ 13-6-1
    , 13-6-7, and require the payment of daily
    amounts to compensate an aggrieved party, Joyce’s Submarine Sandwiches, Inc. v.
    Cal. Public Emps. Ret. Sys., 
    195 Ga. App. 748
    , 749–50, 
    395 S.E.2d 257
    , 258–60
    6
    (1990) (clause in lease agreement requiring $50 payment each day lessee remained
    closed provided liquidated damages instead of a penalty). The district court did
    not err in granting summary judgment in favor of Seaborne.
    The belated argument of Aerotech that the district court should have
    “allow[ed] discovery to proceed according to” an order entered after Seaborne
    moved for summary judgment also fails. “District judges are accorded wide
    discretion in ruling upon discovery motions, and appellate review is accordingly
    deferential.” Harris v. Chapman, 
    97 F.3d 499
    , 506 (11th Cir. 1996). Aerotech
    stated in its request for discovery its belief “that limited discovery . . . may be
    needed,” but Aerotech never argued in the district court, nor does it argue in this
    Court, that additional evidence was required to adjudicate this controversy. The
    district court did not abuse its discretion.
    We AFFIRM the summary judgment that confirmed the arbitration award in
    favor of Seaborne.
    7