Hanover Insurance Company v. Bay Meadows Consulting LLC , 579 F. App'x 742 ( 2014 )


Menu:
  •           Case: 13-14482   Date Filed: 08/29/2014   Page: 1 of 10
    [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 13-14482
    Non-Argument Calendar
    ________________________
    D.C. Docket No. 7:13-cv-00506-LSC
    HANOVER INSURANCE COMPANY, THE,
    Plaintiff-Appellee,
    versus
    ATLANTIS DRYWALL & FRAMING LLC, et al.,
    Defendants,
    BAY MEADOWS CONSULTING LLC,
    MARILOURDES DEYO,
    LAURENCE LAMPHERE,
    CHRISTIN M. LAMPHERE,
    Defendants-Appellants.
    ________________________
    Appeal from the United States District Court
    for the Northern District of Alabama
    ________________________
    (August 29, 2014)
    Case: 13-14482      Date Filed: 08/29/2014   Page: 2 of 10
    Before HULL, MARCUS and KRAVITCH, Circuit Judges.
    PER CURIAM:
    In this interlocutory appeal, we must determine whether the district court
    properly denied Bay Meadows Consulting (Bay Meadows), Marilourdes Deyo, and
    Laurence and Christin Lampheres’ motions to compel arbitration. For the reasons
    that follow, we vacate and remand.
    I.
    In 2010, the University of Alabama North Bluff Residential Community
    Project hired Brice Building Company (Brice) as the general contractor for
    development of a student housing complex. In March 2011, Brice subcontracted
    with Atlantis Drywall and Framing (Atlantis) for work on the North Bluff project.
    The subcontract contained an arbitration clause requiring arbitration over any
    dispute or claim “between the parties (i) arising out of or related or collateral to the
    provisions and/or subject matter of this Subcontract or the breach thereof . . . .”
    The clause further provided that “[t]he parties intend that the scope of this
    arbitration clause shall be construed as broadly as possible so as to include, but not
    be limited to, the enforcement of this arbitration provision, the arbitrability of a
    particular claim or dispute . . . .”
    In order to work on State of Alabama projects like the North Bluff complex,
    Atlantis was required to obtain payment and performance bonds, which they
    2
    Case: 13-14482      Date Filed: 08/29/2014      Page: 3 of 10
    secured from Hanover Insurance Company (Hanover). Before Hanover would
    issue any bonds, however, it required indemnification by Atlantis, Bay Meadows,
    Deyo, and the Lampheres.1 The Indemnification Agreement did not contain an
    arbitration clause, nor did it expressly incorporate by reference any other
    document. All parties entered into the Indemnification Agreement in May 2011.
    On June 30, 2011, Hanover issued the payment and performance bonds. The
    bonds specifically referenced and incorporated the subcontract between Brice and
    Atlantis.
    Atlantis later defaulted on the work, and Hanover made payments under the
    bonds. Hanover then sought indemnification. When the parties failed to comply,
    Hanover filed a complaint in the district court naming as defendants Bay
    Meadows, Marilourdes Deyo, and Laurence and Christin Lamphere (collectively,
    “the indemnitors”).2 Hanover sought indemnification, exoneration and quia timet,
    specific performance, and damages for breach of contract. The indemnitors
    moved to compel arbitration under the Federal Arbitration Act (FAA), 9 U.S.C. §
    1, et seq.3
    In the motions to compel, the indemnitors argued that Hanover was required
    to arbitrate its claims under the arbitration clause in the subcontract. They further
    1
    Deyo and Laurence Lamphere are members of Atlantis and Bay Meadows.
    2
    The complaint also named Atlantis and Jeffrey Deyo, who are not parties to the appeal.
    3
    Laurence and Christin Lamphere filed a joint motion to compel. Although the remaining
    defendants each filed separate motions, they adopted the Lampheres’ motion.
    3
    Case: 13-14482        Date Filed: 08/29/2014         Page: 4 of 10
    argued that Hanover was bound by the arbitration clause because the
    Indemnification Agreement incorporated the subcontract between Brice and
    Atlantis.
    The district court denied the motions to compel, finding that Hanover did not
    agree to arbitrate, the Indemnification Agreement did not explicitly incorporate any
    other contract because it did not “expressly refer to and sufficiently describe” the
    bonds or subcontract, and the court could not view the three documents as a single
    transaction because the parties differed. 4 Finally, the court explained that Hanover
    could not be compelled to arbitrate because Hanover’s claims did not arise out of
    the subcontract, as Hanover was not claiming a direct right or benefit under the
    subcontract but was seeking only to enforce the terms of the Indemnification
    Agreement. This interlocutory appeal under 9 U.S.C. § 16(a) followed.
    II.
    Indemnitors Bay Meadows, Deyo, and the Lampheres argue on appeal that
    the district court erred by concluding that they could not enforce against Hanover
    an arbitration clause contained in the subcontract between Brice and Atlantis. The
    parties do not dispute that the payment and performance bonds Hanover issued to
    4
    In a separate action, the district court found that Hanover was required to arbitrate its claims
    against Brice because Hanover was subject to the arbitration agreement after incorporating the
    subcontract into the bonds. See Hanover Ins. Co. v. Brice, 7:13-cv-00547-LSC, doc. 21 (N.D.
    Ala. May 31, 2013). The district court also granted a motion to compel Hanover to arbitrate its
    claims against Atlantis. See Hanover Ins. Co. v. Lamphere, 7:13-cv-00506-LSC, doc. 41 (N.D.
    Ala. Oct. 7, 2013).
    4
    Case: 13-14482    Date Filed: 08/29/2014   Page: 5 of 10
    Atlantis and Brice incorporated by reference the subcontract. The indemnitors
    contend that the subcontract was sufficiently incorporated by reference into the
    Indemnification Agreement to require arbitration of Hanover’s claims against the
    indemnitors.
    “We review de novo the district court’s denial of a motion to compel
    arbitration.” Lawson v. Life of the South Ins. Co., 
    648 F.3d 1166
    , 1170 (11th Cir.
    2011) (citation omitted). The FAA establishes a “liberal federal policy favoring
    arbitration agreements.” CompuCredit Corp. v. Greenwood, 
    132 S. Ct. 665
    , 668-69
    (2012) (citations and internal quotations omitted). And “[c]ourts must rigorously
    enforce agreements to arbitrate, even if doing so means piecemeal litigation.”
    Nobles v. Rural Cmty. Ins. Servs., 
    122 F. Supp. 2d 1290
    , 1295 (M.D. Ala. 2000)
    (citing Dean Witter Reynolds, Inc. v. Byrd, 
    470 U.S. 213
    , 218-20 (1985)).
    “Because arbitration is a matter of contract, however, the FAA’s strong
    proarbitration policy only applies to disputes that the parties have agreed to
    arbitrate.” Klay v. All Defendants, 
    389 F.3d 1191
    , 1200 (11th Cir. 2004) (citation
    omitted). Thus, where the parties have not agreed to arbitrate, a court cannot
    compel them to arbitration. See 
    id. An exception
    to this rule allows a nonparty to
    “force arbitration ‘if the relevant state contract law allows him to enforce the
    agreement’ to arbitrate.” See 
    Lawson, 648 F.3d at 1170
    (quoting Arthur Andersen
    LLP v. Carlisle, 
    556 U.S. 624
    , 632 (2009)); see also McDougle v. Silvernell, 738
    5
    Case: 13-14482      Date Filed: 08/29/2014   Page: 6 of 
    10 So. 2d 806
    , 808 (Ala. 1999) (“Whether a contract to arbitrate exists must be
    determined under general state-law contract principles”).
    As an initial matter, there is little dispute that Hanover consented to arbitrate
    claims arising out of the subcontract between Brice and Atlantis; the performance
    and payment bonds incorporated by reference the subcontract, and the subcontract
    contained the arbitration clause. See U. S. Fid.& Guar. Co. v. West Point Constr.
    Co., 
    837 F.2d 1507
    , 1508 (11th Cir. 1988). At issue, is whether the indemnitors
    can force Hanover to arbitrate Hanover’s claims against them under the arbitration
    clause in the subcontract between Brice and Atlantis. Because the indemnitors
    were not signatories on the subcontract, and the Indemnification Agreement does
    not expressly contain an arbitration clause, the indemnitors can compel arbitration
    in only limited circumstances.
    First, the indemnitors can compel arbitration if the Indemnification
    Agreement incorporated the subcontract. 
    McDougle, 738 So. 2d at 808
    (explaining
    that a party may incorporate by reference another document containing an
    arbitration provision). To incorporate another document, the writing must
    “expressly refer[] to and sufficiently describe[]” the other document. Fid. &
    Deposit Co. of Maryland v. Jefferson Cnty. Comm’n, 
    756 F. Supp. 2d 1329
    , 1337
    (N.D. Ala. 2010).
    6
    Case: 13-14482     Date Filed: 08/29/2014    Page: 7 of 10
    Alternatively, the subcontract may be incorporated by reference if it is part
    of the same transaction, that is, if the bonds, Indemnification Agreement, and
    subcontract are all part of a single transaction. Dan Wachtel Ford, Lincoln,
    Mercury, Inc. v. Modas, 
    891 So. 2d 287
    , 290 (Ala. 2004). Generally, this involves
    documents signed by the same parties at or near the same time. See, e.g., Lloyd
    Noland Found., Inc. v. City of Fairfield Healthcare Auth., 
    837 So. 2d 253
    , 267
    (Ala. 2002) (“two or more instruments executed contemporaneously by the same
    parties in reference to the same subject matter constitute one contract and should
    be read together in construing the contract” (internal citation omitted)); cf. Bailey
    v. Hannibal & St. J.R. Co., 
    84 U.S. 96
    , 108 (1872) (“[I]t is well-settled law that
    several writings executed between the same parties substantially at the same time
    and relating to the same subject-matter may be read together as forming parts of
    one transaction, nor is it necessary that the instruments should in terms refer to
    each other if in point of fact they are parts of a single transaction”). But Alabama
    law has never held that the parties must be the same. See Ex parte Harris, 
    837 So. 2d 283
    , 288 (Ala. 2002) (accepting that “two or more agreements may be
    construed as one contract even though the parties to the agreements are not all the
    same, such as where some of the documents are executed by parties who have no
    part in executing the others, provided that the agreements in question relate to the
    same subject matter”); see also Haddox v. First Ala. Bank of Montgomery, 449
    7
    Case: 13-14482        Date Filed: 08/29/2014   Page: 8 of 
    10 So. 2d 1226
    , 1229-30 (Ala. 1984) (reading as a single contract several documents
    concerning the same subject matter but signed by different parties).
    Lastly, under Alabama law, a nonsignatory can seek arbitration if (1) the
    nonsignatory is a third-party beneficiary of the contract containing an arbitration
    provision, and (2) the nonsignatory’s claims are “intertwined with” and “related
    to” the contract. Cook’s Pest Control, Inc. v. Boykin, 
    807 So. 2d 524
    , 526-27 (Ala.
    2001). Where the specific language of the arbitration clause limits its scope to
    claims involving the parties, courts have been reluctant to compel nonsignators
    into arbitration. See 
    id. at 527.
    The district court found none of these circumstances present here. We
    disagree because we conclude that the Indemnification Agreement, bonds, and
    subcontract should be viewed as a single transaction. Although the parties
    involved in signing each document differed, and the documents were signed on
    three separate occasions between March and June 2011, the contracts relate to the
    same subject matter. See Ex parte 
    Harris, 837 So. 2d at 288
    ; see also Love v.
    Fleetway Air Freight & Delivery Serv.,875 So.2d 285, 289 (Ala. 2003) (explaining
    that the court would construe documents together even though they were not
    executed contemporaneously, as long as the documents refer to one another);
    K&C Dev. Corp. v. AmSouth Bank, 
    597 So. 2d 671
    , 674 (Ala. 1992) (considering
    together documents that were signed more than six months apart). Moreover, the
    8
    Case: 13-14482    Date Filed: 08/29/2014    Page: 9 of 10
    parties were aware that Hanover required the Indemnification Agreement before it
    would issue the bonds, and thus the issuance of the bonds depended on the
    indemnification. And Atlantis could not perform its work under the subcontract
    without the bonds. See, e.g., Kandlis v. Houtari, 
    678 A.2d 41
    , 43 (Me. 1996)
    (construing guaranties signed by different shareholders as one agreement because
    the guaranties concerned the same subject matter and were signed “for the same
    purpose”) (cited with approval in Ex parte 
    Harris, 837 So. 2d at 287
    ). The
    Indemnification Agreement refers to bonds that Hanover may enter into, even
    though it does not specifically identify the bonds at issue. And although the
    Indemnification Agreement is not limited to the Atlantis-Brice subcontract and
    bonds, there is no dispute that the parties entered into the Indemnification
    Agreement with the Brice-Atlantis subcontract and the specific payment and
    performance bonds in mind.
    The district court’s conclusion that the documents were not related because
    “at any of these stages the parties could have contracted with someone else without
    destroying the contract” misses the point. The parties were interconnected and the
    documents concerned the same subject matter. Thus, we cannot conclude that the
    Indemnification Agreement pertains to a different subject matter than the
    subcontract and bonds, and the district court erred when it declined to read the
    three documents as a single transaction. See Ex parte 
    Harris, 837 So. 2d at 288
    .
    9
    Case: 13-14482   Date Filed: 08/29/2014   Page: 10 of 10
    We thus vacate and remand with instructions to the district court to compel
    arbitration.
    VACATED and REMANDED.
    10