Developers Surety & Indemnity Company v. Archer Western Contractors, LLC ( 2020 )


Menu:
  •            Case: 18-13271   Date Filed: 04/17/2020   Page: 1 of 8
    [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 18-13271
    ________________________
    D.C. Docket No. 6:16-cv-01875-PGB-KRS
    DEVELOPERS SURETY & INDEMNITY COMPANY,
    a foreign corporation,
    Plaintiff - Counter Defendant - Appellee,
    versus
    ARCHER WESTERN CONTRACTORS, LLC,
    a foreign corporation,
    Defendant - Counter Claimant - Appellee,
    PRINCE LAND SERVICES, INC.,
    Interested Party - Intervenor - Appellant.
    ________________________
    Appeal from the United States District Court
    for the Middle District of Florida
    ________________________
    (April 17, 2020)
    Case: 18-13271       Date Filed: 04/17/2020       Page: 2 of 8
    Before HULL, MARCUS and EBEL, * Circuit Judges.
    PER CURIAM:
    Prince Land Services, Inc. (“Prince”) appeals from an order of the district
    court denying its motion to intervene as of right in the now-concluded litigation
    between Developers Surety and Indemnity Company (“DSIC”) and Archer
    Western Contractors, LLC (“Archer”). Because Prince’s Notice of Appeal was
    filed in an untimely manner, we do not have jurisdiction to hear the case, and,
    accordingly, dismiss this appeal.
    In May 2012, Archer hired Prince as a landscaping subcontractor for the
    Central Florida Commuter Rail Transit Station Finishes Project, for which it was
    the general contractor. Archer acquired a performance bond from DSIC
    guaranteeing Prince’s work. Disputes arose between Archer and Prince in the
    spring of 2014 and culminated in Archer sacking Prince and hiring another
    company to complete its work.
    Disputes between Archer and DSIC followed. Archer demanded DSIC pay
    for the costs of finishing the project, pursuant to the performance bond. DSIC
    argued that it was not obligated to do so because Archer had not given adequate
    notice of Prince’s alleged default. On October 26, 2016, DSIC brought an action
    *
    Honorable David M. Ebel, United States Circuit Judge for the Tenth Circuit, sitting by
    designation.
    2
    Case: 18-13271     Date Filed: 04/17/2020     Page: 3 of 8
    against Archer, in the U.S. District Court for the Middle District of Florida,
    seeking a declaratory judgment that the bond was void. Archer counterclaimed for
    breach of contract.
    On February 8, 2017, Prince attempted to intervene in the action. Prince
    argued that it was entitled to intervene as of right pursuant to Fed. R. Civ. P. 24(a),
    because it intended to sue Archer for breach of contract, and if Archer were to win
    its counterclaim against DSIC, Prince would have an interest in the damages
    award. The district court denied intervention on May 25, 2017, observing that
    Prince’s potential economic interest in the outcome of a lawsuit was not of the
    “direct, substantial, and legally protectable” sort that would entitle it to intervene
    as of right. Mt. Hawley Ins. Co. v. Sandy Lake Props., Inc., 
    425 F.3d 1308
    , 1311
    (11th Cir. 2005).
    For reasons that remain unexplained, Prince never appealed this ruling,
    despite having been entitled to do so on a provisional interlocutory basis. See Fed.
    Sav. & Loan Ins. Corp. v. Falls Chase Special Taxing Dist., 
    983 F.2d 211
    , 214
    (11th Cir. 1993) (explaining that this Court has interlocutory jurisdiction to correct
    a district court’s erroneous denial of a motion to intervene as of right). Instead,
    Prince moved the district court on June 26, 2017 to reconsider its ruling, raising the
    additional argument that Prince’s performance on the subcontract was at issue in
    the case, and that it feared it could face an indemnification claim from DSIC. On
    3
    Case: 18-13271        Date Filed: 04/17/2020         Page: 4 of 8
    August 8, 2017, the district court denied the motion because Prince’s new
    arguments, it explained, had been available the first time around. Prince did not
    appeal this ruling either.
    Many months later, on May 7, 2018, the district court granted summary
    judgment on the issue of liability to Archer. Soon thereafter, on June 15, Archer
    and DSIC executed a settlement agreement on the issue of damages. The next day,
    Prince filed a self-styled “Renewed Motion to Intervene, Motion for
    Reconsideration or Clarification, and Incorporated Memorandum of Law”
    (“Renewed Motion”). Prince made substantially identical arguments just as it had
    in its first two failed attempts to intervene -- asserting that it wanted to sue Archer
    for breach of contract and that it had a contractual duty to indemnify DSIC. Prince
    also raised one additional argument: that by discussing Prince’s default in its grant
    of summary judgment to Archer, the district court had made real Prince’s fear that
    the litigation between DSIC and Archer would implicate its performance under the
    subcontract. The parties did not respond to the Renewed Motion. On June 22,
    2018, Archer and DSIC stipulated to the dismissal of their case with prejudice
    under Fed. R. Civ. P. 41(a)(1)(A)(ii).1 In its July 6, 2018 order, the district court
    1
    Rule 41 permits a plaintiff to voluntarily dismiss an action by filing “a stipulation of dismissal
    signed by all parties who have appeared.” Fed. R. Civ. P. 41(a)(1)(A)(ii).
    4
    Case: 18-13271      Date Filed: 04/17/2020     Page: 5 of 8
    explained that this stipulation deprived it of jurisdiction over the case, and it denied
    Prince’s outstanding Renewed Motion.
    Finally, Prince decided to bring its argument to this Court. On August 3,
    2018, Prince filed a Notice of Appeal, purporting to challenge the district court’s
    July 6, 2018 order. Archer moved this Court to dismiss the appeal for lack of
    jurisdiction; the question was carried with the case.
    Our controlling case law is clear. “In a civil case . . . the notice of appeal . . .
    must be filed with the district clerk within 30 days after entry of the judgment or
    order appealed from.” Fed. R. App. P. 4(a)(1)(A). This 30-day time limit is
    “mandatory and jurisdictional.” Love v. Wal-Mart Stores, Inc., 
    865 F.3d 1322
    ,
    1324 (11th Cir. 2017) (quoting Bowles v. Russell, 
    551 U.S. 205
    , 209 (2007)). If
    an appealable interlocutory motion is denied, and the aggrieved person “fails to file
    an appeal within the prescribed time-frame, it may not file a successive motion
    requesting the same relief ‘simply to revisit the initial . . . decision or resurrect an
    expired time for appeal.’” Birmingham Fire Fighters Ass’n 117 v. Jefferson
    County, 
    290 F.3d 1250
    , 1253 (11th Cir. 2002) (quoting 16 Charles Alan Wright,
    Arthur R. Miller & Edward H. Cooper, Federal Practice and Procedure § 3924.2
    (2d ed. 1996)). However, where substantially “new circumstances, evidence, or
    law” make a new motion a “viable being in its own right instead of merely a re-
    packaging in new garb of the corpse of an old motion in an attempt to resurrect it,”
    5
    Case: 18-13271      Date Filed: 04/17/2020     Page: 6 of 8
    a party may file, and appeal, a new motion so long as it “starts with the proposition
    that the original, unappealed order was correct when entered.”
    Id. at 1254.
    2
    By the time Prince filed its Notice of Appeal in August 2018, far more than
    30 days had passed since the district court first denied Prince’s motion to intervene
    on May 25, 2017, and then denied, on August 8, 2017, its motion to reconsider.
    Prince’s Renewed Motion is identical in substance to its earlier motions. Prince
    has continued to seek precisely the same remedy -- intervention in the action
    between Archer and DSIC -- and for the same essential reason -- that the litigation
    between Archer and DSIC in some sense involved Prince’s breach-of-contract
    claims against Archer. Thus, the only question before us today is whether a
    substantial change of circumstances justified Prince’s Renewed Motion. It did not.
    Prince’s only argument to the contrary is that the district court’s summary
    judgment opinion effected a substantial change of circumstances by making real
    Prince’s fear that the case would implicate its performance under the subcontract.
    But the performance bond, the alleged breach of which was the basis of Archer’s
    counterclaim against DSIC, could only have been triggered by Archer’s assertion
    that Prince had defaulted. Thus, to rule for Archer on its counterclaim, the district
    2
    Though Birmingham Fire Fighters considered successive motions for preliminary injunction,
    we have applied these same principles to motions to intervene as of right. See Meek v.
    Metropolitan Dade County, 
    985 F.2d 1471
    , 1477 (11th Cir. 1993), abrogated on other grounds
    by Dillard v. Chilton Cty. Comm’n, 
    495 F.3d 1324
    (11th Cir. 2007).
    6
    Case: 18-13271       Date Filed: 04/17/2020       Page: 7 of 8
    court would have to make some determination related to Prince’s performance.3
    And when Prince made its initial motion to intervene, it was plainly foreseeable
    that Archer might win the lawsuit -- after all, either Archer was going to win, or
    DSIC was. There was no substantial change of circumstances when the district
    court resolved the case one way rather than the other.
    Moreover, Prince’s Renewed Motion did not “start[ ] with the proposition
    that the original, unappealed order was correct when entered,” Birmingham Fire
    Fighters Ass’n 
    117, 290 F.3d at 1254
    , which in fact it was required to accept. The
    Renewed Motion pays lip service to the possibility that the court’s rulings on the
    first two motions were correct, saying that Prince now has the right to intervene
    “even if denial of the motion to intervene was previously justifiable.” But it
    proceeds to do no more than relitigate Prince’s prior motions. Prince said in its
    Renewed Motion:
    By virtue of having (a) a claim for breach of contract against
    [Archer] that requires Prince to show that it performed its
    3
    We note, however, that it does not appear the district court made any definitive finding that
    would be entitled to preclusive effect as to whether Prince actually breached the subcontract.
    Instead, it merely noted that the Bond “authorized Archer to take remedial action if Archer
    determined, ‘at [i]ts sole discretion,’ that Prince materially breached the Subcontract.” The
    district court went on to state that, under Florida law, the use of the phrase “sole discretion”
    granted Archer “substantial leeway” in determining whether it considered Prince to be in breach,
    though Archer was “limited somewhat by the covenant of good faith.” Thus, the district court’s
    summary judgment analysis with regard to Archer’s counterclaim was limited to whether
    “Archer acted within its ‘discretion’ when it terminated [Prince] for material breach of the
    Subcontract.” In granting Archer’s motion, the district court had only to conclude that Archer
    reasonably exercised the considerable discretion granted to it under the terms of Bond. It had no
    need to—and, indeed, did not—opine on whether Prince actually breached the terms of the
    subcontract.
    7
    Case: 18-13271     Date Filed: 04/17/2020   Page: 8 of 8
    contractual obligations to [Archer], (b) a duty to indemnify DSIC
    for amounts DSIC is required to pay, and (c) joint and several
    liability to [Archer] under the bond, Prince has a direct,
    substantial and legally protectable interest in this case.
    These are precisely the same arguments that Prince advanced in support of
    its motion to reconsider. The district court found them to have been abandoned
    because they were not raised in Prince’s initial motion to intervene. Prince has
    offered no explanation as to how the district court’s refusal to consider these
    arguments was correct when the motion to reconsider was denied on August 8,
    2017, but has since ceased to be so. The long and short of it is that, rather than
    having started with the proposition that the original rulings were correct, Prince
    really seeks to challenge them anew in this Court. This it cannot do, because it
    was obliged to perfect its appeal within 30 days of the district court’s order of
    August 8, 2017.
    Accordingly, this appeal must be and is dismissed for want of jurisdiction.
    DISMISSED.
    8