Case: 18-13271 Date Filed: 04/17/2020 Page: 1 of 8
[DO NOT PUBLISH]
IN THE UNITED STATES COURT OF APPEALS
FOR THE ELEVENTH CIRCUIT
________________________
No. 18-13271
________________________
D.C. Docket No. 6:16-cv-01875-PGB-KRS
DEVELOPERS SURETY & INDEMNITY COMPANY,
a foreign corporation,
Plaintiff - Counter Defendant - Appellee,
versus
ARCHER WESTERN CONTRACTORS, LLC,
a foreign corporation,
Defendant - Counter Claimant - Appellee,
PRINCE LAND SERVICES, INC.,
Interested Party - Intervenor - Appellant.
________________________
Appeal from the United States District Court
for the Middle District of Florida
________________________
(April 17, 2020)
Case: 18-13271 Date Filed: 04/17/2020 Page: 2 of 8
Before HULL, MARCUS and EBEL, * Circuit Judges.
PER CURIAM:
Prince Land Services, Inc. (“Prince”) appeals from an order of the district
court denying its motion to intervene as of right in the now-concluded litigation
between Developers Surety and Indemnity Company (“DSIC”) and Archer
Western Contractors, LLC (“Archer”). Because Prince’s Notice of Appeal was
filed in an untimely manner, we do not have jurisdiction to hear the case, and,
accordingly, dismiss this appeal.
In May 2012, Archer hired Prince as a landscaping subcontractor for the
Central Florida Commuter Rail Transit Station Finishes Project, for which it was
the general contractor. Archer acquired a performance bond from DSIC
guaranteeing Prince’s work. Disputes arose between Archer and Prince in the
spring of 2014 and culminated in Archer sacking Prince and hiring another
company to complete its work.
Disputes between Archer and DSIC followed. Archer demanded DSIC pay
for the costs of finishing the project, pursuant to the performance bond. DSIC
argued that it was not obligated to do so because Archer had not given adequate
notice of Prince’s alleged default. On October 26, 2016, DSIC brought an action
*
Honorable David M. Ebel, United States Circuit Judge for the Tenth Circuit, sitting by
designation.
2
Case: 18-13271 Date Filed: 04/17/2020 Page: 3 of 8
against Archer, in the U.S. District Court for the Middle District of Florida,
seeking a declaratory judgment that the bond was void. Archer counterclaimed for
breach of contract.
On February 8, 2017, Prince attempted to intervene in the action. Prince
argued that it was entitled to intervene as of right pursuant to Fed. R. Civ. P. 24(a),
because it intended to sue Archer for breach of contract, and if Archer were to win
its counterclaim against DSIC, Prince would have an interest in the damages
award. The district court denied intervention on May 25, 2017, observing that
Prince’s potential economic interest in the outcome of a lawsuit was not of the
“direct, substantial, and legally protectable” sort that would entitle it to intervene
as of right. Mt. Hawley Ins. Co. v. Sandy Lake Props., Inc.,
425 F.3d 1308, 1311
(11th Cir. 2005).
For reasons that remain unexplained, Prince never appealed this ruling,
despite having been entitled to do so on a provisional interlocutory basis. See Fed.
Sav. & Loan Ins. Corp. v. Falls Chase Special Taxing Dist.,
983 F.2d 211, 214
(11th Cir. 1993) (explaining that this Court has interlocutory jurisdiction to correct
a district court’s erroneous denial of a motion to intervene as of right). Instead,
Prince moved the district court on June 26, 2017 to reconsider its ruling, raising the
additional argument that Prince’s performance on the subcontract was at issue in
the case, and that it feared it could face an indemnification claim from DSIC. On
3
Case: 18-13271 Date Filed: 04/17/2020 Page: 4 of 8
August 8, 2017, the district court denied the motion because Prince’s new
arguments, it explained, had been available the first time around. Prince did not
appeal this ruling either.
Many months later, on May 7, 2018, the district court granted summary
judgment on the issue of liability to Archer. Soon thereafter, on June 15, Archer
and DSIC executed a settlement agreement on the issue of damages. The next day,
Prince filed a self-styled “Renewed Motion to Intervene, Motion for
Reconsideration or Clarification, and Incorporated Memorandum of Law”
(“Renewed Motion”). Prince made substantially identical arguments just as it had
in its first two failed attempts to intervene -- asserting that it wanted to sue Archer
for breach of contract and that it had a contractual duty to indemnify DSIC. Prince
also raised one additional argument: that by discussing Prince’s default in its grant
of summary judgment to Archer, the district court had made real Prince’s fear that
the litigation between DSIC and Archer would implicate its performance under the
subcontract. The parties did not respond to the Renewed Motion. On June 22,
2018, Archer and DSIC stipulated to the dismissal of their case with prejudice
under Fed. R. Civ. P. 41(a)(1)(A)(ii).1 In its July 6, 2018 order, the district court
1
Rule 41 permits a plaintiff to voluntarily dismiss an action by filing “a stipulation of dismissal
signed by all parties who have appeared.” Fed. R. Civ. P. 41(a)(1)(A)(ii).
4
Case: 18-13271 Date Filed: 04/17/2020 Page: 5 of 8
explained that this stipulation deprived it of jurisdiction over the case, and it denied
Prince’s outstanding Renewed Motion.
Finally, Prince decided to bring its argument to this Court. On August 3,
2018, Prince filed a Notice of Appeal, purporting to challenge the district court’s
July 6, 2018 order. Archer moved this Court to dismiss the appeal for lack of
jurisdiction; the question was carried with the case.
Our controlling case law is clear. “In a civil case . . . the notice of appeal . . .
must be filed with the district clerk within 30 days after entry of the judgment or
order appealed from.” Fed. R. App. P. 4(a)(1)(A). This 30-day time limit is
“mandatory and jurisdictional.” Love v. Wal-Mart Stores, Inc.,
865 F.3d 1322,
1324 (11th Cir. 2017) (quoting Bowles v. Russell,
551 U.S. 205, 209 (2007)). If
an appealable interlocutory motion is denied, and the aggrieved person “fails to file
an appeal within the prescribed time-frame, it may not file a successive motion
requesting the same relief ‘simply to revisit the initial . . . decision or resurrect an
expired time for appeal.’” Birmingham Fire Fighters Ass’n 117 v. Jefferson
County,
290 F.3d 1250, 1253 (11th Cir. 2002) (quoting 16 Charles Alan Wright,
Arthur R. Miller & Edward H. Cooper, Federal Practice and Procedure § 3924.2
(2d ed. 1996)). However, where substantially “new circumstances, evidence, or
law” make a new motion a “viable being in its own right instead of merely a re-
packaging in new garb of the corpse of an old motion in an attempt to resurrect it,”
5
Case: 18-13271 Date Filed: 04/17/2020 Page: 6 of 8
a party may file, and appeal, a new motion so long as it “starts with the proposition
that the original, unappealed order was correct when entered.”
Id. at 1254. 2
By the time Prince filed its Notice of Appeal in August 2018, far more than
30 days had passed since the district court first denied Prince’s motion to intervene
on May 25, 2017, and then denied, on August 8, 2017, its motion to reconsider.
Prince’s Renewed Motion is identical in substance to its earlier motions. Prince
has continued to seek precisely the same remedy -- intervention in the action
between Archer and DSIC -- and for the same essential reason -- that the litigation
between Archer and DSIC in some sense involved Prince’s breach-of-contract
claims against Archer. Thus, the only question before us today is whether a
substantial change of circumstances justified Prince’s Renewed Motion. It did not.
Prince’s only argument to the contrary is that the district court’s summary
judgment opinion effected a substantial change of circumstances by making real
Prince’s fear that the case would implicate its performance under the subcontract.
But the performance bond, the alleged breach of which was the basis of Archer’s
counterclaim against DSIC, could only have been triggered by Archer’s assertion
that Prince had defaulted. Thus, to rule for Archer on its counterclaim, the district
2
Though Birmingham Fire Fighters considered successive motions for preliminary injunction,
we have applied these same principles to motions to intervene as of right. See Meek v.
Metropolitan Dade County,
985 F.2d 1471, 1477 (11th Cir. 1993), abrogated on other grounds
by Dillard v. Chilton Cty. Comm’n,
495 F.3d 1324 (11th Cir. 2007).
6
Case: 18-13271 Date Filed: 04/17/2020 Page: 7 of 8
court would have to make some determination related to Prince’s performance.3
And when Prince made its initial motion to intervene, it was plainly foreseeable
that Archer might win the lawsuit -- after all, either Archer was going to win, or
DSIC was. There was no substantial change of circumstances when the district
court resolved the case one way rather than the other.
Moreover, Prince’s Renewed Motion did not “start[ ] with the proposition
that the original, unappealed order was correct when entered,” Birmingham Fire
Fighters Ass’n
117, 290 F.3d at 1254, which in fact it was required to accept. The
Renewed Motion pays lip service to the possibility that the court’s rulings on the
first two motions were correct, saying that Prince now has the right to intervene
“even if denial of the motion to intervene was previously justifiable.” But it
proceeds to do no more than relitigate Prince’s prior motions. Prince said in its
Renewed Motion:
By virtue of having (a) a claim for breach of contract against
[Archer] that requires Prince to show that it performed its
3
We note, however, that it does not appear the district court made any definitive finding that
would be entitled to preclusive effect as to whether Prince actually breached the subcontract.
Instead, it merely noted that the Bond “authorized Archer to take remedial action if Archer
determined, ‘at [i]ts sole discretion,’ that Prince materially breached the Subcontract.” The
district court went on to state that, under Florida law, the use of the phrase “sole discretion”
granted Archer “substantial leeway” in determining whether it considered Prince to be in breach,
though Archer was “limited somewhat by the covenant of good faith.” Thus, the district court’s
summary judgment analysis with regard to Archer’s counterclaim was limited to whether
“Archer acted within its ‘discretion’ when it terminated [Prince] for material breach of the
Subcontract.” In granting Archer’s motion, the district court had only to conclude that Archer
reasonably exercised the considerable discretion granted to it under the terms of Bond. It had no
need to—and, indeed, did not—opine on whether Prince actually breached the terms of the
subcontract.
7
Case: 18-13271 Date Filed: 04/17/2020 Page: 8 of 8
contractual obligations to [Archer], (b) a duty to indemnify DSIC
for amounts DSIC is required to pay, and (c) joint and several
liability to [Archer] under the bond, Prince has a direct,
substantial and legally protectable interest in this case.
These are precisely the same arguments that Prince advanced in support of
its motion to reconsider. The district court found them to have been abandoned
because they were not raised in Prince’s initial motion to intervene. Prince has
offered no explanation as to how the district court’s refusal to consider these
arguments was correct when the motion to reconsider was denied on August 8,
2017, but has since ceased to be so. The long and short of it is that, rather than
having started with the proposition that the original rulings were correct, Prince
really seeks to challenge them anew in this Court. This it cannot do, because it
was obliged to perfect its appeal within 30 days of the district court’s order of
August 8, 2017.
Accordingly, this appeal must be and is dismissed for want of jurisdiction.
DISMISSED.
8