Case: 19-11148 Date Filed: 04/23/2020 Page: 1 of 16
[DO NOT PUBLISH]
IN THE UNITED STATES COURT OF APPEALS
FOR THE ELEVENTH CIRCUIT
________________________
No. 19-11148
Non-Argument Calendar
________________________
D.C. Docket No. 4:17-cv-00125-HLM
GEORGIA POWER COMPANY,
Plaintiff - Appellee,
versus
ABB, INC.,
Defendant - Appellant.
________________________
Appeal from the United States District Court
for the Northern District of Georgia
________________________
(April 23, 2020)
Before WILLIAM PRYOR, MARTIN, and JILL PRYOR, Circuit Judges.
PER CURIAM:
Case: 19-11148 Date Filed: 04/23/2020 Page: 2 of 16
Georgia Power Company (“Georgia Power”) brought a third-party complaint
against ABB, Inc. (“ABB”) seeking indemnification and alleging a breach of
contract for ABB’s failure to make Georgia Power an additional insured on ABB’s
liability insurance policy. The District Court granted summary judgment to
Georgia Power on all claims. On appeal, ABB argues that summary judgment on
Georgia Power’s indemnification claims was not warranted because ABB’s
contract with Georgia Power was ambiguous as to whether ABB had to indemnify
Georgia Power for its own negligence. ABB also argues that Georgia Power was
not entitled to summary judgment on its breach of contract claim because it did not
show independent damages. After careful consideration, we affirm.
I.
Since at least 2000, ABB has provided equipment and services in support of
the automatic control systems at Georgia Power’s power generation facilities. In
2015, one of ABB’s senior field technicians, David Garrison, was severely injured
while performing electrical work at Plant Bowen, a power plant owned and
operated by Georgia Power. Garrison and his wife brought personal injury claims
against Georgia Power, alleging that Georgia Power had negligently operated Plant
Bowen. Georgia Power in turn sought indemnification from ABB for the
Garrisons’ lawsuit. Citing the indemnification provision in its contract with
Georgia Power, ABB responded that it was not required to provide indemnification
2
Case: 19-11148 Date Filed: 04/23/2020 Page: 3 of 16
for liability arising from Georgia Power’s own negligence. That indemnification
provision says ABB must indemnify Georgia Power for all losses and liability,
“except to the extent caused by Company’s negligence.” The dispute over
indemnification thus turns on whether “Company” refers to Georgia Power.
A. The Contract
The relationship between ABB and Georgia Power is governed by a series of
agreements between ABB and Southern Company Services, Inc. (“SCS”). SCS is
a subsidiary of Southern Company that provides certain services to Southern
Company and its operating divisions, including Georgia Power. ABB and SCS
entered a Master Agreement for Services (the “Master Agreement”) in 2007, and
Amendment One to the Master Agreement (“Amendment One”) in 2013. The
Master Agreement and Amendment One (together, “Contract”) set forth the terms
by which Georgia Power and other SCS-affiliated entities purchase equipment and
services from ABB.
B. The Indemnification Provisions
Both the Master Agreement and Amendment One contain indemnification
clauses, but these clauses differ in material respects. Under the Master
Agreement’s indemnification clause, ABB agrees to fully indemnify “Persons
Indemnified” for all covered claims except those “result[ing] from the sole
3
Case: 19-11148 Date Filed: 04/23/2020 Page: 4 of 16
negligence, fraud or intentional wrongdoing of a Person Indemnified.” The Master
Agreement’s definition of “Persons Indemnified” includes Georgia Power.
In Amendment One, ABB again agreed to indemnify “Persons Indemnified,”
which continues to refer to Georgia Power. However, the indemnification
provision in Amendment One provides that, upon determination that “Company”
was negligent, “Company” would be responsible for a pro rata share of its own
negligence:
General Indemnification. To the fullest extent permitted by applicable
law, Contractor will indemnify, defend and hold harmless the Persons
Indemnified from and against any and all loss, damage, costs . . . , or
liability, except to the extent caused by Company’s negligence . . . .
Contractor shall assume the defense of any claim subject to this
Indemnity and defend it until such time there is a determination of
negligence by the Company, either by court, arbitrator, or agreement,
and at which time liability for the fault shall be shared on a pro rata
basis to the extent of the Company's negligence.1
Both parties agree that the indemnification clause in Amendment One, and not the
indemnification provision in the Master Agreement, governs this dispute.
C. The Contract’s Definition of “Company” and “Affiliate”
The Master Agreement defines both “Company” and “Affiliate” in its
preamble paragraph:
This Agreement is entered by Southern Company Services, Inc., an
Alabama corporation with its principal office at 600 North Eighteenth
Street, Birmingham, Alabama 35203 (acting for itself and as agent for
1
While the parties dispute the meaning of “Company” in the Contract, they agree that
“Contractor” refers to ABB.
4
Case: 19-11148 Date Filed: 04/23/2020 Page: 5 of 16
Alabama Power Company, Georgia Power Company (“GPC”), Gulf
Power Company and Mississippi Power Company (individually,
“Affiliate” and collectively “Affiliates”) as may be applicable under the
circumstances), (“Company”) and ABB, Inc., a Delaware corporation
with its principal office at 501 Merritt Parkway, Norwalk, Connecticut
(“Contractor”).
Meanwhile, Amendment One defines “Company” in its title, which reads:
“AMENDMENT NO. ONE (1) to Master Agreement for Services between
Southern Company Services, Inc. (‘Company’) and ABB Inc. (‘Contractor’)
Agreement No. 8981 (‘Agreement’).”
Paragraph 1.3 of the Master Agreement explains the relationship between
“Company” and its “Affiliates”:
The Parties agree that Company is entering into this Agreement not
only for its own benefit, but also and equally for the direct benefit of its
parent, Southern Company, and Affiliates, both present and future. All
rights, benefits, discounts, remedies and warranties accruing to
Company in this Agreement will likewise accrue to the Affiliates,
including the right to enforce this Agreement in their respective names.
The same provision says that Affiliates could make purchase orders to ABB under
the Master Agreement, but that for any such order, “[e]ach Affiliate [would] be
solely responsible for its own transactions, including payment obligations.”
D. District Court Proceedings
After ABB refused to fully indemnify Georgia Power—including for
liability arising out of Georgia Power’s own negligence—Georgia Power brought a
third-party complaint against ABB. The complaint made claims for
5
Case: 19-11148 Date Filed: 04/23/2020 Page: 6 of 16
indemnification; breach of contract with respect to ABB’s failure to indemnify;
and attorney’s fees and costs for enforcing the Contract’s indemnification
provision (collectively, “Indemnification Claims”). Separately, the complaint
alleged a breach of contract with respect to ABB’s failure to add Georgia Power to
its liability insurance (“Insurance Claim”). Georgia Power sought summary
judgment on all claims.
The district court granted summary judgment to Georgia Power on its
Indemnification Claims after concluding the Contract unambiguously defined
“Company” as referring only to SCS, and not Georgia Power. The district court
based this conclusion primarily on the fact that “Company” was defined as SCS in
the introductory paragraph of the Master Agreement. It also held that even if the
term “Company” were ambiguous, it would resolve that ambiguity in favor of
Georgia Power because holding otherwise would render certain terms in the
contract meaningless. Finally, the district court granted Georgia Power summary
judgment on its Insurance Claim because (a) ABB did not contest that part of
Georgia Power’s summary judgment motion; and (b) the undisputed facts showed
that ABB breached its contractual duty to provide Georgia Power with insurance in
connection with the Garrisons’ claims. 2 This appeal followed.
2
The district court also held (1) based on the undisputed facts, ABB or a member of its
personnel had been negligent, thus triggering ABB’s obligation to indemnify under the Contract;
and (2) the language of the indemnification clause was sufficiently explicit, under Georgia law,
6
Case: 19-11148 Date Filed: 04/23/2020 Page: 7 of 16
II.
We review de novo a district court’s grant of summary judgment. Mangieri
v. DCH Healthcare Auth.,
304 F.3d 1072, 1075 (11th Cir. 2002). “The
interpretation of a contract is a question of law that the court reviews de novo.”
Daewoo Motor Am., Inc., v. Gen. Motors Corp.,
459 F.3d 1249, 1256 (11th Cir.
2006). Whether a contract is ambiguous, and whether that ambiguity can be
resolved without submission to a jury, is also a question of law reviewed de novo.
See Underwriters at Lloyd Subscribing to Cover Note B0753PC1308275000 v.
Expeditors Korea, Ltd.,
882 F.3d 1033, 1039 (11th Cir. 2018).
III.
On appeal, ABB raises two arguments. First, it challenges the district
court’s determination that “Company” in the Contract refers only to Southern
Company Services. Second, it argues that Georgia Power was not entitled to
summary judgment on its insurance claim because Georgia Power provided no
evidence of “independent damages.” We address each argument in turn.
A. The Indemnification Claims
so as to indemnify Georgia Power for its own negligence. ABB does not challenge these aspects
of the summary judgment order, and we do not address them on appeal.
7
Case: 19-11148 Date Filed: 04/23/2020 Page: 8 of 16
Under Georgia law, 3 courts interpret contracts in three steps. First, we
determine whether the contract language is unambiguous. City of Baldwin v.
Woodard & Curran, Inc.,
743 S.E.2d 381, 389 (2013). If it is, we enforce the
contract according to its plain terms.
Id. If the contract is ambiguous, we must
apply Georgia’s rules of contract construction to resolve the ambiguity.
Id. And if
ambiguity remains after applying the rules of construction, “the issue of what the
ambiguous language means and what the parties intended must be resolved by a
jury.”
Id.
A contract is ambiguous when “the words used in the contract leave the
intent of the parties in question—i.e., that intent is uncertain, unclear, or is open to
various interpretations.” Grange Mut. Cas. Co. v. Woodard,
861 F.3d 1224, 1231
(11th Cir. 2017) (quoting Capital Color Printing, Inc. v. Ahern,
661 S.E.2d 578,
583 (Ga. Ct. App. 2008)). Georgia courts have defined ambiguity as “duplicity,
indistinctness, an uncertainty of meaning or expression used in a written
instrument.” First Acceptance Ins. Co. of Ga., Inc. v. Hughes,
826 S.E.2d 71, 75–
76 (Ga. 2019) (quotation marks omitted). On the other hand, “no ambiguity exists
where, examining the contract as a whole and affording the words used therein
their plain and ordinary meaning, the contract is capable of only one reasonable
3
The parties agreed that the Contract would be governed by Georgia law.
8
Case: 19-11148 Date Filed: 04/23/2020 Page: 9 of 16
interpretation.” Grange, 861 F.3d at 1231 (quoting Capital Color Printing,
661
S.E.2d at 583).
1. The Contract Unambiguously Defines “Company” as Southern Company
Services.
The Contract defines “Company” in two different provisions. First, the
Master Agreement’s preamble states, “This agreement is entered by Southern
Company Services, Inc., . . . (acting for itself and as agent for Alabama Power
Company, Georgia Power Company [], Gulf Power Company and Mississippi
Power Company (Individually, ‘Affiliate’ and collectively, ‘Affiliates’) . . . )
(‘Company’) and ABB Inc., . . . (‘Contractor’).” And second, Amendment One
states in its title that it is amending the Master Agreement “between Southern
Company Services, Inc. (‘Company’) and ABB Inc. (‘Contractor’).”
Both the preamble to the Master Agreement and the title of Amendment One
thus indicate that “Company” is a defined term that refers to Southern Company
Services. See HIP, Inc. v. Hormel Foods Corp.,
888 F.3d 334, 339 (8th Cir. 2018)
(recognizing the principle that a “defined term is defined by tucking it at the end of
the definition, in parentheses” (quotation marks omitted)); Bryan A. Garner, The
Elements of Legal Style § 4.5, at 81 (2d ed. 2002) (describing parentheses with
quotation marks inside as sufficient to signal a defined term). Meanwhile, the
preamble provides that Georgia Power is an “Affiliate,” rather than the
9
Case: 19-11148 Date Filed: 04/23/2020 Page: 10 of 16
“Company.” See Olympus Ins. Co. v. AON Benfield, Inc.,
711 F.3d 894, 898 (8th
Cir. 2013) (holding that a parenthetical term defines the term preceding it).
ABB argues the preamble’s definition of “Company” is difficult to decipher
due to its use of nested parentheticals, and that this difficulty itself raises a factual
ambiguity as to whether the term “Company” includes Georgia Power. But
Georgia courts have held time and again that “[a] contract is not ambiguous even
though difficult to construe.” F & F Copiers, Inc. v. Kroger Co.,
391 S.E.2d 711,
713 (Ga. Ct. App. 1990) (quotation marks omitted). And while the preamble was
not artfully written, the term “Company” indisputably refers to SCS and not
Georgia Power. Beyond that, the title to Amendment One clears up any potential
confusion by plainly associating “Company” with its directly adjacent term,
“Southern Company Services, Inc.” We therefore disagree with ABB that the
Master Agreement’s preamble renders “Company” ambiguous.
2. ABB Waived its Argument that the Contract’s “Broad” and “Narrow”
Uses of “Company” Rendered that Term Ambiguous.
ABB also argues that the term “Company” is ambiguous because the
Contract sometimes uses a “broad” definition of “Company” that refers to both
SCS and Affiliates such as Georgia Power, as well as a “narrow” definition that
applies only to SCS. The parties disagree on whether ABB waived this argument
by failing to raise it in the district court. We hold that ABB did not make this
argument in the district court, and that we need not consider it on appeal. And
10
Case: 19-11148 Date Filed: 04/23/2020 Page: 11 of 16
even if we were to consider this new argument, we reject the idea that the contract
employs a “broad” definition of “Company” that must refer to both SCS and
Georgia Power.
To start, at no point in ABB’s summary judgment briefing did it argue that
the Contract was ambiguous by virtue of its varying broad and narrow usages of
the term “Company.” Rather, ABB argued (1) that the Contract “specifically”
defines Company as both SCS and Georgia Power; and (2) that the definition of
Company includes Georgia Power because SCS entered the Contract acting as
Georgia Power’s agent. And while ABB contended that any potential ambiguity
would have to be resolved against Georgia Power, ABB did not specifically argue
that the Contract is ambiguous, let alone that the Contract’s inconsistent
deployment of “Company” is the reason for that ambiguity. See Trade Am Int’l,
Inc. v. Cincinnati Ins. Co., 504 F. App’x 860, 861 (11th Cir. 2013) (per curiam)
(unpublished) (refusing to consider an issue on appeal because the “specific”
argument was not raised below).
“As a general rule, an issue not raised in the district court and raised for the
first time in an appeal will not be considered by this court.” See Blue Martini
Kendall, LLC v. Miami Dade County,
816 F.3d 1343, 1349 (11th Cir. 2016)
(quotation marks omitted). However, this rule is discretionary in nature, and our
Circuit has established specific exceptions for where courts may consider
11
Case: 19-11148 Date Filed: 04/23/2020 Page: 12 of 16
arguments not raised below.
Id. One such exception is when the issue “involves a
pure question of law, and [] refusal to consider it would result in a miscarriage of
justice.” Id. at 1350 (quotation marks omitted). This court has previously held that
a refusal to consider an issue would result in a miscarriage of justice where the
issue involves a constitutional issue, or an “issue of general impact.” Id.; see In re
Worldwide Web Sys., Inc.,
328 F.3d 1291, 1301 (11th Cir. 2003) (holding that a
refusal to consider an issue would result in a miscarriage of justice where the issue
was of “transcending public importance”). We are more willing to consider an
issue not previously raised on an appeal from summary judgment. See Blue
Martini, 816 F.3d at 1349.
ABB’s new argument fails to satisfy any of the exceptions to the general rule
prohibiting consideration of issues raised for the first time on appeal. While it is
true that ABB’s new argument raises a pure question of law, our refusal to consider
it is far from what we have traditionally deemed a “miscarriage of justice.”
Compare Blue Martini, 816 F.3d at 1350 (holding that “application of an
unconstitutional statute” would result in a miscarriage of justice), with Cita Tr. Co.
AG v. Fifth Third Bank,
879 F.3d 1151, 1156 (11th Cir. 2018) (“[W]e can discern
no miscarriage of justice in enforcing the express terms of a contract . . . between
two sophisticated parties.”); OMV Assocs. Ltd. P’ship v. TriMont Real Estate
Advisors, 484 F. App’x 299, 306 (11th Cir. 2012) (per curiam) (unpublished) (“A
12
Case: 19-11148 Date Filed: 04/23/2020 Page: 13 of 16
litigant’s inability to inject a new ambiguity into a contract . . . will rarely be a
miscarriage of justice . . . .”). And although it is true that we are more willing to
consider unpreserved arguments on an appeal from summary judgment, that fact
alone is not a permissible basis for exercising our discretion. See Blue Martini,
816 F.3d at 1350. We therefore hold that ABB waived its argument that Contract
used the term “Company” inconsistently.
Even if we were to consider ABB’s new argument, it lacks merit. ABB says
that the Contract varies between using “broad” and “narrow” definitions of
“Company.” The narrow definition is used when the Contract expressly
differentiates between “Company” and “Affiliate,” such as when the two terms are
used in the same sentence or paragraph. And the “broad” definition is used,
according to ABB, when the Contract describes the terms of ABB’s products and
services. Those provisions, for the most part, refer only to “Company,” rather than
the “Affiliate.” For instance, the Contract says ABB will provide warranties for its
services to “Company,” but does not include any similar provision for Affiliates.
Similarly, the Contract says “Company” will pay for purchase orders to ABB.
According to ABB, a definition of “Company” that excludes Georgia Power would
render these provisions nonsensical because, for example, only SCS would receive
warranties for work that ABB provides to Georgia Power. Similarly, SCS, and not
13
Case: 19-11148 Date Filed: 04/23/2020 Page: 14 of 16
Georgia Power, would have to pay for products and Services ABB provides to
Georgia Power.
But ABB’s argument overlooks Paragraph 1.3 of the Agreement. That
provision says that any “rights, benefits, discounts, remedies and warranties
accruing to Company . . . likewise accrue to the Affiliates,” and that “[e]ach
Affiliate will be solely responsible for its own transactions, including payment
obligations.” Paragraph 1.3 thus makes clear that any rights and warranties
associated with ABB’s work extend from “Company” to “Affiliates” such as
Georgia Power. A definition of “Company” that refers only to SCS would not,
therefore, preclude Affiliates such as Georgia Power from receiving warranties for
work provided by ABB. Similarly, because Paragraph 1.3 says Affiliates are
solely responsible for their payment obligations, a definition of “Company” that is
limited to SCS would not make SCS responsible for paying off Georgia Power’s
purchase orders. In light of Paragraph 1.3, we reject ABB’s argument that the
Contract used “Company” to refer to both SCS and its Affiliates.
Because we have determined that the express language of the Contract
unambiguously defines “Company” as SCS, we need not resort to Georgia’s rules
of contract construction. Calhoun, GA NG, LLC v. Century Bank of Ga.,
740
S.E.2d 210, 212 (Ga. Ct. App. 2013) (“[W]here the contract terms are clear and
unambiguous, the court will look to that alone to find the true intent of the parties.”
14
Case: 19-11148 Date Filed: 04/23/2020 Page: 15 of 16
(quotation marks omitted)). We therefore affirm the district court’s grant of
summary judgment on Georgia Power’s Indemnification Claims.
B. The Insurance Claim
ABB argues that the district court erred when it granted Georgia Power
summary judgment on its Insurance Claim. That claim alleged ABB breached its
obligation, under the Contract’s insurance provision, to list Georgia Power “as [an]
additional insured[] under” ABB’s liability insurance policies. The Contract’s
insurance clause also says ABB’s insurance obligation is “consistent with [ABB’s]
indemnification obligations.” ABB argues on appeal that because its insurance
obligation was coextensive with its indemnification obligation, the damages
Georgia Power seeks under its Insurance Claim are the same as those sought under
its Indemnification Claims. According to ABB, Georgia Power is not entitled to
summary judgment on its Insurance Claim because it did not show damages
“independent” from the those associated with its Indemnification Claims.
As an initial matter, ABB did not raise this argument in the district court,
and in fact did not respond at all to the part of Georgia Power’s summary judgment
motion addressing its Insurance Claim. ABB does not contend that this argument
fits into any of the exceptions to our rule prohibiting consideration of arguments
raised for the first time on appeal. See Blue Martini, 816 F.3d at 1349–50.
15
Case: 19-11148 Date Filed: 04/23/2020 Page: 16 of 16
Therefore, we hold that ABB waived its argument concerning Georgia Power’s
Insurance Claim.
Even if we were to consider ABB’s argument, we would reject it because it
is based on the fallacy that a breach of contract claim must allege damages
“independent” from all other claims. While it is true that Georgia law prohibits
“double recovery of the same damages for the same wrong,” Marvin Nix Dev. Co.
v. United Cmty. Bank,
692 S.E.2d 23, 25 (Ga. Ct. App. 2010) (quotation marks
omitted), parties are allowed to proceed on different theories in pursuit of the same
damages, Pope v. Prof’l Funding Corp.,
472 S.E.2d 116, 119 (Ga. Ct. App. 1996).
The cases cited by ABB, such as Bates v. JPMorgan Chase Bank, NA,
768 F.3d
1126 (11th Cir. 2014), do not hold to the contrary. Rather, they stand only for the
unremarkable proposition that damages are a required element of any breach of
contract claim.
Id. at 1130. 4
IV.
We AFFIRM the district court’s order granting summary judgment to
Georgia Power on all its claims.
4
Because we affirm the district court’s grant of summary judgment on Georgia Power’s
Indemnification Claims, we do not address ABB’s separate argument that a reversal as to
Georgia Power’s Indemnification Claims would require reversal on Georgia Power’s Insurance
Claim.
16