Nihon Rufuto Co., LTD vs Nidek Medical Products, Inc. , 437 F. App'x 782 ( 2011 )


Menu:
  •                                                            [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________                  FILED
    U.S. COURT OF APPEALS
    No. 11-10444                ELEVENTH CIRCUIT
    Non-Argument Calendar              AUGUST 11, 2011
    ________________________               JOHN LEY
    CLERK
    D.C. Docket No. 2:09-cv-00041-JHH
    NIHON RUFUTO CO., LTD.,
    Plaintiff-Appellant,
    versus
    NIDEK MEDICAL PRODUCTS, INC.,
    Defendant-Appellee.
    ________________________
    Appeal from the United States District Court
    for the Northern District of Alabama
    ________________________
    (August 11, 2011)
    Before HULL, MARTIN and ANDERSON, Circuit Judges.
    PER CURIAM:
    Plaintiff-Appellant Nihon Rufuto Co., Ltd., (“Nihon Rufuto”) appeals the
    district court’s order granting summary judgment to Defendant-Appellee Nidek
    Medical Products, Inc. (“Nidek”) on Nihon Rufuto’s breach of contract claim
    under Alabama law. After review, we affirm.
    I. FACTS
    A.    Unity Project Business Proposal
    Plaintiff Nihon Rufuto, a Japanese company, imports medical equipment
    from the United States and Europe. In early 2002, Nihon Rufuto approached
    Defendant Nidek, an Alabama corporation, about designing and developing an
    oxygen concentrator. Nihon Rufuto wanted an oxygen concentrator similar to the
    Mark 6 oxygen concentrator that Nidek had developed for Koike Medical for the
    Japanese market. However, Nihon Rufuto wanted its oxygen concentrator to be
    smaller and quieter, with less power consumption. The parties referred to the
    project as the “Unity Project.”
    On April 19, 2002, Nidek sent Nihon Rufuto a business proposal that
    outlined the Unity Project, but noted that each company’s contributions were still
    “to be discussed.” Nihon Rufuto’s contributions would include, inter alia, funding
    the development costs, defining product specifications and coordinating third
    party testing and regulatory approvals (with Japan’s Ministry of Health). Nidek’s
    contributions would include, inter alia, agreeing with Nihon Rufuto’s product
    specifications and project goals, preparing quality measures with Nihon Rufuto’s
    2
    agreement, contracting with a noise consultant and an industrial design firm and
    working with Nihon Rufuto’s engineers to improve system performance.
    The business proposal contained a list of specifications and other product
    requirements. The specifications included an oxygen flow of three liters per
    minute; an oxygen concentration of greater than ninety percent;1 a weight of less
    than 32 kilograms; a noise level of 37 A-weighted decibels in an ordinary room
    and 32 A-weighted decibels in an anechoic chamber; power of less than 260 watts
    “at 100v 50Hz” and less than 300 watts “at 100v 60Hz”; and meeting standard
    “IEC 601-1 or applicable JQA standard.” The concentrator would have four
    casters for mobility and an outlet pressure of 5 Psig. The molecular sieve would
    be “Oxy Sieve 7 or MDX.” The compressor would be a “Thomas 32 stroke.” The
    cabinet construction and system alarm, however, were still “[t]o be discussed.”
    B.     Condensed Project Plan and Budget
    On May 8, 2002, Nidek’s president, Anand Chitlangia, sent a letter to Nihon
    Rufuto’s president, Tadao Ichida, containing a “condensed project plan and
    budget” prepared by Nidek for the “OEM Concentrator” project, i.e., the Unity
    Project. Chitlangia’s letter stated, “Although, as a result of our meeting, we have
    1
    The parties later agreed on an oxygen concentration of ninety percent, plus or minus
    three percent.
    3
    [a] basic understanding of your requirements, we are sure that as we progress
    towards this project, we will have some questions, which may change the scope of
    our proposal.” Nidek’s Chitlangia expressed “hope that these questions will be
    resolved in the next few meetings.”
    Nidek’s Chitlangia’s letter explained that “[i]n the meantime, [Nidek] ha[d]
    made certain assumptions” in developing its project plan. Nidek’s project plan
    divided the Unity Project into phases with Nidek coordinating “the engineering
    and design effort” with support from Nihon Rufuto’s business and technical staff.
    Chitlangia’s letter outlined ten “broad categories” of items left open for either
    future agreement between the parties or for future contracting with third party
    consultants, including an industrial design firm, a sound control consultant,
    electronic design consultant and a tooling supplier:
    1.    Specific agreement with Nihon Rufuto for product
    specifications and project goals.
    2.    Preparation of quality measures for product and agreement
    with Nihon Rufuto.
    3.    Contracting with an industrial design firm for the purpose
    of preparing [sic] that meets the project goals. This will
    include ergonomic, appearance and packing requirement
    and other elements associated with the product and support
    as required for preparing test models & prototypes.
    4.    Contracting the services of a sound Control consultant at
    the early stages of the product design.
    5.    Contracting with an electronic design consultant for the
    purpose of verifying electronic functions and preparation
    4
    of a printed circuit board that would consolidate all
    electronic functions including the Oxygen Monitoring
    System & system alarms.
    6.    Contracting with a tooling supplier for the preparation of
    necessary tooling.
    7.    Preparation of manufacturing processes and procedures in
    agreement with Nihon Rufuto.
    8.    Preparation of quality procedures and documents with
    agreement with Nihon Rufuto.
    9.    Preparation of suitable manufacturing & assembly area.
    10.   Support to Nihon Rufuto engineers for the purpose of
    securing regulatory approvals.
    Although Chitlangia’s letter states that the project is divided into five phases, the
    attached budget listed only four phases, as follows:
    PHASE I   COMPONENT REVIEW & SELECTION
    COST: $22,500 PLUS EXPENSES*
    PHASE II INDUSTRIAL DESIGN
    COST: $43,500 PLUS EXPENSES*
    PHASE III TOOLING DESIGN
    COST: $31,000 PLUS EXPENSES*
    PHASE IV PRE-PRODUCTION PILOT
    COST: $16,000 PLUS EXPENSES*
    *EXPENSES: ALL OUT OF POCKET EXPENSES RELATED TO
    THIS PROJECT INCLUDING TRAVEL EXPENSES, COST OF 10
    ALPHA PROTOTYPES, INDUSTRIAL DESIGN CHARGES, FEES
    FOR NOISE & ELECTRONIC DESIGN CONSULTANT, TOOLING
    COST AND COST OF 100 PROTOTYPES.
    WE ESTIMATE THE TOTAL OF ALL EXPENSES TO BE $220,000
    THIS CAN BE REDUCED IF NIHON RUFUTO CO., LTD., WILL
    REQUIRE ONLY FEW PRE-PRODUCTION UNITS INSTEAD OF
    5
    ESTIMATED 100 UNITS.
    The sums in the four phases total $113,000, but Nidek also would be reimbursed
    for out of pocket expenses, including any sums paid to the numerous consultants.
    Both Chitlangia and Ichida signed the May 8, 2002 letter.
    C.    Email With Target Completion Dates
    On May 25, 2002, Chitlangia sent Ichida an email regarding the “OEM
    Proposal” that listed seven general tasks with ballpark dates for their completion:
    1. We would need a written acceptance of our proposal by you. It can
    be done either by you signing our proposal sent to you and returning it
    to us or by you sending us a letter stating your acceptance. - End of May
    2. Upon receipt of the above, we will contract with the design firm for
    the purpose of creating few (between 3 and 6) designs. We will forward
    these to you for your review. - Mid June
    3. With your input, we will select one of the above as a final design. - -
    3rd week of June
    4. The next step will be to create a schematic of the entire machine,
    detailing the position of the components inside the machine. - - 1st
    week of July
    5. Upon approval of that from you, we will then proceed to make
    prototype parts and then two(2) prototypes. One will be retained at our
    factory to run tests and collect data and the second will be shipped to
    you for your engineers to run tests and collect data. - - End of July
    6. This way we can compare the results and make changes as required.
    - - 1st week of August
    7. After all the changes are made then we will build one more prototype
    and collect data which then can be submitted to MOH of [sic] approval.
    - - End of August
    Chitlangia’s email stated, “Assuming that everything proceeds without any major
    6
    glitches, we will then be ready to order tooling in September.” With regard to
    payment, Chitlangia’s email added that to proceed, Nidek would need some up-
    front payment:
    1. A retainer fee of $20,000 which will be adjusted at the completion of
    the project.
    2. A payment of $33,000, which represents 50% of the amount stated in
    our proposal for Phases I and II.
    3. A payment of $33,000 which will represent the balance of the amount
    stated in our proposal for Phases I and II.
    NOTE: ALL OUT OF POCKET EXPENSES WILL BE BILLED TO
    YOU AT THE END OF EACH MONTH. YOU WILL BE ADVICED
    [SIC] AND YOUR PERMISSION WILL BE REQUESTED PRIOR TO
    MAKING ANY MAJOR EXPENSES - IN SOME CASES THE
    ESTIMATED AMOUNT WILL BE GIVEN WITH A DEFINITE ‘NOT
    TO EXCEED’ LIMITS.
    Ichida signed the email. From May 2002 to September 2002, Nihon Rufuto paid
    Nidek $129,350 for Nidek’s work on the oxygen concentrator.2
    D.     Changes to First and Second Prototypes
    In October 2002, at a trade show in Atlanta, Nidek presented Nihon Rufuto
    with a prototype of the oxygen concentrator. Nihon Rufuto was pleased with the
    prototype, but asked for some changes, including, inter alia, changes to the control
    panel, the positioning of a “cannula hook suction cup” and a “patient humidifier
    2
    We could locate no breckdown in the record of what part was for Nidek’s work and what
    part was for expense reimbursement for consultants.
    7
    bottle.” According to the notes of Paul Holman, Nidek’s project manager on the
    Unity Project, Nidek was to “continue to work on reducing component/unit
    vibration and noise” and, to that end, would “investigate the possibilities of
    reducing the tank boot intake size.”
    Between the end of 2002 and the Spring of 2003, Nidek revised the
    prototype based on Nihon Rufuto’s comments. In March 2003, Nidek sent a
    second prototype to Nihon Rufuto in Japan. In an email acknowledging receipt of
    the revised prototype, a Nihon Rufuto employee stated that the revised prototype
    was impressive and that President Ichida was “very happy about this
    workmanship.”3 The Nihon Rufuto email: (1) discussed changes to the location of
    the oxygen outlet and to the cannula check light, and (2) advised that Nihon
    Rufuto would “finish revising” and return the prototype to Nidek.
    E.     2003 Change to Five Liter Compressor
    Throughout the rest of 2003, Nihon Rufuto asked Nidek for even more
    changes. One significant change was from a three liter compressor to a five liter
    compressor. The five liter compressor increased the size of the motor, generated
    more noise, used more wattage and required some different parts. At Nihon
    3
    In his deposition, Ichida explained that in this email he meant only that he was pleased
    with the way the prototype looked and that he had not yet had a chance to evaluate whether the
    prototype met the specifications.
    8
    Rufuto’s request, Nidek worked on designing models with a three liter compressor
    and with a five liter compressor. Nihon Rufuto also asked for a redesign of the
    oxygen monitoring system board and tweaks to the cabinet design. At a July 2003
    meeting in Birmingham, Nihon Rufuto inspected the three liter and five liter
    compressors. By January 2004, Nihon Rufuto planned to submit first the three
    liter model to Japan’s Ministry of Health and follow with the five liter model.
    In March 2004, Nidek shipped another three liter prototype with a 32 stroke
    compressor to Nihon Rufuto. After testing that prototype, Nidek determined that
    it met the oxygen purity, noise and wattage requirements. Nihon Rufuto’s own
    test results confirmed a 90+ percent oxygen purity and its electrical test was
    positive. Nihon Rufuto advised Nidek that Nihon Rufuto would proceed with the
    approval application with the Ministry of Health. Over the next several months
    Nidek worked to prepare the prototype and the documentation Nihon Rufuto
    needed for the application.
    F.    2004 Change to 2505 BLDC Compressor
    The original April 19, 2002 business proposal listed a “Thomas 32 stroke
    compressor.” However, at an October 2004 meeting, Nihon Rufuto asked Nidek
    to incorporate a 2505 BLDC compressor into the Unity Project. The 2505 BLDC
    compressor was not yet sold on the market and a sample unit was unavailable for
    9
    testing. Further, the 2505 BLDC compressor ran on DC power, while the Thomas
    compressor in the prototypes used AC power.4 And, the 2505 BLDC compressor
    was more expensive. Nihon Rufuto also asked Nidek, among other things, to
    reduce the cabinet size. Nidek spent many hours making the requested changes
    and researching the 2505 BLDC compressor and the adjustments needed to
    incorporate it into the oxygen concentrator.
    At meetings in March and August 2005, Nihon Rufuto asked for even more
    design changes and other modifications, including reducing the weight of the
    concentrator by ten kilograms. Nihon Rufuto insisted on incorporating the 2505
    BLDC compressor even though it was still not available on the market and also
    asked for drastic changes to the oxygen monitoring system board and a total
    cabinet redesign. According to Nidek’s Holman, Nihon Rufuto’s requested
    changes transformed the Unity Project into “another project altogether,” and
    placed “unreasonable demands” on Nidek. Although Nidek spent hundreds of
    hours making Nihon Rufuto’s changes, Nihon Rufuto did not want to pay any
    additional money to Nidek.
    G.     2005 Termination of Unity Project
    4
    It appears that at some point the parties agreed to switch to a Thomas 34 stroke
    compressor; however, both compressors used AC power.
    10
    On August 8, 2005, Nihon Rufuto’s president Ichida sent a letter to Nidek
    stating that three years after the agreement to commence the Unity Project, “this
    project and the specification as well as the exterior design is still so far away to be
    accepted in [the] Japanese market.” Nidek continued to make changes to the CAD
    database and oxygen monitory system board specification charges into 2006.
    Once this work was completed, Nidek submitted its drawings and documents to
    Nihon Rufuto. Nihon Rufuto turned these documents over to companies outside
    Nidek’s control. Nihon Rufuto terminated the Unity Project and, in June 2006,
    sent a demand letter for $1,7020,000 in damages.
    H.    District Court Proceedings
    On January 9, 2009, Nihon Rufuto filed this diversity action against Nidek
    alleging claims of breach of contract and fraud under Alabama law. The district
    court concluded that Nihon Rufuto’s fraud claim was time-barred. Nihon Rufuto’s
    appellate brief expressly abandons the fraud claim.
    With respect to the contract claim, Nihon Rufuto alleged that Nidek’s
    oxygen concentrator prototypes never met the agreed-upon specifications and that
    Nidek abandoned further efforts to fulfill its part of the contract in May 2006.
    Following discovery, Nidek moved for summary judgment, arguing, inter
    alia, that the terms of the alleged contract between the parties were too indefinite
    11
    to be enforceable under Alabama law. The district court agreed and entered
    summary judgment in favor of Nidek on Nihon Rufuto’s breach of contract claim.
    Nihon Rufuto filed this appeal.5
    II. DISCUSSION
    Under Alabama law, to establish a breach of contract claim the plaintiff
    must prove: “(1) the existence of a valid contract binding the parties in the action,
    (2) his own performance under the contract; (3) the defendant’s nonperformance,
    and (4) damages.” S. Med. Health Sys., Inc. v. Vaughn, 
    669 So. 2d 98
    , 99 (Ala.
    1995). Thus, Nihon Rufuto bore the burden to prove that it entered into a valid
    contract with Nidek. We agree with the district court that Nihon Rufuto did not
    present evidence of a valid contract under Alabama law.
    “A contract cannot be formed without an offer, an acceptance,
    5
    “This Court reviews de novo summary judgment rulings and draws all inferences and
    reviews all evidence in the light most favorable to the non-moving party.” Moton v. Cowart, 
    631 F.3d 1337
    , 1341 (11th Cir. 2011). Summary judgment is appropriate “if the movant shows that
    there is no genuine dispute as to any material fact and the movant is entitled to judgment as a
    matter of law.” Fed. R. Civ. P. 56(a). If the nonmoving party “fails to make a showing sufficient
    to establish the existence of an element essential to that party’s case, . . . . [t]here can be ‘no
    genuine issue as to any material fact,’ since a complete failure of proof concerning an essential
    element of the nonmoving party’s case necessarily renders all other facts immaterial.” Celotex
    Corp. v. Catrett, 
    477 U.S. 317
    , 322-23, 
    106 S. Ct. 2548
    , 2552 (1986) (quoting former Rule
    56(c)). Whether a contract is too indefinite to be enforced is a question of law. White Sands
    Grp., LLC v. PRS II, LLC, 
    998 So. 2d 1042
    , 1052-53 (Ala. 2008). Accordingly, our review of
    this legal issue is also de novo. See Zaklama v. Mount Sinai Med. Ctr., 
    906 F.2d 650
    , 652 (11th
    Cir. 1990) (stating that issues of contract interpretation are questions of law generally reviewed
    de novo).
    12
    consideration, and mutual assent to those terms essential to the contract.”
    Drummond Co., Inc. v. Walter Indus., Inc., 
    962 So. 2d 753
    , 754 (Ala. 2006). “To
    be enforceable, the essential terms of a contract must be sufficiently definite and
    certain, and a contract that leaves material portions open for future agreement is
    nugatory and void for indefiniteness.” White 
    Sands, 998 So. at 1042
    (citations,
    quotation marks and brackets omitted). A contract can lack definiteness as to
    “time of performance, the price to be paid, work to be done, property to be
    transferred, or miscellaneous stipulations in the agreement.” 
    Id. (emphasis added).
    “The terms of a contract are reasonably certain if they provide a basis for
    determining the existence of a breach and for giving an appropriate remedy.” 
    Id. (quotation marks
    and emphasis omitted); see also Smith v. Chickamauga Cedar
    Co., 
    82 So. 2d 200
    , 203 (Ala. 1955) (“[I]f the offer is in any case so indefinite as
    to make it impossible for a court to decide just what it means, and to fix exactly
    the legal liability of the parties, its acceptance cannot result in an enforceable
    agreement.”). “Additionally, in order for an alleged contract to be considered void
    based on the indefiniteness of its terms, the indefiniteness must reach the point
    where construction becomes futile.” Poole v. Prince, 
    61 So. 3d 258
    , 275 (Ala.
    2010) (quotation marks and brackets omitted). “A court will, if possible, interpret
    doubtful agreements by attaching a sufficiently definite meaning to a bargain if the
    13
    parties evidently intended to enter into a binding contract.” 
    Id. Further, “[w]here
    it is clear that a written instrument was not intended to reflect the full agreement of
    the parties” and there is evidence that the parties reached an agreement as to
    omitted terms rather than left them “open for future agreement,” the parties may
    use parol evidence “to clarify the omitted terms.” 
    Id. at 279-80
    (quotation marks
    omitted).
    As evidence of an alleged contract with Nidek, Nihon Rufuto points to: (1)
    the May 8, 2002 letter by Nidek’s Chitlangia that listed the ten broad catagories of
    work associated with the project; and (2) the May 25, 2002 email by Nidek’s
    Chitlangia outlining seven general tasks and ballpark completion dates in 2002. In
    addition, Nihon Rufuto contends that Nidek’s April 19, 2002 business proposal
    contains the product specifications and goals and is admissible parol evidence to
    fill in omitted terms.
    These three documents, even taken together, are too indefinite as to the
    work Nidek was to perform be enforceable. The documents reflect that many of
    the engineering and design details for the oxygen concentrator were to be settled
    by future agreement or were contingent upon Nihon Rufuto’s later approval. For
    example, according to the April 19, 2002 business proposal, both Nihon Rufuto’s
    and Nidek’s contributions were still “to be discussed,” and Nihon Rufuto would
    14
    still need to “[d]efin[e] the product specifications” (although some specifications
    were attached), “[p]rovid[e] guidance for cabinet design,” and agree with the
    quality measures Nidek had yet to prepare. The attached list of specifications and
    other project requirements notes that both the system alarm and the cabinet
    construction are “[t]o be discussed.”
    The May 8, 2002 letter states that, after meeting with Nihon Rufuto, Nidek
    had “[a] basic understanding of [Nihon Rufuto’s] requirements” for the Unity
    Project, but that “as [they] progress toward this project, [Nidek] will have some
    questions, which may change the scope of [Nidek’s] proposal.” After making
    “certain assumptions,” (that are unspecified) the letter states that Nidek proposes
    dividing the project into four phases: component review and selection, industrial
    design, tooling design and pre-production pilot. The letter outlines ten “broad
    categories” to be included in the proposed engineering and design effort, some of
    which will require Nihon Rufuto’s approval. The first category is “[s]pecific
    agreement with Nihon Rufuto for product specifications and project goals,” clearly
    indicating that the parties had not yet had a meeting of the mind on those terms.
    The second category reiterates that Nidek will need Nihon Rufuto’s agreement as
    to quality measures. Similarly, as to the seventh and eighth categories, Nidek will
    need Nihon Rufuto’s agreement as to the manufacturing process and procedures
    15
    and the quality procedures and documents.
    The final document, Nidek’s Chitlangia’s May 25, 2002 email, outlines a
    series of steps Nidek proposed to take, many of which would require Nihon
    Rufuto’s approval or “input” before Nidek could proceed to the next step. For
    instance, Nidek agreed to select a design with Nihon Rufuto’s input and await
    Nihon Rufuto’s approval of the machine’s schematic before making prototype
    parts and two prototypes. Then, depending of the results of both parties’ testing of
    the prototypes, the email contemplates changes to the design, only after which
    would Nidek build another prototype to be submitted for regulatory approval with
    the Ministry of Health. The number of contingencies and Nihon Rufuto’s ability
    to vary the plans at different phases suggests the parties did not have mutual assent
    as to the work Nidek was to do.
    Nihon Rufuto argues that any uncertainties were removed by Nidek’s
    development of the prototypes, for which Nihon Rufuto paid Nidek $129,350. See
    Chickamauga Cedar 
    Co., 82 So. 2d at 203
    (“stating that “[o]ffers which are
    originally too indefinite may later acquire precision and become valid offers, by
    the subsequent words or acts of the offeror or his assent to words or acts of the
    offeree”). The problem for Nihon Rufuto is that the parties’ subsequent words and
    actions in developing the prototypes do not add precision. Instead, subsequent
    16
    events only further highlight that there was no firm understanding between the
    parties as to what exactly Nidek was required to design.
    Nihon Rufuto began asking for changes as soon as Nidek delivered the first
    prototype and continued asking for changes over the entire three-year period
    Nidek worked on the Unity Project. In addition to requests to reposition various
    component parts, to redesign the oxygen monitoring system board and to
    repeatedly tweak the cabinet design, Nihon Rufuto asked for three different
    compressors to be incorporated into the machine—first a three liter compressor,
    then a five liter compressor and finally a 2505 BLDC compressor. These
    compressor changes required Nidek to redesign other aspects of the machine and
    the cabinet, such that Nidek’s project manager said it became “another project
    altogether.” In sum, the Unity Project was a constantly moving target, and the
    parties actions during the development of the prototypes did not remove the
    uncertainty as to what work Nidek was to perform under the alleged contract.
    Because the three documents Nihon Rufuto relies upon to show a contract
    are too indefinite as to the essential term of what work Nidek was to perform, they
    do not provide a basis for determining whether Nidek breached the alleged
    contract. Thus, under Alabama law, the alleged contract is unenforceable, and the
    district court properly granted summary judgment to Nidek.
    17
    AFFIRMED.
    18